Loading...
HomeMy WebLinkAbout20180307PAC to Staff UT Q810FEAS.pdfPACIFICORP Large Generator Interconnection Feasibility Study Report Completed for ("Interconnection Customer") Q0810 Proposed Primary Point of Interconnection Q0715 Point of Interconnection Substation (shared tie-line with Q0715) Proposed Alternate Point of Interconnection Q0715 Point of Interconnection Substation (separate tie-line from Q0715) September 8,2017 V PACF I CORP s...;g¡¡¡gystudy Report TABLE OF CONTENTS 1.0 DESCRIPTION OF THE GENERATING FACILITY ..............................................................1 2.0 SCOPEOFTHESTUDY ...............................................................................................................1 3.0 TYPE OF INTERCONNECTION SERVICE..............................................................................1 4.0 DESCRIPTION OF PROPOSED INTERCONNECTION.........................................................1 4.1 OTHER OPTIONSCONSIDERED(NERC REQUIREMENT)...............................................2 5.0 STUDY A SSUMPTI ONS ...............................................................................................................4 6.0 ENERGY RESOURCE(ER)INTERCONNECTION SERVICE..............................................5 6.1 REQUIREMENTS-PRIMARY POINT OF INTERCONNECTION...............................................5 6 1.1 Generating Facility Modifications............................................5 6 1.2 Transmission System Modifications.............................................7 6 1.3 Existing Circuit Breaker Upgrades -Short Circuit...........................................7 6 1.4 Protection Requirements...........................................7 6 1.5 Data (RTU)Requirements .........................................................................7 6.2 COST ESTIMATE -PRIMARY POINT OF INTERCONNECTION.................................................S 6.3 SCHEDULE-PRIMARY POINT OF INTERCONNECTION.....................................................................9 6 3.1 Maximum Amount o Power that can be deliveredinto NetworkLoad,with No Transmission Modifications(for in ormationalpurposes only)............................................................................9 6 3.2 Additional Transmission ModificationsRequired to Deliver 100%o the Power into NetworkLoad (or in ormationalpurposes only)...................................................................9 6.4 REQUIREMENTS-SECONDARYPOINT OF INTERCONNECTION ..............................................9 6 4.1 Generating Facility Modifications............................................9 6 4.2 Transmission System Modifications..............................................11 6 4.3 Existing Circuit Breaker Upgrades -Short Circuit............................................12 6 4.4 Protection Requirements...........................................12 6 4.5 Data (RTU)Requirements ..............................................................................13 6.5 COST ESTIMATE -SECONDARYPOINT OF INTERCONNECTION...............................................14 6.6 SCHEDULE-SECONDARYPOINT OF INTERCONNECTION ...............................................................14 6 6 1 Maximum Amount o Power that can be deliveredinto NetworkLoad,with No Transmission Modifications(or in ormationalpurposes only).........................................................................15 6 6 2 Additional Transmission ModificationsRequired to Deliver 100%o the Power into NetworkLoadin addition to the ER requirements and with all assumed upgrades in service(forin ormational purposes only).............................................................15 7.0 NETWORK RESOURCE (NR)INTERCONNECTION SERVICE .......................................15 7.1 REQUIREMENTS................................................15 7 1.1 Generating Facility Modifications............................................15 7 1.2 Transmission System Modifications...........................................15 7.2 COST ESTIMATE................................................15 7.3 SCHEDULE..............................................16 8.0 PARTICIPATION BY AFFE CTED SYSTEMS........................................................................16 9.0 APPEND ICES ...............................................................................................................................16 9.1 APPENDIX 1:HIGHER PRIORITY REQUESTS................................................17 9.2 APPENDIX 2:PROPERTYREQUIREMENTS..............................................18 9.3 APPENDIX 3:STUDY RESULTS ..............................................20 Page i September 8,,2017 ,Q0810 Y PACIFICORP Feasibility Study Report 1.0 DESCRIPTION OF THE GENERATING FACILITY ("InterconnectionCustomer")proposed interconnecting 101 MW of new generationto the Point of Interconnection substation proposed to be constructed on PacifiCorp's ("Transmission Provider")Whitneytap of the Canyon Compression-Railroad as part of the Q0715 project located in Uinta County,Wyoming.The Interconnection Customer's primary Point of Interconnection is an addition to the Q0715 project.The Interconnection Customer has also proposed interconnecting the new generationin a new position at the Q0715 Point of Interconnection substation.The project ("Project")will consist of 44 GeneralElectric 2.3 MW turbines for a total output of 101 MW.The requested commercial operation date is July 1,2019 Interconnection Customer will NOT operate this generator as a Qualified Facility as defined by the Public Utility Regulatory Policies Act of 1978 (PURPA). The Transmission Provider has assigned the Project "Q0810." 