HomeMy WebLinkAbout20090212IPC to Staff 1-30.pdfLISA D. NORDSTROM
Senior Attorney
~IDA~POR~
An IDACORP Company
February 11, 2009
VIA HAND DELIVERY
Jean D. Jewell, Secretary
Idaho Public Utilities Commission
472 West Washington Street
P.O. Box 83720
Boise, Idaho 83720-0074
Re: Case No. IPC-E-08-22
RuleH
Dear Ms. Jewell:
Enclosed for filing please find an original and three (3) copies of Idaho Power's
Response to the Commission Staffs First Production Request to Idaho Power Company in
the above matter.
i would appreciate it if you would return a stamped copy of this letter for Idaho
Power's file in the enclosed stamped, self-addressed envelope.
Very truly yours,
~:v d. '1Pt~
Lisa D. Nordstrom
LDN:csb
Enclosures
P.O. Box 70 (83707)
1221 W. Idaho St.
Boise, 10 83702
LISA D. NORDSTROM, ISB No. 5733
BARTON L. KLINE, ISB No. 1526
Idaho Power Company
P.O. Box 70
Boise, Idaho 83707
Tel: 208-388-5825
Fax: 208-338-6936
Inordstrom~idahopower.com
bkline~idahopower.com
QEC'¡:I'\n:I",. ".. .. '," L-.. " "",",' ~,..,.f
2009 FEB I I PM q: 52
IDAHO ~:~;¡:
UTIUi!ES CO:,;
Attorneys for Idaho Power Company
Street Address for Express Mail:
1221 West Idaho Street
Boise, Idaho 83702
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION )
OF IDAHO POWER COMPANY FOR ) CASE NO. IPC-E-08-22
AUTHORITY TO MODIFY ITS RULE H )
TARIFF RELATED TO NEW SERVICE ) IDAHO POWER COMPANY'S
ATTACHMENTS AND DISTRIBUTION ) RESPONSE TO THE COMMISSION
LINE INSTALLATIONS OR ALTERATIONS ) STAFF'S FIRST PRODUCTION
) REQUEST TO IDAHO POWER
) COMPANY
)
COMES NOW, Idaho Power Company ("Idaho Powet' or "the Company"), and in
response to the First Production Request of the Commission Staff to Idaho Power
Company dated January 21,2009, herewith submits the. following information:
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 1
REQUEST NO.1: Please provide a table of current costs charged by Idaho
Power for overhead and pad-mounted transformers for all sizes and types typically used
for Schedule 1, 7, 9 and 24 customers. For each size and type of transformer, list the
number installed in 2007 and 2008.
RESPONSE TO REQUEST NO.1: The information requested is both time and
labor intensive to compile. As previously discussed with Staff, Idaho Power needs
additional time to complete its response and intends to produce the information
requested by Friday, February 13, 2009.
The response to this Request was prepared by Scott Sparks, Senior Pricing
Analyst, Idaho Power Company, in consultation with Barton L. Kline, Lead Counsel,
Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 2
REQUEST NO.2: Please provide a summary of service attachments made for
Schedule 1 customers for each of the years 2006 - 2008. In the summary, include at
least the following:
a. Total number of new residential line extensions;
b. Average actual cost for all service extensions;
c. Number of underground and overhead service cable installations;
d. Number of installations in which conduit was installed;
e. Number of transformers installed, whether pad mounted or overhead, and
their size rating;
f. Average number of customers per transformer;
g. Number of single and three phase installations;
h. Average length of service cable;
i. Number of meters by meter type and cost; and
j. Average cost of other incidental equipment.
RESPONSE TO REQUEST NO.2: The information requested is both time and
labor intensive to compile. As previously discussed with Staff, Idaho Power needs
additional time to complete its response and intends to produce the information
requested by Friday, February 13,2009.
The response to this Request was prepared by Scott Sparks, Senior Pricing
Analyst, Idaho Power Company, in consultation with Barton L. Kline, Lead Counsel,
Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 3
REQUEST NO.3: Please provide a list of service attachments made for
Schedule 7, 9, and 24 customers for 2008. For each service attachment, include at
least the following:
a. Actual cost of the service attachment;
b. Connected load in kW;
c. Whether service cable was underground or overhead;
d. Whether conduit was installed;
e. Whether transformer was installed, number and rating of transformers;
f. If transformer installed, was it overhead or pad mounted;
g. Whether single or three phase;
h. Length of service cable;
i. Meter type and cost; and
j. Cost of other incidental equipment.
RESPONSE TO REQUEST NO.3: The information requested is both time and
labor intensive to compile. As previously discussed with Staff, Idaho Power needs
additional time to complete its response and intends to produce the information
requested by Friday, February 13, 2009.
The response to this Request was prepared by Scott Sparks, Senior Pricing
Analyst, Idaho Power Company, in consultation with Barton L. Kline, Lead Counsel,
Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 4
REQUEST NO.. 4: Please provide an analysis for the cost of the Company's
engineering fee.
RESPONSE TO REQUEST NO.4: The Company's $58.31 engineering fee was
determined based on the following: The current wage rate for a Senior Distribution
Designer is $35.61 per hour, with benefits of $17.09 per hour based on 2006 actual
benefit expenditures, plus general overhead of $5.61 per hour for equipment based on
current accounting guidelines.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
. STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 5
REQUEST NO.5: Please provide an analysis for the cost of temporary service
attachment charge for underground and overhead, and for each service:
a. How the Company determines the appropriate size of the crew for each
type of service attachment;
b. How the Company determines the amount of trip time;
c. How the Company calculated the labor cost and what is included in that
cost for each type of service attachment;
d. If applicable, please provide the cost of each required material for each
type of service attachment;
e. A breakdown of costs showing how much of that price is travel cost, labor
cost, material cost, or any other costs that contribute to the final proposed cost.
