Loading...
HomeMy WebLinkAbout20130806IPC to Staff 1-10.pdfSIffi*. An IDACORP Company ?t!l:l A[J{} -t Pi'l ti: trS ri., !r',1i t-r-,, r : i .t i LISA D. NORDSTROM Lead Counsel lnordstrom@idahopower.com August 6,2013 VIA HAND DELIVERY Jean D. Jewell, Secretary ldaho Public Utilities Commission 472 West Washington Street Boise, ldaho 83702 Re: Case No. IPC-E-13-16 Bridger CPCN - ldaho Power Company's Response to the First Production Request of the Commission Staff Dear Ms. Jewell: Enclosed for filing in the above matter are an original and three (3) copies of ldaho Power Company's Response to the First Production Request of the Commission Staff to ldaho Power Company. ln addition enclosed are an original and three (3) copies of ldaho Power Company's Confidential Response to the First Production Request of the Commission Staff. Also, enclosed are four (4) copies of the confidential disk containing information responsive to the Commission Staff's Request for Production Nos. 1,3,4, and g. Please handle the confidential information in accordance with the ProtectiveAgreement executed in this matter. Sincerely, o{r-C fr*o"* Lisa D. Nordstrom LDN:evp Enclosures 1221 W. ldaho St. (83702) P.O. Box 70 Boise, lD 83707 LISA D. NORDSTROM (lSB No. 5733) JENNIFER M. REINHARDT-TESSMER (lSB No. 7432) Idaho Power Company 1221West ldaho Street (83702) P.O. Box 70 Boise, Idaho 83707 Telephone: (208) 388-5825 Facsimile: (208) 388-6936 I nordstrom@ ida hopower. com i rei n hardt@ id a hopower. co m Attorneys for ldaho Power Company IN THE MATTER OF IDAHO POWER COMPANY'S APPLICATION FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR INVESTMENT IN SELECTIVE CATALYTIC REDUCTION CONTROLS ON JIM BRIDGER UNITS 3 AND 4. 'i,i i:: !'5 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-13-16 IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO !DAHO POWER COMPANY COMES NOW, ldaho Power Company ("ldaho Powed' or "Compo[y"), and in response to the First Production Request of the Commission Staff ("Staff') to ldaho Power Company dated July 15,2013, herewith submits the following information: IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REOUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 1 REQUEST NO. 1: Please provide a cost breakdown of the entire Jim Bridger Units 3 and 4 Environmental Compliance upgrade project that makes up the Commitment Estimate. Please include a narrative or description for each element of cost. Also, please provide a copy of the Engineering, Procurement and Construction (EPC) contract including all cost estimates, timelines for completion, etc. RESPONSE TO REQUEST NO. 1: Please see the confidential attachment provided on the confidential CD for the cost breakdown of the Jim Bridger Units 3 and 4 Selective Catalytic Reduction ("SCR') project and description for each element of cost. This attachment contains information that is confidential, proprietary, and/or has commercial value. The confidentia! CD will be provided to those parties that have executed the Protective Agreement in this proceeding. ldaho Power will make the confidentia! EPC contract available for viewing at its corporate office in Boise, Idaho pursuant to the signing of a confidentiality agreement. Please contact Doug Jones at 388-2615 or Camilla Victoria at 388-5821 to view the materials. The response to this Request was prepared by John Carstensen, Engineering Project Leader, ldaho Power Company, in consultation with Lisa D. Nordstrom, Lead Counsel, ldaho Power Company. