HomeMy WebLinkAbout20171016Attachment 55.pdfGATEWAY WEST TRANSMISSION LINE PROJECT
Pre-construction Items,including Notices to Proceed for Segments 1 --4
Applicable to the Shirley Basin to Aeolus to Jim Bridger Segments
(Greyed rows are completed)
October 6,2017
Notice to
ITEM Reference Proceed Status Timing Remarks/Comments
(Y/N)
Master Plan of Most recent version See Construction Spread There are 17 Appendices (C -S)
Development August 2013 POD.in the Master POD that may be
(POD)reviewed and approved
individually or in groups.(For Segments 1 -4)Finalized by
Construction NOTE:Two Master POD are
ROW Grant _Contractor anticipated,one for Segments 1 -
Y 4 and the other for Segments 5 -Stipulationla 10.
Since the company is proceeding
with only portions of Segments 1
-4,a Master POD won't be
developed,just the specific
Constructiog Spreg PODs.
Environmental Accepted in RODCompliancePOD,AppendixC Y (11/12/13)Management Plan
1
Notice to
ITEM Reference Proceed Status Timing Remarks/Comments
(Y/N)
Reclamation Plan NLTI one year prior to Develop specific reclamation
construction 4/1/18 monitoringrequirements,
including seed mixes and
.monitoringsites (POD,AppendixFrameworkPlaninD-Section 5 &7).
POD -finalized byPOD,AppendixD Y Construction NLT 120 days prior to Finalize Plan (POD Appendix D,
Contractor construction 12/1/18 Section 1.2).
Plan reviewedby BLM Field
Office Staffwith acceptance by
Authorized Officer.
Noxious Weed Plan NLT one year prior to Coordinate with BLM.to identify
construction -4/1/18 weed species to target for
preconstruction surveys and
location reporting format.
Conduct surveys.(POD,
Appendix E,Section 4.2).
ROW Grant -Framework Plan in Plan submitted for reviewbyStipulations10&11 Y POD -finalized by BLM Field Office Staffwith
Construction acceptance by Authorized
POD,AppendixE Contractor officer.
NLT 120 days prior to
construction 12/1/18 Determine if any preconstruction
surveys required or planned --
see EPM REC-14.
Pesticide Use Proposals reviewed
and approved (EPM:REC-5)
1This tracking sheet was developed collaboratively with the Bureau of Land Management project manager.The No Later Than (NLT)dates listed represent Bureau of Land
Management's initial recommended submittal dates.These dates will be refined as EPC work plans are submitted in December 2017 and a Compliance Inspection
Contract is awarded the end of January 2018.
2
Notice to
ITEM Reference Proceed Status Timing Remarks/Comments
(Y/N)
Stormwater NLT 120 days prior to Coordinated with approvals from
Pollution Framework Plan in construction 12/1/18 WY DEQ (POD Appendix F,
Prevention Plan POD -finalized by Section 2).
POD,AppendixF Y Construction Plan reviewedby BLM FieldContractorOfficeStaffwithacceptanceby
Authorized Officer.
Spill Prevention,NLT 120 days prior to Designates locations for storage,
Containment,and .construction 12/1/18 refueling,and lubrication of
Countermeasures Framework Plan in equipment and materials (POD
POD -finalized by Appendix G,Sections 1 &4).Plan POD,AppendixG Y Construction
Contractor Plan reviewedby BLM Field
Office Staffwith acceptance by
Authorized Officer.
Plant and Wildlife Framework Plan in NLT 120 days prior to Plan reviewedby BLM Field
Conservation POD -finalized by construction 12/1/18 office Staffwith acceptance by
Measures Plan POD,AppendixH Y Construction Authorized Officer.
Contractor
Wetland Delineation for denied Prior to construction,Right of entry needed for
Delineations EPM:WET-2 N access parcels pending needed for 404 permit multiple parcels in Wyoming.
ROE.Elmg.
