Loading...
HomeMy WebLinkAbout20070705IPC to Staff 1-14.pdfBarton L. Kline (ISB No. 1526) Lisa D. Nordstrom (ISB No. 5733) IDAHO POWER COMPANY 1221 West Idaho Street O. Box 70 Boise, 1083707 Tel: 208-388-2682 Fax: 208-338-6936 " ,!: .: ~, ,, '" , ,:,;, , , Attorneys for Idaho Power Company BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASSIA GULCH WIND PARK LLC AND CASSIA WIND FARM LLC Case No. IPC-06- Complainants IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFFIDAHO POWER COMPANY Respondent COMES NOW , Idaho Power Company ("Idaho Power" or "the Company ) and, in response to the First Production Request of the Commission Staff to Idaho Power Company dated June 19, 2007, herewith submits the following information: IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page REQUEST FOR PRODUCTION NO.What is the significance of interconnection requests submitted during the period January 1 , 2005 through June 29 2006 as discussed in Section 4 on page 3 of the Settlement Stipulation? How does Idaho Power propose to handle interconnection requests made after the period listed above? RESPONSE TO REQUEST FOR PRODUCTION NO. Idaho Power received in excess of 390 MW of generation interconnection requests for locations in the Magic Valley throughout the 2005 calendar year. Idaho Power was aware that transmission constraints in the 230 and 138 kV transmission system west of Midpoint Substation would not be able to accommodate all of the requested capacity. It was determined that a single system impact study demonstrating the total capability of the transmission system would be more efficient than performing studies for each project. This system impact report was finalized on June 8, 2006 and demonstrated that 305 MW could accommodated with transmission network improvements. Idaho Power selected the cluster study window end date of June 29, 2006 based on the 390 MW of interconnection requests coupled with the study capacity of 305 MW. It is not intended to exclude other interconnection requests that would have an impact on the computation of costs and construction of facilities associated with the Twin Falls "cluster . Idaho Power proposes to handle interconnection requests within the "cluster" made after the June 29, 2006 date in the same manner as those projects falling within the above-referenced timeframe. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 2 The response to this request was prepared by David Angell , Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline , Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 3 REQUEST FOR PRODUCTION NO.Please provide a map showing Idaho Power s transmission system in the Magic Valley area, the capacity ratings and voltage of each transmission line , the locations of each project requesting transmission service locations of relevant substations , and the proposed point of interconnection for each project. Please designate on the map the geographic boundaries for which future projects will require transmission upgrades and may be subject to similar redispatch requirements. RESPONSE TO REQUEST FOR PRODUCTION NO. To avoid the significant adverse results arising out of the public disclosure requirements of FERC's Standards of Conduct and the Critical Infrastructure Protection Standards , promulgated by NERC, Staff has agreed to withdraw this request and obtain the requested information by way of Staff's statutory audit authority. The response to this request was prepared by Barton L. Kline, Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 4 REQUEST FOR PRODUCTION NO.Please provide a copy of the Generation Interconnection System Impact Study referred to in Section 5 of page 3 of the Settlement Stipulation. RESPONSE TO REQUEST FOR PRODUCTION NO. The generation system impact study named "Up to 305 MW of New Generation on the 138 kV Transmission System in the Twin Falls Area" is enclosed. The response to this request was prepared by David Angell, Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline, Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION ST AFF, Page 5 REQUEST FOR PRODUCTION NO.Please provide a copy of the Redispatch Study" referred to in Section 5 of page 3 of the Settlement Stipulation. RESPONSE TO REQUEST FOR PRODUCTION NO. The generation impact study report named "Up to 330 MW of New Generation on the 138 kV Transmission System in the Twin Falls Area" is enclosed. The response to this request was prepared by David Angell , Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline, Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 6 REQUEST FOR PRODUCTION NO.: Will it be necessary for all projects in the queue to agree to be subject to redispatch? If not, what cost would be assessed projects that decline to be subject to redispatch , assuming Idaho Power makes transmission upgrades only sufficient to accommodate all projects in the queue if all projects are subject to redispatch? Please provide an example similar to the format used in Exhibit B showing capacity and cost allocations if some projects agree to redispatch and others do not. RESPONSE TO REQUEST FOR PRODUCTION NO. , Idaho Power will not require all projects in the generation interconnection queue or the cluster group to be subject to "Cassia Redispatch." In order to provide an example of project cost allocation for the scenario of some projects committing to Cassia Redispatch while others do not, the transmission network upgrades identified in both system impact studies will be combined as shown in Table 1. The allocation of project capacity to the network upgrade phases for projects 114 through 136 committing to Cassia Redispatch , while 154 through 170 do not, is shown in Table 2 and the allocation of project cost per phase is shown in Table 3. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 7 Table 1: Transmission upgrade projects with only a portion of projects committing to Cassia Redispatch Total CapacityPhase Available (MW) Phase Capacity MW added CostProject Upper Salmon Series Reactor 290,000 Lucky Peak Series Reactor 290 000 Lower Malad Series Reactor 153 290,000 Midpoint 1/3 Series Capacitor Bypass 156 100,000 King 230/138 Transformer 235 $ 10,320,000 Reconductor Midpoint Dram 230 kV line 305 170 $ 47 525 000 Total $ 58 815 000 Table 2: Project capacity allocation by network upgrade phase with projects 114 to 136 committing to Cassia Redispatch and 154 to 170 do not , allocation assumingII . tproJec s comp e e cons ruc Ion Project No.Capacity Phase I Phase 2 Phase 3 Phase 4 Phase 5 Phase 6 Total 114 116 10.10. 117 101.21.10. 128 10.10.101. 134 18.18.10. 135 18. 136 154 155 11.11. 157 11. 158 159 170 Totals 304.79.4 68.304. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 8 Table 3: Project cost allocation by network upgrade phase with projects 114 to 136 committing to Cassia Redispatch and 154 to 170 do not, allocation assuming projects complete construction Project No.Capacity Phase I Phase 2 Phase 3 Phase 4 Phase 5 Phase 6 Total 114 116 10. 117 101.$290,000 $137 627 427 627 128 10.$ 51 610 610 134 18.$ 92 898 898 135 $ 7 864 $ 100,000 $ 2 001 612 $ 2 109,476 136 $ 8,318,388 $ 8,318,388 154 $ 1 586,006 $ 1 586 006 155 11.$ 8,012 776 $ 8,012 776 157 $12,412 217 $12,412 217 158 $12,412 217 $12,412 217 159 $12,412 217 $12 412 217 170 689,568 689,568 Totals 304.