Loading...
HomeMy WebLinkAbout19910419Brown Petition for Reconsideration.pdftr/*ffi C. TOM ARKOOSH RODEN & ARKOOSHAttorneys at Law 8O2 West Bannock, Suite 900P.O. Box 21L0Boise, Idaho 83701Telephone: 208-336-793O IN THE MATTER OF THE APPLICATION OF IDAHO POWER COMPANY FOR APPROVAL OF AN INTERCONNECTTON TARIFF FOR NON-UTILITY GENERATION - SCHEDULE 72 i1[CEIV;D E-ILTD il iI ffPR 19 Pn z 15 iuiiii 0 i'U uLii,; rjl ; l-rTl i s c0or,, 53 :r,il{ ATTORNEYS FOR PROTESTANT BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION z ) ) ) ) ) ) Case No. IPC-E-90-20 PETITION FOR RECONSIDERATION Comes now the protestant in the above entitled action, A. W. Brown, Inc., a California corporation qualified to do business in the State of Idaho fBrown], by and through his counsel of record, c. Tom Arkoosh of the firm of Roden & Arkoosh, Boise, Idaho, and herein respectfully petitions the fdaho Public Utilities Commission ICommission] for reconsideration of its Order No. 2363L, entered in the above matter, based upon the fol1owing showing: 1. The Commj-ssion found in s,eid order that, Previously, the terms and condj-i:ions for interconnectionof non-utility generation to the Company'stransmission/distribution system have been individuallynegotiated, although the terms and conditions have provedto be substantially similar. This finding directly conflicts with the previous findings of the Commission. fndeed, this finding conflicts wj.th the practice of the Idaho Power Company requiring the payment of the j-nterconnectj-on costs at Idaho Power prices before it will allow PETITION FOR RECONSIDERATION -]-- interconnection, and the Conmissionrs rulings which sanctify this practice. For example, in Order No. 19442, Case No. IJ-LOO6-237, the Commission addressed these issues: The rrRemote Disconnectiontr fssue. May ldaho Power install remote disconnection equipmentat the Arkooshesr cost? The |tlnterconnection Costrr Issue. What expense may Idaho Power charge the Arkooshesfor interconnecting the Geo-Bon #2 project toIdaho Powerrs line? The Commission addressed both these j-ssues, and concluded that Idaho Power could charge a developer its costs plus .7eo monthly maintenance. fn reaching this conclusion, the Commission rejected the developers argument that the federal regulations allow a charge for interconnection only in excess of what the rate-payer vrould pay if the utility interconnected its own new capacity. This identical argument was made by Brown in the pending matter, and also rejected. fn Order No. L9442, the Commission accepted that the federal regulations defined Itinterconnection costsrt as the cost over and above what the utility would pay for interconnection of its own capacity, but presumed that those costs were included in the avoided costs calculation: Idaho Powerrs remote disconnection (and otherinterconnection) costs for additional generation purchase are presumable already in place; if they are not, nothingin the record quantifies them for comparison. order No. 19442, page L1. In the present case, the Commission has glossed over that the f ederal regulations def ine rrinterconnection costsrr as only the costs of interconnection over and above the costs that the 3 4 PETITION FOR RECONSIDERATTON -2- I ratepayer $rou1d ordinarily pay for the new capacity. The Commissj-on then acknowledges that, in any event, rrIPCo points out that the avoided cost rates paid to qualifying facilities (QF.s) al1ow for the recovery of interconnection costs by the QF. " The signatory of this brief has reviewed the pre-filed testj-mony of the joint utility panel in Case No. U-l-500-170, setting forth the capital cost of plant used to calculate the avoided costs using the surrogate avoidable resource methods (SAR), and does not perceive that the interconnection costs, line rebuild costs, and the like which are charged to QF's are in fact included in the avoided costs. Instead, they appear not to be included j-n avoided costs. Because the U-1500-170 case is the only record available on this question, the Commission should have made a determination of the numerical value of the ttinterconnection costsrr as the same are defined in the regulations, and determined whether indeed it cost the ratepayer more to interconnect a QF, than it would for the utility to interconnect equivalent capacity: It is respectfully submitted, given the overcharges pointed out by Brown in his protest that the cost of interconnecting utility capacity is much higher than the cost of interconnecting QF. capacity. Thus, a developer should be required to pay nothing for interconnection, and it would be a bargain for the ratepayer. 2. The Commission avoided the question of whether fdaho Power is overcharging on its interconnection costs by noting, rrCompetitive third party pricing and construction is not precluded under Schedule 72.tt If this were correct, it would appear to solve PETITION FOR RECONSIDERATION -3- I this problem in the future. Schedule 72 provides, however, The Company will construct, own, operate andmaintain all Disconnection Eguipment, Metering Equipment,and Upgrades and Relocation. These are the very items about which Brown complains that Idaho Power imposes exorbitant overcharges. Brown points out in his protest that these items are simple, avaj-1abIe on the market much cheaper than from Idaho Power, and, in some instances, better suited to the project than the itens Idaho Power provides. 3 . The Commissj-on rejected Brorarnts protest to the .72 maintenance charges imposed by Inot negotiated with] Idaho Power on the interconnectj-on costs. He points out that he has already, in 35 months, paJ-d $4,805.28 to maintain $4500 worth of equipment. Even accepting ldaho Powerts contention that the value of the interconnection equipment sold to Brown is $19r00o, he will have paid its ful1 value for mere maintenance in 12 years at the rate of $L33.48 per month. Using a realist future value analysis, and accruing the maintenance money dt, for instance, LoZ interest, Brown re-pays Idaho Power for this equipment every 94.5 months, or 7.8 years. Over the life of a 35 year contract, Brown wil-1 have paid to replace the interconnection equipment 5 and L/2 times once originally and 4 and 1/2 times to Idaho Power. The Commission need only contemplate whether the O & Iq on sma11 hydro projects are projected to be this high to conclude that .72 O & M charge does not accurately or reasonably reflect actual costs based upon actual experience. PETITION FOR RECONSIDERATION -4- CONCLUSION The Commission is herein respectfully requested to conduct a hearing and take evidence regarding its findings concerning Schedule 72; or, alternatively, hold this matter in abeyance until the heari-ng in Case No. IPC-E-91-2, concerning these identical issues. It is apparent from the face of the findings which support the Order under consideration that the facts relied upon are inaccurate, and should be reconsidered by the Commission. DATED this day of Apri1, L991. CERTIFICATE OF MATLING r hereby certify that on the fu- day of April , Lsst, r served a true and correct copy of the foregoing docurnent upon thefollowing persons, by causing to be deposited a copy thereof in theUnited States Mai1, first class postage prepaid: BARTON L. KLINEAttorney at LawP.O. Box 959Boise, Idaho 8370L SCOTT WOODBURY Idaho Public Utilities Commission StatehouseBoise, fdaho 83720 /@ PETER J. RICHARDSON DAVIS WRTGHT TREMAINE 350 North 9th Street, Boise, Idaho 83702 Suite 400 ,4 PETITION FOR RECONSIDERATION -5- C. TOM ARKOOSH