Loading...
HomeMy WebLinkAbout20210625IPC to Staff 18-23 - Amended.pdf DONOVAN E. WALKER Lead Counsel dwalker@idahopower.com June 25, 2021 VIA ELECTRONIC MAIL Jan Noriyuki, Secretary Idaho Public Utilities Commission 11331 West Chinden Blvd., Building 8 Suite 201-A Boise, Idaho 83714 Re: Case No. IPC-E-21-09 Idaho Power Company’s Application for Capacity Deficiency To Be Utilized For Avoided Cost Calculations Dear Ms. Noriyuki: Attached for electronic filing is Idaho Power Company’s Response to the Amended Third Production Requests of the Commission Staff in the above entitled matter. If you have any questions about the attached documents, please do not hesitate to contact me. Very truly yours, Donovan E. Walker DEW:cld Enclosures RECEIVED 2021June 25, PM 2:14 IDAHO PUBLIC UTILITIES COMMISSION IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 1 DONOVAN E. WALKER (ISB No. 5921) Idaho Power Company 1221 West Idaho Street (83702) P.O. Box 70 Boise, Idaho 83707 Telephone: (208) 388-5317 Facsimile: (208) 388-6936 dwalker@idahopower.com Attorney for Idaho Power Company BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF IDAHO POWER COMPANY’S APPLICATION FOR APPROVAL OF THE CAPACITY DEFICIENCY TO BE UTILIZED FOR AVOIDED COST CALCULATIONS. ) ) ) ) ) ) ) ) ) CASE NO. IPC-E-21-09 IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUEST OF THE COMMISSION STAFF COMES NOW, Idaho Power Company (“Idaho Power” or “Company”), and in response to the Amended Third Production Request of the Commission Staff to Idaho Power Company dated June 16, 2021, herewith submits the following information: IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 2 REQUEST NO. 18: Should the load and resource balance (“L&R”) and the capacity deficiency date filed in Case No. IPC-E-21-09 be updated to include the following items? In the Company’s response, please explain why the deficit date should or should not change by considering each item below: a. The growth in peak loads referenced in the Company’s Notice of Intent (“NOI”) driving the issuance of 2021 All-Source Request for Proposals (“RFP”). b. The constraints of the transmission system external to the IPC service territory also referenced in the Company’s NOI. RESPONSE TO REQUEST NO. 18: The decision to update the L&R and associated capacity deficiency date filed in Case No. IPC-E-21-09 is ultimately a decision for the Commission to make in the case. Factors that influence the Company’s L&R are never static, which can bring about a certain “regulatory lag” in any price setting processes that rely on a prior Integrated Resource Plan (“IRP”) for inputs. Adjustments to correct for the impacts of any such lag effects in this case should be carefully considered to ensure that those adjustments result in fair prices for both third-party resource developers and the retail customers that pay the associated cost. a. Idaho Power’s current forecast of peak loads between 2021 and 2025 has not increased as compared to the peak load forecast used in the 2019 IRP. While it is true that load growth is contributing to the capacity deficiencies referenced in the NOI, the growth is not expected to occur at a higher level than forecast in the Company’s most recently acknowledged IRP. Because peak load growth is not a driver of the change in the deficiency dates between the 2019 IRP and IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 3 those mentioned in the NOI, it should not be considered as an L&R input to be updated in Case No. IPC-E-21-09. b. The Company acknowledges that there have been recent changes in the transmission markets reducing transmission capacity availability as compared to the 3rd party-transmission assumptions developed for the 2019 IRP. Specifically, other transmission provider’s systems are becoming more constrained, such that transmission capacity on their systems that may historically have been regularly available for purchase by the Company to import energy to serve load on a short-term basis is no longer available. The Company further acknowledges that those changes may warrant consideration in this case. However, the Company does not take a position in this response as to whether, or not, such changes should be reflected in the capacity deficiency date at issue in this case. The response to this Request is sponsored by Tim Tatum, Vice President of Regulatory Affairs, Idaho Power Company. IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 4 REQUEST NO. 19: Are there any recently signed transmission or firm energy contracts that are not included in the Company’s filed L&R or in the L&R provided in response to Staff Production Request No. 17? If so, please list and describe these contracts. Are these contracts incremental to the amount of Market Purchases in the L&Rs or are these contracts considered already included in Market Purchases? RESPONSE TO REQUEST NO. 19: There are no recently signed transmission or firm energy contracts that are not included in the response to Staff Production Request No. 17. The Market Purchases in the load and resource balance assume that all Idaho Power transmission from the northwest set aside for load service is available. Market Purchases already account for any potential transmission or energy contract additions from the northwest. Transmission to southern hubs was reduced to 50 MW to account for lack of available firm transmission on neighboring systems. There are no new signed transmission or firm energy contracts from the south. The response to this Request is sponsored by Jared Hansen, Resource Planning Leader, Idaho Power Company. IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 5 REQUEST NO. 20: Please identify the amount of peak capacity that the Company needs to acquire through the RFP broken down by the following: a. Load Growth b. Lack of external firm transmission capacity c. Early exit date of Valmy Unit #2 RESPONSE TO REQUEST NO. 20: The Company’s response to this request assumes Staff is referencing changes in the quantification of peak capacity needs that occurred between the development of the 2019 IRP