RESPONSE TO REQUEST NO.5: Idaho Powets analysis on construction
costs is based on travel time, equipment, labor, and materials. The Company
construction costs are determined by the standard construction staffng level, the
equipment that is required to complete the work, the time it takes to safely finish a
project, and the travel time to the construction destination. Currently, Idaho Power uses
a computer softare system called "Asset Suite" to track material expenses and
determine construction costs.
a. The crew size for both overhead and underground temporary service is 1
person, determined by the Company's standard construction staffing leveL.
b. Travel time is based on average travel time, which is 0.5 hours. In urban
areas, traffc constraints may cause delays greater than 0.5 hours, and in rural areas,
. IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 6
remote location may require travel time greater than 0.5 hours, but, on average, travel
time to jobs is approximately 0.5 hours.
c. Labor cost is a combination of travel time and "wrench time." Wrench time
includes time spent doing the work and vehicles used. Wrench time has been
calculated using time and motion studies that have been integrated into the work order
construction and inventory system.
d. Underground services have no materials associated with these costs, it is
labor only. Overhead services include 100 feet of #2 triplex aluminum conductor, 2
dead end wedge clamps, and assorted nuts, bolts, and washers.
e. The underground service cost includes two components: (1) travel time of
$26.90 and (2) wrench time of $14.22. For an overhead service, the cost includes three
components: (1) travel time of $26.90, (2) wrench time of $54.10, and (3) $100.95 in
materials.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 7
REQUEST NO.6: Please provide an analysis for the cost of temporary return
trip charge and:
a. How the Company determines the appropriate size of the crew for each
type of service attachment;
b. How the Company determines the amount of trip time;
c. How the Company calculated the labor cost and what is included in that
cost for each type of service attachment;
d. If applicable, please provide the cost of each required material for each
type of service attachment;
e. A breakdown of costs showing how much of that price is travel cost, labor
cost, material cost, or any other costs that contribute to the final proposed cost.
RESPONSE TO REQUEST NO.6: Idaho Powets analysis on construction
costs is based on travel time, equipment, labor, and materials. The Company
construction costs are determined by the standard construction staffng level, the
equipment that is required to complete the work, the time it takes to safely finish a
project, and the travel time to the construction destination. Currently, Idaho Power uses
a computer softare system called "Asset Suite" to track material expenses and
determine construction costs.
a. The crew size for an overhead or underground temporary return trip
charge is 1 person. The return trip charge is determined by the Company's standard
construction staffng leveL.
b. Travel time is based on average travel time, which is 0.5 hours. In urban
areas, traffc constraints may cause delays greater than 0.5 hours, and in rural areas,
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 8
remote location may require travel time greater than 0.5 hours, but, on average, travel
time to jobs is approximately 0.5 hours.
c. Labor cost is a combination of travel time and "wrench time." Wrench time
includes time spent doing the work and vehicles used. Wrench time has been
calculated using time and motion studies that have been integrated into the work order
construction and inventory system.
d. Return trip charge is labor only.
e. No materials are associated with return trip charges, they include labor
only.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 9
REQUEST NO.7: Please provide an analysis for the cost of the underground
return trip charge and:
a. How the Company determines the appropriate size of the crew for each
type of service attachment;
b. How the Company determines the amount of trip time;
c. How the Company calculated the labor cost and what is included in that
cost for each type of service attachment;
d. If applicable, please provide the cost of each required material for each
type of service attachment;
e. A breakdown of costs showing how much of that price is travel cost, labor
cost, material cost, or any other costs that contribute to the final proposed cost.
RESPONSE TO REQUEST NO.7: Idaho Powets analysis on construction
costs is based on travel time, equipment, labor, and materials. The Company
construction costs are determined by the standard construction staffng level, the
equipment that is required to complete the work, the time it takes to safely finish a
project, and the travel time to the construction destination. Currently, Idaho Power uses
a computer softare system called "Asset Suite" to track material expenses and
determine construction costs.
a. The crew size for an underground return trip charge is 2 people,
determined by the Company's standard construction staffng leveL.
b. Travel time is based on average travel time, which is 0.5 hours. In urban
areas, traffc constraints may cause delays greater than 0.5 hours, and in rural areas,
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 10
remote location may require travel time greater than 0.5 hours, but, on average, travel
time to jobs is approximately 0.5 hours.
c. Labor cost is a combination of travel time and "wrench time." Wrench time
includes time spent doing the work and vehicles used. Wrench time has been
calculated using time and motion studies that have been integrated into our work order
construction and inventory system.
d. Underground return trip charges are for labor only.
e. No materials are associated with underground return trip charges, they
include labor only.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 11
REQUEST NO.8: Please provide an analysis for the cost of the underground
service attachment charge's base charge from underground, overhead including 2"
riser, and overhead including 3" riser, and for each service:
a. How the Company determines the appropriate size of the crew for each
type of service attachment;
b. How the Company determines the amount of trip time;
c. How the Company calculated the labor cost and what is included in that
cost for each type of service attachment;
d. If applicable, please provide the cost of each required material for each
type of service attachment;
e. A breakdown of costs showing how much of that price is travel cost, labor
cost, material cost, or any other costs that contribute to the final proposed cost.
RESPONSE TO REQUEST NO.8: Idaho Powets analysis on construction
costs is based on travel time, equipment, labor, and materials. The Company
construction costs are determined by the standard construction staffng level, the
equipment that is required to complete the work, the time it takes to safely finish a
project, and the travel time to the construction destination. Currently, Idaho Power uses
a computer softare system called "Asset Suite" to track material expenses and
determine construction costs.
a. The crew size for an underground service is a 2 person crew, determined
by the Company's standard construction staffng leveL.
b. Travel time is based on average travel time, which is 0.5 hours. In urban
areas, traffc constraints may cause delays greater than 0.5 hours, and in rural areas,
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 12
remote location may require travel time greater than 0.5 hours, but, on average, travel
time between jobs is approximately 0.5 hours.
c. Labor cost is a combination of travel time and "wrench time." Wrench time
includes time spent doing the work and vehicles used. Wrench time has been
calculated using time and motion studies that have been integrated into our work order
construction and inventory system.
d. Underground services are connections only, with no materials. Overhead
materials are as follows:
2" pole riser material list includes: 30 feet of 1/0 underground cable, 2"
pvc conduit, 2" metal conduit, and a
number of nuts, bolts, brackets, and
washers.
3" pole risér material list includes: 30 feet of 4/0 underground cable, 3"
pvc conduit, 3" metal conduit, and a
number of nuts, bolts, brackets, and
washers.
e.Underground services Labor
2" pole riser material list includes: Travel and vehicles
Materials
Labor
Total
3" pole riser material list includes: Travel and vehicles
Materials
Labor
Total
$ 41.00
$ 53.80
$211.49
$141.71
$407.00
$ 53.80
$354.50
$149.70
$558.00
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 13
REQUEST NO.9: Please provide an analysis for the cost of the distance charge
(per foot) for Company installed facilities with 1/0 underground cable, 4/0 underground
cable, and 350 underground cable, and for each service:
a. How the Company determines the appropriate size of the crew for each
type of service attachment;
b. How the Company determines the amount of trip time;
c. How the Company calculated the labor cost and what is included in that
cost for each type of service attachment;
d. If applicable, please provide the cost of each required material for each
type of service attachment;
e. A breakdown of costs showing how much of that price is travel cost, labor
cost, material cost, or any other costs that contribute to the final proposed cost.
