HomeMy WebLinkAbout20180504Staff 1-15 to IDOA.pdfKARL T. KLEIN DEPUTY ATTORNEY GENERAL IDAHO PUBLIC UTILITIES COMMISSION PO BOX 83720 BOISE, IDAHO 83720-0074 (208) 334-0320 IDAHO BARNO.5156 IN THE MATTER OF THE PETITION OF THE ) IDAHO DEPARTMENT OF ADMINISTRATION ) FOR AN EXEMPTION FROM THE rDAHO ) PUBLIC UTILITIES COMMISSION'S MASTER. ) METERING RULES FOR ELECTRIC ) UTILITIES AND THE IDAHO POWER ) MASTER.METERING STANDARDS. ) CASE NO. IPC-E.18.08 FIRST PRODUCTION REQUEST OF'THE COMMISSION STAFF TO THE IDAHO DEPARTMENT OF ADMINISTRATION RECEIVED t[lt, tthT -h PH Z: 36 ,,,,,Ili#*?ntk"Bt'oH Street Address for Express Mail: 472W. WASHINGTON BOISE, IDAHO 83702-5918 Attorneys for the Commission Staff BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION The Staff of the Idaho Public Utilities Commission, requests that the Idaho Department of Administration (IDOA) provide the following documents and information as soon as possible, and no later than FRIDAY, MAY 18,2018.r Please provide answers to each question and supporting workpapers that detail, or are the source of information used in, any calculations. Besides the written copies provided as response to the questions, please provide all Excel and electronic files on CD with formulas activated. I Staff is requesting an expedited response. If responding by this date will be problematic, please call Staff s attorney at (208) 334-0320. FIRST PRODUCTION REQUEST TO THE IDAHO DEPARTMENT OF AMINISTRATION I MAY 4,2018 These production requests and interrogatories are continuing. IDOA is requested to provide, by way of supplementary responses, additional documents and information that it or any person acting on its behalf may later obtain that will augment the documents and information produced. In preparing your responses, please restate in full each question asked, then state in full your response to the question and the name and telephone number of the person(s) who prepared the response and would be able to answer questions about it or sponsor it at hearing if needed. See IDAPA 31.01.01.228. REQUEST NO. 1: Please provide a schematic drawing for the State of Idaho Chinden Office Complex (the "Campus") indicating the placement and item tag for each of the sub-meters planned to directly or indirectly track electrical energy use. REQUEST NO. 2: Please provide a table corresponding to the schematic drawing requested above, which lists the sub-meter by item tag, specified type, whether the sub-meter directly or indirectly measures electrical energy use, the data collected, and the corresponding units for the data collected (i.e. kW, kw-hr, BTU, degrees, gpm, etc.). REQUEST NO. 3: Please provide the specification or manufacturer cut sheet that details each type of sub-meter planned for use in the table requested above. REQUEST NO. 4: Please provide a detailed description of the methodology to allocate the Idaho Power Campus-wide billing to all the sub-entities (including leases). This description should provide enough detail so it describes the calculations from the data collected from all the sub-meters (identified by item tag) and how this data will be used to reconcile and allocate the different charges within the overall campus-wide bill (i.e. customer, demand, energy) to all the sub-entities. REQUEST NO. 5: Please provide the plan for tenant notification and estimated outage impacts as construction and the sub-meter installation is performed. FIRST PRODUCTION REQUEST TO THE IDAHO DEPARTMENT OF AMINISTRATION 2 MAY 4,2018 REQUEST NO. 6: Please provide the short and long-term plans for energy system operation and maintenance at the Campus. REQUEST NO. 7: With respect to the Campus, will electricity costs be a separately identified component on each bill provided to non-state tenants? Will electricity costs be a separately identified component on the bill provided to state agencies? Please provide a sample bill for tenants at the Campus. REQUEST NO. 8: With respect to the Campus, has the IDOA entered into an Energy Savings Performance Contract(s) as described in Idaho Code $ 67 -57 | 1D? If so, please provide copies of any contract. If not, does IDOA intend to enter into any such contract? Please explain. REQUEST NO. 9: In its preparation for state office occupancy in Building 2,has IDOA installed, or does it intend to install, any energy efficiency measures in the near future? Please explain. REQUEST NO. 10: Staff understands the Campus is served by Idaho Power, who supplies primary service under Rate Schedule 19. Rate Schedule 19 has several components: service charge, basic charge, demand charge (varies by season), on-peak demand charge, and energy charges for on-peak, mid-peak and off-peak usage (varies by season). Staff also understands that HP Inc.'s lease provides that IDOA only will bill HP Inc. for HP Inc.'s actual costs. How will total costs of electricity be recovered for HP Inc.? REQUEST NO. 11: Please provide the energy sources for the Campus boilers REQUEST NO. 12: Building 8 is separately metered, but it appears that Building 8 does not pay its own electrical costs under its lease. How is that cost recovered? Please explain in detail. FIRST PRODUCTION REQUEST TO THE IDAHO DEPARTMENT OF AMINISTRATION aJ MAY 4,20T8 REQUEST NO. 13: On page 11 of its petition, IDOA states: "Initial estimates for equivalent separate metering range from two to three million dollars. These costs will either require appropriation of taxpayer funds by the 2019 Idaho Legislature or will be paid in part by electric ratepayers through Commission approved processes." a. Please provide a copy of the cost estimate for separate metering, showing how that estimate was determined b. Please explain why IDOA believes that electric ratepayers might have to pay for metering costs incurred by IDOA. REQUEST NO. 14 Staff understands that IDOA requested Idaho Power to prepare an estimate of costs to operate and maintain electrical facilities for the Campus. Has Idaho Power submitted its estimate to IDOA? If so, please provide a copy of that estimate. If IDOA intends to use another entity to operate and maintain the electrical facilities, please include that estimate of costs. REQUEST NO. 15: Please provide the Site Power Distribution document included in the Petition, in electronic format. DATED at Boise, Idaho, this q$ day of May 2018 allN Karl T. Klein Deputy Attorney General Technical Staff: Rick Keller (l-4, l5) Rachelle Farnsworth (5 -6) Beverly Barker (7-14) umisc:prodreq/ipcel8.Skkrkrfbb prod req I FIRST PRODUCTION REQUEST TO THE IDAHO DEPARTMENT OF AMINISTRATION 4 MAY 4,2078 CERTIFICATE OF SERVICE I HEREBY CERTIFY THAT I HAVE THIS 4th DAY OF MAY 2018, SERVED THE FOREGOTNG FIRST PRODUCTION REQUEST OF THE COMISSION STAFF TO THE IDAHO DEPARTMENT OF ADMINISTRATION, IN CASE NO. IPC-E-18-08, BY MAILING A COPY THEREOF, POSTAGE PREPAID, TO THE FOLLOWING: JULIE K WEAVER DEPUTY ATTORNEY GENERAL DEPT OF ADMISTRATION PO BOX 83720 BOrSE rD 83720-00r0 CONNIE ASCHENBRENNER IDAHO POWER COMPANY PO BOX 70 BOrSE ID 83707-0070 E-mail : caschenbrenner@idahopower. com LISA D NORDSTROM REGULATORY DOCKETS IDAHO POWER COMPANY PO BOX 70 BOISE ID 83707-0070 E-mail : lnordstrom@idahopower. com dockets@idahopower.com SECRE Y CERTIFICATE OF SERVICE