HomeMy WebLinkAbout20210909IPC to Staff 12-16-Redacted.pdfLISA D. NORDSTROM
Lead Counsel
lnordstrom@idahopower.com
September 9, 2021
VIA ELECTRONIC FILING
Jan Noriyuki, Secretary
Idaho Public Utilities Commission
11331 W. Chinden Blvd., Bldg 8,
Suite 201-A (83714)
PO Box 83720
Boise, Idaho 83720-0074
Re: Case No. IPC-E-21-17
In the Matter of Idaho Power Company’s Application for Authority to
Increase Its Rates for Electric Service to Recover Costs Associated with the
Jim Bridger Power Plant
Dear Ms. Noriyuki:
Enclosed for electronic filing, pursuant to Order No. 35058, please find Idaho
Power Company’s Response to the Second Production Request of the Commission Staff
to Idaho Power Company. Due to the voluminous nature of confidential and non-
confidential information provided in response to data requests in this case, the Company
is posting the attachments to these requests to the secure FTP site to allow parties to
view the requested information remotely. Because certain attachments contain
confidential information, the FTP site is divided between confidential and non-confidential
information. The login information for the non-confidential portion of the FTP site was
provided to all parties on July 21, 2021, and the login information for the confidential
portion was provided to those parties that executed the Protective Agreement in this
matter on July 21, 2021.
The response to Production Request No. 16 contains confidential
information. Idaho Power will transmit this to the Commission and parties that have
signed the Protective Agreement separately via encrypted email.
If you have any questions about the attached filing, please do not hesitate to
contact me.
Very truly yours,
Lisa D. Nordstrom
LDN:sg
Enclosures
RECEIVED
2021 SEP 9 PM 4:20
IDAHO PUBLIC
UTILITIES COMMISSION
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 1
LISA D. NORDSTROM (ISB No. 5733)
Idaho Power Company
1221 West Idaho Street (83702)
P.O. Box 70
Boise, Idaho 83707
Telephone: (208) 388-5825
Facsimile: (208) 388-6936
lnordstrom@idahopower.com
Attorney for Idaho Power Company
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE IDAHO POWER
COMPANY’S APPLICATION FOR
AUTHORITY TO INCREASE ITS RATES
FOR ELECTRIC SERVICE TO RECOVER
COSTS ASSOCIATED WITH THE JIM
BRIDGER PLANT
)
)
)
)
)
)
)
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY’S
RESPONSE TO THE SECOND
PRODUCTION REQUEST OF
THE COMMISSION STAFF
COMES NOW, Idaho Power Company (“Idaho Power” or “Company”), and in
response to the Second Production Request of the Commission Staff (“Staff”) dated
August 19, 2021, herewith submits the following information:
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 2
REQUEST NO. 12: In reference to the potential for one or more units of Jim
Bridger being converted to natural gas, please respond to the following:
a. Has Idaho Power performed an analysis on converting units of Jim Bridger
to natural gas? Please explain and provide the analysis if performed; and
b. How would the natural gas conversion of one or more units of Jim Bridger
affect the Company’s proposed depreciation schedule, balancing account,
and revenue requirement provided in this case? Please explain.
RESPONSE TO REQUEST NO. 12:
a. Idaho Power is performing an analysis on the conversion of Bridger units
to natural gas as part of the 2021 Integrated Resource Plan.
b. The potential conversion of one or more Bridger units to natural gas is an
example of the fluid nature of the operating lives of the Bridger units. One
of the benefits of the Company’s proposed balancing account mechanism
is that it would allow for flexible timing and recovery of the remaining
Bridger revenue requirement, including any expenditures associated with
the conversion to natural gas, while also smoothing revenue requirement
impacts and providing rate stability for customers.