RESPONSE TO REQUEST NO.9: Idaho Powets analysis on construction
costs is based on travel time, equipment, labor, and materials. The Company
construction costs are determined by the standard construction staffng level, the
equipment that is required to complete the work, the time it takes to safely finish a
project, and the travel time to the construction destination. Currently, Idaho Power uses
a computer softare system called "Asset Suite" to track material expenses and
determine construction costs.
a. The crew size for an underground service is a 2 person crew, determined
by the Company's standard construction staffng leveL.
b. Travel time is based on average travel time, which is 0.5 hours. In urban
areas, traffic constraints may cause delays greater than 0.5 hours, and in rural areas,
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 14
remote location may require travel time greater than 0.5 hours, but, on average, travel
time to jobs is approximately 0.5 hours.
c. Labor cost is a combination of travel time and "wrench time." Wrench time
includes time spent doing the work and vehicles used. Wrench time has been
calculated using time and motion studies that have been integrated into the work order
construction and inventory system.
d. Underground service cable charges are for material only, based on 100
feet, and are as follows:
e.1/0 service includes:
4/0 service includes:
350 service includes:
1/0 Wire
4/0 Wire
350 Wire
Travel and vehicles
Materials
Labor & Equipment
Overhead Service Differential
Total
Travel and vehicles
Materials
Labor & Equipment
Overhead Service Differential
Total
Travel and vehicles
Materials
Labor & Equipment
Overhead Service Differential
Total
$173.26
$229.91
$415.70
$134.50
$173.26
$568.37
-:$155.00::
$721.13
$134.50
$229.91
$569.65
-:$155.00::
$799.06
$134.50
$415.70
$603.95
-:$155.00::
$999.15
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY -15
REQUEST NO. 10: Please provide an analysis for the cost of the distance
charge (per foot) for customer provided trench and conduit with 1/0 underground cable,
4/0 underground cable, and 350 underground cable, and for each service:
a. How the Company determines the appropriate size of the crew for each
type of service attachment;
b. How the Company determines the amount of trip time;
c. How the Company calculated the labor cost and what is included in that
cost for each type of service attachment;
d. If applicable, please provide the cost of each required material for each
type of service attachment;
e. A breakdown of costs showing how much of that price is travel cost, labor
cost, material cost, or any other costs that contribute to the final proposed cost.
RESPONSE TO REQUEST NO. 10: Idaho Powets analysis on construction
costs is based on travel time, equipment, labor, and materials. The Company
construction costs are determined by the standard construction staffng level, the
equipment that is required to complete the work, the time it takes to safely finish a
project, and the travel time to the construction destination. Currently, Idaho Power uses
a computer softare system called "Asset Suite" to track material expenses and
determine construction costs.
a. The crew size for an underground service is a 2 person crew, determined
by the Company's standard construction staffng leveL.
b. Travel time is based on average travel time, which is 0.5 hours. In urban
areas, traffc constraints may cause delays greater than 0.5 hours, and in rural areas,
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 16
remote location may require travel time greater than 0.5 hours, but, on average, travel
time to jobs is approximately 0.5 hours.
c. Labor cost is a combination of travel time and "wrench time." Wrench time
includes time spent doing the work and vehicles used. Wrench time has been
calculated using time and motion studies that have been integrated into the work order
construction and inventory system.
d. Underground service cable charges are for material only, based on 100
feet, and are as follows:
e.1/0 service includes:
4/0 service includes:
350 service includes:
1/0 Wire
4/0 Wire
350 Wire
Travel and vehicles
Materials
Labor & Equipment
Overhead Service Differential
Total
Travel and vehicles
Materials
Labor & Equipment
Overhead Service Differential
Total
Travel and vehicles
Materials
Labor & Equipment
Overhead Service Differential
Total
$ 94.97
$151.58
$262.56
$ 53.80
$ 94.97
$217.79
-:$155.00::
$211.56
$ 53.80
$151.58
$215.23
-:$155.00::
$265.61
$ 53.80
$262.56
$245.64
-:$155.00::
$407.00
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 17
RE.QUEST NO. 11: Please provide data showing the number of vested interest
refunds made during years 1, 2, 3, 4, and 5 for 2007 and 2008.
RESPONSE TO REQUEST NO. 11: The table below outlines the number of
vested interest refunds made during years 1, 2, 3, 4, and 5 for 2007 and 2008.
Vested Interest
Refunds 2007 2008
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 18
REQUEST NO. 12: Please describe what is meant by "administrative burden" as
stated on p. 9, lines 20 - 21 of the testimony of Scott Sparks.
RESPONSE TO REQUEST NO. 12: The term "administrative burden" was used
to describe the Company's additional administrative labor and computer system
requirements for tracking vested interest refunds. In examining historical records, the
Company determined that vested interest refunds provided in the fifth year are typically
very small in terms of number of refunds provided and dollar amounts eligible for refund.
This modification was proposed in an attempt to reduce the time and administrative
labor costs associated with tracking refunds in the fifth year of recovery.
The response to this Request was prepared by Scott Sparks, Senior Pricing
Analyst, Idaho Power Company, in consultation with Barton L. Kline, Lead Counsel,
Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 19
REQUEST NO. 13: Please explain the process used by Idaho Power to qualify
construction contractors who perform line extension construction work for the Company.
In addition, please provide a list of contractors used by Idaho Power to perform line
extension work.
RESPONSE TO REQUEST NO. 13: Idaho Power requires a contractor to
complete the attached Contractor Qualification Assessment LGL 037. Upon receiving
the completed assessment, Idaho Power wil evaluate the information supplied on the
form, call references, research the contractor on the web, and perform a credit
evaluation, if there is published data available. Idaho Power is very familiar with most of
the contractors that perform line extension construction work in its service area.
Contractors that perform line extensions for Idaho Power are 4T Construction,
H&H Utility Contractors, Track Utilities, Eureka Construction, KV Construction, and
Western Line Builders. Aslett Electric and DAVCO Services have provided Idaho
Power line extension work for the last several years; however, both companies went out
of business in January of this year.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 20
REQUEST NO. 14: For line extension construction work performed by
contractors, please explain any competitive processes employed by the Company to
insure that the costs to construct line extensions is minimized.
RESPONSE TO REQUEST NO. 14: Idaho Power has developed a process to
allow it to competitively bid line extension contracts. Idaho Power uses two types of
contracts for line extensions. The first contract is a Master Construction Agreement for
the installation of overhead and underground distribution facilities. These contracts are
awarded for each Operations Center. Typically separate contractors have the overhead
and underground portion of the work. To competitively bid these contracts, Idaho
Power has developed bid units for the labor to install all electrical distribution equipment
by region. Idaho Power prefers to have at least six qualified bidders to bid on each
contract and these bids are evaluated based on estimated quantities of the work for
each bid unit to develop a total contract cost. The contracts are then awarded to the
lowest cost bidder. Due to the size and complexity of the contracts, the term is set for
either three or five years.
