HomeMy WebLinkAbout20180122PIIC 19-20 to PAC.pdfWILLIAMS ·BRADBURY
ATToRNEYS AT LAW RECElVED
20\8 JAN 22 AM ll:43
January 22,2018 SlON
Ms.Diane Hanian
Commission Secretary
Idaho Public Utilities Commission
472 W.Washington
Boise,ID 83702
Re:PAC-E-17-07
Dear Ms.Hanian:
Please find enclosed for filing the original and three copies of PacifiCorp Idaho
Industrial Customers'Fourth Production Request to Rocky Mountain Power in the above
referenced case.
Thank you for your assistance in this matter.Please feel free to give me a call should
you have any questions.
Sincerely,
Ronald L.Williams
RLW
Enclosures
P.O.Box 388 -Boise,ID 83701
Phone:208-344-6633 -www.williamsbradbury.com
Ronald L.Williams,ISB No.3034 RECEI VEDP.O.Box 388,802 W.Bannock Street,Suite 900
Boise,ID 83702 20ÍÛ JM 22 ggyTelephone:(208)344-6633
Email:ron @ williamsbradbury.com UCBSSION
Attorneys for PacifiCorp Idaho Industrial Customers
BEFORE THE IDAHO PUBLIC UTILITES COMMISSION
IN THE MATTER OF THE APPLICATION OF )Case No.PAC-E-17-07
ROCKY MOUNTAIN POWER FOR )
CERTIFICATES OF PUBLIC CONVENIENCE )FOURTH PRODUCTION REQUESTOF
AND NECESSITY AND BINDING )PACIFICORP IDAHO INDUSTRIAL
RATEMAKING TREATMENT FOR WIND )CUSTOMERS TO ROCKY MOUNTAIN
AND TRANSMISSION FACILITIES )POWER
PacifiCorp Idaho Industrial Customers ("PIIC"),by and through its attorney of record
Ronald L.Williams and pursuant to the Rules of Procedure of the Idaho Public Utilities
Commission ("Commission"),hereby requests that Rocky Mountain Power ("RMP")provide the
followingdocuments and information as soon as possible,and no later than February 7 2018.
PIIC recognizes that the response time requested is 16 days,not the full 21 days,as
provided by Rule.Justification for this requested shortening of time is:(1)to give PIIC
sufficient time to analyze the response and prepare and file testimony on February 16,2018,and
(2)the below requests ask for missing but critical workpapers that PIIC believed it asked for in
its second production request,but which were not provided by the Company in its response.
This Production Request is continuing,and RMP is requested to provide,by way of
supplementary responses,additional documents that it or any person acting on its behalf may
later obtain that will augment the documents produced.
Please provide answers to each question,and supporting work papers that provide detail
or are the source of information used in calculations.RMP is reminded that responses pursuant to
PIIC THIRD PRODUCTIONREQUEST TO ROCKY MOUNTAIN POWER Page 1
Commission Rules of Procedure must include the name and phone number of the person
preparing the document,and the name,location and phone number of the record holder and if
different the witness who can sponsor the answer at hearing if need be.IDAPA 31.01.01.228.
In addition to the written copies provided as response to the questions,please provide all
Excel and electronic files on CD with formulas activated.
REQUEST NO.19.Reference the Jan 16th 2018 Supplemental Direct Testimony
workpaper of Mr.Link titled:"\Transmission Project\Gateway_IRP Data 21%US Tax
(VL).xlsx":
a.Please explain why the formulas in this workpaper have been replaced with a link to the
following file:"Energy Gateway GM 2017 03 13 21%US Tax.xlsm."
b.Please provide a copy of Excel the file "Energy Gateway GM 2017 03 13 21%US
Tax.xlsm,"identified in the referenced workpaper.
c.Please explain why the annual revenue requirement computations for the Transmission
Projects,which were included in the Transmission Project workpapers accompanying the
Company's Direct Testimony,havebeen excluded from the referenced workpaper.
d.Please provide all of the revenue requirement computations,which were used in the
referencedworkpaper to develop annualrevenue requirements for the Transmission
Projects.Please provide these computations in a manner substantially similar what was
provided in Direct Testimony (e.g.the "Generic Model"in the file titled "Energy
Gateway GM 2017 03 13 w Bonus.xlsm").
e.In the revenue requirement computations provided in response to sub-request"d."of this
request,please identify each change that was made to the revenue requirement
computations to incorporate the provisions of the Tax Cuts and Jobs Act,relative to the
workpapers used in the Company's Direct Testimony.
PIIC THIRD PRODUCTION REQUEST TO ROCKY MOUNTAIN POWER Page 2
In the revenue requirement computations provided in response to sub-request "d."of this
request,please identify any other changes made that were unrelatedto the Tax Cuts and Jobs
Act,relative to the workpapers used in the Company's Direct Testimony.