Idaho Power has proposed a depreciable life of year-end 2030 for
all Bridger units. Should an integrated resource plan indicate that a
conversion to natural gas with a later exit from Bridger would provide a
more favorable economic outcome as compared to the proposed
depreciable life assumption of 2030, the balancing account mechanism
would allow for an update to the depreciable life and an adjustment to the
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 3
levelized revenue requirement, maintaining a relatively stable level of
annual recovery even though an underlying cost driver changed.
The response to this Request is sponsored by Matt Larkin, Revenue
Requirement Senior Manager, Idaho Power Company.
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 4
REQUEST NO. 13: In reference to State Implementation Plan (“SIP”) provided in
Response to Staff’s Production Request No. 7. Please respond to the following:
a. When was the SIP submitted to the U.S. Environmental Protection Agency;
and
b. Have Idaho Power and PacifiCorp been modeling the Voluntary Visibility
Enhancing Emissions Limits discussed in the SIP in their Jim Bridger IRP
analyses? If so, provide an explanation of the assumptions used in
modeling the Voluntary Visibility Enhancing Emissions Limits, such as when
the Limits would start. If not, explain why the Limits were not included.
RESPONSE TO REQUEST NO. 13:
a. The State of Wyoming submitted the State Implementation Plan (“SIP”) to
the U.S. Environmental Protection Agency on May 14, 2020.
b. Idaho Power is modeling the Voluntary Visibility Enhancing Emission Limits
for Bridger in the 2021 IRP. Idaho Power worked with the plant engineering
personnel to identify the estimated maximum generation available each
month based on the voluntary emission limits (and yearly total maximum).
Idaho Power’s share of the estimated maximum monthly generation starting
on January 1, 2022, and modeled in the 2021 IRP is listed below:
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 5
Maximum Average MW
January 587
February 587
March 587
April 587
May 619
June 649
July 649
August 649
September 649
October 629
November 629
December 587
The response to this Request is sponsored by John Carstensen, Joint Projects
Leader, Idaho Power Company.
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 6
REQUEST NO. 14: Please provide a list of all assumptions used for each Bridger
unit in the Company’s IRP modeling analysis.
RESPONSE TO REQUEST NO. 14: The current Bridger unit modeling
assumptions for the 2021 IRP that are also used in the quantification of the Bridger
levelized revenue requirement are identical, with the exception of the two adjustments
made in the levelized revenue requirement calculation discussed in Mr. Larkin’s
testimony: (1) the inclusion of only interim future decommissioning costs and (2) the
exclusion of large forecasted capital expenditures expected in 2028 and 2029. These
cost assumptions were provided in the Confidential Attachment 1 to the Company’s
Response to the Industrial Customers of Idaho Power’s Request No. 1. In addition,
please see the Company’s Response to Staff’s Request No. 12 for a discussion of the
potential natural gas conversion of the Bridger units. The final cost
forecast/assumptions used in the 2021 IRP will consider the conversion of two units to
natural gas.
The response to this Request is sponsored by Randy Henderson, Principal Joint
Projects Coordinator, Idaho Power Company.
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 7
REQUEST NO. 15: In reference to the file named “Request 1-
CONFIDENTIAL Attachment 1- Exhibit No. 1 and workpapers – Bridger Levelized
Rev Req” provided in Response to the Industrial Customers of Idaho Power’s First
Production Request No. 1 as Confidential Attachment 1. Please explain the
amount shown for Unit 3 capital expense for the year 2025 in the “Capex Forecast”
tab.
RESPONSE TO REQUEST NO. 15: There is no capital spend on Unit 3 in 2025
assumed in the forecast shown on the Capex Forecast tab. A major overhaul on Unit 3
is scheduled to occur in 2024. As described in Mr. Adelman’s testimony, a major
overhaul of each unit is required every four years and entails repairs and upgrades on
major components of the unit. If capital needs arise in 2025 for Unit 3 then the costs will
be tracked and the Bridger levelized revenue requirement would be adjusted over
time through the proposed balancing account mechanism to reflect any actual costs
the Company incurs.
