HomeMy WebLinkAbout20090608IPC to Staff 85.pdfRECE,VEO
'PM It: 54
esIDA""POR~
An IDACORP Company
BARTON L. KLINE
Lead Counsel
June 5, 2009
VIA HAND DELIVERY
Jean D. Jewell, Secretary
Idaho Public Utilities Commission
472 West Washington Street
P.O. Box 83720
Boise, Idaho 83720-0074
Re: Case No. IPC-E-09-03
LANGLEY GULCH POWER PLANT
Dear Ms. Jewell:
Enclosed for filing are an original and three (3) copies of Idaho Power Company's
Response to Staffs Production Request No. 85 of the Staffs Third Production Request to
Idaho Power Company in the above matter.
Very truly yours,&J~
Barton L. Kline
BLK:csb
Enclosures
P.O. Box 70 (83707)
1221 W. Idaho St.
Boise. 10 83702
BARTON L. KLINE, ISB #1526
LISA D. NORDSTROM, ISB #5733
Idaho Power Company
P.O. Box 70
Boise, Idaho 83707
Telephone: 208-388-2682
Facsimile: 208-388-6936
bklinecæidahopower.com
Inordstromcæidahopower.com
RECEIVED
2009 JUH -5 PH~: 54
IDAHO PUBLIC
UTILITIES COMMISSION
Attorneys for Idaho Power Company
Street Address for Express Mail:
1221 West Idaho Street
Boise, Idaho 83702
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER
COMPANY'S APPLICATION FOR A
CERTIFICATE OF PUBLIC
CONVENIENCE AND NECESSITY FOR
THE LANGLEY GULCH POWER PLANT.
)
) CASE NO. IPC-E-09-03
)
) IDAHO POWER COMPANY'S
) RESPONSE TO THE THIRD
) PRODUCTION REQUEST OF THE
) COMMISSION STAFF TO IDAHO
) POWER COMPANY
COMES NOW, Idaho Power Company ("Idaho Powet' or "the Company"), and in
response to the Third Production Request of the Commission Staff to Idaho Power
Company dated May 21, 2009, herewith submits the following information:
IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 1
REQUEST NO. 85: In response to Request No. 20 of the Industrial Customers
of Idaho Power, the Company stated that it is working on developing a new load
forecast that wil be available in late summer of 2009. Given the significance of the
proposed Langley Gulch project in terms of cost and added generation capacity, and
given that the need for the Langley Gulch project was presumably based on a prior load
forecast, please explain why Idaho Power has not prepared a more current load
forecast. Can the load forecast update that is expected to be completed in late summer
be expedited for use in the current Langley Gulch case? If so, please provide a copy of
the revised load forecast.
RESPONSE TO REQUEST NO. 85: There is no need to expedite the late
summer 2009 sales and load forecast to confirm the need for Langley Gulch. Idaho
Power has prepared a number of updated load forecasts since the 2006 IRP was
published. The Company typically updates its load forecast annually. The September
2008 forecast was used for the 2009 IRP. Recent economic conditions prompted the
Company to update the September 2008 load forecast in December of 2008 and then
again in May 2009. The December 2008 update was discussed in the Company's
Response to the Industrial Customers' Request No. 20. As noted in that Response, the
residential and commercial class loads were updated. The most recent update,
performed in May of 2009, updated the forecast loads for special contract customers as
part of preparing the newest load forecast, which is expected to be completed in late
summer 2009. Updating the forecast for special contract customers is one component
of the complete load forecast update expected to be completed late this summer. The
December 2008 and May 2009 forecasts were provided in the Company's Response to
Staff Request No. 84.
IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 2
As a result of these updates, the September 2008 "95th percentile" forecast of
peak-hour load for July of 2009 through July of 2012, inclusive, (after accounting for
expected performance of existing DSM programs) was dropped from 3,405 MW;
3,465MW; 3,543 MW; and 3,636 MW to 3,338 MW; 3,422 MW; 3,502 MW; and 3,608
MW, respectively. This translates into forecast peak-hour load reductions of 68 MW, 44
MW, 41 MW, and 28 MW for July of 2009-2012, respectively. The average energy
forecast for July of 2009 through July of 2012 (after accounting for expected
performance of existing DSM programs) was dropped from 2,457 MW; 2,494 MW;
2,543 MW; and 2,603 MW to 2,395 MW; 2,449 MW; 2,503 MW; and 2,577 MW,
respectively. This translates into average energy reductions of 62 aMW, 44 aMW, 40
aMW, and 26 aMW for July of 2009 through July of 2012, respectively.