Stream,Wetland,NLT 120 days prior to Coordinate with USACE
Well and Spring Framework Plan in construction 12/1/18 permitting (POD Appendix I,
Protection Plan POD -finalized by Section 1).
POD,AppendixI Y Construction Plan reviewedby BLM FieldContractorOfficeStaffwithacceptanceby
Authorized Officer.
3
Notice to
ITEM Reference Proceed Status Timing Remarks/Comments
(Y/N)
Paleontological NLT 6 months prior to Conduct preconstruction surveys
Resources Plan construction 10/1/18 in Class 3,4,and 5 Areas to
establish construction monitoringFrameworkPlaninlocations(POD Appendix J,POD,AppendixJ Y POD -finalized by Section 5 and EPM PALEO-5).
EPM:PALEO-5 Construction
Contractor Plan reviewedby regional
Paleontologist in Wyoming State
Office with acceptance by
Authorized Officer.
Agriculture Accepted in ROD
Protection Plan POD,AppendixK Y (11/12/13)
Traffic and NLT 9 months prior to Finalize project network,assign
Transportation Plan construction 7/1/18 road disturbance types,and
document preconstruction road
Framework Plan in conditions.Coordinate with state
POD -finalized by and county highway departments
POD,AppendixL Y (POD,Appendix L,Sections 1,5Constructionand8).Contractor
Plan reviewedby BLM Field
Office Staffwith acceptance by
Authorized Officer.
Blasting Plan Framework Plan in NLT 120 days prior to POD,Appendix M,Section 1
POD -finalized by construction 12/1/18
POD,AppendixM Y Plan reviewedby BLM FieldConstructionOfficeStaffwithacceptancebyContractorAuthorizedOfficer.
Erosion,Dust Framework Plan in NLT 120 days prior to POD,Appendix N,Section 1
Control and Air POD -finalized by construction 12/1/18
uali Pl POD,AppendixN Y Plan reviewedby BLM FieldQtyanConstructionOfficeStaffwithacceptancebyContractorAuthorizedOfficer.
Fire Prevention and Framework Plan in NLT 120 days prior to POD,Appendix O,Section 1
SuppressionPlan POD,AppendixO Y POD -finalized by construction 12/1/18
4
Notice to
ITEM Reference Proceed Status Timing Remarks/Comments
(Y/N)
Construction Plan reviewed by BLM Fire
Contractor Personnel with acceptance by
Authorized Officer.
Hazardous Framework Plan in NLT 120 days prior to POD,Appendix P,Section 1
Materials POD -finalized by construction 12/1/18
Management Plan POD,AppendixP Y Plan reviewed by BLM FieldConstructionOfficeStaffwithacceptancebyContractorAuthorizedOfficer.
Construction Framework Plan in NLT 120 days prior to POD,Appendix Q,Section 1
Emergency POD -finalized by construction 12/1/18
Preparedness and POD,AppendixQ Y Plan reviewed by BLM Field
Response Plan Construction Office Staffwith acceptance byContractorAuthorizedOfficer.
Operations,NLT 120 days prior to
Maintenance and Complete except for construction 12/1/18POD,AppendixR YEmergency emergency contact list
Response Plan
Cultural Resources Accepted in ROD Additional Cultural NTP
Protection Plan POD,AppendixS Y (11/12/13)requirements on page 10.
Preconstruction Accepted in ROD InformationalAppendix
Checklist POD,AppendixT N (11/12/13)
Flagging,Fencing Framework Plan in NLT 120 days prior to POD,Appendix U,Section 1
and Signage Plan POD -finalized by construction 12/1/18
POD,AppendixU Y Plan reviewed by BLM FieldConstructionOfficeStaffwithacceptancebyContractorAuthorizedOfficer
PacifiCorp's
Transmission Accepted in RODPOD,AppendixV YConstruction (11/12/13)
Standards
PacifiCorp's and .Accepted m RODIdahoPower's POD,AppendixW Y (11/12/13)Vegetation
5
Notice to
ITEM Reference Proceed Status Timing Remarks/Comments
(Y/N)
Management
Program
Legal Land POD,AppendixX N Accepted in ROD InformationalAppendix
Descriptions (11/12/13)
Other Information Accepted in ROD Placeholder AppendixPOD,AppendixY N (11/12/13)
Environmental Accepted in RODPOD,AppendixZ YProtectionMeasures (11/12/13)
Construction Number and location of First draft for BLM review Construction POD specific to the
Spread PODs spreads determinedby January 2019.