The second contract is the Joint Trench contract which is used for underground
line extensions that have more than one utility in the trench. The joint trench
contractors dig and backfll trenches, place conduits and transformer pads, and other
non-electrical equipment. Idaho Power works jointly with Intermountain Gas to qualify
contractors and develop bid unit costs by region. The contracts are competitively bid
and awarded similar to the above listed contracts, the only difference being that in areas
where the work is significant enough to warrant two contractors, the two lowest bidders
wil be selected. Once selected, Idaho Power and Intermountain Gas work jointly to
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 21
determine a cost for each trench unit, between the lowest cost bid and the second
lowest cost bid for the unit. Both contractors have to accept this pricing before the
contracts are fully executed. Setting these costs allows Idaho Power and Intermountain
Gas to compensate both contractors the same rates for the shared trench portion of the
work. The terms of these contracts are three years.
Idaho Power can negotiate extensions to these contracts based on current
economic conditions. Extensions to the contracts can only be negotiated if the
contracts have previously been competitively bid, and the contractor accepts no
increase, or an increase equal to or less than the Consumer Pricing Index ("CPI") for the
duration of the contract.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 22
REQUEST NO. 15: Please explain how Idaho Power determines whether a
contractor or its own construction crews wil be used for specific jobs. What percentage
of construction jobs are completed by contractors in typical years?
RESPONSE TO REQUEST NO. 15: Idaho Power determines whether a
contractor or its own construction crews wil be used for specific jobs by first assigning
Idaho Power crews. Contractors are only used for construction jobs in which Idaho
Power crews cannot meet predetermined startcompletion deadlines. The percentage
of construction jobs completed by contractors in 2007 was 40.6 percent. In 2008, the
percentage completed by contractors was 34.5 percent.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,.
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 23
REQUEST NO. 16: In instances where a contractor constructs a line extension,
are materials procured and provided by the contractor or by Idaho Power? Please
explain.
RESPONSE TO REQUEST NO. 16: When a contractor constructs a line
extension, most materials are procured and provided by Idaho Power. The exception
pertains to underground conduit, concrete enclosures, fiberglass bases, concrete pads,
fiberglass splice boxes, and concrete vaults, which contractors can procure and provide
through Idaho Power vendors at Idaho Power pricing levels. In other words, contractors
pay and charge back to Idaho Power at the same pricing levels incurred had Idaho
Power purchased and provided the same materials.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 24
REQUEST NO. 17: In instances where a contractor constructs a line extension,
are the overhead rates charged by Idaho Power different than if the work was
completed by Idaho Power's own crews? Please explain.
RESPONSE TO REQUEST NO. 17: No, the Company charges customers the
same regardless of whether Idaho Power crews or contract crews complete a line
extension.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 25
REQUEST NO. 18: Please explain any criteria or circumstances under which
Idaho Power solicits competitive bids for individual line extension jobs. Similarly,
explain any criteria or circumstances under which Idaho Power does not solicit
competitive bids for individual line extension jobs. Are there circumstances in which the
same contractor is retained to perform multiple jobs without bidding on each job
individually?
RESPONSE TO REQUEST NO. 18: Except when Idaho Power uses its own
crews, the Company solicits competitive bids for line extensions projects. Idaho Power
uses two types of contracts for line extension work as described in its Response to
Request No. 13, both of which are competitively bid. If there is a non-typical line
extension and the estimated hours for the project exceed 2000 hours, Idaho Power
would competitively bid the individual project. The only exception of soliciting
competitive bids would be for customer driven work that falls outside the scope or time
requirements of the two line extension contracts. Due to time constraints by the
customer, some portions of the work may be negotiated with the contractor.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 26
REQUEST NO. 19: Are customers requesting new line extensions biled an
amount based on a pre-construction estimate or based on a post-construction tabulation
of the actual costs incurred? If customers are biled based on estimates and there is a
difference between the estimate and the cost actually incurred, how is the difference
reconciled, either for each customer individually or for all customers collectively?
Explain any circumstances in which costs charged to the customer are adjusted based
on the actual costs incurred by the Company.
RESPONSE TO REQUEST NO. 19: Customers requesting new line extensions
are biled on a pre-construction estimate and not post-construction actual costs.
Differences between estimates and costs actually incurred are not reconciled or trued-
up between the customer and Idaho Power. Costs identified in pre-construction designs
as "unusual conditions" are the only costs that are reconciled and trued-up between the
customer and Idaho Power.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 27
REQUEST NO. 20: Please explain any competitive process used by Idaho
Power for purchasing major materials such as poles, transformers and conductor used
in line extension construction.
RESPONSE TO REQUEST NO. 20: Idaho Power Company uses a strategic
sourcing methodology for the procurement of major materials, including poles,
transformers, conductor, meters, hardware, and other related materials to ensure value
to the Company and customers, using a total cost of ownership ("TCO") model
approach. This process is a structured, fact-driven, collaborative methodology that
enables effective decision making regarding the sourcing of goods and services.
Please refer to the attached document to identify the steps included in strategic
sourcing, as well as the total cost of ownership modeL.
When purchasing other individual major equipment or specialized equipment, a
competitive process is stil used. This includes identifying a sourcing strategy,supplier
selection, and contract implementation.
The response to this Request was prepared by Deb Kunkler, Procurement
Manager, Idaho Power Company, in consultation with Barton L. Kline, Lead Counsel,
Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 28
REQUEST NO. 21: Please discuss how Idaho Power can reassure customers
that the costs charged to customers for line extensions are fair and reasonable.
Discuss any competitive procurement practices, bidding practices, contractor selection
methods, or other practices and processes that are employed by the Company.
RESPONSE TO REQUEST NO. 21: Please refer to Response to Request No.
20 to answer the question relating to competitive procurement and bidding practices.
Please refer to Responses to Requests Nos. 13 and 14 for contractor selection
and competitive bidding practices for line extension construction work.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 29
REQUEST NO. 22: If lot refunds in subdivisions are discontinued, please
explain whether Idaho Power believes it wil be at risk for recovering the cost of facilities
installed in the subdivision if the subdivision does not fully build out.
RESPONSE TO REQUEST NO. 22: No. Lot refunds represent additions to rate
base at the time of the refund. If refunds are eliminated, rate base no longer grows by
refunded amounts. Instead, a customer's contribution in aid of construction remains an
offset to rate base. If lot refunds are discontinued, the Company wil not be required to
refund any portion of installation costs related to subdivision work orders. In turn,
CIACs paid up front on work orders for facilities installed within subdivisions wil not be
offset by the costs of providing lot refunds.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 30
REQUEST NO. 23: Please provide a cost breakdown of $1,780 Standard
Terminal Facilities allowance for single phase line installations and service attachments
showing how much of that cost is the transformer, service conductor, etc.
