HomeMy WebLinkAbout20020904Volume 3, pg 248-319.pdf
1 (The following proceedings were
2 had in open hearing.)
3 MR. FELL: And we'd move for the
4 admission of Exhibits 1 through 3, and 17 through
5 22.
6 COMMISSIONER SMITH: Without
7 objection, we will admit Exhibits 1 through 3, and
8 17 through 22.
9 (PacifiCorp Exhibit Nos. 1 through
10 3 and 17 through 22 were admitted into evidence.)
11 MR. FELL: And Mr. Taylor is available
12 for cross-examination.
13 COMMISSIONER SMITH: Thank you.
14 Mr. Olsen, do you have questions?
15 MR. OLSEN: Yes.
16
17 CROSS-EXAMINATION
18
19 BY MR. OLSEN:
20 Q. Mr. Taylor, after Monsanto, wasn't it
21 fair to say that the irrigation class, which is on
22 the PacifiCorp schedule as number ten, is the second
23 largest class of customers on the PacifiCorp's Idaho
24 system?
25 A. Oh, I'd have to look and see. Let me
248
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 look at something real quick. Okay?
2 Q. Sure.
3 A. If you're speaking in terms of
4 revenue, in terms of kilowatt hour?
5 Q. Demand, revenue?
6 A. That appears to be correct. They're
7 just slightly larger than the residential class.
8 Q. Now, I worked with you on the prior
9 PAC-E-02-01 case, and in that case we recently
10 reached a settlement between Irrigators and
11 PacifiCorp, and as part of that, the load control
12 feature that the Irrigators had before was removed
13 from the tariff. Isn't that correct?
14 A. That's correct.
15 Q. Now, you're familiar with the prior
16 tariff schedule which was previously referred to as
17 the ABC rates for the Irrigators?
18 A. Yes, generally.
19 Q. Generally. Now, did the A rate
20 provide a firm service to the customers?
21 A. The A rate was the rate for which
22 there were no option to curtail, yes.
23 Q. And the C rate was a curtailment
24 option?
25 A. At the Company's option, yes.
249
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Q. At the Company's option. Okay.
2 Now, what was the price differential,
3 generally, between those two rates?
4 A. I don't recall. If you have a
5 number --
6 Q. Just the A rate was higher?
7 A. A rate was higher. The B rate, which
8 was a designated day rate, was somewhat lower than
9 the C rate, was lower than that.
10 Q. But, generally, interruptibility
11 feature provided some credit back for that?
12 A. Yes, those Irrigators that took the C
13 option had a lower price for electricity.
14 Q. And would it be fair to say that most
15 irrigation customers were on the C rate?
16 A. The bulk of the customers were on the
17 C rate, yes.
18 Q. Now, there has been some discussion in
19 various testimony that the Irrigators had removed
20 interruptibility provisions from the tariff schedule
21 in the recent settlement that had been reached with
22 PacifiCorp.
23 Isn't it fair to say that the ability
24 to allow them to remove that interruptibility
25 feature was due in large part to the -- I guess the
250
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 extraordinary BPA credit that mitigated potential
2 price increases and the pass-through of the excess
3 power costs?
4 A. Right. The Company was able to obtain
5 a substantial benefit from Bonneville Power
6 Administration through the BPA credit, the bulk of
7 which or a large substantial portion of which flows
8 to the irrigation customers. Combining that with
9 the rate meant that the Irrigators could actually
10 pump at a lower price than they had previously and
11 get full firm service without any potential
12 interruptions. So the irrigation community thought
13 that was a good deal, the Company thought that was a
14 good deal, and so those options were eliminated.
15 Q. Now, as part of that settlement,
16 wasn't the agreement conditioned on if there was
17 ever a change in the cost of service structure or if
18 the BPA credit expired, that that agreement would go
19 away?
20 A. I don't specifically recall all the
21 issues in the settlement.
22 Q. Subject to check, or I could represent
23 that that was the case?
24 A. Yes, subject to check, I would agree
25 with you.
251
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Q. Now, upon expiration of the BPA
2 credit, which in large part made it -- the ability
3 of the Irrigators to agree to the current rate
4 structure as it is, wouldn't you agree that the
5 irrigation class could potentially face a dramatic
6 increase in energy prices or electric prices upon
7 this expiration of the BPA credit?
8 A. Well, if the BPA credit changes and
9 becomes smaller, then the net price that customers
10 would pay would be higher, yeah.
11 Q. Okay. I want to just ask you a
12 hypothetical scenario:
13 Assume that Monsanto receives a rate
14 in this proceedings that when combined with I guess
15 the world phosphate markets, it just doesn't make it
16 economically feasible for them to operate again or
17 operate here in Idaho. Would it be fair to say that
18 the operating costs for your PacifiCorp's Idaho
19 system that were covered by Monsanto's load and
20 their revenue would have to be re-allocated to other
21 Idaho customer classes?
22 A. No, not necessarily, because what
23 would happen if Monsanto went away completely as a
24 customer, that would change not only costs in Idaho
25 but costs across the whole system and the
252
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 jurisdictional allocation would also change, and so
2 Idaho -- any impact of that, Idaho would only see
3 its proportional share.
4 Q. But wouldn't that depend on whether
5 you treat Monsanto as a system customer or a situs
6 customer?
7 A. No. If you treat Monsanto as a situs
8 customer and they shut down, then there's no longer
9 any load for Monsanto to be part of the allocation
10 to Idaho, and so any costs which were formerly
11 allocated to Idaho as a result of serving Monsanto
12 would now go away and be redistributed across all
13 the states through the allocation process.
14 Q. So, I mean, basically there would be
15 no costs that would have to be shifted to the Idaho
16 customers basically?
17 A. I didn't say there were no costs. I
18 mean, if there is a negative impact on the total
19 system -- and at this point we don't know that that
20 would be the case; it might be a net benefit to the
21 system just depending on the load to resource
22 balance -- but any impact on the system, Idaho would
23 see their proportional share, but they wouldn't see
24 the total impact.
25 Q. They wouldn't see the total impact
253
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 being positive or negative, and assuming it's
2 negative, then they see their proportionate share
3 from that situation?
4 A. That's correct.
5 Q. Let's just say, for example, we have a
6 situation where either the BPA credit has gone away
7 or Monsanto has gone away and we have pressure on
8 irrigation prices to go up. Would the
9 reimplementation or a further refinement of the
10 irrigation load program be a valid rate-making tool
11 to help keep the irrigation prices low?
12 A. I think if the situation presented
13 itself, that the Company looked at that and there
14 was a benefit to both the Company and to the
15 irrigation customers, we could look at reinstituting
16 some form of load control program or some other
17 instrument that would provide value to both.
18 Q. Do you recall in the most recent rate
19 case here that we had negotiated commitment by the
20 Company to I guess work with the Irrigators to
21 continue a load control program?
22 A. I think we reached an agreement that
23 we would continue to explore those options.
24 Q. And as I recall, we were supposed to
25 do that hopefully by some time the first of January
254
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 or the end of January, 2003.
2 MR. OLSEN: I don't have any further
3 questions.
4 COMMISSIONER SMITH: Thank you,
5 Mr. Olsen.
6 Mr. Woodbury.
7 MR. WOODBURY: Thank you, Madam Chair.
8
9 CROSS-EXAMINATION
10
11 BY MR. WOODBURY:
12 Q. Good afternoon, Mr. Taylor.
13 A. Good afternoon.
14 Q. You're familiar with the structural
15 realignment proposal of the Company?
16 A. Yes.
17 Q. You make reference to it on page 7 of
18 your testimony.
19 Do you know what the status of -- does
20 the Company have a filing docket in this -- in this
21 state?
22 A. I'm not sure of the exact status state
23 by state. In some states that filing is just on
24 hold pending the multistate process discussions; in
25 some other states, it's actually suspended. So I
255
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 don't know what the exact status is in Idaho, if
2 it's still just pending on being delayed or if it
3 was actually suspended.
4 Q. There's been no action in that docket
5 for some time. Would you agree?
6 A. Yes.
7 Q. And you're familiar also with the
8 multistate process?
9 A. Yes.
10 Q. And would you agree that there are
11 issues being taken up in the multistate process
12 which have a direct bearing on the contract that
13 we're considering today?
14 A. Yeah. Could you be specific in what
15 you're referring to?
16 Q. Sure. Interruptibility, value, the
17 situs versus system treatment of interruptible
18 customers. Those are all presently being discussed
19 in the MSP process?
20 A. Yes, there have been lengthy
21 discussions on how interruptible contracts and other
22 nontariff contracts should be treated in the context
23 of jurisdictional allocation.
24 Q. Is there any reason to put this case
25 into a hold pattern until those issues are resolved
256
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 in the MSP forum?
2 A. Well, I'm not sure how long that
3 holding pattern would be. I would like to think
4 we'll get the issues in MSP resolved in the next few
5 months, but that may be very optimistic on my part.
