Loading...
HomeMy WebLinkAbout20141211IPC to Staff 5.pdf7!lDryp NIPO1TER An IDACORP Company 20lir DtC I : l.l/ l, i .. lJ llLlli:i I PH 3122 DONOVAN E. WALKER Lead Counsel dwalker@idahopower.com December 11,2014 VIA HAND DELIVERY tJean D. Jewell, Secretary ldaho Public Utilities Commission 472 West Washington Street Boise, ldaho 83702 Re: Case No. IPC-E-14-33 Simco Solar, LLC - ldaho Power Company's Response to the Third Production Request of the Commission Staff Dear Ms. Jewell: Enclosed for filing in the above matter are an original and three (3) copies of ldaho Power Company's Response to the Third Production Request of the Commission Staff. An external hard drive containing the requested files is provided. The files provided on the extemal hard drive are confidential and should be handled in accordance with the Protective Agreement in this matter. DEW:csb Enclosures 1221 W. ldaho St. (83702) PO. Box 70 Boise, lD 83707 hovan E. Walker DONOVAN E. WALKER (lSB No. 5921) ldaho Power Company 1221West ldaho Street (83702) P.O. Box 70 Boise, ldaho 83707 Telephone: (208) 388-5317 Facsimile: (208) 388-6936 dwalker@idahopower.com Attorney for ldaho Power Company IN THE MATTER OF THE APPLICATION OF IDAHO POWER COMPANY FOR APPROVAL OR REJECTION OF AN ENERGY SALES AGREEMENT WITH SIMCO SOLAR, LLC FOR THE SALE AND PURCHASE OF ELECTRIC ENERGY. iii:cFi"i"i, I0ll0[C I I pH 3: 23 t iirl,, :,; ,t ,- ,.... , ._. l-iT ll i'f ilS i,'i' ^, i, i ir..S ji_;, BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. !PC-E-14-33 IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY COMES NOW, ldaho Power Company ("ldaho Powe/'), and in response to the Third Production Request of the Commission Staff to ldaho Power Company dated December 10,2014, herewith submits the following information: IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE COMM]SSION STAFF TO IDAHO POWER COMPANY - 1 REQUEST NO. 5: Please re-calculate the rates for the project by using in AURORA the exact generation quantities and hourly and monthly shapes as are represented in Appendix I of the Agreement. Please compare the resulting rates to those contained in Replacement Appendix E included as Attachment 1 to ldaho Poweds lnitial Comments. Please compare the 20-year levelized rates under both scenarios and calculate the difference in the total 2O-year contractual obligation. With your answer, please provide copies of all AURORA and Excel files used for the analysis. RESPONSE TO REQUEST NO. 5: ldaho Power already uses the exact generation quantities and hourly and monthly shapes as contained within Appendix I in the incremental cost lntegrated Resource Plan ("lRP") model in the incremental pricing tool. One input into the AURORA model that is required to establish the hourly generation resource stack of existing resources (not including the proposed qualifying facility ("QF') project) is the estimated hourly generation from all availabb resources that exist prior to the addition of the proposed QF project. In many cases, ldaho Power does not have specific hourly energy estimates from the various QF projects; instead, ldaho Power only has monthly energy estimates. Therefore, to create an hourly energy shape of these QF resources, ldaho Power shapes the monthly energy estimates by using generic information related to the resource types. ln the case of solar projects, this hourly shaping has been based upon industry and local information with regards to solar radiation and the expected energy deliveries from generic solar projects. Because some solar projects are now providing hourly energy estimates, a potential enhancement to the incremental cost IRP model will be to include the project specific hourly energy estimates (when available) in the cumulative solar hourly energy shapes IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 2 that are used in establishing the hourly generation resource stack. ldaho Power has included the applicable information for the revised incremental cost IRP model runs with this response. A comparison of the 2O-year levelized rates under both scenarios is listed below. 20-year Levelized Rates lst Production 3rd Production Below is the difference in the total 2O-year contractual obligation. Z$-year Gontractual Obl i gation-l ncl ud i ng ! nte g ration lst Production 3rd ProductionRequest Request u[Terence $68,083,588 $67,594,1 10 ($489,478) Please see the directory titled "lPC-E-14-33,34 !PUC Staffs Third Production Request" and the confidential subdirectory titled "CONFIDENTIAL-IPC-E-14-33-Simco Solar-IPUC 3rd PROD Request-Response 5" on the external hard drive for the Excel files used for the analysis. In addition, please see the directory titled "|PC-E-14-33,34 IPUC Staffs Third Production Request" and the confidential subdirectory titled 'CONFIDENTIAL-IPC-E-14-33,34-AUROM Change Set-IPUC 3rd PROD Request- Response 5" for the AUROM files. The files and data contain non-public, confidential, and proprietary dispatch costs or project generation of ldaho Power resources and should be handled in accordance with the Protective Agreement. The extemal hard drive and file subdirectories are marked 'CONFIDENTIAL." However, to maintain the integrity of the files, the files themselves are not further marked or identified as confidential. IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 3 Simco Solar Simco Solar Request $64.31 Request $63.94 Difference ($o'ez1 The response to this Request is sponsored by Randy C. Allphin, Energy Contracts Coordinator Leader, Idaho Power Company. DATED at Boise, ldaho, this 11h day of DeEe(mber 2014. DONOVAN E. WALKER Attomey for ldaho Power Company IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION REOUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 4 CERTIFICATE OF SERVICE I HEREBY CERTIFY that on this 11h day of December 2014 I served a true and conect copy of IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY upon the following named parties by the method indicated below, and addressed to the following: Commission Staff Kristine A. Sasser Deputy Attomey General Idaho Public Utilities Commission 472 West Washington (83702) P.O. Box 83720 Boise, ldaho 83720-007 4 Simco Solar, LLC Ron Williams Williams Bradbury, P.G 1015 West Hays Street Boise, ldaho 83702 Ben Fairbanks Director, Development First Wind Hand Delivered U.S. Mall Overnight Mail FAXX Email kris.sasser@puc.idaho.oov _Hand Delivered U.S. Mail Overnight Mail FAXX Emai! ron@williamsbradbury.com Hand Delivered U.S. Mail Ovemight Mail FAXX Email bfairbanks@firstwind.com IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 5 Christa Bearry, Legal