RE:UT Docket No.17-035-40
WRA 2nd Set Data Request (1-2)
Please find enclosed Rocky Mountain Power's 16'SupplementalResponse to WRA 2nd Set Data
Request 2.1.Provided on the enclosed Confidential CD is Confidential Attachment WRA 2.1 16
Supplemental.Confidential information is provided subject to Public Service Commission of
Utah (UPSC)Rules 746-1-602 and 603.
If you have any questions,please call me at (801)220-2823.
Sincerely,
Jana Saba
Manager,Regulation
Enclosures
C.c.:Dan Kohler/DPU dkoehk@dgyggarkeamm (C)
Dan Peaco/DPU dpeaco@d_ay_markea_ggn(C)(W)
Aliea Afnan/DPU _aafhan@daygiarkeagom (W)jkwgdayngagea.com (W)
Béla Vastag/OCS bvasttaggäLtahgov (C)
Philip Hayet/OCS p_h_ayet ägkenngom (C)
Gary A.Dodge/UAE gdodge@_hj_dlawayn (C)
Phillip Russell/UAE Prussyggbjyllayy,coln (C)
Kevin Higgins/UAE};hi£4£úns@eneggggtral;;tal (C)
Neal Townsend/UAE ntç vnsengny (C)(W)
Sophie Hays/UCE 292¾Ø¾WilmLE (C)
Kate Bowman/UCE kid ߊstalige uieng;(C)(W)
Emma Rieves/UCE e @gigh;y (C)(W)
Erika Tedder/DPU dg et<;çà);r (C)
Lisa Tormoen Hickey/Interwestlisa)egg 2.cois (C)
Mitch Longson/Interwest mlongstorgill¾(C_)
Peter J.Mattheis/Nucor (C)
Eric J.Lacey/Nucor Morg (C)(W)
17-035-40 /Rocky Mountain Power
December 1,2017
WRA Data Request 2.1 -1st Supplemental
WRA Data Request 2.1
During the October 11,2017 Technical Conference held in Salt Lake City,Rick Link
stated that his team's modeling demonstrates that output from Wyodak and Dave
Johnston would increase and the output from Jim Bridger decline as a result of the
Combined Projects (1240 MW of new wind plus 140 mile 500 kV transmission line plus
the 230 kV Network Upgrades).Attachment OCS 1.31 -2 CONF.xlsx displays this
incremental output for Wyodak and Dave Johnston -specifically,the attachment displays
the GWh of increased generation in the case of new wind and transmission as compared
with wind repowering only for the years 2017 -2036.
(a)Reproduce Attachment OCS 1.31 -2 CONF.xlsx using current assumptions and
modeling parameters (if not previouslyused)but include generationdata for the Jim
Bridger plant.Display results using unit data level data.
(b)Does the additional transmission impact the dispatch of PacifiCorp's share of either
the Craig or Hayden plants?If so,include generation from Craig and Hayden in the
reproduction of OCSl.31 -2 CONF.xlsx.Provide unit level data.
(c)Do the Combined Projects impact the dispatch of the Hunter and Huntingtonunits?If
so,include generation from Hunter and Huntingtonin the reproduction of OCSl.31 -2
CONF.xlsx.Provide unit level data.
(d)Do the Combined Projects impact the dispatch of PacifiCorp's share of Colstrip?If
so,include Colstrip in the reproduction of OCSl.31 -2 CONF.xlsx.Provide unit level
data.
WRA Data Request 2.1 -16*SupplementalRequest
Quoted from WRA Data Request 2.1:"Attachment OCS 1.31-2 CONF.xlsx displays
incremental output for Wyodak and Dave Johnston -specifically,the attachment displays
the GWh of increased generation in the case of new wind and transmission as compared
with wind repowering only for the years 2017 -2036".
(a)Do the Combined Projects impact the dispatch of the Naughton and Bridger?If so,
reproduce Attachment OCS 1.31-2 CONF.xlsx but include generation from the Jim
Bridger and Naughton plants.Display results for all plants using unit level data.Your
response should be the equivalent for the Wyoming units of Attachment WRA 2.1-1
CONF.xlsx which provides redispatch information for the Hunter and Huntington
units and Attachment WRA 2.1-2 CONF.xlsx which provides redispatch information
for the Colstrip units.
(b)Do the Combined Projects impact the dispatch of PacifiCorp's share of either Craig
or Hayden?If so,include generationfrom Craig and Hayden in the reproduction of
OCS1.31-2 CONF.xlsx.Provide unit level data.Your response should be the
17-035-40 /Rocky Mountain Power
December 1,2017
WRA Data Request 2.1 -16*Supplemental
equivalent for the Colorado units of Attachment WRA 2.1-1 CONF.xlsx which
provides redispatch information for the Hunter and Huntingtonunits and Attachment
WRA 2.1-2 CONF.xlsx which provides redispatch information for the Colstrip units.
16'SupplementalResponse to WRA.Data Request 2.1
Please refer to the Confidential Attachment WRA 2.1 16'Supplemental,which provides
the requested information for Naughton,Jim Bridger,Craig and Hayden.
Confidential information is provided subject to Public Service Commission of Utah Rules