6 I think a Decision needs to be made here at least
7 that would be implemented in the interim until a
8 final resolution on the treatment of special
9 contracts is agreed to amongst all states in the
10 MSP.
11 Q. It's been -- it's been represented in
12 this case that PacifiCorp in its merger case made a
13 commitment and agreed to assume the risk of
14 disparate treatment I guess by its individual
15 jurisdictional states. Do you recall reading that?
16 A. I'm aware that we've -- that we have
17 committed to take upon ourselves the risk of
18 jurisdictional allocations, yes.
19 Q. And why should this Commission not
20 hold the Company to that commitment?
21 A. Because I think what we're doing here
22 is we're trying to mitigate the issues of exposure
23 of jurisdictional allocation risk. We're still
24 bearing it; we're just trying to do things in this
25 case to mitigate it or manage it. So I think
257
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 there's a difference between taking action here and
2 saying the Company doesn't have any responsibility.
3 We're taking the responsibility; we're just trying
4 to mitigate it.
5 Q. With respect to in the MSP process,
6 with respect to treatment of interruptible
7 customers, hasn't it been discussed that -- to treat
8 Monsanto as a separate jurisdictional customer?
9 A. I think that issue has been broached
10 somewhat by some parties that perhaps one way to
11 deal with an interruptible customer such as Monsanto
12 and perhaps more than just Monsanto is to put them
13 in their own separate jurisdiction. So far that's
14 just been a proposal that's been thrown out by
15 parties. The only way that it's been discussed at
16 length are the pros and cons of that.
17 Q. If, in fact, that position were
18 adopted, how would that affect contracting with
19 Monsanto?
20 A. Well, I'm not sure, because I'm not
21 sure under which Commission jurisdiction that new
22 special contract jurisdiction would fall. Would
23 have to fall under the jurisdiction of some
24 regulatory body.
25 Q. Okay. And could you -- is it
258
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 reasonable that it should fall under this
2 Commission's jurisdiction?
3 A. If Monsanto were the only customer in
4 that jurisdiction, it would seem to make sense that
5 it should fall here.
6 One of the troubling things I have
7 with a single customer jurisdiction is what do you
8 do in the case if the final establishment of the
9 revenues to be collected from the customer does not
10 match the allocated revenue requirement to the
11 jurisdiction. I don't know how you deal with that
12 if there's only one customer in the jurisdiction.
13 Q. You're familiar with the 1995 contract
14 with Monsanto?
15 A. Generally.
16 Q. And that contract was approved by this
17 Commission in 1995, and as part of that, there was a
18 $30 million payment for a contract buyout payment?
19 A. Yes.
20 Q. Is that your understanding of what
21 that was?
22 A. Yes.
23 Q. And you indicate in your testimony
24 that taking that payment and amortizing that out
25 over the length of the contract gives you an
259
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 effective rate of 23.2 mills?
2 A. Yes, if you amortize the 30 million.
3 Q. And that was amortizing it out over
4 how many years?
5 A. I believe there were 74 months in that
6 contract term, if my memory serves me correctly.
7 Q. And should the Federal District Court
8 determine that a longer period was required, what
9 would that do to the amortization amount?
10 A. Well, if you were to spread that over
11 an additional year, it would obviously lower the
12 annual amount.
13 Q. It was represented by PacifiCorp when
14 it presented the '95 contract for Commission
15 approval that Monsanto had other -- had viable
16 alternatives, and could you indicate what those
17 alternatives to service were?
18 A. I didn't participate in that, so I'll
19 tell you what my understanding is and I may not
20 catch them all, but creating I think a municipal
21 utility or something from which to take service from
22 is perhaps one alternative. Going to a different
23 production process that required less energy usage
24 or something I think was another. But there may
25 have been others that I'm not specifically familiar
260
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 with.
2 Q. And in considering your negotiation
3 with Monsanto in this case, did the Company perceive
4 that any of those alternatives continue to remain
5 viable?
6 A. I think other than switching the
7 production process to something different, I don't
8 know that the other alternatives are maybe still on
9 the table as viable alternatives.
10 Q. The results -- or, you used a 1999
11 test period in your class cost of service, and the
12 results of operations, those were 1998 results of
13 operations that were pro-formed (sic) to 1999. Is
14 that your understanding?
15 A. I think it was they were both 1999
16 periods, but I could be mistaken.
17 Q. And when you say that they were
18 already filed with the Commission in a particular
19 case docket --
20 A. Well, we have a filing requirement
21 that used to be annual but now it's every other year
22 to file an informal cost-of-service study under an
23 unbundling set of procedures, and this '99 study was
24 originally filed in that proceeding. However, in
25 that proceeding, you know, all special contracts
261
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 were treated as system resources, and so there were
2 some modifications made to that.
3 Q. Do you understand -- PacifiCorp
4 understands Monsanto's stated need for price
5 certainty and stability in its contracts?
6 A. Well, Monsanto has certainly made a
7 point of that.
8 Q. Is it PacifiCorp's position that, in
9 fact, Monsanto doesn't need price certainty in its
10 contract?
11 A. I think we're accepting their
12 statements as they lay out that price stability is
13 very important to them.
14 Q. And PacifiCorp is insisting on
15 reopener provisions in both -- both of the
16 contracts, the retail sales and the wholesale
17 purchase, of some form?
18 A. That's my understanding, that
19 Mr. Griswold represented that.
20 Q. Do you know -- are you familiar with
21 the recent contracts of Magcorp and Empire?
22 A. I'm familiar with the Magcorp contract
23 to some degree.
24 Q. And did -- are there reopener
25 provisions included in that contract?
262
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 A. That contract's I believe only a
2 three-year duration. The contract -- and I think
3 there are some provisions after the second year
4 based upon the findings of the task force in Utah
5 that has some limited options to revisit it.
6 Q. I believe that Mr. Griswold indicated
7 a one- to three-year contract was a short contract.
8 Are you stating that if a three-year contract were
9 acceptable to Monsanto, that the Company would not
10 be insisting on reopener provisions?
11 A. I think there would be less need for
12 those.
13 Q. In the cost-of-study analysis entered
14 into this case, you're proposing some adjustments.
15 Do you believe it's appropriate to adjust cost of
16 service outside of a general rate case?
17 A. Well, it's been a long time since
18 we've had a general rate case that addressed cost of
19 service issues in Idaho and so I made some specific
20 adjustments here that I thought were relevant to the
21 case at hand, particularly relevant to treating
22 Monsanto as part of the cost-of-service analysis.
23 Q. You do state in your rebuttal
24 testimony that any change in cost allocation away
25 from Monsanto causes a shift of cost toward other
263
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 customers?
2 A. That's correct.
3 Q. In looking at that Exhibit 9 letter
4 from Frank Mitchell, it says that PacifiCorp agreed
5 to change several assumptions in a cost-of-service
6 model that reduced the estimate of cost of service
7 for Monsanto by over 10 percent. Do you know
8 whether those changes have been incorporated into
9 the Company's proposal in this case?
10 A. Right. The changes that we made were,
11 one, we agreed to look at the allocation to Idaho
12 under a rolled-in allocation methodology as opposed
13 to modified accord. We made that adjustment because
14 the Staff had indicated that that was the direction
15 they were leaning as they had reviewed the Company's
16 results in the last couple years.
17 Second, we agreed to use a lower rate
18 of return than originally proposed. We proposed
19 originally a 11-and-a-half-percent return on equity,
20 which was consistent with the Company's findings at
21 the time. We agreed to use a rate of return that
22 was more in line to what the Idaho jursidiction is
23 currently producing.
24 And, third, we agreed to a change in
25 how the allocation of demand-side management or
264
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 energy efficiency costs were shared among customer
2 classes in a way that assigned fewer of those to
3 Monsanto, so those were incorporated into this
4 filing.
5 Q. And so the result of those changes
6 would be a shifting of costs to Idaho's other
7 customers?
8 A. That's only the last one of those
9 would be a shifting of cost to other customers. The
10 others was a shifting of cost to Idaho -- a
11 reduction of cost to Idaho which would benefit all
12 customers. The rate of return issue was just simply
13 the rate was used to set the target for Monsanto, so
14 that, in and of itself, didn't have any impact on
15 other customers. The change in the allocation of
16 DSM costs, yes, would shift costs between customer
17 classes.
18 Q. Regarding the '95 contract, what would
19 have been the contract price if the previous
20 contract had expired in '95?
21 A. I'm not quite sure I track your
22 question.
23 Q. Assuming that there was -- assuming
24 that the previous contract expired by its terms and
25 the Company was made ineffective if it had an
265
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 agreement and you were successful in exercising it
2 and it expired in '95?
3 A. Well, actually, I think it would have
4 expired in the end of 1997.