2.0 SCOPE OF THE STUDY The Interconnection Feasibility Study ("Study")report shall provide the followinganalyses for the purpose of identifying any potential adverse system impacts that would result from the interconnection of the GeneratingFacility as proposed: preliminaryidentification of any circuit breaker short circuit capability limits exceeded as a result of the interconnection; preliminaryidentification of any thermal overload or voltage limit violations resulting from the interconnection;and preliminarydescription and non-binding estimated cost of facilities required to interconnect the Generating Facility to the Transmission Provider's Distribution or Transmission System and to address the identified short circuit and power flow issues. 3.0 TYPE OF INTERCONNECTION SERVICE The Interconnection Customer has selected Network Resource (NR)Interconnection Service,but has also elected to have the interconnection studied as an Energy Resource (ER).The Interconnection Customer will select NR or ER prior to the facilities study. 4.0 DESCRIPTION OF PROPOSED INTERCONNECTION The Interconnection Customer's proposed GeneratingFacility is to be interconnecteddirectly with the Q0715 project via the same interconnection point.Figure 1 below,is a one-line diagram that illustrates the interconnection of the proposed Generating Facility to the Transmission Provider's system at the primary Point of Interconnection. Page 1 September 8,,2017 ,Q0810 V PAGRCORP s...ystudyReport Whitney Ca on i CanyonCompression Q0715 POI Sub a ion Interconnection 138 kV Railroad Change of Ownership 6 Miles 68/90/112MVA138-34.5kV Z =9 % Q0810 34.5 kVCollector Substation 34.5 kV C le tor Q0715 Collector Substation Figure 1:Simplified System One Line Diagram -Primary Point ofInterconnection 4.1 Other Options Considered (NERC Requirement) The followingalternative Point of Interconnection will be considered in this report: The Interconnection Customer's proposed GeneratingFacility is to be interconnectedvia a new line position in the Point of Interconnection substation proposed to be constructed by the Q0715 project. Page 2 September 8,,2017 ,Q0810 V PACR CORP s...;g¡¡¡¡y study Report Figure 2 below,is a one-line diagram that illustrates the interconnection of the proposed Generating Facility to the Transmission Provider's system at the alternate Point of Interconnection. Whitney Canyon i Canyon Compression /Q0715 POI 138 kV Q0715Railroad Change of Ownership 6 Miles 68/90/112 MVA 138 -34 5 kV Z =9 % Q0810 34.5 kVCollector Substation Figure 2:Simplified System One Line Diagram -Alternate Point ofInterconnection Page 3 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report 5.0 STUDYASSUMPTIONS All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are listed in Appendix 1.If any of these requests are withdrawn, Transmission Provider reserves the right to restudy this request,and the results and conclusions could significantlychange. For study purposes there are two separate queues: o Transmission Service Queue:to the extent practical,all Network Upgrades that are required to accommodate active transmission service requests will be modeled in this study. o Generation Interconnection Queue:Interconnection Facilities associated with higher queue interconnection requests will be modeled in this study. The Interconnection Customer's request for Energy or Network Resource Interconnection Service in and of itself does not convey transmission service.Only a Network Customer may make a request to designate a generatingresource as a Network Resource.Because the queue of higher priority transmission service requests may be different when a Network Customer requests Network Resource designation for this Generating Facility,the available capacity or transmission modifications,if any,necessary to provide Network Resource Interconnection Service may be significantlydifferent.Therefore,the Interconnection Customer should regard the results of this study as informational rather than final. Under normal conditions,the Transmission Provider does not dispatch or otherwise directly control or regulate the output of generation facilities.Therefore,the need for transmission modifications,if any,which are required to provide Network Resource Interconnection Service will be evaluated on the basis of 100 percent deliverability (i.e.,no displacement of other resources in the same area). This study assumes the Project will be integrated into Transmission Provider's system at agreed upon and/or proposed Point of Interconnection ("POI"). The Interconnection Customer will construct and own any facilities required between the POI and the Project unless specifically identified by the Transmission Provider. Line reconductor or fiber underbuild required on existing poles will be assumed to follow the most direct path on the Transmission Provider's system.If during detailed design the path must be modified it may result in additional cost and timing delays for the Interconnection Customer's project. Generatortripping may be required for certain outages. All facilities will meet or exceed the minimum Western Electricity Coordinating Council ("WECC"),North American Electric ReliabilityCorporation ("NERC"),and the Transmission Provider's performance and design standards. All system improvements associated with the prior queued projects are in service before Q0810. The Q0715 project must be complete prior to the interconnection of this Project. The Energy Gateway West (2024)and Energy Gateway South (2024)projects are assumed to be in service;the Dave Johnston to Amasa to Aeolus (future)230 kV line is assumed to be rebuilt as part of the Gateway projects.Note that these dates are inconsistent with the Q0810 Project planned in-service date. Page 4 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report A Remedial Action Scheme ("RAS")that will drop up to 600 MW of generation (whichmay include this project)for the followingoutages is assumed to be in-service: o Aeolus -Anticline 500 kV line o Anticline -Populus 500 kV line o Aeolus -Clover 500 kV line o Clover 500/345 kV auto transformer This report is based on information available at the time of the study.It is the Interconnection Customer's responsibility to check the Transmission Provider's web site regularly for Transmission System updates at http://www.pacificorp.com/tran.html 6.0 ENERGY RESOURCE(ER)INTERCONNECTION SERVICE Energy Resource Interconnection Service allows the Interconnection Customer to connect its Generating Facility to the Transmission Provider's Transmission System and to be eligible to deliver electric output using firm or non-firm transmission capacity on an as available basis. 