Loading...
HomeMy WebLinkAbout20180307PAC to Staff UT Q715FS.pdfPACIFICORP TRANSMISSION Large Generator Interconnection Facilities Study Report Final Completed for ("Interconnection Customer") Q0715 Proposed Point of Interconnection Canyon Compression-Railroad 138 kV transmission line (Near Whitney Canyon Tap,near Structure #116) March 7,2017 PAciFICORPTRANSMISSION FINAL Facilities Study Report TABLE OF CONTENTS 1.0 DESCRIPTIONOF THE PROJECT........................................................................................1 2.0 STUDY SCOPE AND OBJECTIVES........................................................................................1 3.0 STUDYASSUMPTIONS ........................................................................................1 4.0 TYPE OF INTERCONNECTIONSERVICE............................................................................2 5.0 PROPOSED POINTOF INTERCONNECTION..........................................................................2 6.0 SCOPE OF WORK ........................................................................................................3 6.1 Generating Facility Modifications ............................................................................3 6.1.1 Interconnection Customer to be Responsible For.....................................................3 6.2 Tie Line Requirements ............................................................................................6 6.2.2 Transmission Provider to be Responsible For ........................................................6 6.3 Point of Interconnection...............................................................................................7 6.3.1 Interconnection Customer to be Responsible For.....................................................7 6.3.2 Transmission Provider to be Responsible For ........................................................7 6.4 Other..............................................................................................................................9 6.4.1 TRANSMISSIONPROVIDER TO BE RESPONSIBLE FOR..................................................9 7.0 CosT ESTIMATE (+/-20%)..........................................................................................10 8.0 SCHEDULE..........................................................................................................................12 9.0 PARTICIPATIONBY AFFECTED SYSTEMS .........................................................................12 10.0 APPENDICES..............................................................................................................13 10.1 Appendix 1:Higher Priority Request..............................................................14 10.2 Appendix 2:Property Requirements ..............................................................15 March 7,2017 Q0715 Page i CONFIDENTIAL/FINAL VAPAclFICORPTRANSMISSION FINAL Facilities Study Report 1.0 DESCRIPTION OF THE PROJECT ("Interconnection Customer")proposed interconnecting 120 MW of new generation to PacifiCorp's ("Transmission Provider")Canyon Compression-Railroad 138 kV transmission line near WhitneyCanyon Tap (near structure #116)located in Uinta County,Wyoming.The project ("Project")will consist of sixty (60)GE 2.0-116 turbines for a total output of 120 MW.The requested commercial operation date is July 1,2017. Interconnection Customer will NOT operate this generator as a Qualified Facility as defined by the Public Utility Regulatory Policies Act of 1978 (PURPA). The Transmission Provider has assigned the Project "Q0715." 2.0 STUDY SCOPE AND OBJECTIVES The objective of the facilities study is to: complete a facilities analysis,which shall specify and estimate the cost of equipment, engineering,procurement,and construction required to address issues as outlined in the system impact study,and provide a scope of work and an estimated cost and schedule for completing the scope of work. 3.0 STUDYASSUMPTIONS All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are listed in Appendix 1.If any of these requests are withdrawn, the Transmission Provider reserves the right to restudy this request,as the results and conclusions contained within this study could significantlychange. For study purposes there are two separate queues: o Transmission Service Queue:to the extent practical,all network upgrades that are required to accommodate active transmission service requests will be modeled in this study. o Generation Interconnection Queue:Interconnection Facilities associated with higher queue interconnection requests will be modeled in this study. The Interconnection Customer's request for energy or network resource interconnection