In addition to incorporating the forecast peak-hour and average energy
reductions noted above, the load and resource balances provided in the Company's
Response to Staffs Request No. 84 have been updated to include all DSM program
impacts as of May 2009, including new demand response programs for Irrigation,
Commercial, and Industrial customers proposed in the 2009 IRP process. The total
DSM contribution forecast for peak-hours during July of 2009 through July of 2012 is
185 MW, 261 MW, 332 MW, and 365 MW, respectively. On an average energy basis,
the total DSM contribution forecast during July of 2009 through July of 2012 is 17 aMW,
33 aMW, 49 aMW, and 65 aMW.
Utilizing the May 2009 load forecast, along with the forecast peak-hour DSM
contributions and the assumed level of purchases from the Pacific Northwest, Idaho
Power is stil projecting peak-hour deficits during July of 2009 through July of 2012 of 40
MW,21 MW,91 MW, and 183 MW, respectively. From an average energy perspective,
IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 3
using the May 2009 load .forecast along with the forecast DSM contributions to reduce
average energy requirements and the assumed level of purchases from the Pacific
Northwest, Idaho Power is stil projecting average energy deficits during July of 2009
through July of 2012 of 397 MW, 418 MW, 465 MW, and 535 MW, respectively.
Forecast average energy and peak-hour deficits are shown in the load and resource
balances provided in the Company's Response to Staffs Request No. 84. However,
these load & resource balances do not include 75 MW of recent July and August HL
purchases at Mead (southern Nevada) for 2009,2010, and 2011. These purchases will
utilize transmission on NV Energy's system and Idaho Powets transmission rights from
Red Butte to Borah/Brady to deliver this energy to Idaho Powets east side on an as-
needed basis.
In spite of the fact that recent economic conditions have been very volatile, Idaho
Power's load forecasts have been very accurate. The chart below ilustrates that
accuracy. The chart below compares the December 2008 load forecast to the weather-
adjusted actual loads for January, February, March, and April of 2009.
Month Weather Adjusted December 2008 Difference (aMW)
Actual Loads (aMW)Load Forecast (aMW)Dec minus WA Act
January 2009 1,774 1,859 86
February 2009 1,683 1,714 31
March 2009 1,499 1,519 20
April 2009 1,445 1,504 59
The table shows that the absolute value of average difference between the
weather adjusted actual and the December 2009 load forecast is approximately 50
aMW - with the December 2009 load forecast slightly exceeding weather-adjusted
actual loads. The average difference (using absolute values) between the weather
IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 4
adjusted actual loads and the forecast from January 2009 through April of 2009 is
approximately 3 percent. Looking at the May 2009 load forecast, the weather-adjusted
actual load for May was 13 aMW greater than the May 2009 forecast.
In May of 2009, the load forecast was updated again, making specific
adjustments to the load forecast for Idaho Powets special contract customers. In this
update, the load forecast was reduced again, with the largest reductions (94 aMW and
97 MW during peak-hours) occurring in late 2009. This reduction at least partially
offsets some of the approximately 50 MW of variance in the December 2009 forecast
discussed above.
As Staff noted in this Request, Idaho Power is currently in the process of
updating the forecast again and the new forecast should be available late this summer.
However, as described in the above discussion, significant deficits continue to be
forecast for July of 2012 on both an average energy and peak-hour basis - even with
hundreds of MWs of DSM anticipated in the forecast. Furthermore, in July of 2012,
Power Supply plans to receive a 115 MW set-aside of firm network transmission to
import purchases from the Pacific Northwest. Yet to meet peak hour loads, the
Company is planning to import 315 aMW of energy from the Pacific Northwest during
the same month. This means the majority of the planned imports wil be on Secondary
Network (non-firm) transmission. Based on the Company's current projections, Langley
Gulch, or another similarly sized resource, is needed in the 2012 timeframe to reduce
the risk of a shortage of imported energy availability and wholesale market price risk.
The resource need that the Langley Gulch project will meet was identified in the
20041RP. In the 2004 IRP, 500 MW of seasonal ownership coal-fired generation was
identified for 2011. This was updated in the 2006 IRP, which included 250 MW of coal-
IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 5
fired generation in 2013 and an additional 225 MW of transmission import capacity in
2012. The 2008 IRP Update included a 250 MW CCCT resource and the 225 MWof
import capacity on the Hemingway-Boardman transmission line in 2012. The Boardman
to Hemingway ("B2H") transmission line has been recently delayed until 2015. With the
B2H project delayed, development of additional generation resources that do not utilze
transmission capacity over the Company's constrained western interconnections, such
as Langley Gulch, becomes even more important.