6.1 Requirements-PrimaryPoint of Interconnection 6.1.1 Generating Facility Modifications All interconnecting synchronous and non-synchronous generators are required to design their Generating Facilities with reactive power capabilities necessary to operate within the full power factor range of 0.95 leading to 0.95 lagging.This power factor range shall be dynamic and can be met using a combination of the inherent dynamic reactive power capability of the generator or inverter,dynamic reactive power devices and static reactive power devices to make up for losses.For synchronous generators,the power factor requirement is to be measured at the Point of Interconnection.For non-synchronous generators,the power factor requirement is to be measured at the high-side of the generator substation. The generating facility must provide dynamic reactive power to the system in support of both voltage scheduling and contingency events that require transient voltage support,and must be able to provide reactive capability over the full range of real power output.If the generating facility is not capable of providing positive reactive support (i.e.,supplying reactive power to the system)immediately followingthe removal of a fault or other transient low voltage perturbations,the facility must be required to add dynamic voltage support equipment.These additional dynamic reactive devices shall have correct protection settings such that the devices will remain on line and active during and immediately followinga fault event. Generators shall be equipped with automatic voltage-control equipment and normally operated with the voltage regulation control mode enabled unless written authorization (or directive)from the Grid Operator is given to operate in another control mode (e.g.constant power factor control).The control mode of generatingunits shall be accuratelyrepresented in operating studies.The generators shall be capable of operating continuouslyat their maximum power output at its rated field current within +/-5%of its rated terminal voltage. Generating Facilities capable of operating with a voltage droop are required to do so. Page 5 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report Voltage droop control enables proportionate reactive power sharing among generation facilities.Studies will be required to coordinate voltage droop settings if there are other facilities in the area.It will be the Interconnection Customer's responsibility to ensure that a voltage coordination study is performed,in coordination with Transmission Provider,and implemented with appropriate coordination settings prior to unit testing. As required by NERC standard VAR-001-la,the Transmission Provider will provide a voltage schedule for the Point of Interconnection.In general,Generating Facilities should be operated so as to maintain the voltage at the Point of Interconnection,or other designated point as deemed appropriatedby Transmission Provider.The Transmission Provider may also specify a voltage and/or reactive power bandwidth as needed to coordinate with upstream voltage control devices such as on-load tap changers.At the Transmission Provider's discretion,these values might be adjusted depending on operating conditions. For areas with multiple generating facilities additional studies may be required to determine whether or not critical interactions,includingbut not limited to control systems, exist.These studies,to be coordinated with Transmission Provider,will be the responsibility of the Interconnection Customer.If the need for a master controller is identified,the cost and all related installation requirements will be the responsibility of the Interconnection Customer.Participation by the generation facility in subsequent interaction/coordination studies will be required pre-and post-commercial operation in order ensure system reliability. To facilitate collection and validation of accurate modeling data to meet NERC modeling standards,PacifiCorp,as the Planning Coordinator,requires Phasor Measurement Units (PMUs)at all new GeneratingFacilities with an individual or aggregate nameplate capacity of 75 MVA or greater.In addition to owning and maintaining the PMU,the Generating Facility will be responsible for collecting,storing and retrieving data as requested by the Planning Coordinator.Data must be collected and be able to stream to Planning Coordinator for each of the GeneratorFacility's step-up transformers measured on the low side of the GSU at a sample rate of at least 30 samples per second and synchronizedwithin +/-2 milliseconds of the Coordinated Universal Time (UTC).Initially,the followingdata must be collected: Three phase voltage and voltage angle (analog) Three phase current (analog) Data requirements are subject to change as deemed necessary to comply with local and federal regulations.All generators must meet the Federal Energy Regulatory Committee (FERC)and WECC low voltage ride-through requirements as specified in the interconnection agreement.As the Transmission Provider cannot submit a user written model to WECC for inclusion in base cases,a standard model from the WECC Approved Dynamic Model Library is required 180 days prior to trial operation.The list of approved generator models is continuallyupdated and is available on the http://www.WECC.biz website. Page 6 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report 6.1.2 Transmission System Modifications No additional modifications to the POI substation are required beyond those identified by Q0715.The modifications identified in Q0715 must be completed prior to commissioning this facility. Modify the existing Naughton West RAS to integratethe Q0810 Project.If the average of the flows West of Naughton &West of Railroad is above approximately 1250 MW, Q0810 will be armed to trip for the N-1-1 and N-2 outages of either the Ben Lomond -Birch Creek and Ben Lomond -Naughton 230 kV lines or the Naughton -Birch Creek and Ben Lomond -Naughton 230 kV lines. o Capability to trip Q0810 Project if necessary under N-1-1 and N-2 outages described above. o Requires redundant communication from the RAS controller to the Project. All improvements below must be in service prior to this facility being commissioned: o The Energy Gateway West (2024)and Energy Gateway South (2024)projects o The Dave Johnston to Amasa to Aeolus (future)230 kV line must be rebuilt as part of the Gateway projects.