HomeMy WebLinkAbout20180307PAC to Staff WY WIEC Set 20 (1-15) (2).pdfROCKY MOUNTAINPOWER
A DIVlSION OF PACIFICORP 1407 W North Temple,Suite 330
Salt Lake City,Utah 84116
March 2,2018
Abigail C.Briggerman,#7-5476
Holland &Hart LLP
6380 South Fiddlers Green Circle,Suite 500
Greenwood Village,CO 80111
acbriggerman@hollandhart.com(C)
RE:Wyoming Docket 20000-520-EA-17
WIEC 20th Set Data Request (1-15)
Please find enclosed Rocky Mountain Power's Responses to WIEC 20th Set Data Requests 20.2,
20.7-20.9,and 20.11.The remaining responses will be provided separately.
If you have any questions,please call me at (307)632-2677.
Sincerely,
Stacy Splittstoesser,
Manager,Regulation
Enclosures
C.C.:Meridith Bell/WPSC meridith.bell@wyo.gov(C)
Lori L.Brand/WPSC lori.brand@wyo.gov (W)
John Burbridge/WPSC john.brubride@wvo.gov(W)
Michelle Bohanan/WPSC Michelle.bohanan@wyo.gov (W)
Kara Seveland/WPSC kara.seveland@wyo.gov(W)
Morgan Fish/WPSC morgan.fish@wyo.gov (W)
Dave Walker/WPSC dave.walker@wvo.ev (W)
Perry McCollom/WPSC perrv.mccollom@wyo.gov(W)
Patti Penn/WIEC PPenn@hollanhart.com(W)
Thor Nelson/WIEC tnelson@hollandhart.com (C)(W)
Emanuel Cocian/WIEC etcocian@hollanhart.com (W)
Adele Lee/WIEC ACLee@hollandhart.com (W)
Nik Stoffel/WIEC NSStoffel@hollandhart.com (C)(W)
Christopher Leger/OCA christopher.leger@wyo.gov (C)
Crystal J.McDonough/NLRAcrystal@medonoughlawlle.com (C)
Callie Capraro/NLRA callie@medonoughlawllc.com
Lisa Tormoen Hickey/Interwestlisahickev@newlawgroup.com (C)
Brandon L.Jensen/RMSC brandon@buddfaln.com(C)
Roxane Perruso/TOTCO Roxane.perruso@tac-denver.com
Jane M.France/TOTCO jfrance@spkm.org (C)
Constance E.Brooks/Anadarko connie@cebrooks.com(C)
Danielle Bettencourt/Anadarko danielle@cebrooks.com (C)(W)
Paul Kapp/Anadarko pkapp@spkm.org (C)
Lisa Christian/TOTCO Lisa.Christian@tac-denver.com (C)
J.Kenneth Barbe/Southlandkbarbe@wsmtlaw.com (C)
20000-520-EA-17 /Rocky Mountain Power
March 2,2018
WIEC Data Request 20.2
WIEC Data Request 20.2
Please provide a narrative description of all efforts the Company has undertakento
ensure the revised final shortlist projects go online before December 31,2020,whether
the projects are BTA or PPA projects.
Response to WIEC Data Request 20.2
As part of each project bid evaluation,PacifiCorp reviewed the bid material submitted by
the bidder,conducted conference calls with the bidder and independentevaluators (IE)to
review bid submittal includingproject schedule,status and schedule of required
permitting,status and schedule of required studies,status and schedule of publicly
available interconnection studies on Open Access Same-Time Information System
(OASIS),status and schedule of wind turbine and balance of plant procurement,and
status and schedule of site control includingrights of ways (ROW)and easements.As
part of its review process,PacifiCorp required that each bidder provide documentation as
available to support status and schedule to achieve a commercial operation date (COD)
on or before December 31,2020.Build transfer agreement (BTA)and power purchase
agreement (PPA)contracts will be negotiatedbetween March 2018 and June 2018,and
will include contractual mechanisms such as schedule requirements,construction
guarantees,and liquidated damages to ensure that any risks associated with construction
and commercial operational delays will be borne by the project developerrather than
PacifiCorp and its customers.