The response to this Request is sponsored by John Carstensen, Joint Projects
Leader, Idaho Power Company.
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 8
REQUEST NO. 16: In the Project Proposals provided in Response to
Staff’s Production Request No. 9c, it states the work will be competitively bid to
multiple contractors. Please explain the competitive bidding process, and provide
copies of all competitive bids received and short-list/final bidding scoring for the
following Appropriation Requests (“APR”):
a. APR – 10007088, Project Title – Jim Bridger Unit 2 Turbine Upgrade
High Pressure/Intermediate Pressure/Low Pressure;
b. APR- 90000565, Project Title – Jim Bridger Unit 2 Turbine Upgrade
High Pressure/Intermediate Pressure/Low Pressure;
c. APR - 10015937, Project Title – U4 Absorber Reline 16; and
d. APR - 90001005, Project Title – U4 Absorber Reline 16.
RESPONSE TO REQUEST NO. 16: The following describes the competitive
bidding used by the operating partner of Bridger, PacifiCorp:
For all bids that are budgeted greater than $50,000, PacifiCorp uses an internet-
based procurement tool for managing the Request for Proposal (“RFP”) process
including the posting of RFP documents, collection of all correspondence and receipt of
respondent proposals. All bidding information is highly confidential and collected
through the internet in a sealed bidding process. If questions are asked by the bidders,
the question and answer is provided to all bidders to ensure everyone receives the
same information. If the project manager requests, a pre-bid meeting will be held at the
plant-site so that bidders are familiar with the work environment and can gather
information directly from the project manager and see the site where work is
performed. Bids are due on a specific date. After receipt, the bids are reviewed and
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 9
analyzed technically by technical reviewers and reviewed commercially by
procurement. The technical reviewers and procurement departments are comprised of
both plant and corporate personnel. Bids of all levels are held confidential.
Due to the voluminous nature of confidential and non-confidential information
provided in response to previous data requests in this case, Idaho Power provided
parties access to an FTP site where copies of all confidential and non-confidential
responses can be found. The confidential attachments to this response can be found in
the confidential portion of that site.
a. APR-10007088 was the original APR and approved prior to identifying the
need for blocking filters with this project. APR-90000565 was written and
approved to include the costs for the turbine upgrade and blocking filters.
This
determination was made following the competitive bidding process and award
for the turbine upgrade on Bridger Unit 1,
The Review Record, provided as
Confidential Attachment 1, reflects the competitive bid chain of approval on
the initial purchase order for Unit 1. Confidential Attachment 2 is the Non-
Competitive Procurement Justification Form specific to the Unit 2 upgrade.
b. See response to a.
c. APR-10015937 was originally written in January 2016 with the best estimate
for the project. After further inspection of the unit, it was determined the
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 10
scope needed to be increased for the project to complete the repair and APR-
90001005 was written with the updated cost estimates. The Evaluation
Matrix, included as Confidential Attachment 3 shows the results of the bid
evaluations. Confidential Attachments 4 through 47 include the bid packages
from the 5 contractors for the project. Idaho Power has separated the
confidential bid packages by contractor into different folders on the FTP site.
d. See response c.
The response to this Request is sponsored by John Carstensen, Joint Projects
Leader, Idaho Power Company.
Respectfully submitted this 9th day of September 2021.
