HomeMy WebLinkAbout20080328Staff to IPC 1.pdfSCOTT WOODBURY
DEPUTY ATTORNEY GENERAL
IDAHO PUBLIC UTILITIES COMMISSION
472 WEST WASHINGTON STREET
PO BOX 83720
BOISE, IDAHO 83720-0074
(208) 334-0320
BARNO. 1895
Idaho PU~/ic Utilties Commission
Office of the Secretary
RECEIVED
MAR 28 2008
Boise, Idaho
Street Address for Express Mail:
472 W. WASHINGTON
BOISE, IDAHO 83702-5983
Attorney for the Commission Staff
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY TO AMEND
SCHEDULE 72 - INTERCONNECTIONS TO
NON-UTILITY GENERATION.
)
) CASE NO. IPC-E-08-5
)
)
) FIRST PRODUCTION
) REQUEST OF THE
) COMMISSION STAFF TO
) IDAHO POWER COMPANY
)
The Staff of the Idaho Public Utilties Commission, by and through its attorney of record,
Scott Woodbury, Deputy Attorney General, requests that Idaho Power Company (Company;
IPC) provide the following documents and information as soon as possible, but no later than
FRIDAY, APRIL 18,2008.
This Production Request is to be considered as continuing, and Idaho Power Company is
requested to provide, by way of supplementar responses, additional documents that it or any
person acting on its behalf may later obtain that wil augment the documents produced.
For each item, please indicate the name of the person(s) preparing the answers, along
with the job title of such person(s) and the witness who can sponsor the answer at hearng.
FIRST PRODUCTION REQUEST TO
IDAHO POWER COMPANY 1 MARCH 28, 2008
REQUEST NO.1: Please provide a copy of the study referred to on page 2 of the
Company's Application that served as the basis for proposing a maximum deposit requirement
for Facilities Studies Agreements equal to 5% of the total project costs capped at $30,000.
DATED at Boise, Idaho, this ~ of March 2008.
~~cott Woodbur I
Deputy Attorney General
Technical Staff: Rick Sterling
i:umisc:prodreq/ipce08.5swrps prod req i
FIRST PRODUCTION REQUEST TO
IDAHO POWER COMPANY 2 MARCH 28, 2008
CERTIFICATE OF SERVICE
I HEREBY CERTIFY THAT I HAVE THIS 28TH DA Y OF MARCH 2008,
SERVED THE FOREGOING FIRST PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER, IN CASE NO. IPC-E-08-5, BY MAILING
A COPY THEREOF, POSTAGE PREP AID, TO THE FOLLOWING:
BARTON L KLINE
DONOV AN E WALKER
IDAHO POWER COMPANY
PO BOX 70
BOISE ID 83707-0070
E-MAIL: bkline!ßidahopower.com
dwalker!ßidahopower .com
JOHNRGALE
IDAHO POWER COMPANY
PO BOX 70
BOISE ID 83707-0070
E-MAIL: rgale!ßidahopower.com
\~~.\(~
SECRETARY
CERTIFICATE OF SERVICE