$290 000 $290 000 $ 100,000 $10 320,000 $47 525 000 $58,525,000 The response to this request was prepared by David Angell, Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline , Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION ST AFF, Page 9 REQUEST FOR PRODUCTION NO.Please discuss how the proposed resdispatch differs from the remedial action schemes discussed earlier in the negotiations. Why is Idaho Power willing to now consider redispatch when it appeared earlier in the negotiations to insist that a remedial action scheme was only a temporary solution? RESPONSE TO REQUEST FOR PRODUCTION NO. The Cassia Redispatch aligns the cluster projects with other network generation that are capable of being dispatched by Idaho Power transmission grid operations. The grid operations personnel direct network generation to increase or decrease output in response to transmission system outages to reduce transmission line overloads. This ability to control the output of generators differs from a remedial action scheme in that it relies on the Idaho Power transmission system operator to determine when and how much "Cassia Redispatch" is required to reduce transmission line overloads. Idaho Power has built its transmission system such that no transmission overloads occur for the outage of a single transmission element (N-1).This performance is required by the North American Energy Reliability Corporation (NERC). Remedial action schemes are generally deployed for multiple element outages or where fast action is required to maintain system voltage or stability. A remedial action scheme employs sensors at substations that detect abnormal conditions, such as line or equipment outages , and respond with predetermined actions, such as generation tripping. Remedial actions schemes typically detect outages and initiate the remedial action in the order of tenths of a second in order to maintain the transmission system integrity. The transmission system overloads identified in the system impact studies IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 10 require action within thirty minutes which is sufficient time for the transmission system operator to respond with appropriate generation dispatch. The response to this request was prepared by David Angell , Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline, Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 11 REQUEST FOR PRODUCTION NO.Please describe the circumstances under which redispatch would occur.Please provide an estimate of the timing, magnitude, and frequency of when redispatCnls expec d to occur In fFi uture. RESPONSE TO REQUEST FOR PRODUCTION NO. The Cassia Redispatch will occur when an outage occurs on a transmission element listed in Exhibit C to the Settlement Stipulation coincident with high cluster group generation and high transmission flows across the west-of-Midpoint transmission system.Idaho Power is restricted by FERC Standards of Conduct from providing estimates of future transmission utilization , however, we are able to average outage and outage duration by transmission class (from years 2002 through 2006), shown in Table , and past ten year outage performance of the transmission lines listed in Exhibit C to the Settlement Stipulation , as shown in the Table 5 below. Transmission Line Class ~ --,. - 138-161 kV 230kV Table 4: Years 2002 to 2006 av~rClg~tr?nsmissionline outagehi~tory ! Ave. Outage Duration i Av..~~ 9.~!~- g~~" p.~r~,t~~E - i__J?~r ,!, ~~!.J~J_r:'ute!;t19 274 1 .17 1389 Table 5: Ten year average transmission line outage history for lines initiating Cassia Redispatctl- Transmission Line ---.._-,-, , - - ,- ~(?!~~.. ~e."rl~tl~..~i5:ip..~irlt :f!_ ?",_?-- ?Q~,!_.._- ",,--,, ..".. "---"--"-"---"""""--"'",,_.........._..---- , Boise Ben~t1:~Jgp.9lQt:f!~"~9.kV ----,, ", -,,-,,--'.._- " Boise Bench-Rattlesnake 230kV ,,------- - - ---- ..-- Danskin-Elmore-Mountain Home Junction 1 138KV --"---"-"..,---,,..-....,,..-..--.. DRAM~"iqpC?.irl!--??9.~'!--_.. ..,,.. ..,- Lower Malad Power Plant-Mountain Home Junction 1 138kV --- .. fy'!idp()irlt-R?ttlesnake 230kV LJPp~r --SalrT1()rlJcSc.2-Mountain Home Junction 1 138kV Ave. Out~-- g~-- s perYear "W_--- ""'--,--",, - ,..-..,------ ,., -" IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 12 The response to this request was prepared by David Angell , Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline, Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 13 REQUEST FOR PRODUCTION NO.Please explain the rationale for Section , Part C of the Settlement Stipulation. Does Idaho Power anticipate making a request for the Commission to authorize it to construct alternative transmission facilities that would eliminate or reduce the costs of Network Upgrades? RESPONSE TO REQUEST FOR PRODUCTION NO. Idaho Power has no current plans to request authorization from the Commission to construct alternative transmission facilities that would eliminate or reduce the cost of the network upgrades specified in Tables B-1 and 8-4 of Exhibit 8 to the Stipulation. However, as the Commission is well aware, Idaho Power is experiencing rapid customer and load growth and transmission planning must remain flexible. All of the network upgrade facilities described in Tables B-1 and B-4 of Exhibit 8 to the Stipulation are facilities that would not have been constructed but for the interconnection of the QF facilities. The cited provision acknowledges that if that situation changes in the near term, a revised cost allocation allocator could be presented to the Commission for its review and approval. The response to this request was prepared by David Angell, Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline , Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 14 REQUEST FOR PRODUCTION NO.: What is the basis for requiring a 50% mechanical availability guarantee in Section 14 of the Settlement Stipulation , rather than some higher percentage such as the 85% that is being proposed in Case No. IPC-07- 04? RESPONSE TO REQUEST FOR PRODUCTION NO. The fifty percent (50%) amount is the product of the settlement negotiations. Because the Cassia Projects and the vast majority of other QF projects included in Table B-2 of Exhibit B to the Stipulation are "grandfathered", they currently have no mechanical availability guarantee in their Firm Energy Sales Agreement , but are subject to the 90%/110% performance band requirement. If the Commission agrees that the cost sharing and other protocols in the Stipulation should be used as a template for future QF interconnections where network upgrades are required , and if the Commission eliminates the 90%/110% performance band in the IPC-07-4 case , Idaho Power believes that it would be reasonable for future QF contracts to include a higher percentage mechanical availability guarantee to qualify for transmission refunds. The response to this request was prepared by Barton L. Kline, Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 15 REQUEST FOR PRODUCTION NO.1 0:How is Idaho Power proposing to determine mechanical availability in hours when there is little or no wind? How will Idaho Power determine the capacity available to generate in each hour when the wind is blowing? Please provide numerical examples to illustrate your answers. RESPONSE TO REQUEST FOR PRODUCTION NO. 10: Idaho Power proposes to determine mechanical availability by utilizing a self- certification system in which the QF developer certifies