service in and of itself does not convey transmission service.Only a Network Customer may make a request to designate a generatingresource as a Network Resource.Because the queue of higher priority transmission service requests may be different when a Network Customer requests network resource designation for this Generating Facility,the available capacity or transmission modifications,if any,necessary to provide network resource interconnection service may be significantlydifferent.Therefore,the Interconnection Customer should regard the results of this study as informational rather than final. This study assumes the Project will be integrated into Transmission Provider's system at the agreed upon and/or proposed Point of Interconnection ("POI"). The Interconnection Customer will construct and own any facilities required between the POI and the Project. March 7,2017 Q0715 Page 1 CONFIDENTIAL/FINAL PAciFICORPTRANSMISSION FINAL Facilities Study Report Generatortripping may be required for certain outages. All facilities will meet or exceed the minimum Western Electricity Coordinating Council ("WECC"),North American Electric ReliabilityCorporation ("NERC"),and Transmission Provider performance and design standards. A synchronous condenser at Standpipe substation is assumed to be in service. The Croyden -Silver Creek 138kV line is assumed to be in service. This report is based on information available at the time of the study.It is the Interconnection Customer's responsibility to check the Transmission Provider's web site regularly for Transmission system updates at (http://www.pacificorp.com/tran.html) 4.0 TYPE OF INTERCONNECTION SERVICE The Interconnection Customer has selected Energy ("ER")Interconnection Service. 5.0 PROPOSED POINT OF INTERCONNECTION The Interconnection Customer's proposed Generating Facility is to be interconnected through a new substation southwest of the Whitney Canyon Tap point in Uinta County on the Canyon Compression -Railroad 138kV transmission line.Figure 1 below is a one-line diagram that illustrates the interconnection of the proposed Generating Facility to the Transmission Provider's system. March 7,2017 Q0715 Page 2 CONFIDENTIAL/FINAL VAPAclFICORPTRANSMISSION FINAL Facilities Study Report WhitneyCanyon 2 0.3 miles |Canyon Compression I I I I I I I \I I I Q0715 POI I Substation i I I I I I I I Pointof I I Interconnection i 138 kV Railroad e 3 3 .5 kV 34.5 kVQ0715 ..Substation i Figure 1:System One Line Diagram 6.0 SCOPE OF WORK 6.1 Generating Facility The followingoutlines the design,procurement,construction,installation and ownership of equipment at the Interconnection Customer's Generation Facility. 6.1.1 INTERCONNECTION CUSTOMER TO BE RESPONSIBLEFOR Provide a separate secured room within the Interconnection Customer's control building which can only be accessed by Transmission Provider personnel via unencumbered access to the building without entering the Interconnection Customer's collector substation.This will include all AC and DC power requirements as outlined during the detailed design phase of the Project.An area within the collector substation March 7,2017 Q0715 Page 3 CONFIDENTIAL/FINAL VAPAclFICORPTRANSMISSION FINAL Facilities Study Report fence,only accessible by the Transmission Provider with access to the control must also be large enough for a standard Transmission Provider vehicle. Provide rack space for Transmission Provider to install fiber nodes,multiplexand fiber termination panels within the collector substation.This equipment will be owned by the Transmission Provider and maintained at the Interconnection Customer's expense. Prior to construction,arrange for construction power with the Transmission Provider. The metering shall conform to the Six State Electric Service Requirements manual as the site is within the Transmission Provider's service territory. Arrange bidirectional metering for permanent station service load.Please note that prior to back feed,Interconnection Customer must arrange distribution voltage retail meter service for electricityconsumed by the Project and arrange backup station service for power that will be drawn from the transmission line when the Project is not generating.Interconnection Customer must call the PCCC Solution Center 1-800-640- 2212 to arrange this service.Approval for back feed is contingent upon obtaining station service. Operate the Generating Facility in voltage control mode with the ability to deliver power output to the POI within the range of+/-0.95 power factor.