HomeMy WebLinkAbout20180329PAC to Staff WY WIEC Set 20 (1-15) (3).pdfROCKY MOUNTAIN
POWER
A DIVISION OF PACIFICORP 1407 W North Temple,Suite 330
Salt Lake City,Utah 84116
March 2,2018
Abigail C.Briggerman,#7-5476
Holland &Hart LLP
6380 South Fiddlers Green Circle,Suite 500
Greenwood Village,CO 80111
acbriggerman@hollandhart.com(C)
RE:Wyoming Docket 20000-520-EA-17
WIEC 20th Set Data Request (1-15)
Please find enclosed Rocky Mountain Power's Responses to WIEC 20th Set Data Requests 20.1
and 20.6.The remaining responses will be provided separately.Also provided is Attachment
WIEC 20.1-1.Provided on the enclosed Confidential CD is Confidential Attachment WIEC
20.1-2.Confidential information is provided subject to the terms and conditions of the protective
agreement in this proceeding.
If you have any questions,please call me at (307)632-2677.
Sincerely,
Stacy Splittstoesser,
Manager,Regulation
Enclosures
C.C.:Meridith Bell/WPSC meridith.bell@wyo.gov(C)
Lori L.Brand/WPSC lori.brand@wyo.gov (W)
John Burbridge/WPSC john.brubride@wyo.gov (W)
Michelle Bohanan/WPSC Michelle.bohanan@wyo.gov (W)
Kara Seveland/WPSC kara.seveland@wvo.gov(W)
Morgan Fish/WPSC morgan.fish@wvo.gov (W)
Dave Walker/WPSC dave.walker@wyo.ev (W)
Perry McCollom/WPSC perry.mccollom@wyo.gov(W)
Patti Penn/WIEC PPenn@hollanhart.com(W)
Thor Nelson/WIEC tnelson@hollandhart.com (C)(W)
Emanuel Cocian/WIEC etcocian@hollanhart.com (W)
Adele Lee/WIEC ACLee@hollandhart.com (W)
Nik Stoffel/WIEC NSStoffel@hollandhart.com (C)(W)
Christopher Leger/OCA christopher.leger@wyo.gov (C)
Crystal J.McDonough/NLRAcrystal@medonoughlawlle.com (C)
Callie Capraro/NLRA callie@medonoughlawllc.com
Lisa Tormoen Hickey/Interwestlisahickey@newlawaroup.com (C)
Brandon L.Jensen/RMSC brandon@buddfaln.com (C)
Roxane Perruso/TOTCO Roxane.perruso@tac-denver.com
Jane M.France/TOTCO ifrance@spkm.ore (C)
Constance E.Brooks/Anadarko connie@cebrooks.com(C)
Danielle Bettencourt/Anadarko danielle@cebrooks.com (C)(W)
Paul Kapp/Anadarko pkapp@spkm.ore (C)
Lisa Christian/TOTCO Lisa.Christian@tac-denver.com (C)
J.Kenneth Barbe/Southlandkbarbe@wsmtlaw.com (C)
20000-520-EA-17 /Rocky Mountain Power
March 2,2018
WIEC Data Request 20.1
WIEC Data Request 20.1
Please provide copies of all EPC contracts,BTAs and PPAs for the revised final shortlist.
Response to WIEC Data Request 20.1
Please refer to the Company's response to WIEC Data Request 14.31.
Any supplemental responses to WIEC Data Request 14.31 will include engineer,procure,
construct (EPC)contract,build transfer agreements (BTA),and /or power purchase
agreements (PPA)as relevant to the Combined Projects (New Wind and New
Transmission)as defined in this proceeding.
In addition,please refer to Attachment WIEC 20.1-1 and Confidential Attachment WIEC
20.-2,which provide the pro-forma contract forms used in connection with the
solicitation of balance of plant (BOP)EPC contract proposals for the Ekola Flats and TB
Flats I and II Wind Projects,and the solicitation of BTA proposals for the Cedar Springs
and Uinta Wind Projects.
Confidential information is provided subject to the protective order in this docket.
Respondent:Bruce Griswold and Richard Goff
Witness:Rick Link and Chad Teply
20000-520-EA-17 /Rocky Mountain Power
March 2,2018
WIEC Data Request 20.6
WIEC Data Request 20.6
Please explain how system impact studies treat and account for higher priority requests.
For example,Exhibit RMP _(RAV-5SS)states at Section 10.1,"All active higher
priority transmission service and/or generator interconnection requests will be considered
in this study and are identified below."However,Exhibit RMP _(RAV-4SS)states at
Section 10.1,"All active higher priority transmission service and/or generator
interconnection request with an in-service date of December 2020 or earlier were
considered in this study and are identified below."Please identify any tariff provisions
that govern the treatment of higher priority requests.
Response to WIEC Data Request 20.6
Section 42.3 of PacifiCorp's Open Access Transmission Tariff (OATT)establishes the
scope of the interconnection system impact study and states:
The Interconnection System Impact Study shall evaluate the impact of the
proposed interconnection on the reliability of the Transmission System.
The Interconnection System Impact Study will consider the Base Case as
well as all generating facilities (and with respect to (iii)below,any
identified Network Upgrades associated with such higher queued
interconnection)that,on the date the Interconnection System Impact Study
is commenced:(i)are directlyinterconnected to the Transmission System;
(ii)are interconnectedto Affected Systems and may have an impact on the
Interconnection Request;(iii)have a pending higher queued
Interconnection Request to interconnect to the Transmission System;and
(iv)have no Queue Position but have executed an LGIA or requested that
an unexecuted LGIA be filed with FERC.
The referenced language from Exhibit RMP _(RAV-4SS)should not be interpreted to
mean that not all higher-queued projects were considered.When updating the
assumptions for the referenced interconnection system impact study to reflect the new
staging of Energy Gateway West Segment D.2 Aeolus-Bridger/Anticlineto be in-service
by December 2020,PacifiCorp considered all higher-queuedinterconnection requests and
projects with executed LGIAs,but some projects with later in-service dates were deemed
not impacted by the updated projected in-service date of Segment D.2.
Respondent:Kris Bremer
Witness:Rick Vail