HomeMy WebLinkAbout20140813IPC to Staff 1-4.pdfli.HCi:-trii' i'
?0lh AUS l3 PH 3: 53
uTilr?#b',ibuu,;is*'u"
3E'ffi*.
An IDACORP Company
DONOVAN E. WALKER
Lead Counsel
dwalker@idahopower.com
August 13,2014
VIA HAND DELIVERY
Jean D. Jewell, Secretary
!daho Public Utilities Commission
472 West Washington Street
Boise, ldaho 83702
Re: Case No. IPC-E-13-22
Update to Wind lntegration Rates and Charges - ldaho Power Company's
Response to the First Production Request of the Commission Staff to ldaho
Power Company
Dear Ms. Jewell:
Enclosed for filing in the above matter are an original and three (3) copies of ldaho
Power Company's Response to the First Production Request of the Commission Staff to
Idaho Power Company.
Also enclosed are four (4) copies of a non-confidential disk containing information
responsive to Staffs production requests.
DEW:csb
Enclosures
1221 W. ldaho St. (83702)
P.O. Box 70
Boise, lD 83707
DONOVAN E. WALKER (lSB No. 5921)
JULIA A. HILTON (lSB No. 7740)
ldaho Power Company
1221 West ldaho Street (83702)
P.O. Box 70
Boise, ldaho 83707
Telephone: (208) 388-5317
Facsimile: (208) 388-6936
dwalker@idahopower.com
ih i lton@idahopower. com
Attorneys for Idaho Power Company
IN THE MATTER OF IDAHO POWER
COMPANY'S APPLICATION TO UPDATE
ITS WIND INTEGRATION RATES AND
CHARGES.
Rf CilVi:l
201!i AUG I 3 PH 3; 53
lDAi';i) ;' .i,,r .
tJT I L l"f l [: S C Ot,{ i-'l tli$ lLiir
CASE NO. IPC.E.13-22
IDAHO POWER COMPANY'S
RESPONSE TO THE FIRST
PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO
POWER COMPANY
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
COMES NOW, ldaho Power Company ("ldaho Powe/' or "Company"), and in
response to the First Production Request of the Commission Staff to ldaho Power
Company dated July 24,2014, herewith submits the following information:
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 1
REQUEST NO. 1: Please provide a copy of the spreadsheet used to derive the
levelized and non-levelized wind integration charges shown on the proposed Schedule
87. Please state the escalation rate used to derive the non-levelized rates and discuss
why that rate was chosen. Please also state the discount rates used in the calculations
and discuss why that rate was chosen.
RESPONSE TO REQUEST NO. 1: Please see the attached Excel file used to
derive the levelized and non-levelized wind integration charges shown on the proposed
Schedule 87. The escalation rate used to derive the non-levelized rates is 3.0 percent
and the discount rate used in the calculation of the 2O-year contract term levelized rates
is 6.7 percent. Both of these rates were chosen because they were the percentage
rates used in the 2013 lntegrated Resource Plan ('lRP"). They can be found in the
Financial Assumptions and Factors section on page 83 of the 2013 !RP, Appendix C:
Technical Report.
The response to this Request is sponsored by Michael Youngblood, Manager of
Regulatory Projects, ldaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 2
REQUEST NO. 2: ldaho Power discusses in its Reply Comments its decision to
base its analysis of integration costs on day-ahead rather than hour-ahead forecasts.
Does ldaho Power believe there could be integration costs associated with both hour-
ahead and day-ahead forecasting errors? Does Idaho Power believe the method it
used in its 2013 Wind lntegration Study captures integration costs associated with hour-
ahead forecasting enors?
RESPONSE TO REQUEST NO. 2: For the 2013 Wind lntegration Study, the
capacity held in reserve on dispatchable generators was based on an analysis of day-
ahead forecast errors. lt is the Company's view that having the capacity held in reserve
on dispatchable generators for responding to day-ahead forecast errors also positions
these generators to respond to smaller hour-ahead forecast errors. Thus, it is unlikely
that there is significant additional integration costs associated with hour-ahead forecast
errors.
