Loading...
HomeMy WebLinkAbout20180307PAC to Staff UT Q810SIS.pdfPACIFICORP Large Generator Interconnection System Impact Study Report Completed for ("Interconnection Customer") Q0810 Proposed Point of Interconnection Q0715 Point of Interconnection Substation (on Canyon Compression- Railroad 138 kV line) February 9,2018 Y PACIFICORP System Impact Study Report TABLE OF CONTENTS 1.0 DESCRIPTION OF THE GENERATING FACILITY .............................................1 2.0 SCOPE OF THE STUDY.....................................................l 3.0 TYPE OF INTERCONNECTION SERVICE ..............................................1 4.0 DESCRIPTION OF PROPOSED INTERCONNECTION...............................................l 5.0 STUDY ASSUMPTIONS....................................................................................3 6.0 ENERGY RESOURCE (ER)INTERCONNECTION SERVICE...............................................4 6.1.1 Requirements 4 6.1.2 Cost Estimate 9 6.1.3 Schedule 10 6.1.4 Maximum Amount of Power that can be deliveredinto NetworkLoad,with No Transmission Modifications(for informationalpurposes only)10 6.1.5 Additional Transmission ModificationsRequired to Deliver 100%of the Power into Network Load (for informationalpurposes only)10 7.0 NETWORK RESOURCE (NR)INTERCONNECTION SERVICE.............................................10 7.1.1 Requirements 10 7.1.2 Cost Estimate 10 7.1.3 Schedule 10 8.0 PARTICIPATIONBYAFFECTEDSYSTEMS.............................................11 9.0 APPENDICES..................................................................................11 9.1 Appendix 1:HigherPriority (PriorQueued)Requests ...............................................12 9.2 Appendix 2:Property Requirements.............................................13 9.3 Appendix 3:Study Results...............................................15 Page i February 9,2018 ,Q0810 V PAC I F\CORP System impact Study Report 1.0 DESCRIPTION OF THE GENERATING FACILITY ("Interconnection Customer")proposed interconnecting 101 MW of new generation to PacifiCorp's ("Transmission Provider")Canyon Compression -Railroad 138 kV line located in Uinta County,Wyoming.The project ("Project")will consist of 44 GE 2.3 inverters for a total output of 101 MW.The requested commercial operation date is July 1,2019. Interconnection Customer will NOT operate this generator as a Qualified Facility as defined by the Public Utility Regulatory Policies Act of 1978 (PURPA). The Transmission Provider has assigned the Project "Q0810." 2.0 SCOPE OF THE STUDY The interconnection system impact study shall evaluate the impact of the proposed interconnection on the reliability of the transmission system.The interconnection system impact study will consider Base Case as well as all generatingfacilities (and with respect to (iii)below,any identified network upgrades associated with such prior queued interconnections)that,on the date the interconnection system impact study is commenced: (i)are directlyinterconnected to the transmission system; (ii)are interconnected to Affected Systems and may have an impact on the interconnection request; (iii)have a pending prior queued interconnection request to interconnect to the transmission system;and (iv)have no Queue Position but have executed an LGIA or requested that an unexecuted LGIA be filed with FERC. This interconnection system impact study will consist of a short circuit analysis,a stability analysis,and a power flow analysis.The study will state the assumptions upon which it is based; state the results of the analyses;and provide the requirements or potential impediments to providing the requested interconnection service,includingpreliminaryindication of the cost and length of time that would be necessary to correct any problems identified in those analyses and implement the interconnection.The study will also provide a list of facilities that are required as a result of the Interconnection Request and a non-binding good faith estimate of the cost responsibility and a non-binding good faith estimated time to construct. 3.0 TYPE OF INTERCONNECTION SERVICE The Interconnection Customer has selected Network Resource (NR)Interconnection Service,but has also elected to have the interconnection studied as an Energy Resource (ER).The Interconnection Customer will select NR or ER prior to the facilities study. 