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 2 REQUEST NO. 2: Please provide an itemized estimate of additional costs if the Company delays the start of the project until November 21, 2013, but is still required to meet the Wyoming State lmplementation Plan (SlP) deadlines for compliance. RESPONSE TO REQUEST NO. 2: ldaho Power and PacifiCorp cannot meet the Wyoming State lmplementation Plan deadlines for compliance if the project start date is delayed to November 21, 2013. Consequently, no estimate of additional costs due to project delay exists. ln January and February of 2013, PacifiCorp requested certain short-listed contractors to advise PacifiCorp of the potential consequences of delaying the Full Notice to Proceed ('FNTP") beyond May 15, 2013. Prior to the request, short-listed bidders had indicated that they would require a "day-for-day" schedule extension in the event the FNTP was issued after the May 15,2013, date. PacifiCorp was advised that an extension would, in turn, prevent Units 3 and 4 at Bridger from meeting SIP compliance dates. In response to PacifiCorp's request, the short-listed contractors provided updated competitive bids that would provide for Limited Notice to Proceed ("LNTP") contract approach that would permit contractors to perform certain limited tasks in order to meet the Wyoming State lmplementation Plan compliance deadlines, but extend the FNTP date beyond May 15, 2013, to December 1, 2013. PacifiCorp recommended this approach to Idaho Power as the least cost alternative to ensure compliance with the legally enforceable compliance obligations. On May 31, 2013, PacifiCorp executed the contract with LNTP provisions included with the selected bidder. ldaho Power reviewed PacifiCorp's recommended course of action. The EPC contractor is currently on track IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 3 to timely complete the limited tasks identified in the LNTP. The response to this Request was prepared by Tom Harvey, Joint Projects Manager, ldaho Power Company, in consultation with Lisa D. Nordstrom, Lead Counsel, ldaho Power Company. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 4 REQUEST NO. 3: Please provide a three-year history by month of unit availability and amount of generation for Jim Bridger Units 3 and 4. RESPONSE TO REQUEST NO. 3: Please see the confidential table provided on the confidential CD which shows the past 36 months of equivalent availability and tota! net generation in megawatt-hours (MWh) for Jim Bridger Units 3 and 4. The generation is the total production of the units and not Idaho Powe/s share of the generation of the units, because ldaho Power takes a share of the plant total generation and is not allocated generation by unit. This attachment contains information that is confidential, proprietary, and/or has commercial value. The confidential CD will be provided to those parties that have executed the Protective Agreement in this proceeding. The response to this Request was prepared by John Carstensen, Engineering Project Leader, ldaho Power Company, in consultation with Lisa D. Nordstrom, Lead Counsel, ldaho Power Company. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 5 REQUEST NO. 4: Please provide an itemized estimate of costs and benefits for each alternative (r.e., emission control upgrade, gas conversion, CCCT replacement), a short description of each element of cosUbenefit, the timing of each element of cosUbenefit (e.9., gas conversion capital cost, mine remediation cost, CCCT capital investment, etc.), and whether each is a one-time cosUbenefit or is re-occurring. RESPONSE TO REQUEST NO. 4: An itemized list of costs and the annual timing for each investment alternative of emissions contro! upgrade, gas conversion and CCCT replacement is shown in confidential Exhibit No. 5 to the testimony of Tom Harvey. Specifically, it is included in the confidential SAIC Report Appendix A, Coal Environmental Compliance Upgrade lnvestment Evaluation Table A-17 Upgrade, Table A-18 Fuel Switch, and Table A19 Retire and Replace on page 48 (Attachment 1 ) for Jim Bridger 3 and Table A-20 Upgrade, Table A-21 Fuel Switch and Table A22 Retire and Replace on Page 49 (Attachment 2) for Jim Bridger 4. The confidential attachments will be provided on the confidentia! CD. These attachments contain information that is confidential, proprietary, and/or has commercia! value. The confidential CD will be provided to those parties that have executed the Protective Agreement in this proceeding. As shown in the CPCN application Exhibit No 6, Page 16, Figure 4-Tota! Portfolio Costs gives the benefit of each alternative as the lower expected cost (highlighted in green) of the alternatives under the 9 future scenarios. The described page is attached as Exhibit No 6, Page 16 (Attachment 3). ln general, a cost or benefit related to a fixed investment is one-time in nature and those related to variable costs are recurring. