HomeMy WebLinkAbout20230929IPC to Staff 308 Attachment 1.pdfHCPR200001 - HCPR U13 Generator Refurbishment Variance Notes CLRIS Budget ID Page (Description, Need, Consequence and notes) HCPR200001_CLRIS Microsoft Project Schedule Notes (PM managed schedules and routine variance notes) 2020 Budget Update 4: Total Project Change: $5.39M Budget Update 1: Accelerated +$651K for the stator rewind contract. Budget Update 2: No Change. Budget Update 3: Accelerated +$5.4M for the stator rewind contract due to failure of HCPR Unit #3. Budget Update 4: Deferred ($617K) per the final negotiated contract payment schedule to accelerate the refurbishment after failure of Unit 3. Budget Update Authorized to Spend 2020 August Detailed Comments: Details of Changes to Project That Impacted Project Cost or Schedule on Annual Basis -Updated project costs to match revised estimates or quotes from suppliers -Updated cash flows to match project schedule due to the failure of unit #3 Latest Current Baseline set after project plan approval. Change Orders -Neutral relocation - Cost:$327,000 -Interpole connection -Cost: $76,826 -Engineering Acceleration -Cost: $23,400 2020 September Detailed Comments: Details of Changes to Project That Impacted Project Cost or Schedule on Annual Basis -Updated project costs to match revised estimates or quotes from suppliers -Updated cash flows to match project schedule due to the failure of unit #3 Latest Current Baseline set after project plan approval. Change Orders -Change order 1: Neutral relocation (executed) - Cost:$327,000 -Change Order 2: Engineering Acceleration (executed) - Cost: $23,400 -Change Order 3: Interpole connection (executed) -Cost: $76,826 -Change Order 4: Project Acceleration (executed) -Cost: $1,762,071 2020 December Detailed Comments: Details of Changes to Project That Impacted Project Cost or Schedule on Annual Basis -Reduced operator labor to match actual use. $191K to $57K -Updated mechanic hours to match actual use. -Pushed services and material purchases unused to 2020 to 2021. -$300K of discovery work will be pushed 2021. Latest Current Baseline set after project plan approval. Budget Update Authorized to Spend 2021 January Detailed Comments: Details of Changes to Project That Impacted Project Cost or Schedule on Annual Basis -Pushed unused services and material purchases to 2020 to 2021. -$300K of discovery work pushed 2021. Latest Current Baseline set after project plan approval. Change Orders -GE change Order 5: Additional NDT inspection of rotor poles and stator Frame (Complete) -Cost: $24K -Change order covers the additional inspection recommended by GE based on the FEA reports of the rotor poles and the stator frame. 2021 February Detailed Comments: Details of Changes to Project That Impacted Project Cost or Schedule on Annual Basis -Due to the damaged rotor poles additional cost will be required for the replacement of the poles. IPC does not have a firm offer for replacing poles but replacement of 60 poles could cost more that $1,000,000. Costs will be updated in the project schedule once a final proposal has been received from GE on the replacement of rotor poles. -Schedule of unit #3 will be pushed due to the replacement of the rotor poles. The impacts to schedule are not official but it is estimated that the unit #3 outage will be pushed to November of 2021. Project schedule will be update once IPC has received final proposal on rotor pole replacement from GE. 2021 April Detailed Comments: Details of Changes to Project That Impacted Project Cost or Schedule on Annual Basis -Schedule of unit #3 will be pushed due to the replacement of the rotor poles. The impacts to schedule are not official but it is estimated that the unit #3 outage will be pushed to February of 2022. Based on lost generation analysis the best option for Unit #1 will be to push the Unit #1 outage to start during the fall of 2022. -GE is currently scheduled to finish stator work August of 2021. Latest Current Baseline set after project plan approval. Change Orders: Change Order 06 - Rotor Pole Supply, Main & Neutral Design Change, Schedule Update -Cost for rotor poles: $1,044,371.00 -Cost for Main & Neutral Redesign: $194,880 2021 June Detailed Comments: Details of Changes to Project That Impacted Project Cost or Schedule on Annual Basis -GE is currently scheduled to finish stator work September of 2021 and scheduled to complete rotor work in January of 2022. Given GE's current issues onsite it is likely that they will not meet their intermediate stator winding complete milestone in September. We do not expect this to push GE's final complete milestone. -IPC's project complete date for unit 3 will now be in March of 2022. -Unit 1 schedule has been updated to start in September of 2022 and will be complete in May of 2023 Latest Current Baseline set after project plan approval. Change Orders: Change Order 06 - Rotor Pole Supply, Main & Neutral Design Change, Schedule Update (Executed) -Cost for rotor poles: $1,044,371.00 -Cost for Main & Neutral Redesign: $194,880 2021 July Detailed Comments: Details of Changes to Project That Impacted Project Cost or Schedule on Annual Basis -GE is currently scheduled to finish stator work September of 2021 and scheduled to complete rotor work in January of 2022. Given GE's current issues onsite it is likely that they will not meet their intermediate stator winding complete milestone in September and will complete this milestone in October. We do not expect this to push GE's final complete