4.0 DESCRIPTION OF PROPOSED INTERCONNECTION The Interconnection Customer's proposed Generating Facility is to be interconnected through the Interconnection Customer Interconnection Facilities to be constructed for the Q0715 project. Figure 1 below,is a one-line diagram that illustrates the interconnection of the proposed Generating Facility to the Transmission Provider's system. Page 1 February 9,2018 Q0810 Y PACIFICORP System Impact Study Report Whitney Canyon Inlet i Canyon Compression 0.3 miles /Q0715 POI Substation Point of Interconnection \Q0810 /Project Sub 34.5 kV 138 kV 68/90/112 MVA - 138 -34.5 kV Z =9 % Tie-Line Substation(Customer-owned) I 34.5 kV 6 Miles Change of 84/112/140MVA 138 -34.5 kVOwnershipZ=9 % i M Q0715 Project Sub Railroad Figure 1:Simplified System One Line Diagram -Point ofInterconnection Page 2 February 9,2018 Q0810 V PAC I F\CORP System impact Study Report 5.0 STUDYASSUMPTIONS All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are listed in Appendix 1.If any of these requests are materiallymodified or withdrawn,the Transmission Provider reserves the right to restudy this request,and the Results and conclusions could significantlychange. For study purposes there are two separate queues: o Transmission Service Queue:to the extent practical,all network upgrades that are required to accommodate active transmission service requests will be modeled in this study. o Generation Interconnection Queue:Interconnection Facilities associated with prior queued interconnection requests will be modeled in this study. The Interconnection Customer's request for energy or network resource interconnection service in and of itself does not convey transmission service.Only a Network Customer may make a request to designate a generating resource as a Network Resource.The provision of transmission service may require additional studies and the construction of additional upgrades. Under normal conditions,the Transmission Provider does not dispatch or otherwise directly control or regulate the output of generating facilities.Therefore,the need for transmission modifications,if any,which are required to provide Network Resource Interconnection Service will be evaluated on the basis of 100 percent deliverability(i.e., no displacement of other resources in the same area). This study assumes the Project will be integrated into the Transmission Provider's system at agreed upon and/or proposed Point of Interconnection. The Interconnection Customer will construct and own any facilities required between the Point of Change of Ownership and the Project unless specifically identified by the Transmission Provider. Line reconductor or fiber underbuild required on existing poles will be assumed to follow the most direct path on the Transmission Provider's system.If during detailed design the path must be modified it may result in additional cost and timing delays for the Interconnection Customer's project. Generatortripping may be required for certain outages. All facilities will meet or exceed the minimum Western Electricity Coordinating Council ("WECC"),North American Electric Reliability Corporation ("NERC"),and the Transmission Provider's performance and design standards. The Q0715 project must be complete before or simultaneously with this Project. The Jordanelle-Midway 138 kV line is assumed to be in service (2019). The Energy Gateway West,Aeolus-Bridger/Anticlinesub-segment D.2,is assumed to be in-service by year end 2020. This report is based on information available at the time of the study.It is the Interconnection Customer's responsibility to check the Transmission Provider's web site regularlyfor Transmission System updates at http://www.pacificorp.com/tran.html Page 3 February 9,2018 Q0810 V PAC I F\CORP System impact Study Report 6.0 ENERGY RESOURCE(ER)INTERCONNECTION SERVICE Energy Resource Interconnection Service allows the Interconnection Customer to connect its Generating Facility to the Transmission Provider's Transmission System and to be eligible to deliver electric output using firm or non-firm transmission capacity on an as available basis. 6.1.1 Requirements 6.1.1.1 GeneratingFacility Modifications All interconnecting synchronous and non-synchronous generators are required to design their Generating Facilities with reactive power capabilities necessary to operate within the full power factor range of 0.95 leading to 0.95 lagging.This power factor range shall be dynamic and can be met using a combination of the inherent dynamic reactive power capability of the generator or inverter,dynamic reactive power devices and static reactive power devices to make up for losses. For synchronous generators,the power factor requirement is to be measured at the Point of Interconnection.For non-synchronousgenerators,the power factor requirement is to be measured at the high-side of the generator substation. The generating facility must provide dynamic