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 6 The response to this Request was prepared by Richard Haener, Senior Fuels Management Coordinator, ldaho Power Company, in consultation with Lisa D. Nordstrom, Lead Counsel, ldaho Power Company. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 7 REQUEST NO. 5: Please provide the cost of transmission investment that could be realistically avoided or delayed if Jim Bridger Units 3 or 4 (or both) were shut down on the Wyoming SIP compliance dates and alternative generation sources were installed close to major load centers. RESPONSE TO REQUEST NO. 5: Removing approximately 550-1 ,100 Megawatts (MW) of resources in Wyoming would undoubtedly change the power flow characteristics of the transmission system in ldaho. Today, ldaho Power's resource fleet is balanced geographically which balances the transmission capacity needs and power flows across the system. Adding generation close to major load centers would certainly require transmission investment to integrate the new resources (aka "Local lnterconnection Costs"). Additionally, large resource additions near the load centers combined with a reduction in Wyoming generation may also require additional transmission investment beyond what is planned today due to the changes in the power system operations and power flows. For example, more power may flow west-to-east across ldaho Powe/s system requiring transmission reinforcements that are not necessary today because of the present geographically balanced resource portfolio. Thus, the addition of generating capacity close to major load centers would result in added costs. There are no large future transmission investments between Jim Bridger and the Treasure Valley that can be avoided if Jim Bridger Units 3 and 4 were to be shut down. Series capacitors at Borah and Kinport substations will need to be replaced in the future due to the age of the equipment, likely in the next 5-10 years. lf no generation is substituted in Wyoming then it is possible that series capacitor replacements may not IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 8 be required, although studies would be required to verify if the system could operate adequately without the series capacitors. The cost estimate for replacement of these series capacitors is roughly $16 million in today's dollars. The response to this Request was prepared by Mitch Colburn, Senior Engineer, ldaho Power Company, in consultation with Lisa D. Nordstrom, Lead Counsel, ldaho Power Company. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 9 REQUEST NO. 6: Please provide the reduction in capacity for Jim Bridger Units 3 and 4 if the Environmental Protection Agency (EPA) places a 0.05 lbs/MMBTU compliance standard for nitrogen oxide at some future date. What are the incremental costs (r.e. capital, maintenance, and operation) associated with the more stringent standard on each unit? RESPONSE TO REQUEST NO. 6: The current proposed Federal lmplementation Plan by the Federal EPA, posted on June 4,2013, approves the state of Wyoming's State lmplementation Plan of 0.07 lbs/MMBtu NOx emissions for Units 3 and 4 at the Jim Bridger Power Plant. A definitive estimate of the SCR run-rate cost implications associated with a requirement to achieve a 0.05 lb/MMBtu permit limit has not been determined. However, it is anticipated that scheduled catalyst fill and replacement events could cost up to approximately ten percent more and ammonia consumption costs could increase by approximately four percent over the respective costs for the 0.07 lb/MMBtu permit limit scenario. At this time, the best estimate of SCR project initial capital cost implications for scope modifications required to achieve a 0.05 lbs/MMBtu permit limit is less than $1.7 million per unit (ldaho Powe/s share). lncremental unit capacity reductions are not anticipated if the NOx emissions limit was established at 0.05 lb/MMBtu. The response to this Request was prepared by John Carstensen, Engineering Project Leader, ldaho Power Company, in consultation with Lisa D. Nordstrom, Lead Counse!, ldaho Power Company. