RE:ID PAC.E.I9.14
IPUC I't Set Data Request (l -5)
Please find enclosed Rocky Mountain Powsr's Responses to IPUC 1't Set Data Requests 1-5.
Also provided are Attachments IPUC 2 and 4.
If you have any questions, please feel free to call me at (801) 220-2963.
---ls/-J. Ted Weston
Manager, Regulation
Enclosures
Sincerely,
PAC-E-19-14 / Rocky Mountain Power
November 12,201,9
IPUC I "t Set Data Request I
IPUC Data Request 1
What schedule(s) will the small usage devices be billed under?
Response to IPUC Data Request 1
Un-metered small usage devices will be billed under Electric Service
Schedule 23.
Recordholder: Rob Stewart
Sponsor: Ted Weston
PAC-E-I9-14 / Rocky Mountain Power
November 12, 2019
IPUC I't Set Data Request 2
IPUC Data Request 2
The Application states, "device's capacity requirements will be provided on the
customer service application." Application at 3. Has the Company produced a
customer service application which includes an option for small usage devices? If
so, please provide. If not, please explain the delay and when it will be completed.
Response to IPUC Data Request 2
A draft service application form has been created. Please see Attachment IPUC 2.
Recordholder: Rob Stewart
Sponsor: Ted Weston
PAC-E-lg- 14 / Rocky Mountain Power
November 12,2019
IPUC l" Set Data Request 3
IPUC Data Request 3
The revised Regulation 4 provided in Attachment I states, "Connections will be
made by Company." Attachment 1 at l. What is the fee for the Company to
install the small usage device?
Response to IPUC Data Request 3
The Company's line extension rule l2 will govem the share, if any, of the cost of
attachment that will be covered bv the customer.
Recordholder: Rob Stewart
Sponsor: Ted Weston
PAC-E-19-14 / Rocky Mountain Power
November 12,2019
IPUC l't Set Data Request 4
IPUC Data Request 4
The revised Regulation 4 provided in Attachment 'l states, "Connections will be
made by Company, subject to the Customer's installation meeting all the
Company's design and installation requirements." Attachment I at 1.
a. Please provide a copy of the written design and installation requirements;
b. If not completed, please provide an outline and explain what will be
included in the requirernents; and
c. When the customer will receive the specific details.
Response to IPUC Data Request 4
a. Please see Attachment IPUC 4 for the Company's small cell antenna
installation guidelines.
b. See response to a.
c. The details will be posted online along with the application form.
Recordholder: Rob Stewart
Sponsor: Ted Weston
PAC-E-19- 14 / Rocky Mountain Power
November 12,2019
IPUC l" Set Data Request 5
IPUC Data Request 5
The revised Regulation 4 provided in Attachment I states, "The Company shall
have the right to test the capacity requirements ofthe small usage devices from
time to time." Attachment 1 at l Please provide the Company's plan for testing
the devices which may include which devices will be tested and how often.
Response to IPUC Data Request 5
The Company intends to do an annual sampling ofa small percentage ofthese
non-metered small usage devices. The frequency and extent to which the
Company tests the devices will need to be determined as the Company gains
experience with its audits. The volume of devices, the accuracy of wattages that
the customer supplies and the availability ofqualified personnel will be factors
that will influence the Company's plans as they evolve.
Recordholder: Rob Stewa(
Sponsor: Ted Weston