HomeMy WebLinkAbout20220513IPC to Staff 3rd Production Response No. 9 - Redacted.pdf
JULIA A. HILTON
Deputy General Counsel and
Director of Legal
jhilton@idahopower.com
May 13, 2022
Jan Noriyuki, Secretary
Idaho Public Utilities Commission
11331 W. Chinden Boulevard
Building 8, Suite 201-A
Boise, Idaho 83714
Re: Case No. IPC-E-22-11
Application of Idaho Power Company for Authority to Implement Power Cost
Adjustment (“PCA”) Rates for Electric Service from June 1, 2022, through May
31, 2023
Dear Ms. Noriyuki:
Attached for electronic filing is Idaho Power Company’s Response to the Third
Production Request of the Commission Staff in the above-entitled matter.
The confidential attachments will be provided in a separate encrypted email to the
parties who sign the protective agreement.
If you have any questions about the attached documents, please do not hesitate to
contact me.
Sincerely,
Julia A. Hilton
JAH:sg
Enclosures
RECEIVED
2022 May 13, PM 2:45
IDAHO PUBLIC
UTILITIES COMMISSION
IDAHO POWER COMPANY’S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE
COMMISSION STAFF - 1
LISA D. NORDSTROM (ISB No. 5733)
Idaho Power Company
1221 West Idaho Street (83702)
P.O. Box 70
Boise, Idaho 83707
Telephone: (208) 388-5825
Facsimile: (208) 388-6935
lnordstrom@idahopower.com
Attorney for Idaho Power Company
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR
AUTHORITY TO IMPLEMENT POWER
COST ADJUSTMENT (“PCA”) RATES
FOR ELECTRIC SERVICE FROM JUNE
1, 2022, THROUGH MAY 31, 2023.
)
)
)
)
)
)
)
)
CASE NO. IPC-E-22-11
IDAHO POWER COMPANY’S
RESPONSE TO THE THIRD
PRODUCTION REQUEST OF THE
COMMISSION STAFF
COMES NOW, Idaho Power Company (“Idaho Power” or “Company”), and in
response to the Third Production Request of the Commission Staff dated May 10, 2022,
herewith submits the following information:
IDAHO POWER COMPANY’S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE
COMMISSION STAFF - 2
REQUEST FOR PRODUCTION NO. 9: Regarding Production Request (PR) No.
6, please respond to the following for Hells Canyon #3 relative to the forced downtime
that started on 4/1/2021 through 4/1/2022 (according to the response).
(a) Please provide a detailed explanation for the cause of the downtime including the
root cause(s).
(b) Is unit #3 still offline? If so, when is it expected to come back on-line?
(c) Why has it been down for over a year? What has the Company done to rectify the
situation to bring the unit back online? If the unit is not currently online, what is the
Company currently doing to rectify the situation and bring the unit back online?
(d) Was it possible to bring the unit on-line sooner? If so, please explain how and
describe the associated cost compared to the Company’s chosen timeline.
(e) According to the response to PR No. 6, 1,143,180 Megawatt-hours during the
2021-2022 PCA deferral period of zero-fuel cost generation were lost. Please
calculate the additional cost of replacing the generation from that unit due to the
outage.
(f) Please provide any documentation showing the Company’s analysis of the
downtime that address the questions above.
RESPONSE TO REQUEST FOR PRODUCTION NO. 9:
a) Unit 3 failed due to a phase-to-phase fault in the stator on June 23, 2020. The likely
root cause was degraded coil insulation. At the time of failure, Idaho Power had
already planned for scheduled maintenance from August 2021 to December 2021
(with a targeted back in service date of February 2022) and was under contract
with Alstom Renewable US (General Electric). As a result of the failure, however,
IDAHO POWER COMPANY’S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE
COMMISSION STAFF - 3
Idaho Power negotiated a change order to accelerate the previously scheduled
rewind project to begin June 1, 2021, establishing an in-service date of August
2021.
b) The unit was back on-line on May 11, 2022.
c) As discussed in part (a) to this response, Unit 3 failed due to a phase-to-phase
fault in the stator. Once the unit was disassembled, additional, unanticipated work
was discovered requiring unexpected manufacturing of additional parts and lead
time for materials. This moved the rewind date to June 1, 2021 to December 18,
2021. The resulting project completion moved to February 2022.
d) While there were some performance and workmanship issues as well as delayed
completion of the contracted work by General Electric, Idaho Power crews
consistently worked twelve-hour days, six to seven days a week, to reassemble
and commission the unit once General Electric left the site in late April 2022.
e) The 1,143,180 megawatt-hours provided in response to Staff’s Production
Request No. 6 represent nameplate capacity multiplied by total hours of downtime.
It does not represent the net impact of the outage to customers, which would
require additional analysis to determine the overall impact of the unit’s lack of
availability on the Company’s operations over that time period. However, as
IDAHO POWER COMPANY’S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE
COMMISSION STAFF - 4
discussed in part (d) to this response,
f) Please see confidential attachments 1 – 5 to this response. Please note that the
three change orders provided contain support for the timelines and values
discussed in parts a, c, and d of this response. Change orders not specific to this
response have not been provided.
The response to this Request is sponsored by Ryan Adelman, Vice President of
Power Supply, Idaho Power Company.
IDAHO POWER COMPANY’S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE
COMMISSION STAFF - 5
DATED at Boise, Idaho, this 13th day of May 2022.
____________________for_________
LISA D. NORDSTROM
Attorney for Idaho Power Company
IDAHO POWER COMPANY’S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE
COMMISSION STAFF - 6
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on the 13th day of May 2022, I served a true and correct
copy of Idaho Power Company’s Response to the Third Production Request of the
Commission Staff to Idaho Power Company upon the following named parties by the
method indicated below, and addressed to the following:
Commission Staff
Dayn Hardie
Deputy Attorney General
Idaho Public Utilities Commission
11331 W. Chinden Blvd., Bldg No. 8,
Suite 201-A (83714)
PO Box 83720
Boise, ID 83720-0074
Hand Delivered
U.S. Mail
Overnight Mail
FAX
_____ FTP Site
X Email: Dayn.Hardie@puc.idaho.gov
Industrial Customers of Idaho Power
Peter J. Richardson
515 N. 27th Street
Boise, Idaho 83702
Hand Delivered
U.S. Mail
Overnight Mail
FAX
_____ FTP Site
X Email: peter@richardsonadams.com
Dr. Don Reading
6070 Hill Road
Boise, Idaho 83703
Hand Delivered
U.S. Mail
Overnight Mail
FAX
_____ FTP Site
X Email: dreading@mindspring.com
________________________________
Stacy Gust, Regulatory Administrative
Assistant
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-22-11
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 9
ATTACHMENT NO. 1
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-22-11
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 9
ATTACHMENT NO. 2
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-22-11
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 9
ATTACHMENT NO. 3
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-22-11
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 9
ATTACHMENT NO. 4
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-22-11
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 9
ATTACHMENT NO. 5