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 1O REQUEST NO. 7: Please provide a copy of the Request for Proposal (RFP) and RFP evaluation results for the EPC contractor. RESPONSE TO REQUEST NO. 7: ldaho Power will make the confidentia! RFP and RFP evaluation results available for viewing at its corporate office in Boise, ldaho, pursuant to the signing of a confidentiality agreement. Please contact Doug Jones at 388-2615 or Camilla Victoria at 388-5821 to view the materials. The response to this Request was prepared by John Carstensen, Engineering Project Leader, ldaho Power Company, in consultation with Lisa D. Nordstrom, Lead Counsel, Idaho Power Company. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 11 REQUEST NO. 8: Please discuss Idaho Power's course of action and the ramifications of those actions if the EPA doesn't finalize its rules by the Final Notice to Proceed deadline (see the direct testimony of Michael Youngblood, pg 18). RESPONSE TO REQUEST NO. 8: Even if the EPA rules are not finalized by the final notice to proceed deadline, ldaho Power and PacifiCorp will still have to comply with the Wyoming Regional Haze SIP and the BART Settlement Agreement which requires the installation of SCRs on Jim Bridger Units 3 and 4,by the years 2015 and 2016 respectively. As Lisa Grow's testimony on page 11, lines 7 through 11, states: "lf the environmental upgrades are not installed within the time frame given by the EPA, ldaho Power would be forced to stop generating from these units. Unlawfully operating the units in violation of federal and state regulations is not an option for ldaho Power." The response to this Request was prepared by John Carstensen, Engineering Project Leader, ldaho Power Company, in consultation with Lisa D. Nordstrom, Lead Counse!, ldaho Power Company. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 12 REQUEST NO. 9: Please provide an explanation of the contractual obligations and costs between ldaho Power and PacifiCorp if ldaho Power were to decide to abandon generation at Jim Bridger on the Wyoming SIP compliance dates for each unit. PIease provide documentation that supports these obligations and costs. RESPONSE TO REQUEST NO. 9: The response and attachments provided in response to this request contain confidential contract terms and will be provided to those parties that have executed the Protective Agreement in this proceeding. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 13 REQUEST NO. 10: Please provide the dates when the useful life of Jim Bridger Units3and4ends. RESPONSE TO REQUEST NO. 10: Currently, in the ldaho Jurisdiction, the depreciable life of Jim Bridger Units 3 and 4 ends in 2034. The response to this Request was prepared by Mitch McClellan, Joint Venture Analyst, ldaho Power Company, in consultation with Lisa D. Nordstrom, Lead Counsel, ldaho Power Company. DATED at Boise, ldaho, this 6h day of August 2019. IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 14 Attorney for ldaho Power Company CERTIFICATE OF SERVICE ! HEREBY CERTIFY that on this 6th day of August 2013 I served a true and correct copy of IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY upon the following named parties by the method indicated below, and addressed to the following: Commission Staff Kristine A. Sasser Deputy Attomey General ldaho Public Utilities Commission 47 2 W est Washington (83702) P.O. Box 83720 Boise, Idaho 83720-007 4 lndustrial Gustomers of Idaho Power Peter J. Richardson