Idaho Power will continue to work on updating its load forecast; however, it is
important to recognize that the load forecast has been updated and that differences in
weather-adjusted actual values from the forecast over that last few months have been
about 50 MW on average, or about 3 percent. Idaho Powets load and resource
balance incorporating the May 2009 load forecast, provided in the Company's
Response to Staffs Request No. 84, indicates deficits significantly in excess of the
recent 3 percent forecast differences. This coupled with the fact that (1) water
conditions can be worse than planned for, (2) economic recovery could be faster than
anticipated, and (3) Idaho Power stil relies on a significant amount of imports during the
summer (a portion of which are imported on non-firm transmission), along with Idaho
Power's obligation to serve, all indicate the need for additional internal generation
resources. The persistence of the projected deficits through continued analysis, recent
adjustments for the economic downturn, and increased DSM, underscores the need for
rapid deployment of this needed resource.
The response to this Request was prepared by Karl Bokenkamp, General
Manager Power Supply Operations and Planning, Idaho Power Company, in
consultation with Barton L. Kline, Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 6
DATED at Boise, Idaho, this 5th day of June 2009.
~-
Attorney for Idaho Power Company
IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 7
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on this 5th day of June 2009 I served a true and correct
copy of IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY upon the
following named parties by the method indicated below, and addressed to the following:
Commission Staff
Scott Woodbury
Deputy Attorney General
Idaho Public Utilities Commission
472 West Washington
P.O. Box 83720
Boise, Idaho 83720-0074
Industrial Customers of Idaho
Power and Northwest and
Intermountain Power Producers
Coalition
Peter J. Richardson, Esq.
RICHARDSON & O'LEARY PLLC
515 North 27th Street
P.O. Box 7218
Boise, Idaho 83702
Dr. Don Reading
Ben Johnson Associates
6070 Hill Road
Boise, Idaho 83703
Snake River Allance
Ken Miler
Snake River Alliance
P.O. Box 1731
Boise, Idaho 83701
Idaho Irrigation Pumpers
Association, Inc.
Eric L. Olsen
RACINE, OLSON, NYE, BUDGE
& BAILEY, CHARTERED
P.O. Box 1391
201 East Center
Pocatello, Idaho 83204-1391
-- Hand Delivered
U.S. Mail
_ Overnight Mail
FAX
-- Email Scott.Woodburycæpuc.idaho.gov
Hand Delivered
-- U.S. Mail
_ Overnight Mail
FAX
-- Email petercærichardsonandoleary.com
Hand Delivered
-- U.S. Mail
_ Overnight Mail
FAX
-- Email dreadingcæmindspring.com
Hand Delivered
-- U.S. Mail
_ Overnight Mail
FAX
-- Email kmillercæsnakeriverallance.org
Hand Delivered
-- U.S. Mail
_ Overnight Mail
FAX
-- Email elocæracinelaw.net
IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 8
Anthony Yankel
Yankel & Associates, Inc.
29814 Lake Road
Bay Vilage, Ohio 44140
Hand Delivered
-- U.S. Mail
_ Overnight Mail
FAX
-- Email tonyayyankel.net
Idaho Conservation League
Betsy Bridge
Idaho Conservation League
710 North Sixth Street
P.O. Box 844
Boise, Idaho 83701
Hand Delivered
-- U.S. Mail
_ Overnight Mail
FAX
-- Email bbridgeaywildidaho.org
Northwest and Intermountain
Power Producers Coalition
Susan K. Ackerman
9883 NW Nottage Drive
Portland, Oregon 97229
Hand Delivered
-- U.S. Mail
_ Overnight Mail
FAX
-- Email Susan.k.ackermanaycomcast.net
Community Action Partnership
Association Of Idaho
Brad M. Purdy
Attorney at Law
2019 North 1 ¡th Street
Boise, Idaho 83702
Hand Delivered
-- U.S. Mail
_ Overnight Mail
FAX
-- Email bmpurdyayhotmail.com
'-
Barton L. Kline
IDAHO POWER COMPANY'S RESPONSE TO THE THIRD PRODUCTION
REQUEST OF THE COMMISSION STAFF TO IDAHO POWER COMPANY - 9