and the issuance of the recent Notice of Intent (NOI), which may lead to a resource RFP for a new Idaho Power resource as early as 2023. Because several changes to inputs and methodology impacted the load and resource (L&R) balance analysis used to determine the peak capacity need referenced in the NOI, it is not possible to isolate the impact that each change had on peak capacity need in any given year. That said, the Company will focus the remainder of this response on the changes in the L&R balance inputs and methodology that may lead to the referenced resource RFP. In addition to reductions in 3rd party transmission capacity, the L&R balance used to inform the actions presented in the NOI also factored in a number of 2021 IRP methodology updates, including the Effective Load Carrying Capability of solar, wind, and demand response, as well as the 2021 IRP’s revised Loss of Load Expectation-derived planning margin. The following addresses factors a – c. However, a full reconciliation of the differences between the L&R balance used as the starting point for the 2019 IRP and IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 6 L&R balance used to inform the actions detailed in the NOI will be provided as a supplement to this request once the Company completes the reconciliation. a. Load Growth – The Company’s current load growth estimates are similar to the estimates from the 2019 IRP, and therefore did not materially contribute to changes in peak capacity need at issue in the NOI. Please refer to the Company’s response to Staff Request No. 25 for the most recent 50th percentile load forecast. b. Between the L&R balance for the 2019 IRP and L&R balance used to inform the actions detailed in the NOI, the assumption for external transmission from southern market hubs was reduced by 310 MW from 360 MW to 50 MW. c. The L&R balance used to inform the actions detailed in the NOI assumed Valmy Unit 2 will remain in service until the end of 2025 - the same assumption used for the L&R balance in the 2019 IRP. The response to this Request is sponsored by Jared Hansen, Resource Planning Leader, Idaho Power Company. IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 7 REQUEST NO. 21: Is the amount of peak capacity to be acquired through the RFP for purposes of resolving the lack of external firm transmission capacity incremental to the amount of Market Purchases in the L&R or is it considered already included in Market Purchases? RESPONSE TO REQUEST NO. 21: The Market Purchases in the Load and Resource Balance assumes the amount of transmission capacity to the Northwest set- aside on the Idaho Power system is fully available for use. Southern market transmission assumptions were reduced to 50 MW firm to account for lack of transmission availability. Idaho Power has an existing 50 MW transmission service reservation with PacifiCorp to the south. If market purchases can be acquired from the south, the market transmission assumption will increase. The response to this Request is sponsored by Jared Hansen, Resource Planning Leader, Idaho Power Company. IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 8 REQUEST NO. 22: Does the Company’s peak load forecast used in the Company’s filing and included in response to Staff Production Request Nos. 11 and 17 include the load growth referenced in the NOI? Please explain. RESPONSE TO REQUEST NO. 22: Yes. The load forecasts used in the application filing and included in the response to Staff Production Requests Nos. 11 and 17 include the load growth referenced in the NOI. Changes in load forecast are not the main driver of the NOI. The need for nearer term resources is driven by transmission availability on neighboring systems and adjustments to the Effective Load Carrying Capability (ELCC) of Demand Response, solar, and wind resources. The response to this Request is sponsored by Jared Hansen, Resource Planning Leader, Idaho Power Company. IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 9 REQUEST NO. 23: Please answer the following: a. Does the Company consider the fundamentals driving the load growth discussed in the NOI permanent or temporary? Please explain. b. Does the Company consider the fundamentals driving constraints in the transmission market as discussed in the NOI to be permanent or temporary? Please explain. c. Given the temporary or permanent nature of these two drivers, how would the existence of a new QF avoid capacity cost for the Company. RESPONSE TO REQUEST NO. 23: a. The load forecast used for the Notice of Intent is intended to represent permanent load additions. b. The Company expects third party transmission availability to remain tight for the foreseeable future until incremental transmission is added to the system. In response to the increased demand for transmission, Idaho Power is reserving transmission on neighboring systems to the Mid-C hub where available. c. The performance of the Qualifying Facility (“QF”) during critical peak hours would determine whether the QF could avoid capacity cost for the Company. Any resource that can provide capacity in the net-peak hours (late afternoon and early evening around the solar ramp) would be beneficial. The response to this Request is sponsored by Jared Hansen, Resource Planning Leader, Idaho Power Company. IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 10 Respectfully submitted this 25th day of June 2021. DONOVAN E. WALKER Attorney for Idaho Power Company IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF - 11 CERTIFICATE OF SERVICE I HEREBY CERTIFY that on this 25th day of June 2021, I served a true and correct copy of the within and foregoing IDAHO POWER COMPANY’S RESPONSE TO THE AMENDED THIRD PRODUCTION REQUESTS OF THE COMMISSION STAFF upon the following named parties by the method indicated below, and addressed to the following: Matt Hunter Deputy Attorney General Idaho Public Utilities Commission Po Box 83720 Boise, Idaho 83720-0074 Hand Delivered U.S. Mail Overnight Mail FAX X Email: matt.hunter@puc.idaho.gov ________________________________ Christy Davenport, Legal Assistant