HomeMy WebLinkAbout20170303IPC to Tidwell Attachment 20.8.pdfPOWER(
An idacorp Company
9/6/201 1
Project ID:T4331101
27340452:T433 KING-WOOD RIVER 138,correct priority
2 DEFECTS.
Location:Ketchum area,between Wood River and Ketchum Substations
Designer:Bill Finlay
Est.Man-Hours:
Required In Service Date:10/27/2011
Scope of Work:
Perform maintenance work on Line 433 consisting of 1 structure replacement (Str 18),6 cross
arm replacements,including 1 truss (Str.526,546 548 549,565,572),4 cross arm repairs (Str.
517,521,537,563),and bell replacements at 3 structures (Str.492,493,494).Some work will
be performed with the line hot and some during a short outage (6 hrs)
Vehicle access is limited to structures and some may require climbing
C Extra bells,shoes,and armor rod have been provided.Replace any additional defects found
while performing the primary maintenance.
Coordination of Work:
Outages:T433 is schedule for a short outage.
Permits:Acquire permits for work done in road right of way.
Locates:The contractor or crew is responsible for notifying digline and acquiring all necessary
locations prior to commencing work.
Contacts:
Project Leader -388-5667
Project Engineer-388-2756
Grid Operator -388-2861
Tom Barber
Bill Finlay
Tim Trimmel
c