Loading...
HomeMy WebLinkAbout19910117Brown Protest.pdf/8;4? nEcElvgi.r Er,LEO tr,sl JRil 1? Pn 3 iB BEFoRE rHE rDAHo puBlrc urrlrrrE" "o*#JA!#3'r[Yr',i,';'r,r,n'9"-'a IN THE IIIATTER OF THE APPLICATTON OF IDAHO POWER COI{PANY FOR APPROVAL OF AN TNTERCONNECTION TARIFF FOR NON-UTTLITY GENERATTON cAsE NO. rPC-E-90-20 PROTEST Comes now A.W. Brown to register a protest before the Commission regarding the above subject matter and in particular certain items delineated in both Order Number 23477 and the attached Tariff Schedule Number 72 which are identified as follows: 1. On page 2 of Order Number 23477, second paragraph, is the statement rrThe Company contends that it will pri-marily recover costs and not realize any significant revenues from implementation of its proposed t,arif f . !l 2. On sheet 27 F of Schedule Number 72 under definitions appears |tConstruction Cost: The costr ds determined by the company of upgrade, relocation or construction of Company furnished interconnection facilitator. rr 3. On sheet 27 H appears: rrCost of Interconnection Facilities: AIl interconnection facilitiers provided under this schedule will be valued at the companyrs construction cost and/or the transfer cost for vesting purposes as well as for operation and maintenance payment obligations. rl ) ) ) ) ) PROTEST -1- {I 4. On sheet 27 K all of the first paragraph is cited and in particular the last sentence which states trThe percentage is O.4 t for 138 kv and 161 kv facilities and O.7 * on facilities below 138 kv. rr It is this protestorrs contention that the statement in itern one above is deliberately nisleading on the part of Idaho Power Conpany (IPC) and that they trillr 6s they have in the past, under a Commission mandate, realize significant profits from this source of construction by overcharging with impunity. The statements of items two, three and four invite the procedure of overcharging because the more a facilityrs cost can be escalated, the more IPC will collect on operation and naintenance charges where the cost has no direct bearing on either the operation or the maintenance. IPC should not have the right under an approval by the Commission to hold a sole source monopoly on interconnection facilityts construction and construct whatever they please whether it fits the situation or not and then collect a fee forever based on an IPc determined cost with no recourse for the hapless non-utility generator. Further, I would propose to the Cornnission that the costs which IPC seeks to charge a small power project are not trj.nterconnection costsrr within the meaning of the federal 1aw, and cannot be passed on to the small polrer project. The federal regulations, as 5292.304, do allow charging ttinterconnection costsrl to a small pohrer producer, but ilinterconnection coststt are defined at 5292.2oL(71 as: PROTEST -2- t ( The reasonable costs of connection, switching, metering,transnission, distribution, safety provisions andadninistrative costs incurred by the electric utilitydirectly related to the installation and maintenance ofthe physical facilities necessary to pernit interconnected operations with a gualifying facility, tothe extent such costs are in excess of the correspondingcosts which the electric utility would have incurred ifit had not engaged in interconnected operations, butinstead generated an equivalent amount of electric energyitself or purchased in equivalent amount of electril ener!ry or capacity fron other sources. Interconnectioncosts do not include any costs included in thecalculation of avoided costs. [Emphasis added. ] It is guite clear that the connection and maintenance costs being charged by fdaho Power would be incurred by them if they were to generate this power themselves in their own capacity, and no showing is made to the contrary. Idaho Powerrs application in this matter is aII the more insidious because it is aimed no doubt for the most part at future non-utility generators who are not yet identified and therefore not notified that the future is being decided for them now to their detriment. In fact, a prospective IPP with no experience with the predatory practices of IPC when dealing with IPC might not read into Schedule No. 72 what I read into it only because of ny ohrn bitter experiences with IPc. The foregoing position taken by this protestor, it is realized, does not by itself present to the commission facts upon which IPC can be exposed. Holrever, these are not empty words and I will cite my frustration and confrontations with IPC when I was attenpting to bring Sunshine Power Number Two to fruition by means of irrefutable evidence of IPC behavior during the construction PROTEST -3- I I phase. 