Respondent:Bruce Griswold /Ken Clark
Witness:Rick Link /Chad Teply
20000-520-EA-17 /Rocky Mountain Power
March 2,2018
WIEC Data Request 20.7
WIEC Data Request 20.7
Regarding the Cedar Springs Wind Project,please explain how the wind facilities,
includingany gen-tie lines,are allocated based on the BTA and PPA components.For
example,is the BTA component for an ownership interest in the entire project,or for
specific wind facilities within the project?
Response to WIEC Data Request 20.7
In the evaluation of Cedar Springs Wind Project,the build transfer agreement (BTA)
projects were evaluated at its bid price with direct-assigned interconnection capital cost
plus the dollars per kilowatt ($/kW)in-service interconnection network upgrade capital
cost based on the BTA capacity (halfof the total project capacity).The other half was
included in the power purchase agreement (PPA)bid price.The two components were
added together to determine the combined BTA/PPA cost for modeling purposes.
The BTA and PPA for the Cedar Springs Wind Project are scheduled to be negotiated
between March 2018 and June 2018.PacifiCorp anticipates the BTA will be tied to
specific equipment,such as individual wind turbine generators (WTG),within the wind
project to the greatest extent possible within a practical project design.
Respondent:Bruce Griswold /Ken Clark
Witness:Rick Link /Chad Teply
20000-520-EA-17 /Rocky Mountain Power
March 2,2018
WIEC Data Request 20.8
WIEC Data Request 20.8
Please provide a copy of Appendix J to the February2018 Final Report of Merrimack
Energy.
Response to WIEC Data Request 20.8
Please refer to the Company's response to WIEC Data Request 17.4.The highly
confidential presentation dated February 12,2018 is Appendix J to the February 2018
Final Report of Merrimack Energy Group,Inc.,regarding the 2017 Renewable Request
for Proposals (2017R RFP).A non-confidential version is available on the website of the
Public Service Commission of Utah:
https://psedocs.utah.gov/electric/17docs/1703523/300421RedacFinRep2-27-2018.pdf
Respondent:Bruce Griswold
Witness:Rick Link
20000-520-EA-17 /Rocky Mountain Power
March 2,2018
WIEC Data Request 20.9 ,
WIEC Data Request 20.9
Please refer to Mr.Vail's Second SupplementalDirect Testimony at pages 1 and 7.
(a)Please provide a complete copy of the updated studies that indicate that RMP can
interconnect 1,510 MW of incremental wind generationbehind the TOT4A/TOT4B
constraint.
(b)Please identifywhether RMP will be purchasing any of the output of the 240 MW
QualifyingFacility that has an executed interconnection agreement that is mentioned
on Page 7 of Mr.Vail's Second SupplementalDirect Testimony.
Response to WIEC Data Request 20.9
(a)Please refer to the Company's response to WIEC Data Request 19.2.
(b)PacifiCorp has a Public Utility Regulatory Policies Act (PURPA)obligation to
contract with and to purchase the output of the 240 megawatt (MW)qualifying
facility (QF)once the project has interconnected and is operating.
Respondent:Craig Quist /Bruce Griswold
Witness:Rick Vail /Rick Link
20000-520-EA-17 /Rocky Mountain Power
March 2,2018
WIEC Data Request 20.11
WIEC Data Request 20.11
Please refer to Mr.Vail's Second SupplementalDirect Testimony at pages 3 through 6
and Mr.Vail's Exhibits RAV-2SS through RAV-5SS.For each of the followingwind
projects,please identify the commercial operation date that must be achieved in order for
the project to be eligible for full receipt of Production Tax Credits (PTCs).
(a)TB Flats I and II.
(b)Cedar Springs.
(c)Ekola Flats.
(d)Uinta.
Response to WIEC Data Request 20.11
Each project must achieve commercial operation by December 31,2020.
Respondent:Bruce Griswold
Witness:Rick Link