(Please see Standard Large Generator Interconnection Agreement,article 9.6.1 and 9.6.2.)Any additional reactive compensation must be designed such that the discrete switching of the reactive device,if required,does not cause step voltage changes greater than ±3%at any load serving bus on the Transmission Provider's system. Operate the Generating Facility to maintain the voltage at the POI,or other designated point as deemed appropriated by Transmission Provider,between 1.00 per unit to 1.04 per unit.As required by NERC standard VAR-001-la,the Transmission Provider will provide a voltage schedule for the POI.The Transmission Provider may also specify a voltage and/orreactivepower bandwidth as needed to coordinate with upstream voltage control devices such as on-load tap changers.At the Transmission Provider's discretion,these values might be adjusted depending on operating conditions.The voltage control settings of the Generating Facility must be coordinated with the Transmission Provider prior to energization (or interconnection).The reactive compensation must be designed such that the discreet switching of the reactive device (if required by the Interconnection Customer)does not cause step voltage changes greater than +/-3%on the Transmission Provider's system. o Ensure the power factor within +/-0.95 is maintained at the POI to minimize the reactive power flow towards the transmission system to prevent high voltages during times of low output levels.Transmission Provider has experienced high voltages in the Wyomingarea when the transmission system is lightly loadedwith low wind conditions in the area.With low wind conditions the wind farms tend to supply reactive power into the transmission system increasing the voltage. o Operate the Generating Facility,if able to do so,with a voltage droop.Voltage droop control enables proportionate reactive power sharing among Generating Facilities.Studies will be required to coordinate voltage droop settings if there are other facilities in the area.It will be the Interconnection Customer's responsibility to ensure that a voltage coordination study is performed,in coordination with March 7,2017 Q0715 Page 4 CONFIDENTIAL/FINAL VAPAclFICORPTRANSMISSION FINAL Facilities Study Report Transmission Provider,and implemented with appropriate coordination settings prior to umt testmg. o Complete any additional studies to determine whether critical interactions, including but not limited to control systems,exist.These studies are to be coordinated with Transmission Provider,and are the responsibility of the Interconnection Customer. o Install Phasor MeasurementUnits (PMUs). o Meet the Federal Energy Regulatory Committee (FERC)and WECC low voltage ride-through requirements as specified in the interconnection agreement.Each of the Interconnection Customer's step-up transformers will need to be switched with a 138 kV circuit breaker. o Provide a standard model from the WECC Approved Dynamic Model Library 180 days prior to trial operation,the Transmission Provider cannot submit a user written model to WECC for inclusion in base cases.The list of approvedgenerator models is continuallyupdated and is available on the http://www.WECC.bizwebsite. 6.1.2 TRANSMISSIONPROVIDER TO BE RESPONSIBLEFOR Design,procure and install communications equipment in Interconnection Customer's control house includingan RTU,fiber nodes,multiplexand fiber termination panels. The RTU will acquire the following data points from the Interconnection Customer's Generating Facility: From the Q0715 collector substation: Analogs: Transformer #1 real power Transformer #1 reactive power Real power flow through 34.5 kV line feeder breaker 1 Reactive power flow through 34.5 kV line feeder breaker 1 Real power flow through 34.5 kV line feeder breaker 2 Reactive power flow through 34.5 kV line feeder breaker 2 Real power flow through 34.5 kV line feeder breaker 3 Reactive power flow through 34.5 kV line feeder breaker 3 Real power flow through 34.5 kV line feeder breaker 4 Reactive power flow through 34.5 kV line feeder breaker 4 Real power flow through 34.5 kV line feeder breaker 5 Reactive power flow through 34.5 kV line feeder breaker 5 A phase 138kV transmission voltage B phase 138kV transmission voltage March 7,2017 Q0715 Page 5 CONFIDENTIAL/FINAL VAPAclFICORPTRANSMISSION FINAL Facilities Study Report C phase 138kV transmission voltage Average Wind speed Average Plant Atmospheric Pressure (Bar) Average Plant Temperature (Celsius) Status: 138kV breaker Tl 34.5 kV collector circuit breaker 1 34.5 kV collector circuit breaker 2 34.5 kV collector circuit breaker 3 34.5 kV collector circuit breaker 4 34.5 kV collector circuit breaker 5 6.2 Tie Line Requirements The followingoutlines the design,procurement,construction,installation and ownership of equipment associated with the radial line connecting the Interconnection Customer's Generating Facility to the Transmission Provider's Point of Interconnection ("POI") substation. 