(2003 through 2021)
Final HCC License Application
Submitted to the FERC
Mon 7/21/03
FERC Issues Notice of
Acceptance of HCC Final
License Application
Wed 12/3/03
IPC and USFWS InitiateFederalAgenciesFileMandatory
Conditions with the FERC
Thu 1/26/06
Informal Development of
Biological Assessment
Mon 2/2/09
Oregon Environmental Quality
Commission Orders ODEQ to
Review Temperature Change
Fri 3/4/11
IPC Submits Revised Site
Specific Standard Change
Mon 5/1/06
Settlement of 1997
Environmental Group
vs FERC ESA Suit Agreement
Wed 12/1/04
Idaho Legislature Approved
Site Specific Standard Change
Thu 3/29/12
USFWS Modifies
Fishway Prescription
Wed 1/3/07 Estimated Date of
Second Hells Canyon
License Issuance
Thu 1/2/21
Idaho State Submits Site
Specific Temperature Change
to EPA
Wed 6/6/12
FERC Notices HCC
License Ready for
Environmental Review
Mon 10/3/05
•••
I I I I I I I I I i r i i i
2003 2004 2005 2006
Site Specific Temperature
Standard Change Submitted
to DEQs
Thu 12/8/05
Original HCC
License Expired
Fri 7/1/05
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2021
FERC Staff Issues
Final Environmental
Impact Statement
Fri 8/31/07
Idaho Board of
Environmental Quality
Approved Temperature
Criteria Change
Thu 11/10/11
IPC Files Current
HCC 401 Application
Fri 7/29/16
FERC Staff Issues
Draft Environmental
Impact Statement
Fri 7/28/06
Comprehensive Settlement
Discussions Discontinued
Mon 6/3/13
FERC Requests Additional
Information Requests
Wed 5/5/04
Baker County
Settlement Signed
Wed 10/1/03
IPC Files Alternative
Prescription Under
Section 241 EPAct
Tue 2/28/06