(Note that these dates are inconsistent with the Q0810 Project planned in-service date.) o A Remedial Action Scheme ("RAS")that will drop up to 600 MW of generation (whichmay include this project)for the followingoutages: Aeolus -Anticline 500 kV line Anticline -Populus 500 kV line Aeolus -Clover 500 kV line Clover 500/345 kV auto transformer 6.1.3 ExistingCircuit Breaker Upgrades -Short Circuit The increase in the fault duty on the system as a result of the addition of the Generating Facility with 44 -GE 2.3 MW wind turbine generators fed through 44 -2.5 MVA 34.5 kV -690 V transformers with 5.75%impedance then fed through one 138 -34.5kV 68/90/112 MVA step-up transformer with 9%impedance will not push the fault duty above the interrupting rating of any of the Transmission Provider's existing fault interrupting equipment. 6.1.4 Protection Requirements. The Interconnection Customer's line relays at the collector substation will need to respond to the combination of the 138 kV fault current being contributed from both the Q0715 and the Q0810 projects for faults on the 138 kV tie line and trip both 138 kV breakers for the two projects.The tie line relays at the Q0715 POI substation's voltage and frequency elements will trip the tie line 138 kV breakers for under or over out of tolerance conditions. Those relays will also operate in a step distance mode to respond to faults on the tie line to the collector substation. 6.1.5 Data (RTU)Requirements Data for the operation of the power system will be needed from the collector substation. Listed is the data that will be acquired from the collector substation. Page 7 September 8,,2017 ,Q0810 V PAGRCORP s...ystudyReport From the Q0715 collector substation: Analogs: Net GenerationMW Net GeneratorMVAR Interchangemetering kWH From the Q0810 collector substation: Analogs: Net GenerationMW Net GeneratorMVAR Interchangemetering kWH 34.5 kV Real power Fl 34.5 kV Reactive power Fl 34.5 kV Real power F2 34.5 kV Reactive power F2 34.5 kV Real power F3 34.5 kV Reactive power F3 34.5 kV Real power F4 34.5 kV Reactive power F4 34.5 kV Real power F5 34.5 kV Reactive power F5 Average Wind Speed Average Plant Atmospheric Pressure (Bar) ·Average Plant Temperature (Celsius) Status: 138 kV line breaker 34.5 kV breakerFl 34.5 kV breakerF2 34.5 kV breakerF3 34.5 kV breakerF4 34.5 kV breakerF5 6.2 Cost Estimate -Primary Point of Interconnection The followingestimate represents only scopes of work that will be performed by the Transmission Provider.Costs for any work being performed by the Interconnection Customer are not included. Direct Assigned Q0810 Collector Substation $413,000 Metering,Communication Coordination,Control House Q0715 Collector Substation $413,000 Metering,Communication Coordination,Control House Page 8 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report Q0715 Point of Interconnection Substation $30,000 Relay and Communication Modifications Naughton Substation $30,000 ModifyRAS Grand Total $886,000 Note:Costs for any excavation,duct installation and easements shall be borne by the Interconnection Customer and are not included in this estimate.This estimate is as accurate as possibly given the level of detailed study that has been completed to date and approximates the costs incurred by Transmission Provider to interconnect this GeneratorFacility to Transmission Provider's electrical distribution or transmission system.A more detailed estimate will be calculatedduring the System Impact Study.The Interconnection Customer will be responsible for all actual costs,regardless of the estimated costs communicated to or approved by the Interconnection Customer. 6.3 Schedule -PrimaryPoint of Interconnection The Transmission Provider estimates it will require approximately 12 months to design, procure and construct the facilities described in the Energy Resource sections of this report followingthe execution of an Interconnection Agreement.The schedule will be further developedand optimized during the System Impact Study. Please note,the Transmission Provider's Gateway Projects,which are required for this Project, are currently assumed to be in service in 2024 which does not support the Interconnection Customer's requested commercial operation date of July 1,2019.In addition,the Interconnection Facilities described and required for Q715 must be in-service either prior to, or concurrent with,Q810. 6.3.1 Maximum Amount of Power that can be delivered into Network Load,with No Transmission Modifications (for informational purposes only). One hundred one (101)MW can be delivered on a firm basis to the Transmission Provider's network loads after the system improvements outlined in section 6.1.2 are done and assuming all improvements identified in section 5.0 are in service. 6.3.2 Additional Transmission Modifications Required to Deliver 100%of the Power into Network Load (for informational purposes only) Assuming the improvements identified under the Section 5.0 Study Assumptions of this report are in service,no additional modifications beyond improvementsmentioned in 6.1.2 are required. 