the percentage of time the facility was mechanically available and provides records for wind speed , forced outages and generation at the individual QF site to verify the mechanical availability of the project on a monthly basis. QFs currently report the nature and duration of forced outages and routine maintenance. The Interconnection Agreement would also include provisions that would give Idaho Power the right to audit the books and records of the QF if a question arises as to the accuracy of the QF'sself-certification and the data provided by the QF to support its self-certification. The response to this request was prepared by David Angell, Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline, Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 16 REQUEST FOR PRODUCTION NO. 11:Please explain why Idaho Power believes it is appropriate to pay full , published avoided cost rates for power received for projects subject to redispatch. If redispatch is necessary at a time when Idaho Power is unable to meet load using its own resources and must make off-system purchases at costs above avoided cost rates , does Idaho Power believe that it should pay those higher costs and impose no penalty on the projects being redispatched? RESPONSE TO REQUEST FOR PRODUCTION NO. 11: First it must be recognized that the Company currently pays full , published avoided cost rates (based on the cost of a dispatchable CCCT) for power received from QF projects even though the QF projects are not dispatchable like the proxy CCCT. This is particularly true for wind generation projects. Second, current pro forma Firm Energy Sales Agreements contain provisions allowing interruptions of energy delivery and purchase for line maintenance and under emergency conditions on Idaho Power s transmission and distribution system. Under the redispatch protocol that will be mandated in amended QF agreements, QF project generation will be limited to a nont-to-exceed set-point if conditions occur on Idaho Power s system that could result in damage to the system and/or degraded service to customers. However, under current QF contracts, there is no obligation on the part of the QF to install equipment and facilities that will allow Idaho Power to limit the generation from the QF project. Currently, all Idaho Power can do if a transmission system emergency occurs is to totally disconnect the QF generation from the system. As a result, the ability to set a not-to-exceed generation limit is an incremental improvement over the current system when transmission overloading occurs. With IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 17 redispatch , the Company may still be able to keep a portion of the QF project generation available to carry load. As a result, while the vast majority of QF projects are not dispatchable and do not provide firm energy as that term is defined by utilities during adverse transmission events the energy from QF projects with "not-to-exceed dispatch" capability are somewhat "firmer" than older QF projects. Finally, Idaho Power acknowledges that paying full avoided costs for power received from QF projects that are subject to redispatch will result in higher costs to customers when compared to a requirement that 100% of the cost of the transmission upgrades be funded by the QF projects to avoid the need for redispatch. Counterbalanced against the potentially higher costs to customers is the reality that if 100% of transmission upgrade costs are allocated to the QF developers , it is likely that the QF projects will not be economically viable. Use of the redispatch protocol as proposed in the Stipulation substantially reduces the cost of transmission upgrades and will certainly improve the economics of most QF wind projects. At the same time , the fact that the Stipulation requires QF developers to (1) provide a significant portion of the network upgrade costs as a nonrefundable contribution and (2) advance half of the cost of the network upgrade subject to refund will provide a strong locational price signal to QF developers and incent them to make economically rational decisions as to where they site QF projects. While the settlement agreement memorialized in the Stipulation may not achieve full customer cost neutrality, it does mitigate the cost impact on customers and provides an opportunity for small QF developers to move forward with renewable resource projects. Development of these renewable resource projects may allow the Company to avoid or defer future , potentially IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 18 more expensive intermittent resource projects identified in the Company s Integrated Resource Plan. For all of these reasons Idaho Power believes that the compromise worked out and memorialized in the Stipulation provides a balanced approach that is fair to customers and is consistent with a public policy to encourage the development of renewable resources in the State of Idaho. The response to this request was prepared by Barton L. Kline, Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 19 REQUEST FOR PRODUCTION NO. 12 Please explain in detail what criteria have been used in determining the available transmission capacity for each phase under the redispatch scenario , as opposed to the available transmission capacity under no redispatch. Please cite and provide a copy of any reliability criteria used as a basis for determining capacity under the redispatch scenario. RESPONSE TO REQUEST FOR PRODUCTION NO. 12: The studies for both the no-dispatch and Cassia Redispatch were evaluated for the transmission system performance under a single element outage (N-1) conditions. The difference in the studies was the allowable transmission system overload. The no- dispatch generation was evaluated at equipment continuous thermal ratings and Cassia Redispatch generation was evaluated at equipment 30-minute emergency ratings 115% of continuous thermal ratings. During both studies, the phased transmission system improvements were added to the power flow case and the generation representing the cluster projects was increased until any transmission element current reached 100% (115% for Cassia Redispatch) of the elements continuous thermal rating. The below criteria is an excerpt from the Appendix A of the "Up to 330 MW of New Generation on the 138 kV Transmission System in the Twin Falls Area. The following acceptability criteria were used in the power flow analysis to determine the acceptability of the alternatives: Loadings on transmission lines and transformers should not exceed 115% of the continuous rating, immediately following any N-1 outage. Loading on the Midpoint 230 kV series capacitors should not exceed 135% of the continuous rating, immediately following any N-1 outage. These loadings levels of 115% on transmission lines and transformers and 135% on Midpoint series capacitors correspond to IPC's 30 minute emergency equipment ratings. Any loadings IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 20 immediately following an N-1 outage , less than the minute emergency rating is acceptable. Loadings which are less than the 30 minute emergency equipment ratings but greater than the equipment continuous ratings, must be reduced to the continuous ratings by generation curtailments, re-dispatch , or someother operating procedure. Any remedial action schemes(RAS) or