reactive power to the system in support of both voltage scheduling and contingency events that require transient voltage support,and must be able to provide reactive capability over the full range of real power output. If the generating facility is not capable of providing positive reactive support (i.e.,supplying reactive power to the system)immediately followingthe removal of a fault or other transient low voltage perturbations,the facility must be required to add dynamic voltage support equipment. These additional dynamic reactive devices shall have correct protection settings such that the devices will remain on line and active during and immediately followinga fault event. Generators shall be equipped with automatic voltage-control equipment and normally operated with the voltage regulation control mode enabled unless written authorization (or directive)from the Grid Operator is given to operate in another control mode (e.g.constant power factor control). The control mode of generating units shall be accurately represented in operating studies.The generators shall be capable of operating continuouslyat their maximum power output at its rated field current within +/-5%of its rated terminal voltage. As required by NERC standard VAR-001-la,the Transmission Provider will provide a voltage schedule for the Point of Interconnection.In general,Generating Facilities should be operated so as to maintain the voltage at the Point of Interconnection,or other designated point as deemed appropriated by Transmission Provider.The Transmission Provider may also specify a voltage and/or reactive power bandwidth as needed to coordinate with upstream voltage control devices such as on-load tap changers.At the Transmission Provider's discretion,these values might be adjusted depending on operating conditions. Generating Facilities capable of operating with a voltage droop are required to do so.Voltage droop control enables proportionate reactive power sharing among generation facilities.Studies will be required to coordinate voltage droop settings if there are other facilities in the area.It will be the Interconnection Customer's responsibility to ensure that a voltage coordination study is Page 4 February 9,2018 Q0810 V PAC I F\CORP System impact Study Report performed,in coordination with Transmission Provider,and implemented with appropriate coordination settings prior to unit testing. For areas with multiplegenerating facilities additional studies may be required to determine whether or not critical interactions,including but not limited to control systems,exist.These studies,to be coordinated with Transmission Provider,will be the responsibility of the Interconnection Customer.If the need for a master controller is identified,the cost and all related installation requirements will be the responsibility of the Interconnection Customer.Participation by the generation facility in subsequent interaction/coordination studies will be required pre-and post-commercial operation in order ensure system reliability. To facilitate collection and validation of accurate modeling data to meet NERC modeling standards,PacifiCorp,as the Planning Coordinator,requires Phasor MeasurementUnits (PMUs) at all new GeneratingFacilities with an individual or aggregate nameplate capacity of 75 MVA or greater.In addition to owning and maintaining the PMU,the Generating Facility will be responsible for collecting,storing and retrieving data as requested by the Planning Coordinator. Data must be collected and be able to stream to Planning Coordinator for each of the Generator Facility's step-up transformers measured on the low side of the GSU at a sample rate of at least 30 samples per second and synchronizedwithin +/-2 milliseconds of the CoordinatedUniversal Time (UTC).Initially,the followingdata must be collected: Three phase voltage and voltage angle (analog) Three phase current (analog) Data requirements are subject to change as deemed necessary to comply with local and federal regulations. All generators must meet the Federal Energy Regulatory Committee (FERC)and WECC low voltage ride-through requirements as specified in the interconnection agreement. As the Transmission Provider cannot submit a user written model to WECC for inclusion in base cases,a standard model from the WECC Approved Dynamic Model Library is required 180 days prior to trial operation.The list of approved generator models is continually updated and is available on the http://www.WECC.bizwebsite. 