LISA D. NORDSTROM
Attorneys for Idaho Power Company
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 11
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on the 9th day of September 2021, I served a true and
correct copy IDAHO POWER COMPANY’S RESPONSE TO THE SECOND
PRODUCTION REQUEST OF THE COMMISSION STAFF upon the following named
parties by the method indicated below, and addressed to the following:
Commission Staff
Erick Shaner
Deputy Attorney General
Idaho Public Utilities Commission
11331 W. Chinden Blvd., Bldg No. 8,
Suite 201-A (83714)
PO Box 83720
Boise, ID 83720-0074
Hand Delivered
U.S. Mail
Overnight Mail
FAX
X Email: Erick.shaner@puc.idaho.gov
_____ FTP Site
Industrial Customer of Idaho Power
Peter J. Richardson
RICHARDSON ADAMS, PLLC
515 North 27th Street (83702)
P.O. Box 7218
Boise, Idaho 83707
Hand Delivered
U.S. Mail
Overnight Mail
FAX
FTP Site
X Email peter@richardsonadams.com
Dr. Don Reading
6070 Hill Road
Boise, Idaho 83703
Hand Delivered
U.S. Mail
Overnight Mail
FAX
X EMAIL dreading@mindspring.com
FTP Site
Idaho Conservation League
Benjamin J. Otto
Idaho Conservation League
710 N. 6th Street
Boise, Idaho 83701
Hand Delivered
U.S. Mail
Overnight Mail
FAX
X EMAIL botto@idahoconservation.org
FTP Site
City of Boise
Ed Jewell
150 N. Capitol Blvd.
P.O. Box 500
Boise, Idaho 83701-0500
Hand Delivered
U.S. Mail
Overnight Mail
FAX
X EMAIL ejewell@cityofboise.org
boiseCityAttorney@cityofboise.org
FTP Site
Hand Delivered
IDAHO POWER COMPANY’S RESPONSE TO THE SECOND PRODUCTION REQUEST OF THE
COMMISSION STAFF - 12
Clean Energy Opportunities for Idaho, Inc.
Kelsey Jae
Law for Conscious Leadership
920 N. Clover Dr.,
Boise, Idaho 83703
U.S. Mail
Overnight Mail
FAX
X EMAIL kelsey@kelseyjae.com
FTP Site
Michael Heckler
Courtney White
Clean Energy Opportunities for Idaho
3778 Plantation River Drive, Suite 102
Boise, ID 83703
Hand Delivered
U.S. Mail
Overnight Mail
FAX
X EMAIL
mike@cleanenergyopportunities.com
courtney@cleanenergyopportunities.com
FTP Site
Sierra Club
Rose Monahan
Ana Boyd
2101 Webster Street, Suite 1300
Oakland, CA 94612
Hand Delivered
U.S. Mail
Overnight Mail
FAX
X EMAIL rose.monahan@sierraclub.org
ana.boyd@sierraclub.org
FTP Site
Micron Technology, Inc.
Austin Rueschhoff
Thorvald A. Nelson
Austin W. Jensen
Holland & Hart LLP
555 17th Street, Suite 3200
Denver, CO 80202
Hand Delivered
U.S. Mail
Overnight Mail
FAX
X EMAIL darueschhoff@hollandhart.com
tnelson@hollandhart.com
awjensen@hollandhart.com
aclee@hollandhart.com
glgarganoamari@hollandhart.com
FTP Site
Micron Technology, Inc.
Jim Swier
8000 S. Federal Way
Boise, ID 83707
Hand Delivered
U.S. Mail
Overnight Mail
FAX
X EMAIL jswier@micron.com
FTP Site
_____ __________________________
Stacy Gust, Regulatory Administrative
Assistant
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16a
ATTACHMENT NO. 1
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16a
ATTACHMENT NO. 2
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 3
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 4
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 5
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 6
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 7
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 8
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 9
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 10
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 11
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 12
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 13
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 14
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO.15
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 16
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 17
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 18
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 19
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 20
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 21
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 22
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 23
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 24
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 25
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 26
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 27
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 28
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 29
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 30
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 31
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 32
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 33
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 34
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 35
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 36
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 37
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 38
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 39
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 40
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 41
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 42
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 43
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 44
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 45
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 46
BEFORE THE
IDAHO PUBLIC UTILITIES COMMISSION
CASE NO. IPC-E-21-17
IDAHO POWER COMPANY
CONFIDENTIAL
REQUEST NO. 16c
ATTACHMENT NO. 47