other transmission switching, must be judged to be reasonable before the alternatives performance can be deemed acceptable. The continuous rating of equipment is assumed to be the normal thermal rating of the equipment. This rating will be as determined by the manufacturer of the equipment or as determined by Idaho Power. Less than or equal to 100% of continuous rating for transmission lines and transformers is acceptable. Less than or equal to 110% of continuous rating for the Midpoint 230 kV series capacitors is acceptable. Transmission voltages, under normal operating conditions are maintained within plus or minus 5% (0.05 per unit) of nominal. Therefore, voltages greater than or equal to 0. pu voltage and less than or equal to 1 .05 pu voltage are acceptable. The stable operation of the transmission system requires an adequate supply of volt-amperes reactive (VARs) to maintain a stable voltage profile under both steady-state and dynamic system conditions. An inadequate supply of V ARs will result in voltage decay or even collapse under the worst conditions. Idaho Power designs its system to integrate Network Resources at full capability during specified outage conditions. The response to this request was prepared by David Angell, Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline , Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 21 REQUEST FOR PRODUCTION NO. 13 What level of subscription would be required before Idaho Power would proceed with a phase of transmission upgrade? For example, referencing table B-6 of Exhibit B , would all projects 135-170 have to commit before Phase 5 would be initiated? If projects 235 and 136 committed, but projects 154- 170 did not, for example , would Idaho Power initiate Phase 5 and allocate all of the costs for Phase 5 to projects 135 and 136? RESPONSE TO REQUEST FOR PRODUCTION NO. 13: Idaho Power has determined that any project of a size greater than allowed in Schedule 84 may be subject to transmission network upgrades. Therefore , the level of subscription that would require Idaho Power to proceed with a transmission upgrade phase is any project capacity greater than 100 kW that is not supported in a prior phase. Only one project, not all , in a phase would have to commit to construction before Idaho Power would commence constructing that phase.If a single project requires a transmission upgrade phase , then that phase cost will be solely allocated to that project. Of course , that broad rule would have to be applied realistically. A 1 MW or 2 MW project , by itself, would not necessarily trigger the need to install a $10 million transformer adding 174 MW of capacity. In that unique situation , other measures would be considered to address system reliability issues. The response to this request was prepared by David Angell, Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline , Senior Attorney, Idaho Power Company. IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 22 REQUEST FOR PRODUCTION NO. 14 If a lower project in the queue is ready to proceed to construction much sooner than higher projects in the queue , how will its share of costs be allocated? For example, referring to Table B-6 of Exhibit B, what costs would be allocated to project number 170 if it was ready to proceed with construction and none of the other projects in Phase 5 were ready to proceed? RESPONSE TO REQUEST FOR PRODUCTION NO. 14: Idaho Power has required all projects in the cluster group to provide network transmission facility study deposits in order to maintain queue position. Idaho Power will require each project to commit to their allocated phase costs at a date following a Commission order on this Settlement Stipulation. The phase cost allocation will be adjusted at that time based on the commitment of the projects.Projects that interconnect after this cluster group will be subject to the terms of this settlement stipulation. In response to the hypothetical posed in this request, referring to Table B-6 of Exhibit B , if project number 170 proceeds to construction prior to the other projects in Phase 5, project 170 would be required to provide seventy-five percent (75%) of $68 300. Fifty percent (50%) of that amount would be subject to refund. Project 170 would also be required to post liquid security in an amount sufficient to cover the cost Idaho Power would reasonably incur if the remaining projects in Phase 5 decided not to proceed.Realistically, if only project 170 decided to proceed it would not be reasonable to expect a 1 MW project to trigger the installation of the King 230/138 transformer adding 174 MW of capacity at a total cost of more that $10 million. A more realistic scenario would be for projects 157, 158 and 159 to proceed ahead of projects IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 23 136, 154 and 155. Projects 157-159 would be required to pay 75% of the approximately $4 million associated with their share of Phase 5 and to post liquid security for $6 million or the remaining portion of the full , approximately $10 million amount. As the other projects in Phase 5 completed construction, the level of projects 157-159'liquid security amount would be reduced proportionately. The response to this request was prepared by David Angell , Manager, Delivery Planning, Idaho Power Company, in consultation with Barton L. Kline, Senior Attorney, Idaho Power Company. DATED at Boise, Idaho , this day of July, 2007. BARTON L. KLINE Attorney for Idaho Power Company IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 24 CERTIFICATE OF SERVICE I HEREBY CERTIFY that on this day of July, 2007, I served a true and correct copy of the within and foregoing document upon the following named parties by the method indicated below, and addressed to the following: Commission Staff Donovan Walker Deputy Attorney General Idaho Public Utilities Commission 472 W. Washington (83702) O. Box 83720 Boise, Idaho 83720-0074 -X- Hand Delivered - U.S. Mail Overnight Mail FAX Email Donovan.walker(g) puc.idaho.qov Industrial Customers of Idaho Power Peter J. Richardson , Esq. Richardson & 0' Leary 515 N. 2ih Street O. Box 7218 Boise, Idaho 83702 Hand Delivered --.2LU.S. Mail Overnight Mail FAX..x Email peter(g) richardsonandolearv.com Don Reading Ben Johnson Associates 6070 Hill Road Boise, Idaho 83702 Hand Delivered --.2L U.S. Mail Overnight Mail FAX..x Email dreadinq (g) mindsprinq.com R. Blair Strong Paine Hamblen et al 717 W. Sprague Ave. Spokane , VVA 99201 Hand Delivered --.2LU.S. Mail Overnight Mail FAX..x Email blair.stronq (g) painehamblen.com David J. Meyer Senior Vice President Avista utilities O. Box 3727 Spokane , VVA 83702 Hand Delivered --.2LU.S. Mail Overnight Mail FAX..x Email dmever(g)avistacom.com Ronald K. Arrington Assoc. Chief Counsel John Deere Credit 6400 NW 86th Street Johnston , IA 50131 Hand Delivered --.2L U.S. Mail Overnight Mail FAX Email arrinqtonronaldk(g) iohndeere.com IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF , Page 25 Brian Dickman Dean S. Brockbank Rocky Mountain Power 201 S. Main Street, Suite 2300 Salt Lake City, UT 84111 Hand Delivered ~ U.S. Mail Overnight Mail FAX Email brian.dickman (Q) pacificorp.com dean. brockban k (Q) pacificorp. com Lawrence R. Lieb Exergy Development Group of Idaho LLC 910 W. Main Street, Suite 310 Boise, Idaho 83702 Hand Delivered~U.S. Mail Overnight Mail FAX Email G-w