6.4 Requirements-Secondary Point of Interconnection 6.4.1 Generating Facility Modifications All interconnecting synchronous and non-synchronous generators are required to design their Generating Facilities with reactive power capabilities necessary to operate within the Page 9 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report full power factor range of 0.95 leading to 0.95 lagging.This power factor range shall be dynamic and can be met using a combination of the inherent dynamic reactive power capability of the generator or inverter,dynamic reactive power devices and static reactive power devices to make up for losses.For synchronous generators,the power factor requirement is to be measured at the Point of Interconnection.For non-synchronous generators,the power factor requirement is to be measured at the high-side of the generator substation.The generating facility must provide dynamic reactive power to the system in support of both voltage scheduling and contingency events that require transient voltage support,and must be able to provide reactive capability over the full range of real power output. If the generating facility is not capable of providing positive reactive support (i.e., supplying reactive power to the system)immediately followingthe removal of a fault or other transient low voltage perturbations,the facility must be required to add dynamic voltage support equipment.These additional dynamic reactive devices shall have correct protection settings such that the devices will remain on line and active during and immediately followinga fault event.Generators shall be equippedwith automatic voltage- control equipment and normallyoperated with the voltage regulation control mode enabled unless written authorization (or directive)from the Grid Operator is given to operate in another control mode (e.g.constant power factor control).The control mode of generating units shall be accurately represented in operating studies.The generators shall be capable of operating continuouslyat their maximum power output at its rated field current within +/-5%of its rated terminal voltage. As required by NERC standard VAR-001-la,the Transmission Provider will provide a voltage schedule for the Point of Interconnection.In general,Generating Facilities should be operated so as to maintain the voltage at the Point of Interconnection,or other designated point as deemed appropriated by Transmission Provider,between 1.00 per unit to 1.04 per unit.The Transmission Provider may also specify a voltage and/or reactive power bandwidth as needed to coordinate with upstream voltage control devices such as on-load tap changers.At the Transmission Provider's discretion,these values might be adjusted depending on operating conditions.Generating Facilities capable of operating with a voltage droop are required to do so.Voltage droop control enables proportionate reactive power sharing among generation facilities.Studies will be required to coordinate voltage droop settings if there are other facilities in the area.It will be the Interconnection Customer's responsibility to ensure that a voltage coordination study is performed,in coordination with Transmission Provider,and implemented with appropriate coordination settmgs prior to unit testing. For areas with multiple generating facilities additional studies may be required to determine whether or not critical interactions,includingbut not limited to control systems, exist.These studies,to be coordinated with Transmission Provider,will be the responsibility of the Interconnection Customer.If the need for a master controller is identified,the cost and all related installation requirements will be the responsibility of the Interconnection Customer.Participation by the generation facility in subsequent Page 10 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report interaction/coordination studies will be required pre-and post-commercial operation in order ensure system reliability. Phasor Measurement Units (PMUs)will be required at any Generating Facilities with an individual or aggregate nameplate capacity of 75 MVA or greater.To facilitate collection and validation of accurate modeling data to meet NERC modeling standards,PacifiCorp, as the Planning Coordinator,requires Phasor Measurement Units (PMUs)at all new Generating Facilities with an individual or aggregate nameplate capacity of 75 MVA or greater.In addition to owning and maintaining the PMU,the Generating Facility will be responsible for collecting,storing and retrieving data as requested by the Planning Coordinator.Data must be collected and be able to stream to Planning Coordinator for each of the Generator Facility's step-up transformers measured on the low side of the GSU at a sample rate of at least 30 samples per second and synchronized within +/-2 milliseconds of the Coordinated Universal Time (UTC).Initially,the followingdata must be collected: Three phase voltage and voltage angle (analog) Three phase current (analog) Data requirements are subject to change as deemed necessary to comply with local and federal regulations.All generators must meet the Federal Energy Regulatory Committee (FERC)and WECC low voltage ride-through requirements as specified in the interconnection agreement.The Interconnection Customer is responsible for the protection of the transmission line between the Generating Facility and the POI substation.In order to provide this protection the Interconnection Customer shall construct and own a tie-line substation to be located at the change of ownership (separate fenced facility adjacent to the Transmission Provider's POI substation)and include an Interconnection Customer owned protective device and associated transmission line relaying/communications.The ground grids of the Transmission Provider's POI substation and the Interconnection Customer's tie-line substation will be connected to support the use of a bus differential protection scheme which will protect the overhead bus connection between the two facilities.As the Transmission Provider cannot submit a user written model to WECC for inclusion in base cases,a standard model from the WECC Approved Dynamic Model Library is required 180 days prior to trial operation.The list of approved generator models is continually updated and is available on the http://www.WECC.bizwebsite. 