5 Q. No, that would have -- I'm saying if
6 the contract had expired and there was no buyout
7 required of the remaining term, what would the
8 Company have established the rate at?
9 A. I don't know. We would have gone
10 through a proceeding then and established a new rate
11 that we felt was cost compensatory to the Company
12 and to other customers.
13 Q. What rate did the contract call for in
14 1995?
15 A. Let me look for a moment. I know that
16 the contract rate was set to go to -- up as high as
17 $26 a megawatt hour towards the end of the
18 contract. I don't remember exactly what it was year
19 by year. I'd have to find that in my highly
20 organized papers here.
21 Q. It would have escalated to $26 in
22 1997?
23 A. That's correct.
24 Q. Is, looking at your rebuttal on
25 page 17, PacifiCorp's intent that the other states
266
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 find the interruptibility credit too high, to come
2 back to this Commission and request situs treatment
3 of the difference? That's correct?
4 A. Yes.
5 Q. Can we discuss, there was concept of
6 gradualism that was addressed by some of the
7 parties -- I believe Monsanto -- and this was
8 apparently an issue in Utah, in your Utah
9 jurisdiction. Does the Company adhere to that
10 concept as it plays into rate shock and --
11 A. Well, it depends on your definition of
12 "gradualism" and what it means by adhering to it.
13 Q. Well, let me say do you feel that the
14 rate that you're proposing for Monsanto in this case
15 and compared to the rate that they presently have
16 is -- could be interpreted by some as rate shock?
17 A. If you look at in that very narrow
18 view going from the rate they pay today to the rate
19 that we propose, that is a big change. You need to
20 understand in the context of that, we're going from
21 one contract that ran for in excess of six years to
22 a new contract. So if you have a fixed-price
23 contract that runs for a long period of time and you
24 go into another fixed-price contract that's set to
25 run for another period of years, you're not going to
267
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 have I wouldn't expect a smooth transition in those
2 prices like you'd expect to see under a situation of
3 ongoing rate cases in a jurisdiction where you have
4 periodic opportunities to change prices. You're
5 going to do that in chunks.
6 Also, if you compare that against the
7 '95 contract, which I believe was established under
8 a unique set of circumstances for a specific period
9 of time, I'm not even sure that's the correct
10 comparison to make as to whether or not this is fair
11 or this is a reasonable or this is a gradual change
12 in prices.
13 Q. The 1995 contract contained a rate of
14 18.5 mills that was essentially in place for the
15 entire term of the contract, but the one that
16 preceded it we hear was escalating to 26 mills in
17 1997?
18 A. That's correct.
19 Q. Is it possible to address that
20 gradualism by stairstepping the rate or having an
21 escalating rate in the contract that we're
22 considering here?
23 A. That's possible.
24 Q. You speak of the 12 CP method in the
25 cost of service study. Wouldn't you agree that
268
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 unless Monsanto is situs and being served at cost of
2 service, any change to 8 CP would increase the cost
3 to other customers?
4 A. Yes, I think going from a 12 CP
5 allocation to an 8 CP allocation would increase the
6 allocation to Idaho, and therefore would increase
7 costs for other customers in Idaho.
8 MR. WOODBURY: Madam Chair, Staff has
9 no further questions.
10 COMMISSIONER SMITH: Thank you,
11 Mr. Woodbury.
12 Let's take about a short break. How
13 about 25 to four we'll be back.
14 (Recess.)
15 COMMISSIONER SMITH: We'll go back on
16 the record. Mr. Budge.
17 MR. BUDGE: Thank you.
18
19 CROSS-EXAMINATION
20
21 BY MR. BUDGE:
22 Q. Mr. Taylor, in the Company's JAM
23 studies -- Jurisdictional Allocation Model
24 studies -- that determine cost of service, that was
25 based on a 1999 test year. Correct?
269
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 A. That's correct.
2 Q. And I think you've clarified now in
3 your correction of your direct testimony that you
4 now agree that that test year was an unaudited
5 number?
6 A. Yes.
7 Q. And the filing with the Commission
8 with respect to that number would have simply been
9 the part of the annual informational filing?
10 A. Yes, that's correct.
11 Q. And is it true that the 1999 test year
12 numbers would have been derived covering a period
13 before the ScottishPower/PacifiCorp merger was
14 approved?
15 A. I think that's right.
16 Q. So when I look at the PacifiCorp 10k
17 report for the fiscal year ending March 31, it makes
18 this statement: The Company achieved 110 --
19 101 million, or 12 percent, reduction in operations
20 and maintenance in administrative, general, and
21 other tax expenses, which can be largely
22 attributable in savings realized in implementation
23 of the transition plan, the May 2000 sale of the
24 Centralia plant and mine, and the favorable variance
25 due to the $23 million pretax write-off of assets
270
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 under construction.
2 Would it be accurate to say that none
3 of those savings would be reflected in the data that
4 were part of the input for your cost-of-service
5 study?
6 A. No, nor would any additional costs
7 that the Company had incurred since that time be
8 reflected in that test period.
9 Q. And when I read the ScottishPower
10 annual review for the next two years, 2001 and 2002,
11 it makes a statement that good progress continues to
12 be made with the PacifiCorp transition plan with the
13 cumulative two-year cost savings achieved of
14 117 million, which is ahead of the $113 million
15 projected in the plan for 2001 and 2002.
16 Is it also true that these are savings
17 that would not be captured or reflected in the
18 cost-of-service study that you put together using
19 1999 test year data?
20 A. Yeah, anything that happened after
21 that date wouldn't be reflected in either cost
22 savings or cost increases in other areas of the
23 Company.
24 Q. And isn't it true that the Company, in
25 fact, sold the Centralia assets after '99?
271
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 A. I don't recall the date of that, but I
2 wouldn't dispute your statement.
3 Q. Would you accept that, subject to
4 check?
5 A. Yes.
6 Q. Is it also true that the Company has
7 not since '99 constructed any new base load plant?
8 A. No new base load plants, no.
9 Q. And is it true the Company has not
10 constructed any new transmission resources?
11 A. I don't know the extent of the
12 transmission investment since then. I'm sure there
13 have been some transmission investments made.
14 Q. Would it be accurate to say that the
15 last time this Commission made a thorough cost of
16 the Company's cost-of-service study and made
17 specific determinations with respect to the various
18 methods that were used in that study would have been
19 the last general rate case?
20 A. I think that's probably correct.
21 Q. And can you tell us when that last
22 general rate case was?
23 A. Well, if my memory serves me
24 correctly, it was about 1990, or that general time
25 frame. If there's been one in between, then someone
272
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 will have to correct me.
2 Q. Certainly been a long time?
3 A. It's been a long time.
4 Q. We do appreciate that.
5 I think you were deferred to by
6 Mr. Griswold regarding some of the proceedings
7 pertaining to the recent power supply cost recovery
8 case in Idaho, the PAC-E-01-2 -- 02-1 case?
9 A. Yes, I recall he gave me the
10 opportunity to answer a couple of questions you sent
11 his way.
12 Q. And you were a testifying witness or
13 participant in that case?
14 A. I participated to some degree in that
15 case.
16 Q. Is it true that the rates were
17 adjusted between the customer classes in that case
18 based on the rate mitigation adjustment?
19 A. That's correct.
20 Q. Is it also true that the basic rate
21 structure for all customer classes, other than the
22 irrigation class, remained unchanged?
23 A. I think that's correct.
24 Q. Would you also accept that the
25 Commission did not, in that case, accept any
273
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 particular cost methodology in its Order approving
2 the settlement?
3 A. Right, they made no finding that I
4 recall on cost-of-service issues.
5 Q. And isn't it a fact that the
6 stipulation between the parties in those cases -- in
7 that particular case -- said specifically that it
8 was not an adoption or approval of any cost
9 methodology? Do you recall that?
10 A. I believe that's correct.
11 Q. You state on page 7 and 8 of your
12 testimony --
13 A. Is that direct or rebuttal?
14 Q. Your direct testimony.
15 -- various reasons why you think it's
16 more appropriate to treat the sales of electricity
17 under a single contract and a firm sale under a
18 separate contract, and then have a separate contract
19 for interruptibility. While the Company may prefer
20 that, would you agree that it's certainly possible
21 to price both in a single, integrated contract?
22 A. Yes. I think the key element here is
23 making sure that you account for the two elements of
24 the contract appropriately. Whether you do it in
25 two contracts or whether you do it in one, the
274
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 important thing is to account for the sale of
2 electricity to the customer under one as a revenue
3 and account for a credit that's provided back as a
4 power purchase. So if you can break those two
5 elements down separately within the contract and
6 separately upon a bill, then it can be done within
7 one contract.
8 I think Mr. Griswold and Mr. Watters
9 have stated some other reasons why they think two
10 contracts are preferable, but it certainly can be
11 done within one.
12 Q. On page 11 of your testimony, you
13 talked about the three basic approaches that you
14 have -- general approaches -- for valuing
15 interruptibility. One was to compare prices, the
16 other one was discounts from a standard tariff, and
17 the other one was to compare what other
18 interruptible customers were paying?