RESPONSE TO REQUEST NO. 23: The single phase standard terminal
facilities allowance is based on three components: (1) travel time and vehicle costs for
a crew of five, (2) materials costs, and (3) labor and equipment costs. The breakdown
of this allowance is as follows:
Travel and Vehicle cost
Material Cost
Labor and Equipment
Total
$ 134.50
$1,435.39
$ 209.61
$1,779.50
The material components include:
Hot Line Clap - connect to the main line
Pole mount bracket for the switch
Switch (Non Load Break)
25 KVA Transformer
Transformerwiring and connectors
125 feet of #2 triplex service wire
Transformer ground rod
Power Meter
Total Material Cost
$ 16.78
$ 37.71
$ 89.95
$1,096.69
$ 46.80
$ 100.95
$ 22.23
$ 24.28
$1,435.39
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 31
REQUEST NO. 24: Similarly, please provide a cost breakdown of $3,803
Standard Terminal Facilities allowance for three phase installations and service
attachments showing how much of that cost is the transformer, service conductor, etc.
RESPONSE TO REQUEST NO. 24: The three phase standard terminal facilities
allowance is based on three components: (1) travel time and vehicle costs for a crew of
five, (2) materials costs, and (3) labor and equipment costs. The breakdown of this
allowance is as follows:
Travel and Vehièle cost
Material Cost
Labor and Equipment
Total
$ 269.00
$ 2,540.90
$ 993.48
$ 3,803.38
The material components include:
Hot Line Clap - connect to the main line
Wood cross arm for switch
Lighting arresters
Switch (Non Load Break)
Transformer mounting Wing
25 KVA Transformer
Transformer wiring and connectors
125 feet of #2 triplex service wire
Transformer ground rod
Power Meter
Total Material Cost
$ 50.34
$ 134.17
$ 142.65
$ 149.46
$ 233.94
$ 1,376.88
$ 98.76
$ 146.03
$ 22.23
$ 186.44
$2,540.90
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 32
REQUEST NO. 25: In the past, Idaho Power has used "time and motion" studies
as the basis for establishing some of the costs used in preparing line extension
estimates. Does Idaho Power stil use time and motion studies? If so, when was the
last study prepared that the Company is using as a basis for cost estimates? Please
provide a copy of pertinent sections of the study currently being used by Idaho Power.
RESPONSE TO REQUEST NO. 25: Idaho Power continues to use "time and
motion" studies to help determine costs for preparing line extension estimates. As new
material is introduced, labor hours are determined for the installation, removal, or
transfer of this material onto the system. The costs of all materials are constantly being
updated as part of the material purchasing process, with these updated costs being
reflected in the tools used to design projects. These costs are updated monthly by
Compatible Unit Codes. The Cost Estimate (Labor Hours) lists the updated material
costs as well as labor associated with each code. The Dictionary provides a description
of each code.
These documents contain confidential pricing information and are available upon
request at Idaho Power Company's corporate offces. Please contact Doug Jones at
388-2615 or Camila Victoria at 388-5821 to arrange a time to review the requested
materiaL.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 33
REQUEST NO. 26: Please provide a detailed explanation of the method used to
determine the 15.75 percent charge for general overheads. Please provide any
formulas, allocation factors and expenses used to calculate this percent. For expenses,
please provide the associated FERC account numbers.
RESPONSE TO REQUEST NO. 26: General overheads are costs that are
incurred in direct support of the Company's construction process, but would be very
diffcult to directly associate to a particular construction job. These costs are
accumulated and allocated back to individual construction jobs based on a cost
allocation methodology. It is Idaho Power Company's policy, per 18 CFR Part 101
Electric Plant Instructions (4) (2007), to apply overheads to construction work orders.
Each cost center that is involved in the construction process has a separate
overhead work order that employees charge to for general support tasks that benefit
both operations and the construction process. These overhead work orders are
allocated between O&M and capital based on yearly studies of the actual split between
direct O&M and direct capital work performed by the cost center. Through the use of
these overhead work orders, the Company determines the amount each cost center has
contributed to overheads. The actual overheads are compared to budgeted overheads
on a monthly basis by leaders to assure that only reasonable and prudent costs are
charged to the accounts. The budgeted overheads are part of our annual corporate
budget process and have the same scrutiny as O&M and capitaL.
To determine the overhead rate, the Company accumulates the budgeted
overheads and groups them by contributing functional area and divides them by the
budgeted construction projects, during the same period by work order type to create the
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 34
overhead rate. The Company has a separate overhead rate for Co-Generation,
Stations, Transmission Lines, and Distribution Lines. The Distribution Line rate applies
to the Rule H work orders. The rate is monitored monthly to assure that actual
overheads and project costs match budgeted costs and adjustments made to the rate if
needed.
To calculate the existing rates, Idaho Power took Delivery Budgeted Construction
Overheads for June through December 2008 divided by Projected Capital Spending by
categqry (Co-Generation, Stations, Transmission Lines, and Distribution Lines) for June
through December 2008. The result was a projected overhead rate for each category.
Considering those rates, and adding or subtracting any under/over-applied balance,
new overhead rates were determined for the remainder of 2008. The 15.75 percent is
the calculated rate for the Distribution Lines Capital Category.
An example of the calculation for the 2009 overhead rate is as follows:
2009 Budget Distribution Capital $73,327,298
2009 Budget Distribution Overheads $11 ,484,220
Calculated Overhead Rate (Overheads 15.75% (rounded from .1566)divided by Capital)
All overhead charges are initially charged to FERC account 107 and move to
FERC account 101 when the work order they have been applied to is completed.
Overhead charges are applied to the work order monthly as a percentage of actual
charges to the work order.
The response to this Request was prepared by Tami White, Finance Team
Leader, Idaho Power Company, in consultation with Barton L. Kline, Lead Counsel,
Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 35
REQUEST NO. 27: Please explain how general overheads are currently
recovered.
RESPONSE TO REQUEST NO. 27: It is Idaho Power Company's policy, per 18
CFR Part 101 Electric Plant Instructions (4) (2007), to apply overheads to construction
work orders. Overhead costs are applied back to actual construction jobs based on the
methodology described in Response to Request No. 26.
When capital work orders are completed, the overhead charges that have been
allocated to those work orders are closed to the individual plant accounts based on the
propert units on the work order. At this point, the overheads become part of Idaho
Power's rate base.