The response to this Request is sponsored by Phil DeVol, Resource Planning
Leader, ldaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 3
REQUEST NO. 3: On page 9 of AWEA and Renewable Northwest's comments
it states "As the wind comes up, a utility will back off more expensive generation
previously made available in the day-ahead time frame to meet load, which saves the
utility operating costs. As the wind drops off, a utility will increase the use of its more
expensive generation, hour-by-hour, adjusting for the wind's output and mindful to not
use any more higher-cost generation than necessary." lf both the utility's day-ahead
and hour-ahead wind forecasts were perfectly accurate, but the utility still had to back
down more expensive generation resources in order to receive wind generation (or
alternatively, less expensive resources), would ldaho Power consider these to be
integration costs? How would these costs be captured by the utility if they are not
considered integration costs? Does ldaho Power believe these costs would be
captured by a wind integration study performed using ldaho Power's method or the
method recommended by AWEA and Renewable Northwest? Does ldaho Power
believe these costs are captured in either the SAR or IRP methodologies employed by
the Commission for calculating avoided cost rates?
RESPONSE TO REQUEST NO. 3: The quoted language from American Wind
Energy Association ("AWEA") and Renewable Northwest starts with an assumption that
the utility backs off and increases more expensive generation to adjust for wind output.
!n reality, because of the Public Utility Regulatory Policies Act of 1978 obligation to
purchase at avoided cost rates and the operation of ldaho Power's hydro system and
other load following generation, it is often a lower cost resource that may be backed off
or ramped up to integrate wind. The Request asks about the difference between
resource integration costs and avoided costs. Avoided costs for a wind project
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY.4
exceeding 100 kilowatts are calculated by ldaho Power using the IRP methodology.
The IRP methodology does simulate "backing down" existing resources to incorporate
must-take resources such as wind. These costs of replacing the more expensive
generation resource (or alternatively, a less expensive resource) are included in the
avoided-cost analysis. Short-term re-dispatch costs and regulation costs, including the
costs of "backing down" existing resources to incorporate must-take resources such as
wind, necessary to accommodate short-term deviations from scheduled energy
deliveries and natura! variations in wind are calculated in integration studies such as this
proceeding on wind integration.
The Request contains an important qualifying statement, "lf both the utility's day-
ahead and hour-ahead wind forecasts were perfectly accurate." ln the case of a
perfectly accurate day-ahead and hour-ahead wind forecast, there are no hour-by-hour
wind integration costs due to forecast error (please note that the assumption is that
"perfectly accurate" means that the day-ahead forecast exactly matches the hour-ahead
forecast and both the day-ahead and hour-ahead forecasts exactly match the actual
hour-by-hour wind energy delivery). However, forecast error is only one component of
wind integration.
The natural variability of wind is also a component of wind integration. There is a
significant difference between a constant wind energy delivery of 400 megawatts
("MW') throughout an hour and wind energy delivery that ranges between 600 MW and
200 MW but delivers an average of 400 MW over the period of an hour. ldaho Power's
wind integration study also includes regulation costs based on the quantity of wind
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 5
energy forecast to be delivered in the hour and the natural variation of wind within the
hour associated with the forecasted quantity of delivered wind energy.
ldaho Power's avoided cost analysis is intended to quantify the resource-
planning cost of dispatch. ldaho Power's wind integration analysis is intended to
quantify short-term costs of re-dispatch. AWEA and Renewable Northwest have not
provided specific detail to enable ldaho Power to comment on re-dispatch costs
calculations contained in an AWEA and Renewable Northwest proposa!.
ln summary, even with a perfectly accurate hourly wind forecast, there will still be
integration costs due to the natural variability of wind within an hour. ldaho Power has
accounted for the natural variability of wind within an hour in the wind integration
analysis.
The response to this Request is sponsored by Thomas A. Noll, Senior Planning
Analyst, ldaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION
REOUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 6
REQUEST NO. 4: Under the proposal described in Idaho Powe/s Reply
Comments, how would wind integration charges be assigned in instances in which the
proposed project's capacity straddled a penetration level in the tariff? For example,
what would be the integration charge for a proposed 40 MW project if the cunent wind
penetration level on ldaho Powe/s system is 678 MW? Would the project be assigned
the integration charge for the 601-700 penetration level, the 701-800 level, or a prorated
amount?