19 A. Now, are you in my rebuttal now?
20 Q. In your rebuttal testimony, I'm sorry,
21 page 11 of your rebuttal.
22 A. Okay.
23 Q. And I recall you had in your testimony
24 some discussion of how you could come up with a
25 discount from standard tariffs and other witnesses
275
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 have presented that, but I didn't see too much in
2 the way of comparing rates to other interruptible
3 customers.
4 Would it be accurate to say that the
5 only other interruptible customer that's recently
6 had its rate set -- its interruptible rate set --
7 would be in the Magcorp case?
8 A. That is the last one that has been
9 approved by Commission. There are two other
10 contracts which are currently in the process of
11 going through the review and approval process.
12 Q. And when I look at the Magcorp case
13 and try to compare what's been offered by Monsanto
14 in this case, is it accurate to say that the notice
15 of interruption requirement for Monsanto is less
16 than the two hours required by Magcorp?
17 A. Oh, I think it depends on what
18 provision of the contract we're talking about.
19 Q. Well, let's talk about the system
20 integrity. There's no notice to Monsanto for those
21 kind of interruptions. Correct?
22 A. Okay.
23 Q. And for the economic interruptions, it
24 was six minutes of notice. Correct? Or, excuse me,
25 operating reserves was six minutes' notice?
276
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 A. I think that's correct.
2 Q. And Magcorp, in their case, required
3 two-hour notice, is that correct, for operational
4 reasons?
5 A. For their economic curtailment I think
6 is similar.
7 Q. And didn't Magcorp simply offer a
8 maximum of a six-hour block per day?
9 A. I think that's correct. I'd have to
10 review to be specific.
11 Q. And the proposal by Monsanto provides
12 the Company full flexibility to select how many
13 hours they may want in a day. Isn't that correct?
14 A. Yes, I think the Monsanto proposal has
15 more flexibility in it than did the Magcorp.
16 Q. And I think Magcorp required that the
17 Company only accept its interruptions during the
18 months of July and August the first year, and then
19 June through September the second year?
20 A. That's correct.
21 Q. And Monsanto makes them available
22 whenever you want, year-around. Is that correct?
23 A. That's correct. However, you also
24 need to understand that the Magcorp contract was
25 viewed as being an experiment on which to gather
277
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 data to learn more. There wasn't a finding by the
2 Commission that that rate was necessarily a
3 cost-justified rate or supported by the evidence in
4 the case. It was accepted as being an experiment to
5 be reviewed and discussed and learned more from.
6 Q. But you would agree that the Utah
7 Commission said the rate was based, in fact, on the
8 Company's cost-of-service study, in part?
9 A. No.
10 Q. Let's take --
11 A. You maybe could refresh my memory on
12 that, but --
13 Q. I believe Exhibit 208 would be the one
14 we need to look at.
15 MR. FELL: May I approach the witness?
16 THE WITNESS: I need a copy of this.
17 MR. BUDGE: Oh, excuse me. Well, let
18 me --
19 MR. FELL: (Indicating.)
20 Q. BY MR. BUDGE: If you would look at
21 the May 24, 2002, Order -- that's the first one of
22 Exhibit 208 -- and turn to page 8?
23 A. Okay.
24 Q. The second full paragraph, the first
25 sentence, states: Our justification for a
278
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 21-mill-per-kilowatt-hour rate is based on the
2 record before us, which contains embedded
3 cost-of-service analyses of the value of
4 interruptibility.
5 And it goes on to state in the
6 following -- second following sentence: PacifiCorp
7 and the Committee each introduced embedded cost
8 analyses to support its view of the appropriate
9 terms.
10 And it says: Each of these embedded
11 cost analyses is consistent with prior Commission
12 rulings.
13 So embedded cost studies presented by
14 the Commission -- or, excuse me -- by the Company
15 were, in fact, considered by the Utah Commission in
16 arriving at that rate, were they not?
17 A. Well, I think that may be a stretch of
18 what this says. I'd have to review this in some
19 more length. It just says that we based it on the
20 record, says the record included this, and people
21 presented evidence. It doesn't say what piece of
22 the record they based their Decision on. So I'm not
23 sure I'd interpret this to say that the Commission
24 based 21 mills on the Company's cost-of-service
25 filing.
279
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Q. So is it your statement then that the
2 Utah Commission did not consider your
3 cost-of-service study?
4 A. Well, it's certainly my statement that
5 there was nothing in my cost-of-service study that
6 would support a 21 mill price for Magcorp.
7 Q. So it isn't always necessarily the
8 case that the Commission needs to follow or accept
9 your cost-of-service study. But if one of your
10 methodologies to value is to see what other
11 Commissions do with other similar interruptible
12 contracts, would you agree that there is some
13 precedent based upon your logic for the Commission
14 to look to other rulings such as Magcorp?
15 A. I would hope the Magcorp Decision is
16 not precedential for anything.
17 Q. We were hoping just the opposite.
18 MR. BUDGE: If I could have just a
19 moment?
20 May I approach the witness, please?
21 COMMISSIONER SMITH: Yes, Mr. Budge.
22 Q. BY MR. BUDGE: Handing you an exhibit
23 that we'll mark Monsanto Exhibit 42 (sic) that
24 consists of two pages, and we'll provide copies to
25 the Commission and others as soon as we can mark it.
280
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 In the interest of time, if you'd look
2 first at the first page, the Company's Response to
3 Request No. 4 regarding the $30 million states that
4 the $30 million prepayment was not included in the
5 cost-of-service study filed in this docket.
6 A. That's correct.
7 Q. Do you see that?
8 A. Uh-huh.
9 Q. And then if you look at the second
10 Response to No. 122, the Company says: The Monsanto
11 prepayment is included in the unadjusted results in
12 the instant filing.
13 Do you see that?
14 A. Uh-huh.
15 Q. Can you tell me which is correct?
16 A. I'll tell you what we did.
17 Q. Well, let's start with which is
18 correct of those two inconsistencies?
19 A. Well, they might both be correct. Let
20 me explain what we did and then we could determine
21 which, if either, of these statements is correct.
22 In my preparation of the
23 cost-of-service study, historically, the
24 amortization of the revenues has been applied as a
25 revenue credit that's been spread system wide, okay,
281
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 and so a small portion of that would accrue to
2 Idaho.
3 When I made the adjustments for
4 bringing the Monsanto load situs to Idaho, I did not
5 make any adjustment to that amortization of the
6 revenue, so I didn't take that revenue and
7 specifically assign it to Monsanto.
8 Q. Does that have the effect of
9 increasing the jurisdictional revenue requirement in
10 Idaho?
11 A. Actually, I think in this particular
12 case it's irrelevant, because by the time we're
13 going to implement this contract, those revenues
14 would have been completely been amortized away, so
15 there's no longer an unamortized balance to offset
16 the rate base implication and there's no more
17 revenue there to apply against the current revenues.
18 What we were trying to do here is to
19 say, What's the appropriate revenue for moving
20 forward.
21 So the only implication of whether or
22 not those revenues were assigned to Monsanto here is
23 in saying what's the delta between current price and
24 the new price. It has no impact on what the new
25 price would be, because those revenues are
282
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 completely amortized and gone. So there's none of
2 that left to offset the cost going forward, so I
3 think it would be inappropriate to recognize that in
4 conjunction with setting the price for Monsanto.
5 The only implication it has at all on a
6 going-forward basis is determining what's the delta
7 to compare against the current price and the
8 proposed price.
9 Q. So what you're saying, Idaho did not
10 get the benefit of the allocation of any of the
11 $30 million for the purposes of your '99
12 jurisdictional allocation model. Correct?
13 A. Because we were using this to set a
14 price for a contract going forward starting 2002.
15 Q. And if, in fact, Idaho had received
16 its proportionate share of the $30 million, would
17 that not have reduced the revenue requirement for
18 Idaho?
19 A. If I had taken the annual -- if I had
20 taken the annual revenue associated with the
21 amortization, assigned that to Monsanto and included
22 that in the results, that would have, on a actual
23 return basis for including Monsanto, the revenue --
24 the rate of return would have been somewhat higher.
25 However, the target rate of return that we set was
283
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 using the rate of return under a system allocation
2 for all contracts, so in that setting, the target
3 rate of return, Idaho got its share of that
4 allocated revenue consistent with its share of the
5 costs for those contracts. So, again, I don't think
6 Idaho was disadvantaged by the way we treated that.
7 Q. But going back to answering the
8 question of the inconsistency between your Response
9 No. 24 and your Response No. 122, the answer is the
10 Company did not include the $30 million in the 1999
11 test year data?
12 A. Well, first of all, there's not
13 $30 million left. There was the remaining year of
14 the amor- -- unamortized portion and the current
15 year's amortization that I did not make an
16 adjustment to situs assign that to Idaho when we
17 made this change.