6.2.1 INTERCONNECTION CUSTOMER TO BE RESPONSIBLEFOR Procure all necessary permits,property rights and/or the rights of way for the new transmission line between the Project collector station the Point of Interconnection substation,the details of which will need to be coordinatedwith Transmission Provider. o The location of the new Q0715 POI substation is currentlyunknown,so for the purposes of this study and associated cost estimate it is assumed to be within one (1)mile of the Carter Creek -Railroad 138kV transmission.The design and cost estimate will be refined during detailed design of the Project. Design (per the Transmission Provider's standards)and install a dead-end structure with sufficient bus to allow for proper attachment to a 138 kV disconnect switch inside the Transmission Provider's substation.The switch will be the change of ownership location. 6.2.2 TRANSMISSIONPROVIDER TO BE RESPONSIBLEFOR Install,own and maintain,at the Interconnection Customer's expense,OPGW fiber on the line from Q0715 POI substation to the Q0715 collector substation.Fiber nodes, multiplexand fiber termination panels are required at both locations. Provide the Interconnection Customer the necessary specifications to allow the ground mats of the Interconnection Customer's tie line substation and the POI substation to be tied together. March 7,2017 Q0715 Page 6 CONFIDENTIAL/FINAL VAPAclFICORPTRANSMISSION FINAL Facilities Study Report Provide the Interconnection Customer the necessary specifications for the bus segments of the Interconnection Customer's tie line substation and the new POI substation to be connected. 6.3 Point of Interconnection The followingoutlines the design,procurement,construction,installation and ownership of equipment at the POI. 6.3.1 INTERCONNECTION CUSTOMER TO BE RESPONSIBLEFOR Construct a tie line substation (having a sole 138kV circuit breaker and associated equipment)adjacent to the Q0715 POI substation with a common fence between the two facilities.The short line segment between the tie line substation and the Q0715 POI substation will be considered a bus section and will be protected with redundant bus differential relay systems.The bus differential relays will be located in the Q0715 POI substation. Tie together the ground mats of the two substations and match the standards of the Q0715 POI substation. Provide the output from two sets of current transformers to be fed into the bus differential relays with a maximum current transformer ratio matching the maximum CT ratio of the breakers at the Q0715 POI substation.If a fault is detected in the short conductor connection,both the 138kV breakers in the Q0715 POI substation and the 138kV breaker in the Interconnection Customer's tie line substation will be tripped. Install facilities capable of detecting and clearing faults on the tie line between the tie line substation and the collector substation in five cycles or less. 6.3.2 TRANSMISSIONPROVIDER TO BE RESPONSIBLEFOR Construct a new 138 kV three breaker ring bus substation southwest of the Whitney Canyon Tap (near structure 116),with associated switches and line terminations to serve as the POI substation.The substation will be approximately 170'x 300'(fence dimensions)based on the Interconnection Customer provided facility requirements, company standards and property requirements.The Q0715 POI substation will be located adjacent to the Interconnection Customer's tie line substation with a common fence between the facilities.The ground grids for the substations will be tied together and conduit will be installed between the substation to facilitate installation of protection,control,and indication cables. The followingis a list of the required major equipment: 3 -138 kV Power Circuit Breakers 6 -138 kV CCVTs 3 -138 kV CT/VT Metering Units 11 -138 kV Switches 9 -138 kV Lightning Arresters 1 -138 kV SSVT 1 -Control House March 7,2017 Q0715 Page 7 CONFIDENTIAL/FINAL VAPAclFICORPTRANSMISSION FINAL Facilities Study Report Loop the Carter Creek-Railroad 138kV transmission line through the new Q0715 POI substation.The construction of these new segments of transmission line will consist of two line routes in and out of the Q0715 POI substation.The loop in/out lines will be single-circuit wood structures with 795ACSR conductor and 1/2"OPGW fiber optic shield wire.The OPGW will also be extended into the new Q0715 POI substation Install redundant communications from the RAS controller to the Project. Install a relay at the Q0715 POI substation to monitor the voltage magnitude and frequency.If the magnitude or frequency of