The response to this Request was prepared by Tami White, Finance Team
Leader, Idaho Power Company, in consultation with Barton L. Kline, Lead Counsel,
Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 36
REQUEST NO. 28: When would Rule H overheads be expensed?
RESPONSE TO REQUEST NO. 28: When capital work orders are completed,
the overhead charges that have been allocated to those work orders are closed to the
individual plant accounts, based on the propert units on the work order. The overhead
charges become part of the cost of the asset and are expensed as depreciation
expense over the useful life of the asset.
The response to this Request was prepared by Tami White, Finance Team
Leader, Idaho Power Company, in consultation with Barton L. Kline, Lead Counsel,
Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 37
REQUEST NO. 29: How are engineers' wages for Rule H projects recorded?
Which FERC accounts are used? Which accounts are expensed or capitalized?
RESPONSE TO REQUEST NO. 29: Either distribution designers or engineers
may design a Rule H project. In both cases, their direct wages for designing Rule H
projects are recorded to each individual Rule H project through a direct charge to the
capital work ordeL FERC account 107 is used to record the charges made to a project
work order. Distribution designers or engineers also charge certain general support
time such as safety meetings to work orders that allocate costs to O&M and capital
overheads based on yearly studies of the actual split between direct O&M and direct
capital work performed by the cost centeL The actual overheads are compared to
budgeted overheads on a monthly basis by leaders to assure that only reasonable and
prudent costs are charged to the accounts. The overhead costs are then allocated back
to the capital projects worked on by the distribution designer or engineer. The overhead
allocation process allows costs appropriately charged to the capital work orders to be
included efficiently, rather than requiring the distribution designer or engineer to allocate
a half hour safety meeting to all the projects they have been working on during a
particular period of time. When the project is completed, the charges get capitalized
and moved to FERC account 101. The distribution designets or engineets wages,
direct charged to Rule H projects, are then expensed as the project is depreciated over
its useful life. When the Company charges the customer for engineering fees, the
collection of those fees reduces the total cost of the work ordeL However, wages and
expenses of leaders and support staff needed to support the distribution designers and
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 38
engineers may not be directly charged to the work order; therefore, the overhead
charges are needed to apply those charges to the work orders.
The response to this Request was prepared by Tami White, Finance Team
Leader, Idaho Power Company, in consultation with Barton L. Kline, Lead Counsel,
Idaho Power Company.
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 39
REQUEST NO. 30: On a prior audit, Staff was told that some wood poles might
be reused as temporary service poles. How are these poles accounted for in inventory?
What is the charge for these poles under Rule H?
RESPONSE TO REQUEST NO. 30: For a pole to be eligible for re-use,
Company policy dictates the pole be less than 5 years old and in new condition. The
pole remains in inventory and is charged at the current price determined by size and
pole class. Salvaged poles and new poles are charged at the same rate.
The response to this Request was prepared under the direction of Scott Sparks,
Senior Pricing Analyst, Idaho Power Company, in consultation with Barton L. Kline,
Lead Counsel, Idaho Power Company.
DATED at Boise, Idaho this 11th day of February 2009.
~~~,~,~L"A NORDSTOM
Attorney for Idaho Power Company
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 40
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on this 11th day of February 2009 I served a true and
correct copy of IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY upon the
following named parties by the method indicated below, and addressed to the following:
Commission Staff
Kristine A. Sasser
Deputy Attorney General
Idaho Public Utilities Commission
472 West Washington
P.O. Box 83720
Boise, Idaho 83720-0074
-.Hand Delivered
U.S. Mail
_ Overnight Mail
FAX
-K Email kris.sasser~puc.idaho.gov
Building Contractors Association of
Southwestern Idaho
Jason S. Risch
Jeremy P. Pisca
RISCH PISCA, PLLC
LAW AND POLICY
407 West Jefferson Street
Boise, Idaho 83702-6049
Hand Delivered
--U.S. Mail
_ Overnight Mail
FAX
~ Email irisch~rischpisca.com
ipisca~rischpisca.com
City of Nampa AND
Association of Canyon County
Highway Districts
Matthew A. Johnson
Davis F. VanderVelde
WHITE PETERSON GIGRA Y
ROSSMAN NYE & NICHOLS, P.A.
5700 East Franklin Road, Suite 200
Nampa, Idaho 83687
Hand Delivered
--U.S. Mail
_ Overnight Mail
FAX
~ Email miohnson~whitepeterson.com
dvandervelde~whitepeterson.com
Kroger Co.
Michael L. Kurt
Kurt J. Boehm
BOEHM, KURTZ & LOWRY
36 East Seventh Street, Suite 1510
Cincinnati, Ohio 45202
Hand Delivered
--U.S. Mail
_ Overnight Mail
FAX
~ Email mkurtz~BKLlawfirm.com
kboehm~BKLlawfirm.com
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 41
Kevin Higgins
Energy Strategies, LLC
Parkside Towers
215 South State Street, Suite 200
Salt Lake City, Utah 84111
Hand Delivered
-lU.S. Mail
_ Overnight Mail
FAX
-- Email khiggins~energystrat.com
¡l ~. lJ. (v~iš. NõrdSiròm1(
IDAHO POWER COMPANY'S RESPONSE TO THE COMMISSION
STAFF'S FIRST PRODUCTION REQUEST TO IDAHO POWER COMPANY - 42
BEFORE THE
IDAHO PUBLIC UTiliTIES COMMISSION
CASE NO. IPC-E-08-22
IDAHO POWER COMPANY
RESPONSE TO STAFF'S
PRODUCTION REQUEST NO. 13
An IDACORP company
Dear Contractor:
The increasingly competitive natue oftoday's electrical utilty industry has challenged
Idaho Power Company to ensure that our contractors are adding value to our end product.
Consequently, we have developed a Contractor Qualification Assessment to assist us in
evaluating a potential contractor's capabilities. Any contractor who desires to be considered for
work for Idaho Power Company must first complete and submit this assessment form, a copy of
which is attched.
After completing the Contract Qualification Assessment form, please retur it and all
certificates of insurance requested in the assessment to:
Idaho Power Company
Attn: Contract Manager
10790 Franin Road
Boise, ID 83709
The information submitted is for Idaho Power Company's internal use only and wil be
kept strictly confidentiaL. Completion of this form does not obligate Idaho Power Company to
request proposals from or contract for the services of any contractor.
Than you for your interest in performing services for Idaho Power Company.
Sincerely,
Contract Management Deparment
Delivery Business Unit
Idaho Power Company
attchment
Contractor Qualification Assessment LGL 037 7/18/08 1221 W. Idaho St. (83702)
P.O. Box 70
Boise, 10 83707
Contractor Qualification Assessment
Delivery Business Unit An IDACORP Company
Contractor Information
Company Name Phone Number
Address City State ¡ZiP
E-mail Address Service Area
Type of Work Performed
Contacts (Please list owner, president, and other key personnel in your organization we may contact.)