18 Q. And part of the Company's case is, is
19 it not, that the Monsanto firm load should be
20 treated as a total situs load? Correct?
21 A. Yes.
22 Q. And so on your jurisdictional
23 allocation model, should not the entire $30 million
24 have been allocated to Idaho, rather than shared
25 with the rest of the states?
284
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 A. The remaining portion of the
2 30 million, I agree, that should have been done in
3 the allocation. That was an oversight.
4 COMMISSIONER SMITH: Mr. Budge, could
5 you let the witness finish? I think the court
6 reporter is having a little difficulty.
7 MR. BUDGE: Excuse me.
8 THE WITNESS: I agree, that was an
9 oversight on my part when we made the adjustment.
10 However, I think the implication of that is pretty
11 minor, because again, we're not talking about having
12 a full $30 million offset to the rate base in
13 Idaho. We're talking about in this case down in
14 probably the million-dollar range and the current
15 year's amortization would just affect the current
16 revenue, won't have any impact on the target revenue
17 going forward. So, again, yes, that's an oversight
18 on my part, but I don't think Idaho was necessarily
19 disadvantaged by that in the calculation.
20 Q. BY MR. BUDGE: Well, when the
21 Commission approved Monsanto's '95 contract, didn't
22 the Company state that the rate treatment would be
23 deferred for another day?
24 A. That seems to be the statements of
25 people.
285
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Q. And yet the Company has chose, as you
2 just described, to amortize that over whatever
3 period it wants?
4 A. Well, we amortized it over the life of
5 the contract. I think the matching principle of
6 accounting would require us to amortize that over
7 the life of the contract.
8 Q. If we were to be consistent with the
9 Company's proposal that the firm contract for
10 Monsanto all be allocated to Idaho, would that not
11 require that the full $30 million be allocated to
12 Idaho rather than the system?
13 A. Yes, if each of those years when we
14 made the amortization had Monsanto's load and
15 Monsanto's revenue been recognized as part of Idaho,
16 it would have been appropriate for the full
17 recognition of the amortization of the revenues to
18 Idaho and the unamortized balance offset Idaho's
19 rate base, that would have been appropriate.
20 MR. BUDGE: We'd mark that as exhibit,
21 and let me go ahead and hand out, if I can, copies
22 of that. If you want to do that, pass one of each.
23 (Monsanto Exhibit No. 242 was
24 marked for identification.)
25 Q. BY MR. BUDGE: Could we go to 19,
286
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 page 19 of your rebuttal testimony, lines 6 through
2 8?
3 A. Okay.
4 Q. And there you basically claim that
5 Mr. Smith's argument is in error regarding
6 allocation of the $30 million to the 1992 contract.
7 Do you recall your testimony about that?
8 A. Well, I think my point here is he just
9 hasn't assigned the money anywhere.
10 Q. Isn't it true that when the '95
11 contract was submitted by PacifiCorp to this
12 Commission for approval, that PacifiCorp did not
13 request any rate-making treatment at that time?
14 A. I'm not specifically aware of that. I
15 do know though that they -- a amortization schedule
16 was established and had been followed in the sense
17 of the implementation of the '95 contract, and the
18 amortization of that has been included in all, you
19 know, results that have been filed with the State of
20 Idaho. And I'm not aware that it's been an issue
21 been taken with the treatment of that here.
22 Q. Would you accept, subject to check,
23 that the Company's Application in that case
24 specifically stated that they were not requesting
25 rate-making?
287
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 A. I accept that. I'm just telling --
2 Q. Excuse me.
3 A. I'm just letting you know what's
4 happening in actual practice.
5 Q. Would you also accept, subject to
6 check, that the Commission's Order approving the '95
7 contract -- and that's Order 26282 -- states, quote,
8 The Company requests that all rate-making issues be
9 reserved for a rate case, period, end quote? Do you
10 accept that subject to check?
11 A. Yes.
12 Q. Isn't it a fact, Mr. Taylor, that
13 PacifiCorp indicated in its Application for approval
14 of the '95 contract that it was -- that the
15 $30 million was paid solely to buy out the old
16 contract?
17 A. I understand that that's what the
18 contract itself says.
19 Q. And that would be reflected in
20 Exhibit 201, I believe, of the Application?
21 A. Okay.
22 Q. Isn't it also a fact that the
23 technical assessment package that the Company
24 submitted along with the contract when it sought
25 approval in '95 -- that's Exhibit 203 -- also stated
288
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 that it was to buy out the old contract?
2 A. Right. In fact, the technical
3 assessment package recognized that immediately, and
4 it takes zero of the contract to resume its present
5 analysis.
6 Q. And would you also accept, subject to
7 check, that the 1995 contract on its face in
8 Paragraph 4.1.2 states, quote, In consideration for
9 termination of the power supply contract dated
10 July 3, 1991, Monsanto shall pay PacifiCorp $30
11 million?
12 A. Yes.
13 Q. Isn't it true that PacifiCorp, in
14 fact, amortized the $15 million payment over both
15 contracts?
16 A. Yes. What PacifiCorp did is they
17 amortized it more rapidly over the remaining period
18 of the old contract, I think in a way to record on
19 the books of the Company essential equivalent of
20 revenue had the old contract not been terminated,
21 and then the unamortized remaining portion was then
22 amortized over the remaining life of the new
23 contract.
24 Q. And under that amortization you just
25 described, isn't it a fact that only 3.32 million --
289
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 3.3 million -- of the payment was actually the
2 amount amortized annually over the new contract?
3 A. Let me look. Okay?
4 Q. You might look at the Company's
5 Response to Data Request No. 122 if you have it, or
6 if not, I'll make it available to you.
7 A. I believe you already made it
8 available to me.
9 Can you restate your question?
10 Q. Isn't it a fact that the Company only
11 amortized $3.3 million annually over the new
12 contract of the 30 million?
13 A. Yes, we amortized on a monthly base
14 $750,000 a month over the remaining term of the old
15 contract, $278,000 a month over the remaining life
16 of the new contract, or the 3.3 million as you
17 state, that's correct.
18 Q. Turning to page 19 of your rebuttal,
19 line 7 or -- lines 9 through 11 --
20 A. What page was that again?
21 Q. Page 19.
22 A. Okay. Lines what?
23 Q. Lines 9 through 11.
24 A. Okay.
25 Q. And here, based on your logic that the
290
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 full $30-million payment is allocated over the new
2 contract -- which wasn't the case, but assuming that
3 logic -- you say the starting point ought to be $23?
4 A. Yes.
5 Q. Correct. And based on the Company's
6 new proposal of $27, that only amounts to a
7 17.6-percent increase?
8 A. I think 17.4.
9 Q. If you compare the difference between
10 23 and 27?
11 A. Yes.
12 Q. If you make that comparison as you
13 attempt to do, Mr. Taylor, aren't you, in fact,
14 comparing firm contract -- we ignore the emergency
15 interruptions that exist in both proposals, the new
16 and old one, aren't you essentially trying to
17 compare the firm contract rate of the '95 contract
18 with your new net interruptible contract rate of 27?
19 A. I guess I never realized that Monsanto
20 considered the '95 contract to be firm. I thought
21 they always said it was an interruptible contract.
22 Q. Let me rephrase it. If we ignore the
23 fact that both the new contract and the old contract
24 contain provisions for emergency interruptions -- in
25 other words, the '95 contract contains no economic
291
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 curtailment, correct -- and when you arrive at the
2 $23 figure, you were talking about the contract with
3 no economic curtailment, which you were trying to
4 compare with the net price after curtailment that's
5 proposed by the Company today. Correct?
6 A. That's correct. All I was doing was
7 showing the delta between the effective prices of
8 the two contracts.
9 Q. Would you agree that that's the
10 comparison of apples to oranges because the two
11 contracts don't contain similar interruptibility
12 terms?
13 A. Yeah. In fact, I think comparing
14 anything to the 1995 contract is probably apples to
15 oranges comparison, because it was a unique contract
16 for a unique set of circumstances.
17 Q. Isn't it a fact, Mr. Taylor, if you
18 look at the price actually paid by Monsanto since
19 1995, there's never been a year in which they've
20 paid more than $18.50 for their power? Correct?
21 A. Yeah, not taking into account the
22 prepayment, that's correct.
23 Q. So is that a "yes" answer or --
24 A. If you look at, you know, what was on
25 the bill to them, yes.
292
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Q. Okay. That's what I'm talking about,
2 looking at the bill.
3 Isn't it a fact if you looked at the
4 years 2000, 2001, 2002, when you looked at their
5 bottom-line bill after what Monsanto received back
6 from PacifiCorp as a result of the operational
7 reserve payments, that the actual price they paid in
8 those years was less than 18.50?
9 A. Taking into account the money that
10 PacifiCorp has given them back, that's correct.
11 Q. And would you accept, subject to
12 check, the numbers provided in Mr. Schettler's
13 testimony that the net price in 2000 was 17.57?