Barton L. Kline IDAHO POWER'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF THE COMMISSION STAFF, Page 26 BEFORE THE IDAHO PUBLIC UTiliTIES COMMISSION CASE NO. IPC-O7- IDAHO POWER COMPANY Response to Staff Request No. GENERA TOR INTERCONNECTION SYSTEM IMP ACT STUDY REPORT for Up to 305 MW of New Generation On the 138 kV Transmission System In the Twin Falls Area IDAHO POWER COMPANY, Transmission Provider TRANSMISSION SYSTEM FINAL REPORT June 8, 2006 1.0 Introduction Multiple new generation projects have contacted Idaho Power Company (IPe) to perfonn Generator Interconnection System Impact Studies for Network Resource Interconnection Service at 138 kV for the integration of new generation projects in the Twin Falls area This report documents the basis for and the results of this System Impact Study. It describes the backbone transmission system improvements required for Network Resource Interconnection Service of the new generation proposed, the study cases used, outage scenarios assumed and results of all work in the areas of concern. Summary The perfonnance of the backbone transmission system was evaluated to integrate up to 200 MW of new generation on the 138 kV transmission system in the Twin Falls area. Four phases of transmission system improvements are required to provide 200 MW of new generation Network Resource Interconnection Service. Phase #1: Phase #2: Phase #3: Phase #4: Install a 19 ohm 138 kV Series Reactor on the Upper Salmon-Mountain Home Junction 138 kV transmission line. Without this improvement, the outage of the Midpoint-Rattlesnake #2 230 kV transmission line results in an overload of the Upper Salmon-Mountain Home Junction 138 kV line with no new generation in the Twin Falls area. This improvement is necessitated by the transmission improvements associated with Generation Project 88 , and as a result should be funded by Idaho Power Company - Delivery. This phase of improvements is estimated at approximately $290 000. Install a 10.5 ohm 138 kV Series Reactor on the Lower Malad-Mountain Home Junction 138 kV transmission line. Without this improvement, the outage of the Midpoint-Rattlesnake #2 230 kV transmission line results in an overload of the Lower Malad-Mountain Home Junction 138 kV line with new generation levels greater than 7 MW in the Twin Falls area. This phase improvements is estimated at approximately $290 000. Fold the Midpoint-DRAM #1 230 kV transmission line into the King Substation and install a 230/138 kV 300 MV A transfonner. Without this improvement, the outage of the Midpoint-Rattlesnake #2230 kV transmission line results in an overload of the Upper Salmon-Mountain Home Junction 138 kV line with new generation levels greater than 60 MW in the Twin Falls area. This phase of improvements is estimated at $10 320 000. Reconductor/rebuild the King-DRAM #1 230 kV transmission line with a two conductor bundle of 795 MCM ACSR "Tern" conductor. This rebuilt line also must be folded into the Rattlesnake Substation north of Mountain Home. In addition, transmission modifications are required at the DRAM end of the line. Without this improvement, the outage of the Midpoint-Rattlesnake #2 230 kV transmission line results in an overload of the Upper Salmon- Mountain Home Junction 138 kV line with new generation levels greater than 135 MW in the Twin Falls area. This phase of improvements is estimated at $47 525 000. These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). The proposed cost allocation is subject to change, as more information is known. These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. Summary of Interconnection Requests Requests were made to Idaho Power Co. by multiple generation projects in the Twin Falls area to study the interconnection of the proposed generation projects to Idaho Power s transmission system at the 138 kV level for Network Resource Interconnection Service. Scope of Interconnection System Impact Study The Interconnection System Impact Study was done and prepared in accordance with the FERC Order 2003-, Standard Large Generator Interconnection Procedures, to provide a preliminary evaluation of the System Impact of the interconnection of the proposed large generating project to the Idaho Power transmission system. This study will only be concerned with the capabilities of the Idaho Power system to manage this new resource within the study area of the proposed interconnection. Description of Existing Transmission Facilities As shown in Figure 1 of Section 7., Midpoint Substation, north of Twin Falls, has three 230 kV lines that carry bulk power westward to the Boise area. Midpoint-DRAM #1 line utilizes single 715.5 MCM conductor and has a continuous rating of339 MV A. The Midpoint-Rattlesnake-Boise Bench #2 line utilizes a 2 conductor bundle of715.5 MCM. This line has a continuous rating of 677 MV A. The Midpoint-Boise Bench #3 line has similar conductors and the same rating as the Rattlesnake-Boise Bench #2 line. In the Mountain Home area, an additional 230 kV line is planned to carry bulk power westward. The Rattlesnake-Bennett Mountain-Danskin-Mora line utilizes single 1272 MCM conductors(478 MV A) from Rattlesnake-Bennet Mountain, single 1590 MCM conductors(550 MV A) from Bennet Mountain-Danskin, and a two conductor bundle of795 MCM(700 MV A) from Danskin-Mora. The Bennett Mountain-Danskin-Mora transmission lines are required for the interconnection of Generation Project 88 ; scheduled to be in-service Spring of 2008. In addition to the Midpoint to the Boise area 230 kV lines previously mentioned, there are two 138 kV circuits which can carry power from the Twin Falls area to the Mountain Home area. They are: King-Lower Malad-Mountain Home Junction 138 kV Line King-Upper Salmon-Mountain Home Junction 138 kV Line Generators located in the Twin Falls area which are intended to serve load growth in the Treasure Valley area, will be adding new incremental flows on top of existing committed east-to-west transactions across the Midpoint West transmission cutplane. This System Impact study will model approximately 1100 MW of transfers across the Midpoint West cutplane, prior to this proposed generator addition. For these studies, the flow level of the Midpoint west cutplane is defined as the sum of the flows on the following lines: . Midpoint-DRAM #1 230 kV line . Midpoint-Rattlesnake #2230 kV Line . Midpoint-Boise Bench #3 230 kV Line Lower Malad-Mountain Home Junction 138 kV Line Upper Salmon-Mountain Home Junction 138 kV Line Description of Configurations Studied Since the most limiting operating conditions are expected during heavy production on the upper and middle Snake and Boise River hydro plants, with heavy east-west transfers across the Idaho Power transmission system, the injection of the new generation at King 138 kV bus was inserted into a power flow case that would simulate committed (approximately 1100 MW) pre-contingency flows on the Midpoint West transmission path. Post-transient Study Results This Interconnection System Impact Study Report is for Network Resource Interconnection Service at 138 kV, for numerous proposed generation additions in the Twin Falls area. System transfers across the Midpoint West cutplane are modeled at approximately 1100 MW prior to the proposed transmission improvements or the proposed generators producing any power. Hydro generation production for the Boise & Snake plants, were modeled at heavy, but realistic levels. Ouput levels for the existing peakers at Danskin and Bennett Mountain were varied over their operating ranges as appropriate. N-O and N-l outage performance for the existing system are recorded. Generation levels at King 138 kV bus are increased until system thermal limits are reached during N-l outages. The most effective and cost-efficient transmission system improvements are then added to the model and King generation is then increased until system thermal limits are reached during N-l outages. Existin2 System The following one line diagram depicts the existing system with no outages. ~!EBCHI- " RlLSNK3" 'TISNX3E d.ointWest = 1111 A ~ , , "'A I -=-_ T:fI-?' ------.:::~ ---- ~A "\~~" 'I .'0"'"" ' O~m'" -------- ::1: """ .'000'"':CRON ,.. ~(II A " 0,A ~ " " ' \1~,.