Re Case No. IPC-E-19-04
Wood Hydro LLC - Black Canyon #3 Hydro Project
ldaho Power Company's Response to the First Production Request of the
Commission Staff
Dear Ms. Hanian:
Enclosed for filing in the above matter please find an origina! and three (3) copies
of ldaho Power Company's Response to the First Production Request of the
Commission Staff.
Very truly yours,
Donovan E. Walker
DEW:csb
Enclosures
1221 W. ldaho 5t. (83702)
P.O. Box 70
Boise, lD 83707
t
DONOVAN E. WALKER (lSB No. 5921)
ldaho Power Company
1221\Nest ldaho Street (83702\
P.O. Box 70
Boise, ldaho 83707
Telephone: (208) 388-5317
Facsimile: (208) 388-6936
dwalker@id .com
Attorney for ldaho Power Company
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
APPLICATION OF IDAHO POWER
FOR CONSIDERATION OF AN ENERGY
SALES AGREEMENT WITH WOOD
HYDRO
CASE NO. rPC-E-19-04
IDAHO POWER COMPANY'S
RESPONSE TO THE FIRST
PRODUCTION REQUEST OF
THE COMMISSION STAFF
COMES NOW, ldaho Power Company ("ldaho Power"), and in response to the
First Production Request of the Commission Staff to Idaho Power Company dated
February 15,2019, herewith submits the following information:
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST
PRODUCTION REOUEST OF THE COMMISSION STAFF - 1
l:'i:fiililI* t]ii 3:li;
)
)
)
)
)
)
)
)
REQUEST NO. 1: Page 4 of the Application states "Wood Hydro plans to
continue operating and maintaining a 150 kilowatt ("kW') (Maximum Capacity Amount,
paragraph B-4, Appendix B) energy facility located near the city of Gooding, ldaho."
However, Appendix B states "The Maximum Capacity Amount is 130 kW...' Please
reconcile these two numbers.
RESPONSE TO REQUEST NO. 1: As stated in Appendix B of the Energy Sales
Agreement between ldaho Power and Wood Hydro LLC for the Black Canyon #3 hydro
project, the Nameplate Capacity and Maximum Capacity Amount of the facility is 130
kilowatts ('kW"). The reference to 150 kW on page 4 of the Application was a
typographical error.
The response to this Request is sponsored by Michael Darrington, Energy
Contracts Leader, ldaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST
PRODUCTION REQUEST OF THE COMMISSION STAFF - 2
REQUEST NO. 2: Page 4 of the Application states "The nameplate rating of this
Facility is 150 kW". However, Appendix B states "Nameplate: 130 kW". Please
reconcile these two numbers.
RESPONSE TO REQUEST NO. 2: Please see ldaho Power's response to
Staff's Request No. 1.
The response to this Request is sponsored by Michael Darrington, Energy
Contracts Leader, ldaho Power Company.
DATED at Boise, ldaho, this 28th day of February 2019.
OVAN E. WA
Attorney for ldaho Power Company
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST
PRODUCTION REQUEST OF THE COMMISSION STAFF - 3
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on this 28th day of February 2019 I served a true and
correct copy of IDAHO POWER COMPANY'S RESPONSE TO THE FIRST
PRODUCTION REQUEST OF THE COMMISSION STAFF upon the following named
parties by the method indicated below, and addressed to the following:
Gommission Staff
Edward Jewell
Deputy Attorney Genera!
ldaho Public Utilities Commission
47 2 W est Wash i ngton Street (83702)
P.O. Box 83720
Boise, ldaho 83720-007 4
X Hand Delivered
_U.S. Mail
_Overnight Mail
_FAXX Email edward.iewell@puc.idaho.sov
Wood Hydro LLC
Ted Sorenson
Wood Hydro LLC
1032 Grand View Drive
lvins, Utah 84738
_Hand Delivered
X U.S. Mail
_Overnight Mail
_FAXX Email ted@tsorenson.net
fry,Assistant
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST
PRODUCTION REQUEST OF THE COMMISSION STAFF - 4
n