14 A. Subject to check, I would accept that.
15 Q. Would you also accept that the actual
16 price paid in 2001 was $16.61?
17 A. Subject to check.
18 Q. Okay. So if we were to take that year
19 2001, for example, which would be a price of $16.61
20 after interruptions, and compare it with the
21 Company's price of $27, which is the net after
22 interruptions, would you accept my math is
23 correct -- if my math is correct -- that that would
24 be a 63-percent increase?
25 A. I'd accept your algebra.
293
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Q. And would you also accept that in that
2 scenario I gave you, you're essentially comparing
3 apples to apples?
4 A. I think you're comparing a contract
5 set under a unique set of circumstances with a
6 contract being established under today's set of
7 circumstances which are a big difference.
8 Q. I had some questions, just a few, that
9 I wanted to ask you on one other topic, and then
10 maybe go back to a couple that were deferred to you,
11 but I think you stated earlier that you agreed the
12 principle of gradualism is a consideration that this
13 Commission should take -- should consider in setting
14 rates?
15 A. Is or is not?
16 Q. Is.
17 Would you agree that the principle of
18 gradualism or avoidance of rate shock is an
19 appropriate rate-making principle that the
20 Commission should consider for purposes of setting
21 the rate for Monsanto?
22 A. I'm just not sure it applies in this
23 case.
24 Q. So you wouldn't agree with that
25 principle?
294
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 A. No.
2 Q. Isn't it a fact that that principle
3 did impact the Company's proposal in the excess
4 power supply case, the E-02-1 case that we've been
5 discussing?
6 A. Yeah, when you're dealing with tariff
7 customers where we have opportunities to change the
8 prices whenever the situation warrants.
9 Q. So you're saying gradualism should
10 apply to some customers, but not all?
11 A. I think when you establish long-term
12 contracts and go from one to another, the concept of
13 gradualism loses a lot of its meaning.
14 Q. Is part of the reason that you don't
15 feel the principle of gradualism should apply is
16 because Monsanto had a rate as a special contract
17 customer which didn't change from 1995 up until
18 whenever the new contract ends?
19 A. I think that's part of the reason.
20 I think another reason is if you look
21 at what I presented in my Exhibit No. 22 where I
22 compared the historical contracts with the '95
23 contract with our proposal, you find that the
24 principle of gradualism appeared to be -- have been
25 ignored compared where the target ending rate in the
295
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 '92 contract and for the new one at 26 versus 18
2 and a half. I mean, I didn't see a lot of
3 gradualism applied when Monsanto was given a
4 lower-priced contract with a much more firm product
5 than they'd been receiving before. So, I didn't see
6 that the principle of gradualism applied then, so
7 I'm not sure why it's such a big issue that it needs
8 to be applied now.
9 Q. So you don't think a 70-percent
10 increase is a big deal to somebody?
11 A. Didn't say it wasn't a big deal. I'm
12 just saying I'm not sure the principle of gradualism
13 is an overriding issue when you're talking about
14 going from one five- or six-year contract into
15 another contract that's going to run for a four-year
16 term.
17 Q. You just made the comment that since
18 Monsanto's rates have been steady for five years,
19 that's a good reason not to be too worried about
20 gradualism. Correct?
21 A. I just think you need to take that
22 into account.
23 Q. So when we look at all of the other
24 jurisdictional customers in Idaho, as well as all of
25 the other states for that matter depicted in
296
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Exhibit 223 that reflects basically the rates have
2 been flat for ten to 12 years, would that factor
3 alone, based on your concept, warrant the Company
4 coming in in a next general rate case and saying, We
5 could ask for a huge increase and forget about
6 gradualism because you've had flat rates for a long
7 time?
8 A. No, because we've had opportunities to
9 review those rates from time to time, and had there
10 been a need for changes, we would have -- those
11 changes would have been implemented.
12 Q. But isn't the principle of gradualism
13 to design -- to prevent a customer from having a
14 drastic change in its electricity costs from one
15 period of time to the next period of time?
16 A. I think that's the intent of
17 gradualism.
18 Q. And would you also agree that when
19 people -- when Commissions view the concept of
20 gradualism, that that should become a concern
21 ordinarily in a general rate case if we're talking
22 about any increase that would be in excess of single
23 digit?
24 A. I don't know what the definition would
25 be, because there are cases where the overall
297
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 revenue changes by more than single digits, so you
2 couldn't apply it in that case to a single-digit
3 change to any customer.
4 Q. In your mind, Mr. Taylor, you said you
5 think it's okay to apply that concept to tariff
6 customers but not to Monsanto as a special contract
7 customer.
8 As a tariff rate customer, at what
9 point in time do you feel that gradualism principle
10 should come into play? Is it a single-digit
11 increase, is it something greater, or do you not
12 have an opinion?
13 A. I think if you look at the last couple
14 of cases that the Company's been involved in,
15 oftentimes you look at changes more than double the
16 average or something like that would be an issue
17 whether or not you should go outside of those
18 bounds. It just changes from time to time based on
19 the size of the overall revenue requirement change,
20 the disparity between the current revenues and
21 customer's cost of service, and all of those issues
22 would play into how big of a change you would expect
23 to get from any one class of customer.
24 Q. Let's say that Monsanto's '95 contract
25 had, in fact, been tied to tariff rates in Idaho.
298
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 What would Idaho be paying today based on the recent
2 deferred accounting cases?
3 A. I'm not sure I'm following the
4 arithmetic here.
5 Q. What would Monsanto -- excuse me.
6 Had Monsanto been a tariff rate
7 customer in '95 or had its special contract been
8 tied to tariff rates, as a result of the
9 recently-concluded excess power supply case in
10 Idaho, the PAC-E-02-1 case, what would Monsanto be
11 paying today?
12 A. I don't know, because I haven't
13 established what the rate would have been set in '95
14 at full cost of service for Monsanto.
15 Q. Didn't Mr. Zhang propose in that case
16 that there would be a five percent bandwidth, that
17 no customer's rate would go up or down more than
18 five percent?
19 A. Right, but that would have been
20 predicated on the current rate Monsanto was paying
21 would have been a cost-of-service-based rate to
22 begin with, not this 18-and-a-half-mill special
23 contract rate.
24 MR. BUDGE: Can I have just a moment,
25 please?
299
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 COMMISSIONER SMITH: Certainly.
2 (Discussion off the record.)
3 COMMISSIONER SMITH: Let's go back on
4 the record.
5 THE WITNESS: Just a bit of
6 clarification of Dr. Zhang's presentation of
7 bringing customers within the plus or minus five
8 percent range in a cost of service, applying that to
9 Monsanto in this case: If 31.40 is cost of the
10 service, then the rate would be plus or minus five
11 percent of 31.40. So, you know, what's that, a mill
12 and a half between 30 and 33, that would be the band
13 upon which they would say they'd move rates from
14 Monsanto.
15 Q. BY MR. BUDGE: Mr. Taylor, you're
16 ignoring the fact, aren't you, that the rate set in
17 the '95 contract was essentially firm other than for
18 the emergency curtailment, and that rate was based
19 on the Company's cost studies at the time that
20 warranted a 18 and a half. Correct?
21 A. No, that rate was based on a
22 contribution of fixed costs standard that showed
23 that revenues over the life of that contract would
24 provide a positive contribution to fixed cost over
25 the incremental costs of serving that load over that
300
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 period of time. That's a far different standard
2 than saying Monsanto's rate was paying a full
3 embedded cost of service rate over that time frame.
4 Two completely different standards. I don't know
5 how you could mix and match them together and say
6 one compares to the other.
7 Q. Let me refer to a couple of questions
8 that were deferred to you, if I may, by other
9 witnesses. Exhibit 207 of Monsanto, which is the
10 Company's historic reflection in graphic form of
11 rates for the various states that show all the rates
12 to be relatively flat, are you familiar with that
13 exhibit?
14 A. No, I need a copy of it, if you want
15 to refer to it. It's in here?
16 Q. Monsanto Exhibit 207. Do you have a
17 copy there?
18 A. We'll see.
19 Okay.
20 Q. The question was deferred to you as to
21 whether or not the recent reductions in the Idaho
22 rates reflected in the 02 case this spring are
23 reflected in Exhibit 207?
24 A. I'm not sure what's reflected in here,
25 whether or not it reflects the results of the recent
301
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 case, but I take some exception with your referring
2 to the recent price change in Idaho as a rate
3 reduction. I mean, there was several pieces to
4 that -- to that case.
5 There was a realignment between some
6 customer classes in their base rates. There was an
7 application of a power cost adjustment, which is an
8 addition to rates. And there was also an
9 application of a new credit from the Bonneville
10 Power Administration. The net of all those resulted
11 in, for some customers, their net bills now are
12 lower than they were before, but there was no
13 reduction to the base rates of the Company as a
14 result of this. In fact, there's an increase of
15 revenue collections to the Company via the power
16 cost adjustment.