ROW Grant -construction contractor.Y Contents follow Draft BLMStipulation1bHandbookH-2801-1 and include
items 10,13,16,17,18,33 and
34 from Appendix T of the POD.
Preconstruction Survey plans and NTP for each species,approved
Special Status protocols for each individually or in groups.
Species Surveys species listed below are
(Listed Below)currentlyunder reviewROWGrant--Y for the 2018 fieldStipulation1cseasonforapproval by
each Bureau of Land
Managementfield
office.
Bald Eagle FEIS 3.11-16,3.11-March --July Habitat in Segments 1 --10.
43 Y
EPM:WILD-4
BurrowingOwl FEIS 3.11-16,3.11-Habitat in Segments 1 -10.
45 Y
EPM:WILD-4
Ferruginous Hawk FEIS 3.11-16 Y Habitat in Segments 1 --10
6
Notice to
ITEM Reference Proceed Status Timing Remarks/Comments
(Y/N)
EPM:WILD-4
Greater Sage-grouse FEIS 3.11-16 Y April -Mid-May (lek Habitat in Segments 1 -10.
EPM:TESWL-5 surveys)
Midget Faded Mid-June Habitat in Segment 3 betweenEPM:TESWL-13 Y MP 11-76Rattlesnake
Migratory Birds Segments 1 -10.Only required
if vegetative clearing is not
EPM:WILD-9 Y completed before breeding
season (generally April 15
through July 31)
Mountain Plover FEIS 3.11-16,3.11-Habitat in Segments 1 -4,WY
47 Y only.
Pygmy Rabbit FEIS 3.11-16,3.11-Y Habitat in Segments 2 -10.
48
Other Raptor Includes Golden Eagle,Prairie
Species EPM:WILD-4 &8 Y Falcon,Red-tailed Hawk,and
Swainson's Hawk
White-tailed Prairie FEIS 3.11-17,3.11-Habitat in Segments 1 -4.
Dog 49 Y
EPM:TESWL-3
WyomingPocket FEIS 3.11-17,3.11-Y Habitat in Segments 2 -4.
Gopher 50
Blowout Penstemon No suitable habitat in June Endangered species in Wyoming
EPM:TESPL-1 Y project area per BA.only.
FWS concur in BO.
.NTP issued 8/27/15NoSurveyrequired
Colorado Butterfly No suitable habitat in July --September Threatened species in Wyoming
Plant project area per BA.only.EPM:TESPL-2 Y .FWS concur m BO.NTP issued 8/27/15NoSurveyrequired
Rare Plant Survey EPM:TESPL-3 Y Survey for plants on BLM &FS
special status species lists.
7
Notice to
ITEM Reference Proceed Status Timing Remarks/Comments
(Y/N)
okseCcrheek EPM:TESPL-6 Y No survey required for May --June Candidate species in Idaho only
Segments 1 -4.(Alternative7K).
Slickspot EPM:TESPL-4 Y No survey required for April --May Habitat in Segments 8 &9.
Peppergrass Segments 1 -4.Multi-year (3)survey required.
Ute Ladies'-tresses Survey completed August No additional survey required per
through 2014.No email from FWS on 7/01/15.
EPM:TESPL-7 Y plants found.
BLM accepted survey
6/10/14 and 2/23/15.