6.4.2 Transmission System Modifications (See Figure 2 for a one-line diagram of the POI and surrounding system) Install a 138 kV circuit breaker at the Q0715 POI substation to create a new bus position. Install a RMP 138 kV meter on the line between the POI and the tie-line substation (customer-owned). The modifications identified in Q0715 must be completed prior to commissioning this facility. Modify the existing Naughton West RAS to integratethe Q0810 Project.If the average of the flows West of Naughton &West of Railroad is above approximately 1250 MW, Page 11 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report Q0810 will be armed to trip for the N-1-1 and N-2 outages of either the Ben Lomond -Birch Creek and Ben Lomond -Naughton 230 kV lines or the Naughton -Birch Creek and Ben Lomond -Naughton 230 kV lines. o Capability to trip Q0810 Project if necessary under N-1-1 and N-2 outages described above. o Requires redundant communication from the RAS controller to the Project. All improvements below must be in service prior to this facility being commissioned: o The Energy Gateway West (2024)and Energy Gateway South (2024)projects o The Dave Johnston to Amasa to Aeolus (future)230 kV line must be rebuilt as part of the Gatewayprojects.(Note that these dates are inconsistent with the Q0810 Project planned in-service date.) o A Remedial Action Scheme ("RAS")that will drop up to 600 MW of generation (whichmay include this project)for the followingoutages: Aeolus -Anticline 500 kV line Anticline -Populus 500 kV line Aeolus -Clover 500 kV line Clover 500/345 kV auto transformer 6.4.3 ExistingCircuit Breaker Upgrades -Short Circuit The increase in the fault duty on the system as a result of the addition of the Generating Facility with 44 -GE 2.3 MW wind turbine generators fed through 44 -2.5 MVA 34.5 kV -690 V transformers with 5.75%impedance then fed through one 138 -34.5kV 68/90/112 MVA step-up transformer with 9%impedance will not push the fault duty above the interrupting rating of any of the Transmission Provider's existing fault interrupting equipment. 6.4.4 Protection Requirements. The ground mats of the Interconnection Customer's tie line substation and the Q0715 POI substation must be tied together so that metallic control cables can be used between the two facilities.Bus differential relays will be applied to detect faults on this connection. With this arrangement the Interconnection Customer must install line relays systems that will detect and clear all faults on the tie lines in 5 cycles or less.A set of non-pilot step distance line relays that will detect faults on the tie line will also be applied at the Q0715 POI substation.Should the Interconnection Customer desire a potential alternative to the tie line substation in order to provide adequate protection to its tie line,the Interconnection Customer may petition the Transmission Provider for an exemption to this arrangement.The Transmission Provider must review and approve the Interconnection Customer's proposed alternative.Without approval of the proposed alternative the tie line substation configuration will be required.The Generation Interconnection Customer will still need is to supply and maintain sets of line relays to be installed at Q0810 collector substation that will detect faults on the 138 kV line back to the Q0715 POI substation. These line relays can be time coordinated with the relays detecting faults on the transmission network and will not communicate with the line relays to be installed at the Q0715 POI substation for the tie line. Page 12 September 8,,2017 ,Q0810 V PAC F1CO RP s..syg¡¡¡gy study Report Protective relay elements in the line relays at the Q0715 POI substation will monitor voltage and frequency.If the voltage,magnitude or frequency is outside of the normal operation range,this relay will trip the 138 kV breakers for the tie line at the Q0715 POI substation. A modification to the Naughton West RAS is planned for the Q0715 project.As part of that project the 138 kV breakers at the Q0715 POI substation on the tie line to that project will be tripped for the loss of transmission lines west of the Naughton.For this project signals will be added to the RAS to trip the breakers at the Q0715 POI substation for the tie line to the Q0810 collector substation. 6.4.5 Data (RTU)Requirements The RTU that is planned to be install in the new Q0715 POI substation which will make is possible for the Transmission Provider to remotely monitor and operate the breakers at the POI substation will be used to control and monitor the new 138 kV breaker at that substation.Data for the operation of the power system will also be needed from the Collector substation.In addition to the control and indication of the 138 kV breakers in POI substation the followingdata will be acquired through the RTU.Also listed is the data that will be acquired from the Collector substation. From the POI Substation: Analogs: Net GenerationMW Net GeneratorMVAR Interchangemetering kWH From the Q0810 collector substation: Analogs: 138 kV A phase voltage 138 kV B phase voltage 138 kV C phase voltage 34.5 kV Real power Fl 34.5 kV Reactive power Fl 34.5 kV Real power F2 34.5 kV Reactive power F2 34.5 kV Real power F3 34.5 kV Reactive power F3 34.5 kV Real power F4 34.5 kV Reactive power F4 34.5 kV Real power F5 34.5 kV Reactive power F5 Average Wind Speed Average Plant Atmospheric Pressure (Bar) ·Average Plant Temperature (Celsius) Page 13 September 8,,2017 ,Q0810 V PAGF\CORP s...ystudyReport Status: 138 kV line breaker 34.5 kV breakerFl 34.5 kV breakerF2 34.5 kV breakerF3 34.5 kV breakerF4 34.5 kV breakerF5 From the Q0810 tie line substation: Status: 138 kV breaker 6.5 Cost Estimate -Secondary Point of Interconnection The followingestimate represents only scopes of work that will be performed by the Transmission Provider.Costs for any work being performed by the Interconnection