HomeMy WebLinkAbout960710.docxDECISION MEMORANDUM
TO:COMMISSIONER NELSON
COMMISSIONER SMITH
COMMISSIONER HANSEN
MYRNA WALTERS
TONYA CLARK
DON HOWELL
STEPHANIE MILLER
DAVE SCHUNKE
RICK STERLING
GARY RICHARDSON
WORKING FILE
FROM:SCOTT WOODBURY
DATE:JULY 10, 1996
RE:CASE NO. IPC-E-96-13
BRIGGS CREEK HYDRO PROJECT
FIRM ENERGY SALES AGREEMENT—FIRST AMENDMENT
On July 1, 1996, Idaho Power Company (Idaho Power; Company) filed an Application with the Idaho Public Utilities Commission (Commission) for approval of a June 25, 1996, First Amendment (attached) to a Firm Energy Sales Agreement (Agreement) with Richard H. Kaster regarding the Briggs Creek Hydro Project. The underlying Agreement dated June 21, 1984, was approved on July 13, 1984 by Commission Order No. 18996 in Idaho Power Case No. U-1006-236.
The Briggs Creek Hydro Project is a 650 kilowatt facility located in the Northeast Quarter of Section 4, Township 9 South, Range 14 East, Boise-Meridian, Twin Falls County, Idaho. The estimated annual generation is 5,256,000 kilowatt hours.
The proposed amendment incorporates several changes that have occurred since the Agreement was first signed:
∙As a substitute for the Agreement requirement of valued loss of income insurance, the Amendment to provide security for the levelized rate payment obligation incorporates various of the security provisions of Commission Order Nos. 21690 and 21800 in the Commission’s generic -292 security case and the insurance requirements of Order No. 25240. Reference Agreement Article I: Definitions ¶¶ 1.19 and 1.20 (new); Article XIV: Indemnification and Insurance; Article XXVIII: Additional Terms and Conditions; Article XXX: Security (new); and Appendix E—Engineer Certifications (new).
∙The adjustable portion of the purchase price is amended per Commission Order No. 25880.
∙A routine change in the Notices article is reflected. Reference Agreement Article XXVII: Notices.
The Company requests that the First Amendment be approved and that all costs relating thereto be allowed to Idaho Power as prudently incurred expenses for ratemaking purposes.
Staff has reviewed the Company’s Application; advises the Commission that the proposed changes are of a type that have been previously approved for other QF projects; and recommends that the proposed First Amendment changes in Case No. IPC-E-96-13 be approved.
Commission Decision
Should the Company’s Application and First Amendment in Case No. IPC-E-96-13 be approved? If yes, a proposed Minute Entry approving the Amendment is attached for your consideration. If no, what is the Commission’s preference?
Scott Woodbury
vld/M:IPC-E-96-13.sw