the voltage is outside of normal range of operation a signal will be sent over the communication system to the collector substation.At the collector substation this signal is to trip open all of the 34.5 kV feeder breakers to disconnect the wind turbine generators.By tripping the 34.5 kV breakers instead of the 138kV breakers the station service to the Generating Facility is maintainedto facilitate the restoration of the generation.This relay will also have phase and ground directional overcurrent elements set to operate for faults in the line between the Q0715 POI substation and the collector substation and serve as a backup to the main protection installed by the Interconnection Customer as indicated in the previous paragraph. Install protective relays for line fault detection at the Transmission Provider's 138kV Q0715 POI substation for the protection of the tie lines to the Interconnection Customer's tie line substation and the line to Railroad substation,where a two-terminal transmission line current differential will be implemented.The lines from the Q0715 POI substation to Compression substation will also be protected with a two-terminal transmission line current differential relay system.The connection to WhitneyCanyon substation will be treated as a load for this line differential. Installingan RTU at the POI substation to acquire the data listed below.This data will be used to operate the power system. Listed below is the data that will be acquired at the Q0715 POI substation. From the Q0715 POI substation: Analogs: Net Generationreal power Net Generatorreactive power Interchangeenergy register From tie substation: Status: 138kV breaker Install fiber on the existing line from Canyon Compression substation to the new Q0715 POI substation. Install a 48 volt communication battery and charger is required for protection circuits at the POI substation. Install substation network at the POI,Canyon Compression and tie line substations.At Canyon Compression substation the communications will be connected to the March 7,2017 Q0715 Page 8 CONFIDENTIAL/FINAL VAPAclFICORPTRANSMISSION FINAL Facilities Study Report Transmission Provider's existing communications backbone via existing fiber and microwave. Install a leased Tl circuit at the Q0715 POI substation with the other end terminated at Naughton substation,for the Naughton RAS requirements for redundant commumcations. Designing,procuring and constructing all interconnection revenue metering,including the instrument transformers,metering panels,junction box and secondary metering wire.The interchange metering will be designed bidirectional and rated for the total net generation of the Project includingmetering the retail load (per tariff)delivered to the Interconnection Customer.The primary metering transformers shall be combination 138 kV,500/5,RF =2,CT/VT extended range for high accuracy metering. o The metering design package will include two revenue quality meters,test switch, with DNP real-time digital data terminated at a metering interposition block.One meter will be designated a primary SCADA meter and a second meter will be designated as backup with metering DNP data delivered to the alternate control center.The metering data will include bidirectional KWH KVARH,revenue quantities including instantaneous PF,MW,MVAR including per phase voltage and amps data.There will be no revenue metering located at the Interconnection Customer's collector substation.There will be operational data gathered at the collector substation. Install an Ethernet connection for retail sales and generation accounting via the MV-90 translation system. 6.4 Other The followingoutlines the design,procurement,construction,installation,and ownership of equipment past the POI. 6.4.1 TRANSMISSIONPROVIDER TO BE RESPONSIBLE FOR Reconductor approximately 28.3 miles of the existing Silver Creek - Snyderville -Cottonwood 138 kV transmission line to increase the line rating.This includes obtaining all necessary easements and permitting. The existing line segments with 397.5 ACSR and 500 AAC conductor will be reconductored with 477 ACSS/TW High Temperature conductor.This work will require approximately 92 of the existing 460 structures to be replaced. Modify the existing Naughton West Remedial Action Scheme ("RAS") to integrate the Q0715 Project.If the average of the flows on west of Naughton and west of Evanston is above 900 MW,Q0715 will be armed to trip for the N-2 outages of either Ben Lomond -Birch Creek 230 kV line +Ben Lomond -Naughton or Naughton -Birch Creek 230 kV line +Ben Lomond -Naughton 230 kV line. March 7,2017 Q0715 Page 9 CONFIDENTIAL/FINAL PAciFICORPTRANSMISSION FINAL Facilities Study Report 7.0 