Customer are not included. Direct Assigned Q0810 Collector and Tie Line Substations $45,000 Communications and Protection &Control Coordination Q0715 POI Substation $1,800,000 Create line position,Metering,Communications and Protection &Control Naughton Substation $30,000 ModifyRAS Grand Total $1,875,000 Note:Costs for any excavation,duct installation and easements shall be borne by the Interconnection Customer and are not included in this estimate.This estimate is as accurate as possibly given the level of detailed study that has been completed to date and approximates the costs incurred by Transmission Provider to interconnect this GeneratorFacility to Transmission Provider's electrical distribution or transmission system.A more detailed estimate will be calculatedduring the System Impact Study.The Interconnection Customer will be responsible for all actual costs,regardless of the estimated costs communicated to or approved by the Interconnection Customer. 6.6 Schedule -Secondary Point of Interconnection The Transmission Provider estimates it will require approximately 24 months to design, procure and construct the facilities described in the Energy Resource sections of this report followingthe execution of an Interconnection Agreement.The schedule will be further developedand optimized during the System Impact Study. Page 14 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report Please note,the Transmission Provider's Gateway Projects,which are required for this Project, are currently assumed to be in service in 2024 which does not support the Interconnection Customer's requested commercial operation date of July 1,2019.In addition,the Interconnection Facilities described and required for Q715 must be in-service either prior to, or concurrent with,Q810. 6.6.1 Maximum Amount of Power that can be delivered into Network Load,with No Transmission Modifications (for informational purposes only). One hundred one (101)MW can be delivered on a firm basis to the Transmission Provider's network loads after the system improvements outlined in section 6.4.2 are done and assuming all improvements identified in section 5.0 are in service. 6.6.2 Additional Transmission Modifications Required to Deliver 100%of the Power into Network Load in addition to the ER requirements and with all assumed upgrades in service (for informational purposes only) Assuming the improvements identified under the Section 5.0 Study Assumptions of this report are in service,no additional modifications beyond improvementsmentioned in 6.4.2 are required. 7.0 NETWORK RESOURCE(NR)INTERCONNECTION SERVICE Network Resource Interconnection Service allows the Interconnection Customer to integrate its Generating Facility with the Transmission Provider's Transmission System in a manner comparable to that in which the Transmission Provider integrates its generating facilities to serve native load customers.The Transmission System is studied under a varietyof severely stressed conditions in order to determine the transmission modifications which are necessary in order to deliver the aggregate generationin the area of the POI to the Transmission Provider's aggregate load.Network Resource Interconnection Service in and of itself does not convey transmission service 7.1 Requirements(Primaryand Secondary POI) 7.1.1 Generating Facility Modifications (See section 6.1.1 or section 6.4.1 as applicable) 7.1.2 Transmission System Modifications (See section 6.1.2 or section 6.4.2 as applicable) 7.2 Cost Estimate No additional costs are anticipated should all improvements identified for Energy Resource Interconnection Service and all assumed improvements be completed for the applicable POI option. Page 15 September 8,,2017 ,Q0810 Y PACIFICORP Feasibility Study Report 7.3 Schedule Please note,the Transmission Provider's Gateway Projects,which are required for this Project, are currently assumed to be in service in 2024 which does not support the Interconnection Customer's requested commercial operation date of July 1,2019. 8.0 PARTICIPATION BY AFFECTED SYSTEMS Transmission Provider has identified the followingas Affected Systems:None 9.0 APPENDICES Appendix 1:Higher Priority Requests Appendix 2:Property Requirements Appendix 3:Study Results Page 16 September 8,,2017 ,Q0810 Y PACIFICORP Feasibility Study Report 9.1 Appendix1:HigherPriority Requests All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are identified below.If any of these requests are withdrawn,the Transmission Provider reserves the right to restudy this request,as the results and conclusions containedwithin this study could significantlychange. Transmission/GenerationInterconnection Queue Requests considered: Q0290 A-C (252 MW)-ER Q0409 A-D (320 MW)-QF Q0542 (240 MW)-QF Q0706 (250 MW)-ER Q0707 (250 MW)-ER Q0708 (250 MW)-ER Q0712 (520 MW)-ER Q0713 (350 MW)-ER Q0715 (120 MW)-ER Q0719 (280 MW)-QF Q0720 (80 MW)-QF Q0783 (30 MW)-QF Q0784 (80 MW)-ER/NR Q0785 (100 MW)-ER/NR Q0786 (100 MW)-ER/NR Q0789 (74.9 MW)-QF Q0795 (20 MW)-QF Q0796 (20 MW)-QF Q0801 (80 MW)-QF Q0802 (80 MW)-ER/NR Q0807 (75.9 MW)-QF Q0809 (20 MW)-QF Page 17 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report 9.2 Appendix2:Property Requirements Property Requirementsfor Point of Interconnection Substation Requirementsfor rights of way easements Rights of way easements will be acquired by the Interconnection Customer in the Transmission Provider's name for the construction,reconstruction,operation,maintenance,repair,replacement and removal of Transmission Provider's Interconnection Facilities that will be owned and operated by PacifiCorp.Interconnection Customer will acquire all necessary permits for the project and will obtain rights of way easements for the project on Transmission Provider's easement form. Real Property Requirementsfor Point of Interconnection Substation Real property for a point of interconnection substation will be acquired by an Interconnection Customer to accommodate the Interconnection Customer's project.The real property