HomeMy WebLinkAbout20170906Staff 48-51 to PAC Revised.pdfBRANDON KARPEN DEPUTY ATTORNEY GENERAL IDAHO PUBLIC UTILITIES COMMISSION PO BOX 83720 BOISE,IDAHO 83720-0074 (208)334-0357 IDAHO BAR NO.7956 Street Address for Express Mail: 472 W.WASHINGTON BOISE,IDAHO 83702-5918 Attorneys for the Commission Staff BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION OF ) PACIFICORP DBA ROCKY MOUNTAIN )CASE NO.PAC-E-17-07 POWER FOR A CERTIFICATE OF PUBLIC )CONVENIENCE AND NECESSITY AND )BINDING RATEMAKING TREATMENT FOR )REVISED SECOND NEW WIND AND TRANSMISSION FACILITIES)PRODUCTION REQUESTOF )THE COMMISSION STAFF )TO ROCKY MOUNTAIN )POWER The Staff of the Idaho Public Utilities Commission requests that Rocky Mountain Power provide the followingdocuments and information as soon as possible,but no later than WEDNESDAY,SEPTEMBER 27,2017. This Production Request is to be considered continuing,and Rocky Mountain Power is requested to provide,by way of supplementary responses,additional documents that it or any person acting on its behalf may later obtain that will augment the documents or information produced. Please provide answers to each question,supporting workpapers that provide detail or are the source of information used in calculations,and the name,job title and telephonenumber of the person preparing the documents.Please identify the name,job title,location and telephone number of the record holder. REVISED SECOND PRODUCTION REQUEST TO ROCKY MOUNTAIN POWER 1 SEPTEMBER 6,2017 In addition to the written copies provided as response to the requests,please provide all Excel and electronic files on CD with formulas activated. REQUESTNO.48:Please compare in detail the Naughton plant's contribution to PacifiCorp's system,with and without the Company's proposed project throughoutthe defined remaining life.Further,please provide the followingfor each plant unit from 2017 to the plant end of life: 1.Total Variable Costs ($)-(i.e.fuel,start-up,CO2,operation and maintenance,...) 2.Total Fixed Costs ($)-(fixed operation and maintenance,depreciation,...) 3.Net Generation(MWh) 4.Capacity Factor (%) 5.Cost per mega-watt hour ($/MWh)based on Total Variable Cost 6.Cost per mega-watt hour ($/MWh)based on Total Variable and Fixed Cost REQUESTNO.49:In the context of Production Request No.49,did the Company evaluate an earlier closure of the Naughton units based on implementation of this project?If so, please provide any analysis.If not,does the Company believe this should be evaluated?Please explain. REQUESTNO.50:Please compare in detail the Hayden plant's contribution to PacifiCorp's system with and without the Company's proposed project throughoutthe defined remaining life.Further,please specifically provide the followingfor each plant unit from 2017 to the plant end of life: 1.Total Variable Costs ($)-(i.e.fuel,start-up,CO2,operation and maintenance,...) 2.Total Fixed Costs ($)-(fixed operation and maintenance,depreciation,...) 3.Net Generation (MWh) 4.Capacity Factor (%) 5.Cost per mega-watt hour ($/MWh)based on Total Variable Cost 6.Cost per mega-watt hour ($/MWh)based on Total Variable and Fixed Cost REVISED SECOND PRODUCTION REQUEST TO ROCKY MOUNTAIN POWER 2 SEPTEMBER 6,2017 REQUESTNO.51:In the context of Production Request No.51,did the Company evaluate a sale or early closure of the Hayden units based on implementation of this project?If so,please provide any analysis.If not,does the Company believe this should be evaluated? Please explain. DATED at Boise,Idaho,this &day of September 2017. Bran Karpen Deputy AttorneyGeneral Technical Staff:Rick Keller/48-51 i:umisc:prodreq/pace17.7bkrk prod req 2 REVISED SECOND PRODUCTION REQUEST TO ROCKY MOUNTAIN POWER 3 SEPTEMBER 6,2017 CERTIFICATE OF SERVICE I HEREBY CERTIFY THAT I HAVE THIS 6TH DAY OF SEPTEMBER 2017, SERVED THE FOREGOING REVISED SECOND PRODUCTION REQUESTOF THE COMMISSION STAFF TO ROCKY MOUNTAIN POWER,IN CASE NO. PAC-E-17-07,BY MAILING A COPY THEREOF,POSTAGE PREPAID,TO THE FOLLOWING: TED WESTON YVONNE R HOGLE ROCKY MOUNTAIN POWER ASSITANT GENERAL COUNSEL 1407 WEST NORTH TEMPLE STE 330 ROCKY MOUNTAIN POWER SALT LAKE CITY UT 84116 1407 WN TEMPLE STE 320 E-MAIL:ted.weston@pacificorp.com SALT LAKE CITY UT 84116 E-MAIL:Yvonne.hogle@pacificorp.com DATA REQUEST RESPONSE CENTER RANDALL C BUDGE E-MAIL ONLY:RACINE OLSON NYE &BUDGE datarequest pacificorp.com PO BOX 1391 POCATELLO ID 83204-1391 E-MAIL:rcb racinelaw.net BRUBAKER &ASSOCIATES RONALD L WILLIAMS 16690 SWINGLEY RIDGE RD #140 WILLIAMS BRADBURY PC CHESTERFIELD MO 63017 PO BOX 388 E-MAIL:kiverson@consultbai.com BOISE ID 83701 mbrubaker@consultbai.com E-MAIL:ron@williamsbradbury.com ELECTRONIC ONLY ELECTRONIC ONLY JOHN DUKE KYLE WILLIAMS IDAHOAN FOODS BYU IDAHO E-MAIL:iduke@idahoan.com E-MAIL:williamsk@byui.edu ELECTRONIC ONLY ERIC L OLSEN VAL STEINER ECHO HAWK &OLSEN NU-WEST INDUSTRIES INC PO BOX 6119 E-MAIL:val.steiner agrium.com POCATELLO ID 83205 E-MAIL:elo echohawk.com ANTHONY YANKEL UNIT 2505 12700 LANE AVENUE LAKEWOOD OH 44107 E-MAIL:tony yankel.net SECRETARY CERTIFICATE OF SERVICE