1 4 2 3 The following paragraphs relate the chronology of eventsl After IPC had accepted by interconnect application and I had established conmunication with the engineering departnent, I was informed that IPC would furnish a company designed protection package with manual and automatic disconnect switching. I was told such a device I had intended as part of the generator controls was not acceptable to IPC. I sent the powerhouse drawing to IPC and in return received an IPC drawing showing the desired location of the rPC equipnent mounted on the inside waII. As time elapsed and the first energry date approached, IPC conducted a site survey and finally it was negotiated that I would install two power poles, transformers, etc. and IPC would install one pole at the interconnect point. The poles f installed included raptor protection and cost approximately $500.00 each installed. The fPC pole did not include raptor protection. I{hen fPC furnished their disconnect equipment it turned out to be nothing like that shown on their drawing. It was rated at 500 amps instead of the expected 20O amps, it was outdoor, weatherproof eguipment and would not fit in the powerhouse without a wiring redesign which cost me more money. My electrical contractor installed the IPC equipment at my expense as well as all the overhead wiring to the 5 5. PROTEST {{ 7 8. o 10. 11. L2. 13. interconnect point. fPc did not even deliver the equipment to the site. The only work the IPC crew performed was the installation of one pole and the actual interconnect to the existing 34 kv line which consumed several hours. For the two manual switches, the autonatic switch and the installation of one power pole I hras obligated to pay $19r069.00 to get on interconnect. I reguested a detailed breakdown of the $19r069.00 bill which has not been made available to me. I then did some price checking through my electrical contractor and learned that 2O0 aurp indoor switches cost approximately $300.00 each. I learned from Sierra Electro Development I could duplicate the IPC automatic control with lock and key for $3r00o.00. In short, I was forced to pay $191069.00 for something that could be duplicated for less than $4r500.00 but that is not the end of it. Ever since the interconnect date I have been paying $133.48 a month for non-existent maintenance on one power pole worth approximately $50O.00, two manual switches that should be worth $30O.OO each and one automatic switch worth maybe $3rOOo.OO. After 36 months of palments I have now paid a total of $4r805.28 for non-existent maintenance on eguipnent only worth $4,5o0.o0. To add insult to injury the IPC directed my electrical PROTEST -5- {I contractor to install 500 amp fuses because the switch gear was so rated. He refused to do this and installed 2O0 amp fuses to that the generating eguipment would be better Protected. L4. In my utter frustration regarding the above actions of IPC which I consider to be nothing short of crininal, I have sought advise from legaI council on how to break this strangle hold on me by IPC. The answer comes back loud and clear that I would be wasting my time since IPC operates in this area under the approval of the IPUC. Please be advised that if the Comnission takes an interest in my views I can, by request, furnish hard evidence in the form of bilIs, palmrents and quotations. fn fact, I request that the Comnrission does verify the behavior of rPC under your mandate and deny fPC approval of Schedule Number 72 as nohl written. ft makes no sense that fPC control the type and sale prices of standard switch gear. Even special switch gear can be made to their specifications which is how they purchase it no!r. As for the standard operational and maintenance fees based on IPC determined costs as requested in Schedule Number 72 where there is no direct bearing between cost and maintenance to think otherwise would be naive. Fina1ly, this letter is meant to be a complaint as vell as a protest against IPC for malpractice. I request that the Commission direct IPC to pay retribution for their criminal difference between the $19rooo.oo cost and the $4r50o.00 worth, including the non- PROTEST -6- { FROTI I{UDEN HRKUU5H I(1I-E.UI t existent maintenance fees pluB interest. I thank the conmission for the opportunlty to flle thls protest and cornp).aint and f loo)c forward to being lnfor:ned as to the actlon taken ln this matter. DATED this 16 day of January, 1991. A--N-{3^-*r--nA. W. BROT{N u1.i.:.lt:, 1 lt,:?4 t', x PROTEST -7-