(g:;;, ,,!N A E~~ A ." "'PJ\~' ~( ~A, - ~ ;~~~;~~:;:- "'A ~., ~~=M "M 1-"" "\81""' WO(Y PI( ' ~ ./ ,- At~~~""~"'A ~~ --:ii .. "'A "'A A~ "'A """'" '"""'AU. 'm"',. " ' ~1~M;-;'~!~M Existing System - No Outages Figure 1 Existine System N-l Outaees The following one line diagram depicts the existing system with no new generation in the Twin Falls area, and the only N-I outage between Midpoint and the Mountain Home area that results in loadings above continuous thennal ratings. '?11~CH MOM ,., , ~ f """,... "\8I~"'I1'P"',.~YPl( ,~~ " ~Ii':.~ ~:~ OWMON-r ~ 'WANFAU. '" ""0"fi..,- - I, "", . ,.,~"" Mid.oint West = 1143 "t%1V- 1:-AU. "" ""'.'M "'" ~M Existing System - Midpoint-Rattlesnake #2 Outage Figure 2 Phase #1 Transmission Improvements The Midpoint Series Capacitor banks are capable of 110% of thennal rating on a continuous basis. As a result, only the Upper Salmon-Mountain Home Junction 103% overload is problematic. The most effective and cost-efficient transmission improvement to alleviate this overload is the installation of a series reactor on the Upper Salmon-Mountain Home Junction 138 kV line to better balance flows on the transmission network. The optimum size of the series reactor was detennined to be 19 ohms for the ultimate build-out of the transmission grid. Since this N-l overload condition pre-exists the addition of any new generation in the Twin Falls area, Idaho Power Company would take responsibility to fund this series reactor installation. The following one line diagram depicts the system with Phase #1 improvements added, no new generation in the Twin Falls area, and the same N-l as Figure 2. 8OlSEBOH """ Mid.oint West = ..1 "'DPO'", VI Q" ",,, KING ""'"~g~.~ ' 5I!ANF .:'-""~.",,'~. Phase #1 Transmission Improvements - Midpoint-Rattlesnake #2 Outage No New Generation Figure 3 ~"' ~'_d""""."ta""'t;"'"'"'. 'I:IfS",. :::~Sokron-"""ta.wo,,"a19o1ms Phase #2 Transmission Im rovements The following one line diagram depicts Phase #1 transmission improvements and 7 MW of new generation in the Twin Falls area, and the only N-l outage between Midpoint and the Mountain Home area that results in loadings above continuous thennal ratings. ?~1'i',CH ANDERS"' ANDE~" "" "" """ """ ~1\W"6~ ...~ tr\':"Jg~ OOWMON,"'8:\'\~ ~AU. . ~. ""',,~- Midpoint West = '85 MW Mln, """"-Lowe. MaIad """,, leatl'" " "" ",""""=e ~5 s~~!~v ~~v Phase #1 Transmission Improvements - Midpoint-Rattlesnake #2 Outage 7 MW of New Generation Figure 4 BURNS """ Mln, ",,",,-\Wel SoImon sen"""",'m' ,1lJO""" 190m. The most effective and cost-efficient transmission improvement to alleviate this overload is the installation of a series reactor on the Lower Malad-Mountain Home Junction 138 kV line to better balance flows on the transmission network. The optimum size of the series reactor was determined to be 10.5 ohms for the ultimate build-out of the transmission grid. This overload is the result of the addition of new generation in the Twin Falls area, and as a result the costs of this improvement will be allocated to new generation interconnections. The following one line diagram depicts the system with Phase #2 improvements added, 7 MW of new generation in the Twin Falls area, and the same N-l as Figure 4. BOISEBCH """ Midpoint West = 1825 MW VI """D ;'::' '4'~I""1'W~u. """ """"""" Phase #2 Transmission Improvements - Midpoint-Rattlesnake #2 Outage 7 MW of New Generation Figure 5 Phase #3 Transmission Improvements The following one line diagram depicts Phase #2 transmission improvements and 60 MW of new generation in the Twin Falls area, and the only N-l outage between Midpoint and the Mountain Home area that results in loadings above continuous thermal ratings. 001"'0.01", OOWMONT 0, '" SWA",AU. 51"" . -jfi-. Midpoint West = 11'1 KING ""'" .J'i "... _II~7- ~'" 4'~" ."1W"' ","i:I".M ","' i:I"." Mtn, Hare-lowa MaIad series reocto.' ,ffi5 "" 0. 10,5 ohms'I1'f"S,. Mtn, fbTIe-Uppeo-"'rronseriesreoctor" ,100,,"0. 19o1Yns Phase #2 Transmission Improvements - Midpoint-Rattlesnake #2 Outage 60 MW of New Generation Figure 6 To interconnect generation quantities greater than 60 MW will require additional transmission system improvements. The required system improvements are referred to as "Phase #3" and include folding the Midpoint-DRAM #1 230 kV transmission line into and back out of the King Substation and installing a 230/138 kV 300 MV A transformer. This overload is the result of the addition of new generation in the Twin Falls area, and as a result the costs of this improvement will be allocated to new generation interconnections. The following one line diagram depicts the system with Phase #3 improvements added, 60 MW of new generation in the Twin Falls area, and the same N-l as Figure 6. ,?!'.~CH Midlloint West = 11" MW MIDPOINT "",:, ~.. "I-AU. .... ""Mow "" ~..._. Mtn. _e-Low., ""'-'d ""~ ,."to, . ,055 pu or 10,5 ohmsffi"',., Mtn- Home-L\Jp.' s.koon ser~ ,""to. . ,100 pu or 19 ohms Phase #3 Transmission Improvements - Midpoint-Rattlesnake #2 Outage 60 MW of New Generation Figure 7 Phase #4 Transmission Improvements The following one line diagram depicts Phase #3 transmission improvements and 135 MW of new generation in the Twin Falls area, and the only N-l outage between Midpoint and the Mountain Home area that results in loadings above continuous thennal ratings. OOISE'CH01'" :~cP "'.M :'1f,l,~ SWANFA~ --- """:. -:t-- , Midlloint West = 1111 MW MIDPOINT "", "1T "" ,. AU. .... "" ......",,~..""'" '"'0" Mtn. Home-lo"", MaIod ""~ ,.,,"" . . 055 pu or 10,5 o/'ms Mtn. Home-uppe, s.rnon ser;es ,""tor' .100 pu or 19 oCrns Phase #3 Transmission Improvements - Midpoint-Rattlesnake #2 Outage 135 MW of New Generation Figure 8 To interconnect generation quantities greater than 135 MW will require additional transmission system improvements. The required system improvements are referred to a "Phase #4" and include reconductoring/rebuilding the King-DRAM #1 230 kV transmission line with a two conductor bundle of 795 MCM ACSR "Tern" conductor. This rebuilt line also must be folded into and back out of the Rattlesnake Substation north of Mountain Home. In addition transmission modifications are required at the DRAM end of the line. This overload is the result of the addition of new generation in the Twin Falls area, and as a result the costs of this improvement will be allocated to new generation interconnections. The following one line diagram depicts the system with Phase #4 improvements added, 135 MW of new generation in the Twin Falls area, and the same N-l as Figure 8. '?1~CH ~"'~!