6.1.1.2 Transmission System Modifications Q0810 is responsible to eliminate the credible N-2 outage of the Transmission Provider's Ben Lomond-Birch Creek and Ben Lomond-Naughton 230 kV transmission lines,which share common structures for approximately eight miles as they exit Ben Lomond substation.This will require construction of a new approximately seven-mile 230 kV line (2-795 ACSR)in a separate right of way,in order for both 230 kV circuits to be on separate structures. 6.1.1.3 Transmission/Distribution Line Modifications Construct a 230 kV single circuit transmission line beginning approximately one mile outside of Ben Lomond substation to structure 525 for the Ben Lomond-Naughton #1 line. This line segment will replace the current Ben Lomond-Naughton #1 circuit which resides on the north side of the 7 mile long lattice tower double circuit with the Ben Lomond-Birch Creek 230 Page 5 February 9,2018 Q0810 V PAC I F\CORP System impact Study Report kV transmission line.This new line will require the procurement of additional rights-of-ways which the Interconnection Customer will be responsible to obtain on behalf of the Transmission Provider.The corridor near Ben Lomond substation where the new transmission line must be constructed is congested.The Transmission Provider anticipates that the procurement of the necessary rights-of-waycould be difficult and may add significant cost and potential delays to the Project. 6.1.1.4 Existing Circuit Breaker Upgrades -Short Circuit The increase in the fault dutyon the system as a result of the addition of the Generating Facility with 44 -GE 2.3 MW wind turbine generators fed through 44 -2.5 MVA 34.5 kV -690 V transformers with 5.75%impedance then fed through one 138 -34.5kV 68/90/112 MVA step-up transformer with 9%impedance will not push the fault duty above the interruptingrating of any of the Transmission Provider's existing fault interruptingequipment. 6.1.1.5 Protection Requirements The Interconnection Customer's line relays at the collector substation will need to respond to the combination of the 138 kV fault current being contributed from both the Q0715 and the Q0810 generationprojects for faults on the 138 kV tie line and trip both 138 kV breakers for the two projects. As this Project will be interconnectedthrough the same facilities planned to be constructed for the Q0715 project it will be included in the bus differential relay system that will trip the 138 kV breaker in the tie line substation to be installed as part of the Q0715 project. The relay to be installed at the Q0715 POI substation as part of the Q0715 project will monitor the voltage magnitude and frequency of the Q0810 Project.If the magnitude or frequency of the voltage is outside of normal range of operation a signal will be sent to trip the tie line 138 kV breakers. New line relay settings will be developed for the Naughton -Ben Lomond and Birch Creek - Ben Lomond 230 kV lines due to the rebuilding of the seven mile section of those lines. 6.1.1.6 Data (RTU)Requirements Data for the operation of the power system will be needed from the Interconnection Customer's collector substation.Listed is the data that will be acquired from the collector substations. From the Q0715 collector substation: Analogs: Net GenerationMW Net GeneratorMVAR Interchangemetering kWH From the Q0810 collector substation: Analows: Net GenerationMW Net GeneratorMVAR Page 6 February 9,2018 Q0810 V PAC I F\CORP System impact Study Report Interchangemetering kWH 34.5 kV Real power F1 34.5 kV Reactive power Fl 34.5 kV Real power F2 34.5 kV Reactive power F2 34.5 kV Real power F3 34.5 kV Reactive power F3 34.5 kV Real power F4 34.5 kV Reactive power F4 34.5 kV Real power F5 34.5 kV Reactive power F5 Average Wind Speed Average Plant Atmospheric Pressure (Bar) Average Plant Temperature (Celsius) Status: 138 kV line breaker 34.5 kV breakerFl 34.5 kV breakerF2 34.5 kV breakerF3 34.5 kV breakerF4 34.5 kV breakerF5 6.1.1.7 Substation Requirements Q810 Collector Station The followingmajor equipment has been identified as being required and may change during detailed design: 3 -138 kV CT/VT combination metering units 1 -Control house The Interconnection Customer will provide a separate graded,groundedand fenced area along the perimeter of the Interconnection Customer's GeneratingFacility for the Transmission Provider to install a control house for metering equipment.This area will share a fence and ground grid with the Generating Facility and have separate,unencumbered access for the Transmission Provider. DC power for the control house will be supplied by the Transmission Provider.AC station service for the control house will be provided by the Interconnection Customer. Q715 Collector Station The followingmajor equipment has been identified as being required and may change during detailed design: 3 -138 kV CT/VT combination metering units Page 7 February 9,2018 Q0810 V PAC I F\CORP System impact Study Report 6.1.1.8 Communication Requirements The Transmission Provider will need to make minor modifications at its primary and secondary control centers to account for the additional generation of this phase in addition to the Q0715 project. 