Loading...
HomeMy WebLinkAbout20230928IPC to Staff Supp 289 Attachment 1.pdfNEWX170001 - NEWX - Reconstruct 138-kV CDAL-HBRD T438 line to add a 230-kV circuit and double circuit distribution underbuild Variance Notes CLRIS Budget ID Page (Description, Need, Consequence and notes) NEWX170001_CLRIS NEWX170001_Solution_CLRIS Microsoft Project Schedule Notes (PM managed schedules and routine variance notes) 1/10/18 Current year: $40,473 reduction Total FAC Change: $48K increase Submission of the draft CUP application did not get completed in late 2017 2018 Budget Update 1 Current Year: Carryover: +59k Due to deferral of the CUP applicaton to 2018. 2/12/18 Current year: $275k reduction Total FAC Change: No Change Reduce forecast of easement payments for 2018 Budget Update Authorized to Spend 2018 Budget Update 2 No Change 4/1/18 Current Year: -$8k Total FAC Change -$-8k Pre-scoping tasks reduced 6/1/18 Current Year: Deferred -$52.7k Total FAC Change: -$46.4k HDR contract had incorrect pricing included in server. Reduced to match contract value ($30k was accounted for in CDAL170001 and contract was listed as $16k higher than actual) 7/1/18 Current Year: Accelerated $37k Total FAC Change: -34k Design of the transmission line for the overpass section accelerated to 2018. $1500k moved from 2021 to 2019 in support of that construction effort. Budget Update Authorized to Spend 8/1/18 Current Year: Accelerated +$70k Total FAC Change $0 Easement purchase at Wood property accelerated due to willingness of customer to sell the easement. (A portion of this easemet still needs to go to CLBA project- likely approx $30k). Will work with Josh on it. 2018 Budget Update 3 Current Year: Deferred -$20.6k Reallocated some permitting effort to 2019. This may accelerate given the project. . 10/1/18 Current Year: Change +$23.3k Total FAC Change: $5.7k Design and easements taking longer than anticiapted. Budget Update Authorized to Spend 11/1/18 Current Year: Accelerated +$55.5k Total FAC Change: $0 Easements Accelerated 2018 ($30k). 2018 design under-budgeted ($25k) 2018 Budget Update 4 Current Year: Accelerated $94k Project Schedule accelerated due to Cloverdale Overpass construction. Rebuilding the first mile of the project in 2019 11/1/18 Current Year: Accelerated +$55.5k Total FAC Change: $0 Easements Accelerated 2018 ($30k). 2018 design under-budgeted ($25k) 12/1/18 Current Year: Accelerated +$17.5k Change +$16.9 Total FAC Change: $16.9 Large portion of Easements moving into 2018 for first mile of project 2019 Budget Update 1 Current year: Change -$445.7k Project had ROW money forecasted that is no longer required. The line has a center line easement that can be used per legal. Budget Update Authorized to Spend 2019 Budget Update 2 Current Year: +$313k Total FAC Change: +$313k ILB was the successful bidder for Ph 1 construction and was approximately $300k over our forecast. The additional $13k is for additional design support, inspector support, and other permitting items. Budget Update Authorized to Spend 6-12-19 Current Year: Deferred $152.7k Total FAC Change: $0 Labor forecasts updated per 20-22 resource updates. $110k in easements deferred to 2020 pending ACHD negotiations. ~$40k deferred in design to 2020. 7-11-2019 Current Year: Change +$37.2k Total FAC Change: +$30k Change order for additional work for ILB not included in SC. 10/10/2019 Current Year: -$28k Total FAC Change -$26k Misc Material Returns 10/10/2019 Current Year: -$28k Total FAC Change -$26k Misc Material Returns 2019 Budget Update 3 Current Year: Deferred -$124.5k Phase 2 Easements deferred to 2020 pending ACHD negotiations. ~$40k deferred in design to 2020. Budget Update Authorized to Spend 11/1/2019 Current Year: Deferred -$16.7k Total FAC Change: -$19k Deferred $10k in dist design to 2020 and reduced PM budget 2020 Budget Update 1 Current Year: Carryover $340k Transmission and Distribution deferred to 2020 per design. Easement purchases also deferred from 2019 to 2020. Budget Update Authorized to Spend 4.12.2020 curernt year: +$270k Total FAC Change +$270k $220k Trinity Meyer Accrual (incorrect materials charge previously) $50k for Geotech Report- extensive since all structures to be foundations Budget Update Authorized to Spend 5.12.2020 Current Year: +$429.3k Total FAC Change: +$1506.8k Current Year: Accelerated $786k of Foundation install into 2020. Reduced CY Easement payments by $300k. Design slightly more expensive than anticpated. FAC Change: Foundation budget went increased by $1.4M due to all structures on foundations (from only DE's). Material approx $224k less. Also expenses increase by $415k to account for landscape repairs, flagging, and larger crane due to size of structures. 6.10.2020 Current Year: +$23k Total FAC Change: -$38k Current Year: Design taking more labor. Foundation design contracted Total FAC: Distribution Design completed and verified. 7.13.2020 Current Year: +$1973k Total FAC Change: -$4.5k Current Year: Steel Pole delivery accelerated into 2020 per Mgmt Total FAC: Extra labor for design 2020 Budget Update 3 Current Year: Change +$2430k $1977k- Steel Pole Bid accelerated into 2020 per Mgmt. $450k- fnd install accelerated to 20 in order to make outage requirements. Budget Update Authorized to Spend 2020 Budget Update 3 Current Year: +$133.2k Project Awarded to Michels construction. Bids came in higher than anticipated. They include an aggressive foundation install in Nov-Dec. 10.13.2020 Current Year: +$133.2k Total FAC Change: +$1836.9k Project Awarded to Michels construction. Bids came in higher than anticipated. There were some expenses that were reduced to accommodate contract inspector. 2021 Budget Update 1 Current Year: Previously Accelerated -$1.4m Project went through signficant change since Aug 2020- Construction bids came in in Sept 2020 and were high, the 2021 budget got updated based on the bids. Project schedule then accelerated all foundation work in 2020, along with material that was schedule to be used in 2021. Result, is acceleration of $1496k being accelerated into 2020- but since compated to August, acceleration looks minimal. Budget Update Authorized to Spend 5/12/2021 Current Year: -$32.2k Total FAC:- $32.2K Project completed under budget. May have a little commissioning time in June. 7/1/21 Current Year: Change +$200k Total FAC Change +$200k Michels have a few change orders resulting from modifications to their SOW as detained in SOW. Working with contracting to get it finalized. These were due to material issues, modifications to design, UG conflicts causing concrete remediation, and stand-by time due to material delay. Budget Update Authorized to Spend