IN THE MATTER OF THE ANNUAL
COMPLIANCE FILING OF IDAHO POWER
COMPANY TO UPDATE THE LOAD AND GAS
F'ORECASTS IN THE INCREMENTAL COST
INTEGRATED RESOURCE PLAN AVOIDED
COST MODEL.
RECEIVED
?011H0\t - I Plt 2: 05
u,j'*Ht*J#',?fiEt'o*
Street Address for Express Mail
472 W. WASHINGTON
BOISE, IDAHO 83702-5918
Attorney for the Commission Staff
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
)
)
)
)
)
)
)
)
CASE NO. IPC.E.I7.Is
FIRST PRODUCTION
REQUEST OF THE
COMMISSION STAFF TO
IDAHO POWER COMPANY
The Staff of the Idaho Public Utilities Commission, by and through its attorney of record,
Camille Christen, Deputy Attorney General, request that Idaho Power Company (Idaho Power or
Company) provide the following documents and information as soon as possible, by
WEDNESDAY, NOVEMBER 22, 2017.
This Production Request is continuing, and Idaho Power is requested to provide, by way
of supplementary responses, additional documents that it or any person acting on its behalf may
later obtain that will augment the documents produced.
Please provide answers to each question and supporting workpapers that provide detail or
are the source of information used in calculations. Idaho Power is reminded that responses
pursuant to Commission Rules of Procedure must include the name and phone number of the
person preparing the document, and the name, location and phone number of the record holder
and if different the witness who can sponsor the answer at hearing if need be. IDAPA
3r.01.01.228.
FIRST PRODUCTION REQUEST
TO IDAHO POWER COMPANY 1 NOVEMER I,2017
In addition to the written copies provided as response to the questions, please provide all
Excel and electronic f,rles on CD with formulas activated.
REQUEST NO. 1: Please explain why Idaho Power changed the natural gas price
forecast from the U.S. EIA Reference Case Forecast for Natural Gas Henry Hub Spot Price used
in Case No. IPC-E-16-22 to the U.S. EIA's Natural Gas Henry Hub Spot Price: High Oil and Gas
Resource and Technology forecast, adjusted for pricing at Sumas and transport for Idaho City
Gate delivery used in this filing.
REQUEST NO. 2: Please explain why Idaho Power chose the U.S. EIA's Natural Gas
Henry Hub Spot Price: High Oil and Gas Resource and Technology forecast and why it believes
that forecast is more accurate than other natural gas forecasts provided by EIA.
,51
Dated at Boise, Idaho, this , day of November 2017.
Cdil^ l),",t.,.,--
Camille Christen
Deputy Attorney General
Technical Staff: Y ao Yin/ I -2
i:umisc:prodreq/ipcel7.l 5ccyy prod reql
FIRST PRODUCTION REQUEST
TO IDAHO POWER COMPANY 2 NOVEMER I,2017
CERTIFICATE OF SERVICE
I HEREBY CERTIFY THAT I HAVE THIS 1ST DAY OF NOVEMBER 2017,
SERVED THE FOREGOING FIRST PRODUCTION REQUEST OF THE
coMMrssroN STAFF To rDAHO POWER COMPANY, IN CASE NO. IPC-E-17-I5,
BY MAILING A COPY THEREOF, POSTAGE PREPAID, TO THE FOLLOWING:
DONOVAN E WALKER
REGULATORY DOCKETS
IDAHO POWER COMPANY
PO BOX 70
BOrSE rD 83707-0070
E-mail : dwalker@idahopower.com
dockets@ idahopower. com
SECRETAR
CERTIFICATE OF SERVICE