COST ESTIMATE (+/-20%) The followingestimate represents only scopes of work that will be performed by the Transmission Provider.Costs for any work being performed by the Interconnection Customer are not included. Interconnection -Direct AssignmentFacilities Q0715 collector substation -Add Communications $219,000 Q0715 Tie Line Substation -Add Relaying $145,000 Q0715 Naughton substation -Modify RAS $105,000 Q0715 POI Substation -Metering,Protection &Control and $1,414,000 line position equipment Total Direct Assignment $1,883,000 Interconnection -Network Upgrade Facilities Q0715 POI substation -Add 138 kV three-breakerring bus $4,665,000 Railroad substation -Add line relays $168,000 Canyon Compression substation -Add line relays $299,000 Carter Creek to Railroad 138 kV -Loop for POI substation and fiber $798,000 Cottonwood to Silver Creek -Reconductor 28.3 miles of 138 kV $6,538,000 Total Network Upgrade $12,468,000 Total Cost $14,351,000 *Any distribution line modifications identified in this report will require a field visit analysis in order to obtain a more thorough understanding of the specific requirements.The estimate provided above for this work could change substantially based on the results of this analysis. Until this field analysis is performed the Transmission Provider must develop the project schedule using conservative assumptions.The Interconnection Customer may request that the Transmission Provider perform this field analysis,at the Interconnection Customer's expense, prior to the execution of an Interconnection Agreement in order to obtain more cost and schedule certamty. March 7,2017 Q0715 Page 10 CONFIDENTIAL/FINAL PAciFICORPTRANSMISSION FINAL Facilities Study Report Note:Costs for any excavation,duct installation and easements shall be borne by the Interconnection Customer and are not included in this estimate.This estimate is as accurate as possibly given the level of detailed study that has been completed to date and approximates the costs incurred by Transmission Provider to interconnect this GeneratorFacility to Transmission Provider's electrical distribution or transmission system.The Interconnection Customer will be responsible for all actual costs,regardless of the estimated costs communicated to or approved by the Interconnection Customer. March 7,2017 Q0715 Page 11 CONFIDENTIAL/FINAL PAciFICORPTRANSMISSION FINAL Facilities Study Report 8.0 SCHEDULE Execute Interconnection Agreement April 28,2017 Provision of Financial Security April 28,2017 Interconnection Customer Design Information Provided May 31,2017 *Transmission Provider Engineering &Procurement Commences July 10,2017 Transmission Provider Reconductor Permitting Commences August 7,2017 Interconnection Customer Property/Permits/ROW Procured December 1,2017 **EnergyImbalance Market Modeling Data Submittal December 15,2017 Transmission Provider Engineering Design Complete January 31,2018 Reconductor Permitting Complete August 5,2019 Construction Begins June 1,2019 Interconnection Customer's Facilities Receive Backfeed Power June 3,2020 Initial Synchronization/Generation Testing July 8,2020 Commercial Operation August 4,2020 *As applicable and determined by the Transmission Provider,within 60 days of the Interconnection Customer's authorization for the Transmission Provider to begin engineering,the Interconnection Customer shall provide a detailed short circuit model of its generation system. This model must be constructed using the ASPEN OneLine short circuit simulation program and contain all individual electrical components of the Interconnection Customer's generation system. **Any design modifications to the Interconnection Customer's GeneratingFacility after this date requiring updates to the Transmission Provider's network model will result in a minimum of 3 months added to all future milestones including Commercial Operation. Please note,the time required to perform the scope of work identified in this report appears to result in a timeframe that does not support the Interconnection Customer's requested Commercial Operation date of July 1,2017 9.0 PARTICIPATION BY AFFECTED SYSTEMS Transmission Provider has identified the followingaffected systems:None. March 7,2017 Q0715 Page 12 CONFIDENTIAL/FINAL PAciFICORPTRANSMISSION FINAL Facilities Study Report 10.0APPENDICES Appendix 1:Higher Priority Requests Appendix 2:Property Requirements March 7,2017 Q0715 Page 13 CONFIDENTIAL/FINAL PAciFICORPTRANSMISSION FINAL Facilities Study Report 10.1 Appendix1:HigherPriority Request All active higher priority transmission service and/or generator interconnection requests will be considered in this study and are identified below.If any of these requests are