17 So I think it's a misstatement to
18 characterize that as a rate reduction.
19 Q. Let me just ask it a different way,
20 back to my basic question. Were the overall rate
21 reductions that occurred earlier this year in Idaho,
22 are they or are they not depicted in Exhibit 207?
23 A. I don't know. I suspect probably not.
24 Q. Okay. Monsanto has offered 1,000
25 hours of economic interruption, all three furnaces,
302
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 two hours' notice only if all three are taken at
2 once. Can you explain how this can best be utilized
3 by PacifiCorp in order to provide the greatest value
4 to PacifiCorp?
5 A. No, you need to -- I think you would
6 address that with Mr. Watters. He could do a much
7 better job than I at answering that question.
8 Q. I think I brought that question up and
9 he deferred it to you.
10 MR. FELL: No, that was not the case.
11 Mr. Watters said that he needed to analyze the new
12 proposal, and when he comes back after analyzing it,
13 he would be able to respond to that.
14 THE WITNESS: I am not the one to
15 assess how those interruptibles bring the most value
16 to the Company.
17 Q. BY MR. BUDGE: Your answer would be
18 the same: You need to analyze it and he would be
19 the one to sponsor that?
20 A. Mr. Watters will address that, yes.
21 Q. I was under the impression that either
22 Griswold or Watters had deferred that to you.
23 A. I hope not.
24 Q. One question I'm sure was deferred to
25 you is whether or not the policy change that I
303
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 discussed with the earlier witnesses where
2 PacifiCorp's changed its policy and no longer wants
3 to have long-term interruptible contracts, I asked
4 the question whether or not that was driven, in
5 part, by allocation problems the Company was
6 experiencing?
7 A. Well I think that's driven by a number
8 of reasons, and certainly one of those reasons is
9 acceptance of the interruptible contracts by other
10 jurisdictions. And let me elaborate on that just a
11 little bit if I could.
12 The reason for breaking the contract
13 into different pieces is so you can reflect,
14 rightfully so, what's the cost of providing service
15 to sell power to a customer. That's a
16 jurisdictional issue, should be recognized by the
17 jurisdiction.
18 The other piece of the transaction
19 which brings system benefits is the fact that
20 customers will allow us to enter into some type of
21 agreement with them through interruptibility or
22 something for a certain payment or a certain credit
23 towards their bill. That's the piece that brings
24 system value.
25 So the reason for separating them into
304
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 two is so you can identify the two pieces separately
2 to make sure that what we're giving as a credit back
3 to the customer is reflective as a value to the rest
4 of the customers in the system.
5 Q. Mr. Taylor, I understand. You
6 testified to all that before. My question was
7 relatively simple:
8 Is, in fact, that policy change driven
9 in part by the allocation problems the Company
10 believes it's experiencing?
11 A. Yes, because once you then break it
12 into the two pieces, then it's easier for the
13 Commissions in all the other states to determine
14 what the Company provided in the terms of a rate
15 discount or what they got in exchange. If all
16 they're looking at is a net price to a customer,
17 it's much more difficult for them to see whether or
18 not that was a prudent resource acquisition by
19 PacifiCorp.
20 Q. Isn't it true that the modified PITA
21 accord provided for the modification of all special
22 contracts to the system?
23 A. The modified -- an amendment to a
24 modified accord in 1997 provided that all special
25 contracts, whether they were interruptible or not,
305
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 would be allocated system wide.
2 Q. Okay.
3 A. I think that was done in recognition
4 of many of the same reasons that the 1995 contract
5 for Monsanto was entered into, the unique set of
6 circumstances that presented themselves.
7 Q. So the change now being proposed by
8 the Company to allocate Monsanto's contract to the
9 situs is, in effect, a change to the modified PITA
10 accord. Correct?
11 A. That's correct.
12 Q. And isn't it true that this is a
13 change then that the Company has chosen to pursue
14 unilaterally?
15 A. Not necessarily.
16 Q. Were there any other states that have
17 agreed to this in some sort of a modified PITA
18 accord proceeding?
19 A. Yeah, in the last Oregon case, the
20 final settlement that was reached in Oregon was
21 reached upon an understanding that contracts would
22 be treated this way going forward.
23 Q. Didn't the PITA accord process involve
24 all the states?
25 A. Right. This has happened post that
306
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 agreement in '97. I mean, almost immediately, that
2 Decision proved to be very unpopular, and in every
3 proceeding we went for, no matter what state it was,
4 the issue was always raised that, wait a minute, our
5 customers are paying for the discounts given to
6 customers in other states. It proved immediately to
7 be extremely unpopular and caused contentions and
8 concern in every proceeding after that. I think
9 that's one of the reasons we proposed a change.
10 Q. Has the state of Idaho walked away
11 from the modified PITA accord?
12 A. We haven't had a full-blown rate case
13 in Idaho or those issues would have had to have been
14 resolved.
15 Q. So from the perspective of the state
16 of Idaho, isn't, in fact, the Company's proposal a
17 uniform withdrawal from the PITA accord as it exists
18 as applied in Idaho?
19 A. It's a change to that element of the
20 accord.
21 Q. And it's a change that the Company has
22 pursued unilaterally?
23 A. We've pursued it because we think it's
24 the right thing to do.
25 MR. BUDGE: No further questions.
307
HEDRICK COURT REPORTING TAYLOR (X)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Thank you.
2 COMMISSIONER SMITH: Thank you,
3 Mr. Budge.
4 Do we have questions from the
5 Commissioners? Commissioner Hansen.
6 COMMISSIONER HANSEN: I just have one.
7
8 EXAMINATION
9
10 BY COMMISSIONER HANSEN:
11 Q. I think it was mentioned earlier that
12 Magcorps's rate increase was phased in over the next
13 couple years. Isn't that correct?
14 A. No, no, the Magcorp was established at
15 $21 a megawatt hour. What was phased in was the
16 number of months for which we could interrupt them.
17 In the first year we could curtail them for two
18 months, and in the years two and three we could
19 curtail them for four months, but the price was
20 constant.
21 Q. And what was the rate increase in that
22 particular case?
23 A. I don't -- I don't know what those
24 numbers are off the top of my head. I could find
25 that for you.
308
HEDRICK COURT REPORTING TAYLOR (Com)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Q. And do you know the number of years
2 since they had previously had a rate increase?
3 A. The Magcorp contract has changed a
4 number of times over the life of its contract. And
5 I think Mr. Griswold, if you would like to ask him
6 those questions, can give you the history of that
7 probably better than I could.
8 Q. Well, I'll check that out.
9 A. Yeah, I'd be happy to provide that. I
10 just don't have that information in front of me.
11 COMMISSIONER HANSEN: Thank you.
12 COMMISSIONER SMITH: Commissioner
13 Kjellander.
14
15 EXAMINATION
16
17 BY COMMISSIONER KJELLANDER:
18 Q. I have just one, maybe two questions
19 on the Magcorp, and then I want to get back to your
20 rebuttal testimony for just a moment or two.
21 With the Magcorp as I read the Orders
22 that were placed and I look at reconsideration,
23 there's this talk of the experiment. What exactly
24 is the experiment in there?
25 And also in that, Magcorp is in
309
HEDRICK COURT REPORTING TAYLOR (Com)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 bankruptcy, is that not correct?
2 A. Not anymore.
3 Q. Not anymore. Okay.
4 A. In fact, Magcorp doesn't exist
5 anymore. There's a new -- a new customer that has
6 assumed that contract.
7 Q. Okay. What's the experiment?
8 A. The experiment is to assess the value
9 in operation of interruptibility and how you reflect
10 that in establishing a contract price.
11 One of the issues that seemed to be
12 very important to the state of Utah as they tried to
13 value interruptibility is how much interruptibility
14 do you need to take a certain customers's load out
15 of the contribution of system peak to avoid the
16 allocation to the state of Utah. That was a real
17 focus of the state of Utah in looking at the Magcorp
18 contract.
19 So I think a big piece of this
20 experiment is looking at the curtailments that we're
21 allowed to make with Magcorp and the seeming
22 implications of those on the contributions -- Utah's
23 contribution to system peak as it relates to
24 jurisdictional allocation.
25 Q. Okay, so then I'm just going to state
310
HEDRICK COURT REPORTING TAYLOR (Com)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 this -- tell me if this is the case or not -- but it
2 sounds like what happened is they set the rate at
3 $21 and then said, We're going to find what kind of
4 interruptibility it takes to get us to $21. Is that
5 what they're doing?
6 A. Well, I'd be hard-pressed to try to
7 guess what they were thinking. It appears that
8 there was.
9 Q. They didn't put a value on
10 interruptibility, a dollar value, but they put a
11 firm rate of $21?
12 A. So is your question why or what was
13 their justification for that?