6.1.1.9 Metering Requirements InterchangeMetering -00715 POI substation: The Q0715 generation metering to be located at the Q0715 POI substation will be reassigned as an interconnection customer intertie with the Transmission provider for the combined Q0715 and Q0810 generation projects Q0715 and Q0810 collector substations: The generationand backfeed metering for both Q0715 and Q0810 projects will be located at the Interconnection Customers'respective collector substations.The generation metering will be located at the 138 kV high side of the Interconnection Customer's transformers and will be loss adjusted to the Transmission Provider's Q0715 POI substation. The Transmission Provider will specify and order all interconnection revenue metering equipment,includingthe 138 kV instrument transformers,metering panels,junction boxes,and secondary metering wire.The current transformers shall be extended range for high accuracy metering with current ratio of 500/5 (0.15%extended range accuracy).The voltage transformers will have a voltage ratio of 700/1 (0.3%accuracy). The metering design package will include four revenue quality meters and supporting hardware. The meters will output DNP real-time digital data terminated at a metering interposition block. The metering design package will include all SCADA metering data terminated at a metering interposition block.The metering data will include bidirectional KWH and KVARH revenue quantities.The metering data will also include PF,MW,MVAR,MVA,per phase voltages,and per phase amps.The interconnection customer may request data outputs from the meters,but the request must be made prior to final design. An Ethernet phone line is required for retail sales and generationaccounting via the MV-90 meter data management system. Station Service/Construction Power Prior to construction,Interconnection Customer must arrange construction power with the Transmission Provider.The metering shall conform to the Six State Electric Service Requirements manual as the site is within the Transmission Provider's service territory. Please note that prior to back feed,Interconnection Customer must arrange transmission retail meter service for electricityconsumed by the Project and arrange back-up station service for power that will be drawn from the transmission or distribution line when the Project is not generatmg. Page 8 February 9,2018 Q0810 V PAC I F\CORP System impact Study Report Interconnection Customer must call the PCCC Solution Center at 1-800-625-6078to arrange this service.Approval for back feed is contingent upon obtaining station service 6.1.2 Cost Estimate The followingestimate represents only scopes of work that will be performed by the Transmission Provider.Costs for any work being performed by the Interconnection Customer are not included. Direct Assigned Q0810 Collector Substation $413,000 Metering and Control House Q0715 Collector Substation $413,000 Meteringand Control House Q0715 Point of Interconnection Substation $30,000 Relay and Communication Modifications Transmission Provider Control Centers $13,000 Communication Modifications Total Direct Assigned $869,000 Network Upgrades Ben Lomond-Naughton#1 Transmission Line $25,785,000 Remove from existing double circuit and construct new 7 mile line Grand Total $26,654,000 *Any distribution line modifications identified in this report will require a field visit analysis in order to obtain a more thorough understandingof the specific requirements.The estimate provided above for this work could change substantially based on the results of this analysis.Until this field analysis is performed the Transmission Provider must develop the project schedule using conservative assumptions.The Interconnection Customer may request that the Transmission Provider perform this field analysis,at the Interconnection Customer's expense,prior to the execution of an Interconnection Agreement in order to obtain more cost and schedule certainty. Note:Costs for any excavation,duct installation and easements shall be borne by the Interconnection Customer and are not included in this estimate.This estimate is as accurate as possibly given the level of detailed study that has been completed to date and approximates