withdrawn,the Transmission Provider reserves the right to restudy this request,as the results and conclusions containedwithin this study could significantlychange. Transmission/GenerationInterconnection Queue Requests considered: Q0199 (200 MW) Q0200 (100 MW) Q0201 (100 MW) Q0290 (252 MW) Q0306-A (48.3 MW) Q0335 (49.6 MW) Q0375 (230 MW) Q0409 (320 MW) Q0542 (240 MW) Q0706 (250 MW) Q0707 (250 MW) Q0708 (250 MW) Q0712 (750MW) Q0713 (350 MW) March 7,2017 Q0715 Page 14 CONFIDENTIAL/FINAL VAPAclFICORPTRANSMISSION FINAL Facilities Study Report 10.2 Appendix2:Property Requirements Property Requirementsfor Point of Interconnection Substation &Tie Line Requirementsfor rights of way easements Rights of way easements will be acquired by the Interconnection Customer in the Transmission Provider's name for the construction,reconstruction,operation,maintenance,repair,replacement and removal of Transmission Provider's Interconnection Facilities that will be owned and operated by PacifiCorp.Interconnection Customer will acquire all necessary permits for the project and will obtain rights of way easements for the project on Transmission Provider's easement form. Transmission Provider will acquire the rights of way easements and permitting for any upgrades made to existing PacifiCorp facilities. Real Property Requirementsfor Point of Interconnection Substation Real property for a point of interconnection substation will be acquired by an Interconnection Customer to accommodate the Interconnection Customer's project.The real property must be acceptable to Transmission Provider.Interconnection Customer will acquire fee ownership for interconnection substation unless Transmission Provider determines that other than fee ownership is acceptable;however,the form and instrument of such rights will be at Transmission Provider's sole discretion.Any land rights that Interconnection Customer is planning to retain as part of a fee property conveyance will be identified in advance to Transmission Provider and are subject to the Transmission Provider's approval. The Interconnection Customer must obtain all permits required by all relevantjurisdictionsfor the planned use including but not limited to conditional use permits,Certificates of Public Convenience and Necessity,California Environmental Quality Act,as well as all construction permits for the project. Interconnection Customer will not be reimbursed through network upgrades for more than the market value of the property. As a minimum,real property must be environmentally,physically,and operationally acceptable to Transmission Provider.The real property shall be a permitted or permittable use in all zoning districts.The Interconnection Customer shall provide Transmission Provider with a title report and shall transfer property without any material defects of title or other encumbrances that are not acceptable to Transmission Provider.Property lines shall be surveyed and show all encumbrances, encroachments,and roads. Examples of potentially unacceptable environmental,physical,or operational conditions could include but are not limited to: 1.Environmental:known contamination of site;evidence of environmental contamination by any dangerous,hazardous or toxic materials as defined by any governmental agency;violation of building,health,safety,environmental,fire, land use,zoning or other such regulation;violation of ordinances or statutes of any governmental entities having jurisdiction over the property;underground or March 7,2017 Q0715 Page 15 CONFIDENTIAL/FINAL PAciFICORPTRANSMISSION FINAL Facilities Study Report above ground storage tanks in area;known remediation sites on property;ongoing mitigation activities or monitoring activities;asbestos;lead-based paint,etc.A phase I environmental study is required for land being acquired in fee by the Transmission Provider unless waived by Transmission Provider. 2.Physical:inadequate site drainage;proximity to flood zone;erosion issues; wetland overlays;threatened and endangered species;archeological or culturally sensitive areas;inadequate sub-surface elements,etc.Transmission Provider may require Interconnection Customer to procure various studies and surveys as determined necessary by Transmission Provider. Operational:inadequate access for Transmission Provider's equipment and vehicles;existing structures on land that require removal prior to building of substation;ongoing maintenance for landscaping or extensive landscape requirements;ongoing homeowner's or other requirements or restrictions (e.g.,Covenants,Codes and Restrictions,deed restrictions,etc.)on property which are not acceptable to the Transmission Provider. March 7,2017 Q0715 Page 16 CONFIDENTIAL/FINAL