IN THE MATTER OF THE APPLICATION OF
IDAHO POWER COMPANY FOR AUTHORITY
TO IMPLEMENT FIXED COST ADJUSTMENT
("FCA") RATES FOR ELECTRIC SERVICE
['ROM JUNE 1,2019, THROUGH MAY 31,2020.
Street Address for Express Mail:
472 W. WASHINGTON
BOISE, IDAHO 83702-5918
Attorney for the Commission Staff
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
CASE NO.IPC-E.T9.10
FIRST PRODUCTION
REQUEST OF THE
COMMISSION STAFF TO
IDAHO POWER COMPANY
The Staff of the Idaho Public Utilities Commission, by and through its attomey of record,
Edward Jewell, Deputy Attorney General, request that Idaho Power Company (Company) provide
the following documents and information as soon as possible, or by WEDNESDAY,
APRIL 24,2019.
This Production Request is continuing, and the Company is requested to provide, by way of
supplementary responses, additional documents that it or any person acting on its behalf may later
obtain that will augment the documents produced.
Please provide answers to each question, supporting workpapers that provide detail or are
the source of information used in calculations. The Company is reminded that responses pursuant
to Commission Rules of Procedure must include the name and phone number of the person
preparing the document, and the name, location and phone number of the record holder and if
different the witness who can sponsor the answer at hearing if need be. Reference IDAPA
31.01.01.228.
FIRST PRODUCTION REQUEST
TO IDAHO POWER
)
)
)
)
)
)
)
)
1 APRIL 3,2019
In addition to the written copies provided as response to the questions, please provide all
Excel and electronic files on CD with formulas activated.
REQUEST NO. 1: Please provide the monthly kWh sales forecast for the 2018-2019 FCA
year for the residential and small general service classes.
REQUEST NO. 2: Please provide the monthly kWh sales forecast for the 2019-2020FCA
year for the residential and small general service classes.
REQUEST NO.3: What level of incremental annual DSM energy efficiency savings did
Idaho Power achieve in 2018? Please break the savings into residential and small general service
components and provide relevant workpapers.
REQUEST NO. 4: For the residential and small general service classes, please provide
actual monthly energy usage from June 1,2017 through May 3 1, 201 8.
-)DATED at Boise, Idaho, this t day of Aprll2019
Deputy General
i:umisc:prodreq/ipce 19. I Oejbe prod reql
FIRST PRODUCTION REQUEST
TO IDAHO POWER 2 APRIL 3,2019
CERTIFICATE OF SERVICE
I HEREBY CERTIFY THAT I HAVE THIS 3'd DAY OF APRIL 2019,
SERVED THE FOREGOING FIRST PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER COMPANY,IN CASE NO. IPC-E-I9-10,
BY MAILING A COPY THEREOF, POSTAGE PREPAID, TO THE FOLLOWNG:
LISA D NORDSTROM
REGULATORY DOCKETS
IDAHO POWER COMPANY
PO BOX 70
BOrSE rD 83707-0070
E-mail : lnordstrom@idahopower. com
dockets@idahopower. com
CONNIE ASCHENBRENNER
IDAHO POWER COMPANY
PO BOX 70
BOISE rD 83707-0070
E-mail: caschenbrenner@idahopower.com
S
CERTIFICATE OF SERVICE