Gregory M. Adams RICHARDSON ADAMS, PLLC 515 North 27th Street (83702) P.O. Box 7218 Boise, ldaho 83707 Dr. Don Reading 6070 Hill Road Boise, ldaho 83703 ldaho Conservation League Benjamin J. Otto ldaho Conservation League 710 North Sixth Street Boise, ldaho 83702 Snake River Alliance Ken Miller, Clean Energy Program Director Snake River Alliance P.O. Box 1731 Boise, ldaho 83701 Hand Delivered U.S. Mail Overnight Mail FAXX Emai! kris.sasser@puc.idaho.qov Hand Delivered U.S. Mail Overnight Mail FAX Email peter@richardsonadams.com qreg@ richa rdsonadams. com Hand Delivered U.S. Mail Overnight Mail FAXX Email dreadinq@mindsprinq.com Hand Delivered U.S. Mail Overnight Mail FAXX Email botto@idahoconservation.orq Hand Delivered U.S. Mail _Overnight Mail _FAXX Email kmiller@snakeriveralliance.orq IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 15 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION GASE NO. IPC-E-13-16 IDAHO POWER COMPANY RESPONSE TO STAFF'S REQUEST NO.4 the twenty-year Aurora generated total portfolio cost to form the basis for the quantitative evaluation of the investment alternatives. Figure 4, below, summarizes the combined NPV results of ldaho Power's Aurora analysis and SAICs fixed costs analysis for each investment option under varying carbon and natural gas futures. The planning case (planning case carbon/planning case natural gas) is denoted in bold. The left column groups each unit with the investment atternatives. The columns to the right show the NPV of the total portfolio costs over the twenty-year period (2013-2032) in 2013 dollars. The green highlighted cell indicates the least cost option for the unit under that scenario. The preponderance of least cost outcomes and the relative cost difference between alternatives helps determine the investment recommendation. Flgure 4. Total Portfolio Costs ldaho Power Company Coal Environmental lnvestment Modelin8 Results Total Portfolio Costs (Aurora Portfolio cost + SAlc Fired Costs l For the 20 year forecast period 2013-2032 NPV ln 2013 SMilliont NPV ofthe Total Portfolio Cost for the 3 natural l.3 and 3 carbon adder futures lnv!stm !nt Alt!rnatives NG High :O, S0 NG High :o2 s14 NG High :or 535 NG low :o, So NG Low :o2 514 NG Low :oz $35 NG Planning 3o, S0 NG )lannihB :o2 514 NG ,lanninB :or 935 /almy 1 (v1) DSI /l 2015 retlre/rcdace wlti CCCI ,1 2015 natural tas conv€rsion 6,Ut5 3,96s 3.922 i.s a,a 5.t7!l d079 3,t69 4,800 0.581 1,012 1,927 +r., +rin6,7t1 t,Tzz 6,?aa c79' /1 v2 Enhanc"d Upgrrdc (SCR & wfGD) 2018 /1 V2 r€tlre/rcplace with CCCT 2018 /1 V2 natural tas convcrsbn 2018 5,157 5,124 z38r 6,961 r.580 4,283 5,372 +983 7,la rA'rt 4,379 5,ltt r,0x 7,1A 4,r03 4,33s 5,9t0 6,979 :TA - v1 V2 Eoftrm.d Upt..de (SCR & WFGDI 2023 fA - Vl v2 retlrc/r€plac! with cccf 2023 ITA - vl v2 natur.l !.! convusion 2023 5.06!7,316 /t 512 5,315 7.t70 1,aB 5"rtE ,,,7L 4,256 4.:Il1 5,8,:l t,u7 1,275 5.(m 7,A75 ..:ll5 tt13 7.1(n im sridter 1 (i81) lnstall scR 81 rctireteplace with CCCI 2023 B1 natural Bas convlrslor 2023 4,054 4,08r 4479 /f,911 6,962 7.005 4,155 r,155 1,t,,? 4,955 69at 4,149 1,L67 a,964 a,ttt 0,943 7.O12 im &id8s 2 (J82)tnstall scfi 82 r?tirG/replrc! with CCCr 2022 82 natural gir convsrion 2022 a,tt? I tnt /t,935 a,928 7,009 7,008 a,198 4,16:t 4981 4,X9 6.3:U /t,201 4,L79 5,65 argit 6,980 z(xrlt im Bridter 3 (J83) lnstall SCR 83 rltir./ref{ace widr CCCT 2016 83 n.tural 8.s converlon 2016 4,231 1.207 5 016 4,989 7,O22 7-O70 4,201 4.154 1,917 L a77 4.853 4,253 La10 5,030lu 6,931 6 q6C im Bridg.r 4 (.,84) lnstall sCR 84 retirelreplace with CCCT 2017 84 naiural !15 converrion 2O17 1,20,3 4.rto 4,985 4961 6,984 6,9E3 4,189 1,LlL 4,935 4.915 5,82s 4,235 4,195 5,0o' a's7t 5,903 6.g:ta rA - JB3 JBr tnst.U SCR ItA - JB3 rB4 retirc/rcpld€ w CCCI 2020-21 lfA -J83 JB4 n.tural 8as ctrvcrllil 2020-21 4,E95 I OtO 5,576 ( (at 7,151 7.54S 4,539 u \47 5,209 ( 1nn 4,712 L An? 5,/ti!6 I lt27.(t86 ,.354 Coal Unit Environmental Analysis Page 16 Exhibit No. 6 Case No. IPC-E-13-16 T. Harvey, IPC Page 16 of 30