RESPONSE TO REQUEST NO. 4: The Company proposes a prorated wind
integration charge be assigned in instances in which the proposed project's capacity
straddles a penetration level in the tariff. For clarification, using the suggested example
of a proposed 40 MW project seeking a contract with a contract on-line year of 2014,
when the current wind penetration level on ldaho Powe/s system is 678 MW, the
proposed wind integration charge would be a prorated amounl of 22 MW charged at the
601-700 MW penetration level rate and 18 MW charged at the 701-800 MW penetration
level rate. The resulting 20-year contract term levelized wind integration charge with an
on-line year of 2014 would be $17.15 per MW. The attached Excel file provides the
proposed wind integration charges for the project in this example.
The response to this Request is sponsored by Michael Youngblood, Manager of
Regulatory Projects, ldaho Power Company.
DATED at Boise, ldaho, this'l3h day of August 2014.
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 7
DONOVAN E. W
Attomey for ldaho Power Company
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on the 13th day of August 2014 t served a true and
correct copy of IDAHO POWER COMPANY'S RESPONSE TO THE FIRST
PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER
COMPANY upon the following named parties by the method indicated below, and
addressed to the following:
Commission Staff
Kristine A. Sasser
Deputy Attomey General
ldaho Public Utilities Commission
472 W est Washington (83702)
P.O. Box 83720
Boise, ldaho 83720-007 4
ldaho Winds LLG
Dean J. Miller
McDEVITT & MILLER LLP
420 West Bannock Street (83702)
P.O. Box 2564
Boise, ldaho 83701
Rick Koebbe, President
ldaho Winds LLC
5420 West Wicher Road
Glenns Ferry, ldaho 83623
Bob Eggers, Legal Counsel
ldaho Winds, LLC
15850 Jess Ranch Road
Tracy, California 95377
Cold Springs Windfarm, LLC; Desert
Meadow Windfarm, LLG; Hammett Hill
Windfarm, LLG; Mainline Windfarm, LLC;
Ryegrass Windfarm, LLG; and Two Ponds
Windfarm, LLC
Peter J. Richardson
RICHARDSON ADAMS, PLLC
515 North 27th Street
Boise, ldaho 83702
Hand Delivered
U.S. Mail
Overnight Mail
FAXX Email kris.sasser@puc.idaho.gov
Hand Delivered
U.S. Mail
Overnight Mail
FAX
Email ioe@mcdevitt-miller.com
Hand Delivered
U.S. Mail
Overnight Mail
FAXX Email rk@powenruorks.com
_Hand Delivered_U.S. Mail
Overnight Mail
FAXX Email re@powenruorks.com
_Hand Delivered
U.S. Mail
Overnight Mail
FAXX Email peter@richardsonadams.com
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 8
Benjamin G. Huang, Manager
c/o Mountain Air Projects
6000 North FoxtailWay
Glenns Ferry, ldaho 83623
Cassia Wind Farm LLC; Hot Springs
Windfarm, LLG; Bennett Creek Windfarm,
LLC; Cassia Gulch Wind Park LLC; Tuana
Springs Energy, LLC; and High Mesa
Energy, LLC
Gregory M. Adams
RICHARDSON ADAMS, PLLC
515 North 27th Street
Boise, ldaho 83702
PaulAckerman
Assistant General Counsel
Exelon Business Services Corporation
100 Constellation Way
Baltimore, Maryland 21202
American Wind Energy Association and
Renewable Northwest Project
Teresa A. Hill
K&L GATES, LLP
One S.W. Columbia Street, Suite 1900
Portland, Oregon 97258
Dina M. Dubson
Renewable Northwest Project
421 SW 6s Avenue, Suite 1125
Portland, Oregon 97204
Hand Delivered
U.S. Mail
Overnight Mail
FAX
Email bhuanq@terna-enerqv.com
Hand Delivered
U.S. Mail
Overnight Mail
FAXX Emai! qreq@richardsonadams.com
Hand Delivered
U.S. Mail
,Overnight Mai!
FAXX Email paul.ackerman@constellation.com
Hand Delivered
U.S. Mail
,Overnight Mail
FAX
Email teresa. hill@kloates.com
Hand Delivered
U.S. Mail
FAX
Overnight Mail
X Email dina@rnp.orq
IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY.9
Christa Bearry, Legal Assistant