the costs incurred by Transmission Provider to interconnect this GeneratorFacility to Transmission Provider's electrical distribution or transmission system.A more detailed estimate will be calculated during the Facilities Study.The Interconnection Customer will be responsible for all actual costs,regardless of the estimated costs communicated to or approvedby the Interconnection Customer. Page 9 February 9,2018 Q0810 V PAC I F\CORP System impact Study Report 6.1.3 Schedule The Transmission Provider estimates it will require approximately 24-30 months to permit,design, procure and construct the facilities described in the Energy Resource sections of this report followingthe execution of an Interconnection Agreement.The schedule will be further developed and optimized during the Facilities Study. Please note,the time required to perform the scope of work identified in this report appears to result in a timeframe that does not support the Interconnection Customer's requested Commercial Operation date of July 1,2019. 6.1.4 Maximum Amount of Power that can be delivered into Network Load,with No Transmission Modifications (for informational purposes only) One hundred one (101)MW can be delivered on a firm basis to the Transmission Provider's network loads assuming all requirements outlined in this report are complete and all requirements of Q0786 are complete. 6.1.5 Additional Transmission Modifications Required to Deliver 100%of the Power into Network Load (for informational purposes only) See section 6.1.1.2. 7.0 NETWORK RESOURCE(NR)INTERCONNECTION SERVICE Network Resource Interconnection Service allows the Interconnection Customer to integrate its Generating Facility with the Transmission Provider's Transmission System in a manner comparable to that in which the Transmission Provider integrates its generating facilities to serve native load customers.The transmission system is studied under a variety of severely stressed conditions in order to determine the transmission modifications which are necessary in order to deliver the aggregate generation in the area of the Point of Interconnection to the Transmission Provider's aggregate load.Network Resource Interconnection Service in and of itself does not convey transmission service. 7.1.1 Requirements 7.1.1.1 GeneratingFacility Modifications See Section 6.1.1.1 7.1.1.2 Transmission System Modifications See Section 6.1.1.2 7.1.2 Cost Estimate No additional costs are anticipated other than those listed in section 6.1.2. 7.1.3 Schedule See section 6.1.3. Page 10 February 9,2018 Q0810 Y PACIFICORP System Impact Study Report 8.0 PARTICIPATION BY AFFECTED SYSTEMS Transmission Provider has identified the followingaffected systems:None. 9.0 APPENDICES Appendix 1:Higher Priority (Prior Queued)Requests Appendix 2:Property Requirements Appendix 3:Study Results Page 11 February 9,2018 Q0810 Y PACIFICORP System Impact Study Report 9.1 Appendix1:HigherPriority (Prior Queued)Requests All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are identified below.If any of these requests are materiallymodified or withdrawn,the Transmission Provider reserves the right to restudy this request,as the results and conclusions containedwithin this study could significantlychange. Transmission/GenerationInterconnection Queue Requests considered: Q0715 (120 MW) Q0720 (80 MW)-QF Q0786 (100 MW)-ER/NR Page 12 February 9,2018 Q0810 V PAC I F\CORP System impact Study Report 9.2 Appendix2:Property Requirements Property Requirementsfor Point of Interconnection Substation Requirementsfor rights of way easements Rights of way easements will be acquired by the Interconnection Customer in the Transmission Provider's name for the construction,reconstruction,operation,maintenance,repair,replacement and removal of Transmission Provider's Interconnection Facilities that will be owned and operated by PacifiCorp.Interconnection Customer will acquire all necessary permits for the project and will obtain rights of way easements for the project on Transmission Provider's easement form. Real Property Requirementsfor Point of Interconnection Substation Real property for a point of interconnection substation will be acquired by an Interconnection Customer to accommodate the Interconnection Customer's project.The real property must be acceptable to Transmission Provider.Interconnection Customer will acquire fee ownership for interconnection substation unless Transmission Provider determines that other than fee ownership is acceptable;however,the form and instrument of such rights will be at Transmission Provider's sole discretion.Any land rights that Interconnection