14 Q. Trying to read that, because I don't
15 see it in the Orders.
16 A. Well, neither do I.
17 Q. Okay.
18 A. My personal opinion is they call it
19 experimental because they couldn't find any basis to
20 support the number.
21 Q. Let me ask this question then: As
22 they go through this experiment of trying to value
23 the interruptibility of Magcorp or whoever the new
24 company is that assumed the contract, the $21 rate
25 doesn't change. Is that correct?
311
HEDRICK COURT REPORTING TAYLOR (Com)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 A. That's correct.
2 Q. Okay. Let's go to your rebuttal
3 testimony if I could, page 18, and in that you have
4 an answer, lines 16 through 24, and in that you
5 quoted a gentleman -- Mr. Racine -- who apparently
6 was an attorney for Monsanto during the '95 case,
7 and the quote essentially gets to the amortization
8 issue of the $30 million payment and it's
9 characterized in part then as creating an effective
10 rate. Is that a correct characterization of that
11 quote?
12 A. Yes.
13 Q. Where does this quote appear? Is that
14 in some official transcript that's filed with this
15 Commission?
16 A. Yes, I believe that was from the
17 approval case of the contract. I actually pulled
18 this directly from Mr. Schunke's testimony, but it
19 was -- that was statements that Mr. Racine made
20 before this Commission in the approval process of
21 that contract.
22 Q. Okay.
23 A. What's the real value of knowing what
24 the effective rate is in that '95 case? I hear you
25 talk about apples and oranges in comparison to
312
HEDRICK COURT REPORTING TAYLOR (Com)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 response to questions made or directed to you from
2 Mr. Budge. What is the value of knowing what the
3 effective rate is? Does that guide this Commission
4 in any direction at all?
5 A. It has absolutely no impact on the
6 cost basis for what the new rate ought to be. The
7 only implication of what that number has is
8 determining what the delta is between the two
9 rates. That's the only implication of that number.
10 Q. Okay, then let's talk about the delta
11 for just a moment. That $30 million apparently to
12 get the $23 effective rate -- that you claim is the
13 effective rate -- is spread out over the life of the
14 contract. Correct?
15 A. That's correct.
16 Q. The '95 contract.
17 Now, the life of that contract has not
18 yet been pinned down by the U.S. District Court. Is
19 that correct?
20 A. That's correct.
21 Q. Okay. So there could be some shifting
22 sand as it relates to what the effective rate is
23 assuming that you can use that down the road, but it
24 really hasn't been determined yet because if the
25 Court decides at the end of this year that that's
313
HEDRICK COURT REPORTING TAYLOR (Com)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 when the contract ends, then you would have to
2 amortize that out over an additional year. Is that
3 correct?
4 A. That's correct.
5 Q. Have you done any math to tell us how
6 much of a shift that might be to determine what the
7 effective rate would be if it extended over another
8 year based on the U.S. District Court Decision?
9 A. Well, let me just do something real
10 quick in my head. If we're talking about the
11 difference between 18 and a half and 23, so that's,
12 what, four and a half mills. If you extend the rate
13 by another year, that's one-sixth. So what's
14 one-sixth of four and a half? That's, what, another
15 point seven. So it takes it down to 22 and a
16 quarter or something, 22.3, something in that range.
17 Q. So then the range then of an effective
18 rate would be the low end of 22 something up to 23.
19 If you were looking for a range, I think I'd use the
20 effective rate in any way, shape, or form in terms
21 of evaluating what the next rate should be?
22 A. I think that would be one way of
23 looking at it.
24 Q. Okay. Thank you.
25 COMMISSIONER SMITH: Makes me feel
314
HEDRICK COURT REPORTING TAYLOR (Com)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 very old to realize that Commissioner Kjellander
2 apparently does not know who Lou Racine is.
3 Do you have much redirect, Mr. Fell?
4 MR. FELL: I do.
5 COMMISSIONER SMITH: Well, let's see
6 how far we can get.
7
8 REDIRECT EXAMINATION
9
10 BY MR. FELL:
11 Q. I was going to start on this issue of
12 gradualism and I couldn't wait to get to it, but
13 maybe I will just make one point. So, Mr. Taylor,
14 would you turn to your Exhibit No. 22?
15 A. Okay.
16 Q. And isn't it true that the blue lines
17 that start on the left side represent the prior
18 contracts up until the 1995 contract?
19 A. That's correct.
20 Q. And if you go to the right side of the
21 table, that's the new proposed price net of the
22 interruptibility values?
23 A. That's correct.
24 Q. Okay. So one of your points -- is one
25 of your points, rather -- I'll ask you the
315
HEDRICK COURT REPORTING TAYLOR (Di)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 question -- the comparison between the last bar of
2 those light -- of the blue, rather, not light blue
3 but blue bars, the last bar in 1997 and the 2002
4 bar?
5 A. Relatively modest increase.
6 Q. Yes. Now then, so that leads you to
7 the question of what accounts for the drop in the
8 price for this contract between -- for the 1995
9 contract. Now, you have talked about the different
10 standards under which these contracts were
11 developed. We'll start with the 2002 contract.
12 This is a contract based on embedded cost of
13 service. Correct?
14 A. That's correct.
15 Q. Okay. For the 1995 contract, was that
16 contract based on embedded cost of service?
17 A. No.
18 Q. If we turn to the exhibit, I believe
19 it is your Exhibit 20 -- 202 -- you explain and as
20 this exhibit shows on page 3, it states this is the
21 Application for approval of the 1995 contract?
22 A. Okay.
23 MR. FELL: May I approach the witness
24 and show the witness this contract?
25 COMMISSIONER SMITH: Yes, you may.
316
HEDRICK COURT REPORTING TAYLOR (Di)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Q. BY MR. FELL: Section 7 on that page
2 states the basis for the pricing done in that
3 contract, and would you explain what that basis was?
4 MR. BUDGE: Excuse me for
5 interrupting. Can you identify where you were on
6 what document you are referring to?
7 THE WITNESS: I'm on Monsanto
8 Exhibit 202, page 3, starting on line 7. You with
9 me, Mr. Budge?
10 MR. BUDGE: Thank you.
11 THE WITNESS: Okay. It lays out two
12 alternatives here. First, it says that Monsanto has
13 a viable alternative to taking electricity from
14 Soda Springs Municipal Electric Light and Power
15 Department; and, second, could displace -- Monsanto
16 could displace much of its elemental phosphorus
17 production at Soda Springs with a product produced
18 from a purified wet acid chemical process.
19 Q. BY MR. FELL: Now with that in mind,
20 Monsanto then was approaching -- in effect, it was
21 approaching PacifiCorp and telling PacifiCorp that
22 it could acquire power at a cheaper price than the
23 embedded cost of service. Was that the substance of
24 that?
25 A. Appears to be, yes.
317
HEDRICK COURT REPORTING TAYLOR (Di)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 Q. Or it could go to a different process
2 and displace its own load, and in that way, in a
3 sense, avoid the higher embedded cost prices?
4 A. That's correct.
5 Q. And so the reaction to that was what
6 in terms of the type of cost development that was
7 used?
8 MR. BUDGE: You know, I'd object.
9 This is beyond the scope of cross, number one.
10 And, number two, I think this
11 witness -- did you not testify you were not a part
12 of the '95 contract negotiations?
13 COMMISSIONER SMITH: Mr. Fell.
14 MR. FELL: It's contained in the
15 technical assessment package, which is the next
16 exhibit. So we could rely on the exhibits that are
17 there but I could argue from them as well, so we can
18 probably move on.
19 MR. BUDGE: That was kind of my
20 concern. This witness said he wasn't involved in
21 the '95 negotiation, the document speaks for itself,
22 and you're asking him to interpret this particular
23 document as to what was intended and he wasn't
24 involved.
25 COMMISSIONER SMITH: I think Mr. Fell
318
HEDRICK COURT REPORTING TAYLOR (Di)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp
1 has agreed we are moving on. Is that correct?
2 MR. FELL: Yes, I think I will do
3 that. I will argue it in the Brief.
4 COMMISSIONER SMITH: In fact, I
5 suggest that we just stop for the evening. Is this
6 an acceptable point, Mr. Fell?
7 MR. FELL: Yes, it is.
8 COMMISSIONER SMITH: I apologize for
9 interrupting you.
10 MR. FELL: No, I'll probably have
11 fewer questions tomorrow.
12 COMMISSIONER SMITH: I figured you'd
13 have more, but I hope you're right. So I think we
14 intend to commence in the morning at 9:00 a.m., and
15 if necessary we won't have I hope constraints that
16 will keep us from going on into the evening if we
17 should need to tomorrow.
18 With that, we're adjourned.
19 (The hearing adjourned at
20 4:43 p.m.)
21
22
23
24
25
319
HEDRICK COURT REPORTING TAYLOR (Di)
P.O. BOX 578, BOISE, ID 83701 PacifiCorp