First Contact Title Phone Number E-mail Address
Second Contact Title Phone Number E-mail Address
Third Contact Title Phone Number E-mail Address
Fourth Contact Title Phone Number E-mail Address
Equal Employment Agreement and Certification
Contractor agrees to comply with all applicable equal employment opportunity, small business, and affrmative action laws
and regulations to which Contractor is subject and agrees to execute and deliver such documents as may be required to
effect or to evidence such compliance. Any contract entered into with Contractor by Idaho Power Company incorporates by
reference the EEO clauses of E.O. 11246, as amended, and 41 CFR 60-741.5 subpart A and 41 CFR 60-250.5 subpart A.
Wil you comply with this statement during performance on all contracts with Idaho Power Company? 0 Yes 0 No
Conflict of Interest
1. Does your company, or any principal with your company, have a financial, business, or personal relationship with Idaho
Power Company, IDACORP, Inc., or any subsidiaries of IDACORP, Inc. or with any employees of these companies,
which may qualify as a conflict of interest? 0 Yes 0 No
2; If Yes, please explain:
Contractor Qualification Assessment LGL 037 7/18/08 -1-IPC
Financial Background
1. If requested, wil you provide Idaho Power with an audited standard financial statement?DYes D No
2. Wil you authorize a credit history review?DYes D No
3. Please list bank references:
Insurance
1. The following insurance requirements are the minimum required for all contractors working for Idaho Power Company.
Depending on the services to be performed, additional coverages may be required.
A. Workers' Compensation Insurance shall be at statutory limits and Employer's Liability Insurance shall have the
following limits:
Bodily Injury by Accident
Bodily Injury by Disease
Bodily Injury by Disease
$100,000 each accident
$500,000 policy limit
$100,000 each employee
B. Automobile Liability Insurance covering all owned, non-owned, or hired automobiles used in connection with the
work. Bodily Injury Liabilty and Propert Damage Liability limits shall not be less than $1,000,000 each accident
Combined Single Limit. An endorsement shall be issued naming Idaho Power Company as an additional
insured.
C. Commercial General Liability Insurance with limits not less than $1,000,000 each occurrence combined single
limit. The insurance shall include coverage for Premises and Operations, Broad Form Propert Damage,
Contractual Liability, Owner's and Contractor's Protective Liability, Products and Completed Operations
(extended for at least 12 months after completion of the operations) and Personal Injury. The policy shall also
include coverage for the hazards commonly referred to as the XCU (explosion, collapse and underground). An
endorsement shall be issued naming Idaho Power Company as an additional insured.
D. Any of Contractor's subcontractors of any tier shall be required by Contractor under the terms of any subcontract
to obtain like insurance coverage to that specified in Paragraphs A, B, C, and E of this Section.
E. Insurance coverage described in Paragraphs A, B, C and D above shall be carried with Insurance companies
satisfactory to Idaho Power Company. Contractor shall provide to Idaho Power Company a Certificate of
Insurance evidencing such Insurance coverage and naming Idaho Power Company as an additional insured on
the coverage described in Paragraphs Band C. These certificates shall contain a provision that coverage
afforded shall not be canceled or changed until at least thirty (30) days prior written notice has been given to
Idaho Power Company.
F. If requested by Idaho Power Company, Contractor shall provide a copy of the original insurance policies and all
endorsements.
2. Does your company maintain the above insurance coverages? DYes D No
3. Please return with this completed assessment Certificates of Insurance meeting subparagraph 1.E above.
(NOTE: Assessments submitted without Certificates of Insurance wil not be considered further.)
Contractor Qualification Assessment LGL 037 7/18/08 -2-¡PC
Personnel/Skil Level
1. List the positions you employ at your company and number of employees at each leveL.
Position No. of Employees Position No. of Employees
2. List the experience, certification, skil levels, and/or training your company requires for each position listed above:
Experience of Company
1. List the type of services your company can provide and the years of experience you have with each type of service:
Services Years
2. List the jobs currently in progress on which your company is working:
Contract Key Contacts
Job Name & Location Value Description and Phone Numbers
Contractor Qualification Assessment LGL 037 7/18/08 -3-IPC
3. List the last five jobs your company has completed:
Contract Key Contacts
Job Name & Location Value Description and Phone Numbers
The following sections must be completed by all construction contractors.
E ui ment (List type, quantity, and age of the following equipment. Attach additional pages as necessary.)
1. Major Equipment (bucket trucks, tractors, loaders):
2. Communication Equipment (mobile phones, two-way radios, cellular phones):
3. Equipment & Tools (List all other available equipment & tools that are applicable for the type of work applied for.):
Contractor Qualification Assessment LGL 037 7/18/08 -4-IPC
Safety
1. Does a comprehensive safety program exist?DYes 0 No
2. Name of person responsible for ensuring that safety program requirements are implemented and maintained:
Training
1. Does a comprehensive training program exist?DYes 0 No
2. Name of person responsible for ensuring that training program requirements are implemented, completed, and
maintained:
3. List additional training conducted by your company that is not required by federal, state, and local regulations.
Training Program Name Date Implemented Hours Mandatory
DYes DNo
DYes DNo
DYes DNo
I certify the answers given above to be tre and accurate
and provide the same with the intention that Idaho Power
Company rely on the same in assessing Contractor's
qualifications.
Signature of Contractots Authorized Representative
Date
Contractor Qualification Assessment LGL 037 7118/08 -5-IPC
BEFORE THE
IDAHO PUBLIC UTiliTIES COMMISSION
CASE NO. IPC-E-08-22
IDAHO POWER COMPANY
RESPONSE TO STAFF'S
PRODUCTION REQUEST NO. 20
St
r
a
t
e
g
i
c
S
o
u
r
c
i
n
g
P
r
o
c
e
s
s
St
r
a
t
e
g
i
c
S
o
u
r
c
i
n
g
e
m
p
l
o
y
s
a
s
t
r
u
c
t
u
r
e
d
,
f
a
c
t
-
d
r
i
v
e
n
,
c
o
l
l
a
b
o
r
a
t
i
v
e
m
e
t
h
o
d
o
l
o
g
y
t
h
a
t
en
a
b
l
e
s
e
f
f
e
c
t
i
v
e
d
e
c
i
s
i
o
n
m
a
k
i
n
g
r
e
g
a
r
d
i
n
g
t
h
e
s
o
u
r
c
i
n
g
o
f
g
o
o
d
s
a
n
d
s
e
r
v
i
c
e
s
.