REQUEST NO.20.Please provide the Excel financial models that were used to
calculate the nominal and levelized revenue requirements for each of the Wind Projects
identified in Table ISD of the Supplemental Direct and Rebuttal Testimony of Rick T.
Link.Please provide these workpapers in a format substantially similar to the workpapers
included in the folder "/Wind Projects"in the Company's Direct Testimony (e.g."TB Flats I
250 RFPBM V l3G_EPC_03312017-30YR-GW4_FINAL.xlsx").
DATED at Boise,Idaho,this 22 day of January,2017.
Respectfully submitted,.
Ronald L.Williams
Williams Bradbury,P.C.
Attorneys for PacifiCorp Idaho Industrial Customers
PIIC THIRD PRODUCTIONREQUEST TO ROCKYMOUNTAIN POWER Page 3
CERTIFICATE OF MAILING
I HEREBY CERTIFY that on this 22nd day of January ,2018,I caused to be served a
true and correct copy of the foregoing document upon the following individuals in the manner
indicated below:
Diane M.Hanian,Secretary Hand Delivery
Idaho Public Utilities Commission US Mail (postage prepaid)
P.O.Box 83702 Facsimile Transmission
472 W.Washington Street Federal Express
Boise,ID 83702-0074 Electronic Transmission
E-Mail:diane.holt@puc.idaho.gov
Ted Weston .Hand DeliveryIdahoRegulatoryAffairsManager .US Mail (postage prepaid)Rocky Mountain Power -..O Facsimile Transmission1407WestNorthTemple,Suite 330 Federal ExpressSaltLakeCity,UT 84116 -...Electronic TransmissionE-Mail:ted.weston@pacificorp.com
Yvonne R.Hogle .Hand DeliveryAssistantGeneralCounsel .US Mail (postage prepaid)Rocky Mountain Power -....O Facsimile Transmission1407WestNorthTemple,Suite 320 Federal ExpressSaltLakeCity,UT 84116 -...
.M Electronic TransmissionE-Mail:yvonne.hogle@pacificorp.com
Data Request ResponseCenter .Hand DeliveryPacificCorpUSMail(postage prepaid)825 NE Multnomah,Suite 2000 ..Facsimile TransmissionPortland,OR 97232
.Federal ExpressE-Mail:datarequests@pacificorp.com
Electronic Transmission
Brandon Karpen .Hand DeliveryDeputyAttorneyGeneral
...US Mail (postage prepaid)Idaho Public Utilities Commission ....Facsimile Transmission472W.Washington (83702)Federal ExpressPOBox83720
Boise,ID 83720 Electronic Transmission
Email:Brandon.karpen@puc.idaho.gov
Randall C.Budge Hand Delivery
Racine,Olson,Nye &Budge,Chtd.US Mail (postage prepaid)
201 E.Center Facsimile Transmission
PO Box 1391 Federal Express
Pocatello,ID 83204-1391 Electronic Transmission
E-Mail:reb@racinelaw.net
Attorney for Monsanto Company
PIIC THIRD PRODUCTION REQUEST TO ROCKY MOUNTAIN POWER Page 4
Brubaker &Associates .
.Hand Delivery16690SwingleyRidgeRoad,#140 .US Mail (postage prepaid)Chesterfield,MO 63017 ....
.Facsimile TransmissionE-Mail:bcollins@consultbai.com Federal Expresskiverson@consultbai.com ...Electronic TransmissionMonsantoCompany
Jim Duke Hand DeliveryIdahoanFoodsUSMail(postage prepaid)357 Constitution Way -----U Facsimile TransmissionIdahoFalls,ID 83742 Federal ExpressE-Mail:duke@idahoan.com -
--Electronic TransmissionPIIC
Kyle Williams Hand DeliveryBYUIdaho
.US Mail (postage prepaid)Email:williamsk@byui.edu -..Facsimile TransmissionPIICFederalExpress
Electronic Transmission
Val Steiner Hand DeliveryNu-West Industries,Inc.
.US Mail (postage prepaid)Email:val.steiner@agrium.com ..Facsimile TransmissionPIICFederalExpress
Electronic Transmission
Bradley Mullins Hand Delivery333S.W.Taylor,St 400 US Mail (postage prepaid)Portland,OR 97204 ----Facsimile TransmissionEmail:brmullins@mwanalytics.com Federal ExpressPIICElectronicTransmission
Eric L.Olsen Hand DeliveryEchoHawk&Olsen PLLC US Mail (postage prepaid)505 Pershing Ave.,Suite 100 Facsimile TransmissionPOBox6119FederalExpressPocatello,ID 83205
Email:elo@echohawk.com Electronic Transmission
Idaho Irrigation Pumpers Association
Anthony Yankel Hand Delivery12700LakeAvenue,Unit 2505 US Mail (postage prepaid)Lakewook,OH 44107 Facsimile TransmissionEmail:tony@ yankel.net Federal ExpressIdahoIrrigationPumpersAssociationElectronicTransmi sion
Ronald L.Williams