milestone. -IPC's project complete date for unit 3 will now is now February 28th, 2022. -Unit 1 schedule has been updated to start in September of 2022 and will be complete in May of 2023 Latest Current Baseline set after project plan approval. Change Orders: -GE Change Directive 01: Stator Frame Repair (Executed) -Actual Cost: $63,757.00 -Reviewing actual costs and drafting the change order. -GE Change Directive 03: Rotor Rim Analysis and Rotor Pole Damage Analysis (Executed) -Waiting for actual costs to be submitted. -GE Change Directive 05: Stator Coil Lashing and Blocking -This change directive covers the supply, engineering, and installation of the additional blocking of the stator coils. -Not to Exceed Cost: $44,000 (this is for both units) Date: 8/12/21 Current Year: Project Change -$8.57M Total FAC Change: Project Change -$1.41M Both current year and the FAC were changed due to as found work on the rotor poles changing the project schedule and a insurance payment made to IPC for the failure of unit 3. Budget Update Authorized to Spend Date: 9/10/21 Current Year: Deferred -$133K Total FAC Change: No Change IPC labored shifted to 2022 due to contractor's schedule delay. Date: 10/7/21 Current Year: Deferred -$276K Total FAC Change: No Change Updated GE milestone payments to reflect current project schedule and pushed assembly material cost to 2022 for IPC assembly. Date: 11/10/21 Current Year: No change Total FAC Change: No Change 2021 Budget Update 4: Total Project Change: ($8.986M) Budget Update 1: Carryover +$188K for deferred services in 2020. Budget Update 2: Project Change ($8.529M) for unit 3 failure insurance payment of $4.1M to IPC and schedule push for unit 3 rotor pole replacement. Unit 1 outage start has pushed from 2021 to 2022 due to the unit 3 schedule push. Budget Update 3: Project Change ($225K) for larger insurance payment from the unit 3 failure. Budget Update 4: Deffered ($420K) for labor and milestone payments due to shift in GE final completion schedule. Date: 1/10/22 Current Year: Project change of $235KK due to increased labor rates for 2022, carryover of $34K for unused labor in 2022.Project change of $235K due to increased labor rates for 2022. Total FAC Change: Project change of $235K due to increased labor rates for 2022. Budget Update Authorized to Spend 2022 Total Project Change: $4.018M Jan: Project Change +$235Kfor increased labor rates, Carryover of $527K or services, labor and materials pushed to 2022 for the Unit 3 Outage. Feb: Project Change $638 more labor used Mar: Project Change $860 more labor used Apr: Project Change $500 more labor used May: Project Change $10K more labor used for the acceleration of assembly and commissioning. June:Project Change $2.175M for spare laminations purchased from Voith. July:Project Change $459K for increase labor and materials used in June to support unit 1 disassembly, added $500K for Voith stator clamping system. Aug: Project Change ($210K) reduced labor to match project plan, $657K for additional install tooling and materials, $115K for additional Voith support services, $5K for additional vehicle use. Sept: Deferred ($15K) for unused materials in this year. Oct: Project Change ($154K) reduced for pressing equipment cost being less than original quote. Nov: Project Change ($33K) in reduced labor for reduced overtime, ($122K) for unneeded onsite QA services, ($132K) in reduced material costs. 2022 Annual Project Change: $4.306M BU1: Project Change +$235K for increased labor rates, Carryover of $527K for services, labor and materials pushed to 2022 for the Unit 3 Outage. BU2: Feb: Project Change $638 more labor used, Mar: Project Change $860 more labor used, Apr: Project Change $500 more labor used BU3: May: Project Change $10K more labor used for the acceleration of assembly and commissioning, June:Project Change $2.175M for spare laminations purchased from Voith, July:Project Change $459K for increase labor and materials used in June to support unit 1 disassembly, added $500K for Voith stator clamping system. BU4: Aug: Project Change ($210K) reduced labor to match project plan, $657K for additional install tooling and materials, $115K for additional Voith support services, $5K for additional vehicle use; Sept: Deferred ($15K) for unused materials in this year; Oct: Project Change ($154K) reduced for pressing equipment cost being less than original quote. 2022 EAC Tracker Total EAC Variance: Apr: $497 May: $22K Project change of labor added to 2022 and 2023 June: Project Change $2.175M for purchase of Voith Laminations. July:Project change $724K for additional labor, materials and services added based on recent quotes and increased labor used in June to support unit 1, added $567K for Voith stator clamping system. Aug: Project change ($100K) for labor changes, $652K for stacking and winding materials, $1.5M for voith labor services, $5k for additional Vehicle use. Sept: Project Change ($3K) for recycled material credit. 2023 Annual Project Change: $783K JAN: Carryover $112K for GE Final Payment. FEB: No change MAR: No Change APR: No change MAY: Project Change ($12k) for reduced labor used for assembly and commissioning. JUN: Project Change $172K for updated insurance claim credit to project JUL: Project Change $6K for increased transportation costs during demobilization. AUG: Project Change $16K for increased labor and transportation costs during demobilization, final equipment rental costs. SEP: Project change $15K for increased labor costs for project closeout.