A.
S
o
u
r
c
i
n
g
A
p
p
r
o
a
c
h
B.
C
a
t
e
g
o
r
y
D
a
t
a
Co
l
l
e
c
t
i
o
n
C.
S
u
p
p
l
y
C
h
a
i
n
C
o
s
t
s
D.
S
t
a
k
e
h
o
l
d
e
r
s
E.
S
o
u
r
c
i
n
g
T
e
a
m
F.
T
e
a
m
K
i
c
k
o
f
f
1
A.
E
x
t
e
r
n
a
l
M
a
r
k
e
t
An
a
l
y
s
i
s
B.
I
n
t
e
r
n
a
l
En
v
i
r
o
n
m
e
n
t
C.
I
n
t
e
r
n
a
l
S
u
p
p
l
y
Ch
a
i
n
A
n
a
l
y
s
i
s
D.
S
u
p
p
l
i
e
r
I
D
a
n
d
1s
t
S
c
r
e
e
n
A.
C
a
t
e
g
o
r
y
S
o
u
r
c
i
n
g
St
r
a
t
e
g
y
B.
B
o
u
n
d
a
r
i
e
s
a
n
d
Go
a
l
s
Id
e
n
t
i
f
i
c
a
t
i
o
n
C.
R
F
P
D
e
v
e
l
o
p
m
e
n
t
A.
R
F
P
a
n
d
2
n
d
Sc
r
e
e
n
B.
S
e
l
e
c
t
i
o
n
C
r
i
t
e
r
i
a
C.
3
r
d
S
u
p
p
l
i
e
r
Sc
r
e
e
n
i
n
g
D.
N
e
g
o
t
i
a
t
i
o
n
s
E.
S
u
p
p
l
i
e
r
S
e
l
e
c
t
i
o
n
F.
R
e
c
o
m
m
e
n
d
a
t
i
o
n
to
M
a
n
a
g
e
m
e
n
t
an
d
A
p
p
r
o
v
a
l
A.
F
i
n
a
l
A
g
r
e
e
m
e
n
t
B.
A
g
r
e
e
m
e
n
t
Co
m
m
u
n
i
c
a
t
i
o
n
C.
S
u
p
p
l
i
e
r
De
v
e
l
o
p
m
e
n
t
In
i
t
i
a
t
i
o
n
Th
e
T
o
t
a
l
C
o
s
t
O
f
Ow
n
e
r
s
h
i
p
(
T
C
O
)
M
o
d
e
l
St
r
a
t
e
g
i
c
S
o
u
r
c
i
n
g
f
o
c
u
s
e
s
o
n
T
C
O
,
t
h
e
p
r
e
s
e
n
t
v
a
l
u
e
o
f
a
l
l
c
o
s
t
s
a
s
s
o
c
i
a
t
e
d
w
i
t
h
a
p
r
o
d
u
c
t
,
se
r
v
i
c
e
o
r
c
a
p
i
t
a
l
e
q
u
i
p
m
e
n
t
t
h
a
t
a
r
e
i
n
c
u
r
r
e
d
o
v
e
r
i
t
s
e
x
p
e
c
t
e
d
l
i
f
e
.
Pr
o
d
u
c
t
s
Se
r
v
i
c
e
s
TC
O
M
o
d
e
l
Ca
p
i
t
a
l
E
q
u
i
p
m
e
n
t
In
t
e
r
n
a
l
Co
s
t
s
Ex
t
e
r
n
a
.
J
Co
s
t
s
1
Th
e
a
m
o
u
n
t
p
a
i
d
f
o
r
t
h
e
p
r
o
d
u
c
t
,
s
e
r
v
i
c
e
o
r
c
a
p
i
t
a
l
e
q
u
i
p
m
e
n
t
Pu
r
c
h
a
s
e
C
o
s
t
s
Al
l
c
o
s
t
s
a
s
s
o
c
i
a
t
e
d
w
i
t
h
b
r
i
n
g
i
n
g
t
h
e
p
r
o
d
u
c
t
,
s
e
r
v
i
c
e
o
r
c
a
p
i
t
a
l
eq
u
i
p
m
e
n
t
t
o
t
h
e
c
u
s
t
o
m
e
r
'
s
l
o
c
a
t
i
o
n
(
s
o
u
r
c
i
n
g
,
a
d
m
i
n
i
s
t
r
a
t
i
o
n
,
fr
e
i
g
h
t
,
a
n
d
t
a
x
e
s
)
.
Pr
o
d
u
c
t
s
-
A
l
l
co
s
t
s
a
s
s
o
c
i
a
t
e
d
wi
t
h
c
o
n
v
e
r
t
i
n
g
in
t
o
a
f
i
n
i
s
h
e
d
pr
o
d
u
c
t
a
n
d
su
p
p
o
r
t
i
n
g
i
t
th
r
o
u
g
h
i
t
s
u
s
a
b
l
e
li
f
e
.
Se
r
v
i
c
e
s
-
A
l
l
c
o
s
t
s
as
s
o
c
i
a
t
e
d
w
i
t
h
th
e
p
e
r
f
o
r
m
a
n
c
e
of
t
h
e
s
e
r
v
i
c
e
t
h
a
t
ar
e
n
o
t
i
n
c
l
u
d
e
d
i
n
th
e
p
u
r
c
h
a
s
e
pr
i
c
e
.
Ca
p
i
t
a
l
E
q
u
i
p
-
A
l
l
co
s
t
s
a
s
s
o
c
i
a
t
e
d
wi
t
h
o
p
e
r
a
t
i
n
g
t
h
e
eq
u
i
p
m
e
n
t
t
h
r
o
u
g
h
it
s
l
i
f
e
.
Al
l
c
o
s
t
s
i
n
c
u
r
r
e
d
w
h
e
n
a
p
r
o
d
u
c
t
,
s
e
r
v
i
c
e
,
o
r
c
a
p
i
t
a
l
e
q
u
i
p
m
e
n
t
re
a
c
h
e
s
t
h
e
e
n
d
o
f
i
t
s
u
s
a
b
l
e
l
i
f
e
,
n
e
t
o
f
a
m
o
u
n
t
s
r
e
c
e
i
v
e
d
f
r
o
m
th
e
s
a
l
e
o
f
r
e
m
a
i
n
i
n
g
p
r
o
d
u
c
t
o
r
t
h
e
e
q
u
i
p
m
e
n
t
.
(
o
b
s
o
l
e
s
c
e
n
c
e
,
di
s
p
o
s
a
l
,
c
l
e
a
n
u
p
,
a
n
d
p
r
o
j
e
c
t
t
e
r
m
i
n
a
t
i
o
n
)
.
2