~"~~" 'tlf", Mtn, Hcrne-lo,,"' Maad so"", 'sactm " .055 PJ m 10,5 ohms Mtn, Hcme-Up,,", Sakron so"", ,eactm " .100 PJ m 19 otrns Phase #4 Transmission Improvements - Midpoint-Rattlesnake #2 Outage 135 MW of New Generation Figure 9 Phase #4 transmission improvements are capable of accomodating approximately 305 MW of new generation in the Twin Falls area. The following one line diagram depicts the system with Phase #4 improvements added, 305 MW of new generation in the Twin Falls area, and the loss of the King 230/138 kV transfonner. \'-- /' I M"""""" ',/1 ".. '4'~:r "1W.t~ MW""M.. - "" i::".,, ~~r "",d """,, reacle.'.O55 pu '" 10,5 am. 'm~ ::: ::::.."" samen """,, reacte. . .100 pu or 19 aim; Phase #4 Transmission Improvements - King 230/138 kV Xfmr Outage 305 MW of New Generation Figure 10 For generator interconnections in excess of 305 MW, the addition of a second 230/138 kV transformer at King is required. Fault Study Results Since this System Impact Study lumps all the proposed generation additions at King 138 kV bus, this Draft Report makes no attempt to address fault study concerns. Each proposed generation project will have to be evaluated individually based on its specific location. Transient Stability Study Results The Midpoint West Transmission System is not transient stability limited. Therefore, no transient stability studies were performed. 10.Conclusions The System Impact of interconnecting up to 200 MW of new generation in the Twin Falls area to Idaho Power s 138 kV transmission system was studied. Four phases of transmission system improvements are required to provide Network Resource Interconnection Service to 200 MW of new generation. Phase #1 is the installation of a 19 ohm 138 kV Series Reactor on the Upper Salmon-Mountain Home Junction 138 kV transmission line. This improvement corrects a N-l overload that exists before any new generation is added in the Twin Falls area. As a result, the estimated $290 000 cost of this improvement will be borne by Idaho Power Company. After approximately 7 MW of new generation is added, Phase #1 improvements are no longer sufficent. Phase #2 improvements require the installation of a 10.5 ohm 138 kV Series Reactor on the Lower Malad-Mountain Home Junction 138 kV transmission line. The 10- estimated $290 000 cost of this improvement should be allocated to new generator interconnections. Following the addition of approximately 60 MW of new generation, Phase #3 transmission improvements are required. Phase #3 involves folding the Midpoint-DRAM #1 230 kV transmission line into and back out of the King Substation and installing a 230/138 kV 300 MV A transfonner. The estimated $10 320 000 cost of this improvement should be allocated to new generator interconnections. Following the addition of approximately 135 MW of new generation, Phase #4 transmission improvements are required. Phase #4 involves reconductoring/rebuilding the King-DRAM #1 230 kV transmission line with a two conductor bundle of 795 MCM ACSR "Tern" conductor. This rebuilt line also must be folded into and back out of the Rattlesnake Substation north of Mountain Home. In addition, transmission modifications are requi~ed at the DRAM end of the line. The estimated $47 525 000 cost of this improvement should be allocated to new generator interconnections. Phase #4 transmission improvements are adequate to interconnect approximately 305 MW of new generation in the Twin Falls area before additional improvements are required. 11- BEFORE THE IDAHO PUBLIC UTiliTIES COMMISSION CASE NO. IPC-O7- IDAHO POWER COMPANY Response to Staff Request No. GENERA TOR INTERCONNECTION SYSTEM IMP ACT STUDY REPORT for Up to 330 MW of New Generation On the 138 kV Transmission System In the Twin Falls Area IDAHO POWER COMPANY, Transmission Provider TRANSMISSION SYSTEM DRAFT REPORT June 29, 2007 1.0 Introduction Multiple new generation projects have contacted Idaho Power Company (IPe) to perfonn Generator Interconnection System Impact Studies for Network Resource Interconnection Service at 138 kV for the integration of new generation projects in the Twin Falls area This report documents the basis for and the results of this System Impact Study. Previous studies were perfonned with these new generation projects being non-dispatchable. This System Impact Study will document the transmission system improvements required if the new generation projects are dispatchable. It describes the backbone transmission system improvements required for Network Resource Interconnection Service of the new generation proposed, the study cases used, outage scenarios assumed, redispatch requirements, and results of all work in the areas of concern. Summary The perfonnance of the backbone transmission system was evaluated to integrate up to 304 MW of new generation on the 138 kV transmission system in the Twin Falls area. Five phases of transmission system improvements are required to provide 304 MW of new generation Network Resource Interconnection Service. Phase #1: Phase #2: Phase #3: Install a 8 ohm 138 kV Series Reactor on the Upper Salmon-Mountain Home Junction 138 kV transmission line. Without this improvement, the outage of the Midpoint-Rattlesnake 230 kV transmission line results in an overload of the Upper Salmon-Mountain Home Junction 138 kV line with no new generation in the Twin Falls area. This improvement is necessitated by the transmission improvements associated with Generation Project 88 , and as a result should be funded by Idaho Power Company - Delivery. This phase of improvements is estimated at approximately $290 000. Install a 4 ohm 138 kV Series Reactor on the Mountain Home Junction-Lucky Peak 138 kV transmission line. Without this improvement, the outage of the Rattlesnake-Boise Bench 230 kV transmission line results in an overload exceeding the 30 minute emergency rating of the Mountain Home Junction- Lucky Peak 138 kV line with new generation levels greater than 42 MW in the Twin Falls area. This phase of improvements is estimated at approximately $290 000. Install a 12.35 ohm 138 kV Series Reactor on the Lower Malad-Mountain Home Junction 138 kV transmission line and increase the impedance of the existing Upper Salmon-Mountain Home Junction 138 kV Series Reactor to 26.2 ohms. Without this improvement, the outage of the Midpoint- Rattlesnake 230 kV transmission line results in an overload exceeding the 30 minute emergency rating of the Lower Malad-Mountain Home Junction 138 kV line with new generation levels greater than 94 MW in the Twin Falls area. This phase of improvements is estimated at approximately $290 000. Phase #4: Phase #5: Re-configure the Midpoint-Rattlesnake 230 kV series capacitor bank to allow 1/3 of the compensation to be bypassed via IPCo s SCADA system and install a "automatic 1/3 bypass scheme" for overloads exceeding series capacitor 30 minute emergency equipment rating of 135%. Without this improvement the outage of the Midpoint-Boise Bench #3230 kV transmission line results in an overload exceeding the 30 minute emergency rating of the Midpoint- Rattlesnake 230 kv Series Capacitor Bank with new generation levels greater than 153 MW in the Twin Falls area. This phase of improvements is estimated at approximately $100 000. Fold the Midpoint-DRAM #1 230 kV transmission line into the King Substation and install a 230/138 kV 300 MV A transfonner. Without this improvement, the outage of the Rattlesnake-Boise