must be acceptable to Transmission Provider.Interconnection Customer will acquire fee ownership for interconnection substation unless Transmission Provider determines that other than fee ownership is acceptable;however,the form and instrument of such rights will be at Transmission Provider's sole discretion.Any land rights that Interconnection Customer is planning to retain as part of a fee property conveyance will be identified in advance to Transmission Provider and are subject to the Transmission Provider's approval. The Interconnection Customer must obtain all permits required by all relevantjurisdictionsfor the planned use includingbut not limited to conditional use permits,Certificates of Public Convenience and Necessity,California Environmental QualityAct,as well as all construction permits for the project. Interconnection Customer will not be reimbursed through network upgrades for more than the market value of the property. As a minimum,real property must be environmentally,physically,and operationally acceptable to Transmission Provider.The real property shall be a permitted or permittable use in all zoning districts.The Interconnection Customer shall provide Transmission Provider with a title report and shall transfer property without any material defects of title or other encumbrances that are not acceptable to Transmission Provider.Property lines shall be surveyed and show all encumbrances,encroachments,and roads. Examples of potentiallyunacceptable environmental,physical,or operational conditions could include but are not limited to: 1.Environmental:known contamination of site;evidence of environmental contamination by any dangerous,hazardous or toxic materials as defined by any governmental agency;violation of building,health,safety,environmental,fire, land use,zoning or other such regulation;violation of ordinances or statutes of any governmental entities having jurisdiction over the property;underground or above ground storage tanks in area;known remediation sites on property;ongoing Page 18 September 8,,2017 ,Q0810 Y PACIFICORP Feasibility Study Report mitigation activities or monitoring activities;asbestos;lead-based paint,etc.A phase I environmental study is required for land being acquired in fee by the Transmission Provider unless waived by Transmission Provider. 2.Physical:inadequate site drainage;proximity to flood zone;erosion issues; wetland overlays;threatened and endangered species;archeological or culturally sensitive areas;inadequate sub-surface elements,etc.Transmission Provider may require Interconnection Customer to procure various studies and surveys as determined necessary by Transmission Provider. Operational:inadequate access for Transmission Provider's equipment and vehicles;existing structures on land that require removal prior to building of substation;ongoing maintenance for landscaping or extensive landscape requirements;ongoing homeowner's or other requirements or restrictions (e.g.,Covenants,Codes and Restrictions,deed restrictions,etc.)on property which are not acceptable to the Transmission Provider. Page 19 September 8,,2017 ,Q0810 V PACI F\CORP s..syg¡¡¡gy study Report 9.3 Appendix3:Study Results Power Flow Study Results A Western Electricity Coordinating Council (WECC)approved 2016 Heavy Summer case was used to perform the power flow studies using PSS/E version 33.7.The 2016 Heavy Summer case was modified for the study.The study was performed assuming the Energy Gateway Projects are in-service.The local 230 kV and 138 kV transmission system outages were considered during the study. N-0 Results:Assuming Energy Gateway,the system improvements associated with the prior queued projects,and the system improvements deemed necessary in this study are in service,no N-0 thermal or voltage issues were observed in the studies. N-1 Results:Assuming Energy Gateway,the system improvements associated with the prior queued projects,and the system improvements deemed necessary in this study are in service,no N-1 thermal or voltage issues were observed in the studies. N-1-1 Results:Assuming Energy Gateway and the system improvements associated with the prior queued projects are all in service there are a number of N-1-1 thermal issues that occur in the ER study if generation in the Naughton/Railroad 138 kV system is not reduced between outages. These N-1-1 outage issues are caused by the loss of one of the lines or transformers in the three systems listed below,as well as a second loss of a different piece of equipment in one of those systems after the system returns to steady state: All 138 kV lines between Naughton and Railroad The three 230-138 kV transformers at Naughton and Railroad The 230 kV line from to Birch Creek to Naughton The 230 kV line from to Birch Creek to Railroad The 230 kV line from Ben Lomond to Birch Creek The 230 kV line from Ben Lomond to Naughton The 138 kV line between the Q0786 POI and Silver Creek The 138 kV line between Jordanelle and Midway The thermal issues that occur during the N-1-1 outage situations are overloads of the following lines: Naughton -Carter Creek -Canyon Compression (35.0 miles) Naughton -Glenco -P204 -MuddyCreek (36.3 miles) Canyon Compression -WhitneyTap -Q0715/Q0810 POI (1.4 Miles) Q0715/Q0810 POI-Railroad (13.7 miles) Longhollow-Painter -Painter Tap (10.9 miles) Silver Creek -Snyderville Tap (9.5 miles) Page 20 September 8,,2017 ,Q0810 Y PACIFICORP Feasibility Study Report Without projects to rebuild and/or reconductor all of these lines these issues will require Grid Operations to trip generationprojects in the area after some outages to prepare for a second outage.Q0810 may be taken offline in these situations for this reason. No N-1-1 voltage issues were observed in the studies. N-2 Results:Assuming Energy Gateway,the system improvements associated with the prior queued projects,and the system improvements deemed necessary in this study are in service,no N-2 thermal or voltage issues were observed in the studies. Page 21 September 8,,2017 ,Q0810