HomeMy WebLinkAbout20141121IPC to Staff 1-2.pdfSEffi*. An IDACORP Companv November 21,2014 VIA HAND DELIVERY Jean D. Jewell, Secretary ldaho Public Utilities Commission 472 West Washington Street Boise, ldaho 83702 Re: Case No. IPC-E-14-36 Orchard Ranch Solar, LLC - ldaho Power Company's Response to the First Production Request of the Commission Staff Dear Ms. Jewell: Enclosed for filing in the above matter are an original and three (3) copies of ldaho Power Company's Response to the First Production Request of the Commission Staff. An external hard drive containing the requested files is provided. The files provided on the externa! hard drive are confidential and should be handled in accordance with the Protective Agreement in this matter. DONOVAN E. WALKER Lead Counsel DEW:csb Enclosures /,U^--= 1221 W. ldaho St. (83702) PO. Box 70 Boise, lD 83707 DONOVAN E. WALKER (!SB No. 5921 1 [i U {] r l"/i:: I ldaho Power Company 1221West Idaho Stre6t @9702) ?flilr hi0Y 2 I PFI 3: 0l P.O. Box 70 ,,-,., ,. Boise, ldaho 83707 ,.lrirlr\ill,d-:,-,;i,:,,,1.,,,;,.-,,, Telephone: (208) 388-5317 Facsimile: (208) 388-6936 dwalker@idahopower. com Attorney for ldaho Power Company BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION rN THE MATTER OF THE APPLTCATTON ) oF |DAHO POWER COMPANY FOR ) CASE NO. IPC-E-14-36 APPROVAL OR REJECTTON OF AN ) ENERGY SALES AGREEMENT WITH ) IDAHO POWER COMPANY'S ORCHARD RANCH SOLAR, LLC FOR THE ) RESPONSE TO THE FIRST SALE AND PURCHASE OF ELECTRIC ) PRODUCTTON REQUEST OF THE ENERGY.) coMMrssroN STAFF To IDAHO ) POWER COMPANY ) COMES NOW, ldaho Power Company ("ldaho Powe/'), and in response to the First Production Request of the Commission Staff to ldaho Power Company dated November 3, 2014, and as revised on November 20, 2014, herewith submits the following information: IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 1 REQUEST NO. 1: Please provide copies of all AURORA input and output files used to generate the 'SOLAR FACILITY ENERGY PRICES' in Appendix E. Please provide prices (and corresponding input and output files) generated based on all displaced resources and monthly naturalgas priceg consisfenf with the Commission's findings and conclusrbns in Order Nos. 33779 and 33180. Please provide the files electronically with all formulas intact. RESPONSE TO REQUEST NO. 1: Please see the confidential directory titled "CONFIDENTIAL-AURORA Files" on the extemal hard drive provided. Because of the very Iarge size of the requested files, they are being provided to Staff on the accompanying external hard drive. The files and data contain dispatch costs of ldaho Power resources, which is non-public, confidential, and proprietary information and should be handled in accordance with the Protective Agreement. The extema! hard drive and file directory are marked "CONFIDENTIAL." However, to maintain the integrity of the files, the files themselves are not further marked or identified as confidential. The response to this Request is sponsored by Ji!! Glenn, Senior Energy Contracts Coordinator, ldaho Power Company. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 2 REQUEST NO. 2: Please provide copies of all Exce! files used to generate the 'SOLAR FACILIry ENERGY PRICES' in Appendix E. Please provide prices (and corresponding input and output files) generated based on all displaced resources and monthly natural gas prices, consisfenf with the Commission's findings and conclusions in Order Nos. 33/79 and 33180. Please provide the files electronically with all formulas intact. RESPONSE TO REQUEST NO. 2: Please see the confidential directory titled 'CONFIDENTIAL-IPC-E-14-36-Orchard Ranch Solar-Response 2" on the extemal hard drive provided. Because of the very large size of the requested files, they are being provided to Staff on the accompanying external hard drive. The files and data contain dispatch costs of ldaho Power resources, which is non-public, confidential, and proprietary information and should be handled in accordance with the Protective Agreement. The externa! hard drive and file directory are marked "CONFIDENTIAL.' However, to maintain the integrity of the files, the files themselves are not further marked or identified as confidential. The response to this Request is sponsored by Jil! Glenn, Senior Energy DONOVAN E. WALKER Attorney for Idaho Power Company IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 3 Contracts Coordinator, Idaho Power Company. DATED at Boise, ldaho, this 21"t day of November 2014. ,')U-4Zu CERTIFICATE OF SERVICE I HEREBY CERTIFY that on this 21st day of November 2014 ! served a true and correct copy of IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY upon the following named parties by the method indicated below, and addressed to the following: Commission Staff Kristine A. Sasser Deputy Attomey General ldaho Public Utilities Commission 47 2 W est Washington (83702) P.O. Box 83720 Boise, ldaho 83720-007 4 Orchard Ranch Solar, LLG Ron Williams Williams Bradbury, P.C 1015 West Hays Street Boise, ldaho 83702 Ben Fairbanks Director, Development First Wind Hand Delivered U.S. Mail Ovemight Mail FAXX Email kris.sasser@puc.idaho.qov Hand Delivered U.S. Mail Overnight Mail FAXX Email ron@williamsbradbury.com Hand Delivered U.S. Mai! Overnight Mail FAXX Email bfairbanks@firstwind.com t IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 4 Christa Bearry, Lega