Customer is planning to retain as part of a fee property conveyance will be identified in advance to Transmission Provider and are subject to the Transmission Provider's approval. The Interconnection Customer must obtain all permits required by all relevantjurisdictionsfor the planned use includingbut not limited to conditional use permits,Certificates of Public Convenience and Necessity,California Environmental QualityAct,as well as all construction permits for the project. Interconnection Customer will not be reimbursed through network upgrades for more than the market value of the property. As a minimum,real property must be environmentally,physically,and operationally acceptable to Transmission Provider.The real property shall be a permitted or permittable use in all zoning districts.The Interconnection Customer shall provide Transmission Provider with a title report and shall transfer property without any material defects of title or other encumbrances that are not acceptable to Transmission Provider.Property lines shall be surveyed and show all encumbrances,encroachments,and roads. Examples of potentiallyunacceptable environmental,physical,or operational conditions could include but are not limited to: 1.Environmental:known contamination of site;evidence of environmental contamination by any dangerous,hazardous or toxic materials as defined by any governmental agency;violation of building,health,safety,environmental,fire, land use,zoning or other such regulation;violation of ordinances or statutes of any governmental entities having jurisdiction over the property;underground or above ground storage tanks in area;known remediation sites on property;ongoing mitigation activities or monitoring activities;asbestos;lead-based paint,etc.A Page 13 February 9,2018 Q0810 Y PACIFICORP System Impact Study Report phase I environmental study is required for land being acquired in fee by the Transmission Provider unless waived by Transmission Provider. 2.Physical:inadequate site drainage;proximity to flood zone;erosion issues; wetland overlays;threatened and endangered species;archeological or culturally sensitive areas;inadequate sub-surface elements,etc.Transmission Provider may require Interconnection Customer to procure various studies and surveys as determined necessary by Transmission Provider. Operational:inadequate access for Transmission Provider's equipment and vehicles;existing structures on land that require removal prior to building of substation;ongoing maintenance for landscaping or extensive landscape requirements;ongoing homeowner's or other requirements or restrictions (e.g.,Covenants,Codes and Restrictions,deed restrictions,etc.)on property which are not acceptable to the Transmission Provider. Page 14 February 9,2018 Q0810 Y PACIFICORP System Impact Study Report 9.3 Appendix3:Study Results Power Flow Study Results A Western Electricity Coordinating Council (WECC)approved 2021-22 Heavy winter and 2022 Heavy summer cases were used to perform the power flow studies using PSS/E version 33.7. Power flow studies were performed on both peak and off-peak load cases.The off-peak load case was chosen to demonstrate the stress on the higher kV transmission system under light load conditions.The Rock Springs/Firehole West path was stressed to 640 MW.The local 230 kV and 138 kV transmission system outages were considered during the study. N-0 Results:No N-0 thermal or voltage issues were observed in the studies. N-1 Results:Assuming the 2.35 miles of the Railroad -Croydon 138 kV line is rebuilt and the jumpers at Canyon Creek and Carter Creek are upgradedby the prior Q0786 project,no additional issues were observed. N-2 Results: The credible N-2 of the Ben Lomond -Birch Creek and Ben Lomond -Naughton 230 kV lines can overload the Naughton -Treasureton 230 kV line and/or the Railroad -Croydon -Coalville -Silver Creek -Synderville -Cottonwood 138 kV lines.The Ben Lomond -Birch Creek and Ben Lomond -Naughton 230 kV circuits share common structures for approximately eight miles. The project cannot be integrated into the Naughton Remedial Action Scheme (RAS)as it exceeds the maximum amount of generation tripping (600-700 MW)to be dropped as a part of RAS. Therefore,elimination of the specific 230 kV N-2 is required.As there is a double circuit 138 line that runs parallel to the 230 kV double circuit in the area,one of the 230 kV circuits can be swapped with one of the 138 kV circuits,reducing the impact of this outage.Approximatelyseven miles of structures on the 138 kV segment would need to be replaced to accommodate the weight of the 230 kV circuit. Page 15 February 9,2018 Q0810