Wyoming Sage-9/6/17 Agency meeting Working with agencies to
grouse Mitigation and field trip to discuss Run HEA model by end of establish oversight committee to
Plan HEA approach and Q4 2017 administer mitigation projects
Agency review Ql 2018 and funding by Ql 2018.On
ROW Grant -
schedule·Finalize HEA Q2 2018 track.
Y IdentifypotentialStipulation1dmitigation
projects/opportunities Q2
2018
Final approval/NTPQ3
2018
Migratory Bird v.BLM accepted Plan Funding will be provided NTP issued when funding
Habitat ROW Grant -12/19/14 with March 2019.provided.YConservationPlanStipulation1e exception to finalize
fund administration
8
Notice to
ITEM Reference Proceed Status Timing Remarks/Comments
(Y/N)
Class III Inventory Amended PA signed Final Class III Report on Class III reviewproceeds as
Reports by FO 2/17/16,dictates Class track for submittal to follows:
Bureau of Land 1.Initial reviewby BonniIIIReportformatfor
.Management on 12/15/17 Bruce or ISOWyommgwhichwillprovidebasis2.Draft Report to each FO
for developing specific 3.Returned to AECom for
2nd Amended PA out Historic Properties corrections
for signature 10/4/17 to Treatment Plans.4.Second reviewby FO
5.Returned to AECom forNationalHistoricNaddressthecurrentcorrectionsPreservationActsegmentphasing·6.Final Reviewand acceptance
by FO
BLM/Native American 7.NativeAmerican
consultation to be consultation
8.Review by SHPOinitiatedFall20179.Returned to SWCA for(Step 7)-corrections
10.Final Acceptance
Draft Class III Report submitted
3/13/201 /
Rawlins FO -Class FinalizingClass III December 2017
III Report N report
Rock Springs FO -FinalizingClass III December 2017
Class III Report N report
9
Notice to
ITEM Reference Proceed Status Timing Remarks/Comments
(Y/N)
Project-wide v.1 submitted 12/18/12 Umbrella HPTP revised Trails included in Segment Plans.
Historic Properties v.2 submitted 9/12/13 submittal due 02/x/2018 Concurring parties review
.complete.Accepted by WYTreatmentPlaninPOD.Plan Acceptance May BLM.Finahzed after ConcurringROWGrant-v.3 submitted 2018 Parties review.Only BLM andStipulation1fY8/15/2015 SHPO need accept.
POD AppendixS,v.4 submitted 02/02/16 BLM coordinating
Attach.S-2 handling of NAGPRA,etc.Site-specific treatment plans
-with WY SHPO for determined by Class III reportFOreviewcompleted.finalization review(ROW Grant Stipulation
lg).
Work Element Will be developedat May 2018 Segment Plan coverages based on
HPTP -Shirley ROW Grant -completion of Class III this phase of the overallGateway
Basin -Aeolus -Stipulation1g report for this segment.West project.
Jim Bridger
Platte River Water needs Reviewof water use Payment made to FWS on
Recovery determined by proposed by the contractor amount of water withdrawnfromROWGrant-(Fall 2018 LNTP).Not to basin.NTP issued with FWSAgreementYconstructioncontractorStipulation1hexceed(96 acre-confirms payment received.NO
feet/year:31.3 M gallons)new net depletion letter received
from State Engineer 4/18/2013
Upper Colorado Water needs Determine needed action Proponents intend to obtain water
River Endangered .determined by when water source and fromsources with existingEndangeredSpeciesamountknown.consultation.If obtamed fromFishRecoveryNconstructioncontractor.Act Fall 2018 after LNTP non-consultation sources,Program consultation and a payment to
FWS is required
Construction/BLM requests bond NLT 6 Bond amount determined based
Reclamation Bond ROW Grant -months prior to on the Final Plans of
Stipulation1k,construction.Bond in Development and the
.Y place NLT 90 days prior to Reclamation,Restoration andTermandCondition.construction.Revegetation Plan;followmg
guidance in BLM Manual
2885.11E
10
11