Bench 230 kV transmission line results in an overload exceeding the 30 minute emergency rating of the Mountain Home Junction-Lucky Peak 138 kV line with new generation levels greater than 156 MW in the Twin Falls area. This phase of improvements is estimated at $10 320 000. Once all five phases of improvements have been completed, the transmission system is capable of interconnecting approximately 330 MW of new generation in the Twin Falls area and serving them on a dispatchable basis. Section 8.0 of this report details the results of studies to quantify generation redispatch requirements following single contingencies on the transmission system. Reductions in the amount of generation which may be redispatched following contingencies, are possible by completing Phase #4 improvements earlier than required or funding optional modifications on the Midpoint-Boise Bench #3 series capacitor bank. These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). The proposed cost allocation is subject to change, as more infonnation is known. These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. Summary of Interconnection Requests Requests were made to Idaho Power Co. by multiple generation projects in the Twin Falls area to study the interconnection of the proposed generation projects to Idaho Power s transmission system at the 138 kV level for Network Resource Interconnection Service. Scope of Interconnection System Impact Study The Interconnection System Impact Study was done and prepared in accordance with the FERC Order 2003-, Standard Large Generator Interconnection Procedures, to provide a preliminary evaluation of the System Impact of the interconnection of the proposed large generating project to the Idaho Power transmission system. This study will only be concerned with the capabilities of the Idaho Power system to manage this new resource within the study area of the proposed interconnection. Description of Existing Transmission Facilities As shown in Figure 1 of Section 7., Midpoint Substation, north of Twin Falls , has three 230 kV lines that carry bulk power westward to the Boise area. Midpoint-DRAM #1 line utilizes single 715.5 MCM conductor and has a continuous rating of339 MV A. The Midpoint-Rattlesnake-Boise Bench #2 line utilizes a 2 conductor bundle of715.5 MCM. This line has a continuous rating of 677 MV A. The Midpoint-Boise Bench #3 line has similar conductors and the same rating as the Rattlesnake-Boise Bench #2 line. In the Mountain Home area, an additional 230 kV line is planned to carry bulk power westward. The Rattlesnake-Bennett Mountain-Danskin-Mora line utilizes single 1272 MCM conductors (478 MVA) from Rattlesnake-Bennet Mountain, single 1590 MCM conductors (550 MV A) from Bennet Mountain-Danskin and Danskin-Mora. The Bennett Mountain-Danskin-Mora transmission lines are required for the interconnection of Generation Project 88; scheduled to be in-service Spring of2008. In addition to the Midpoint to the Boise area 230 kV lines previously mentioned, there are two 138 kV circuits which can carry power from the Twin Falls area to the Mountain Home area. They are: King-Lower Malad-Mountain Home Junction 138 kV Line King-Upper Salmon-Mountain Home Junction 138 kV Line Generators located in the Twin Falls area which are intended to serve load growth in the Treasure Valley area, will be adding new incremental flows on top of existing committed east-to-west transactions across the Midpoint West transmission cutplane. This System Impact study will model approximately 1100 MW of transfers across the Midpoint West cutplane, prior to this proposed generator addition. For these studies, the flow level of the Midpoint west cutplane is defined as the sum of the flows on the following lines: . Midpoint-DRAM #1 230 kV line . Midpoint-Rattlesnake 230 kV Line . Midpoint-Boise Bench #3 230 kV Line Lower Malad-Mountain Home Junction 138 kV Line Upper Salmon-Mountain Home Junction 138 kV Line Description of Configurations Studied Since the most limiting operating conditions are expected during heavy production on the upper and middle Snake and Boise River hydro plants, with heavy east-west transfers across the Idaho Power transmission system, the injection of the new generation at King 138 kV bus was inserted into a power flow case that would simulate committed (approximately 1100 MW) pre-contingency flows on the Midpoint West transmission path. Post-transient Study Results This Interconnection System Impact Study Report is for Network Resource Interconnection Service at 138 kV, for numerous proposed generation additions in the Twin Falls area. System transfers across the Midpoint West cutplane are modeled at approximately 1100 MW prior to the proposed transmission improvements or the proposed generators producing any power. Hydro generation production for the Boise & Snake plants, were modeled at heavy, but realistic levels. Output levels for the existing peakers at Danskin and Bennett Mountain were varied over their operating ranges as appropriate. N-O and N-1 outage perfonnance for the existing system are recorded. For generation projects which will be dispatchable, generation levels at King 138 kV bus are increased until a transmission system component reaches its 30 minute emergency equipment ratings during N-1 outages. IPCo s 30 minute emergency equipment ratings are 115% of continuous thennal ratings on transmission lines and transfonners, and 135% on Midpoint series capacitors. The most effective and cost-efficient transmission system improvements are then added to the model and King generation is then increased until 30 minute emergency equipment ratings are reached during N-1 outages. Following any N-1 outage, transmission line and transfonner loadings which are less than or equal to the 30 minute emergency equipment ratings (115%), but greater than the equipment continuous ratings (100%), must be reduced to the continuous ratings by generation curtailments, redispatch, or some other operating procedure. For the Midpoint series capacitor banks, following any N-1 outage, similar corrective actions are required for loadings which are less than or equal to the 30 minute emergency equipment ratings (135%), but greater than the equipment 8 hour rating (110%). Various options to correct overloads following N -1 outages will be explored. System followinl! Generation Project 88 The following one line diagram depicts the transmission system with no outages, after the addition of Generation Project 88 and its associated improvements. '0""'"0". -::" "~8,'~' "(~\'",'~:: rP - .- "'~~ 1i~~ ~' ~ ' MldDolnt West = 1109 MW '~'"'.- '"'""~ ,"W "'" ,"'M .. ""'1~~" b System following Generation Project 88 - No Outages Figure 1 System followin2 Generation Project 88 with N-1 Outa2es The following one line diagram depicts the transmission system following the addition of Generation Project 88 and its associated improvements in 2008 , with no new generation in the Twin Falls area, and the only N-I outage between Midpoint and the Mountain Home area that results in loadings above continuous thermal ratings on the 138 kV transmission system. '0""'" '-"" MldDolnt West = 1038 MW 5~' '" '- 5wwm "".~~.."" .~~.. System following Generation Project 88 - Midpoint-Rattlesnake 230 kV Outage Figure 2 Phase #1 Transmission Im rovements The Midpoint Series Capacitor banks are capable of 110% of thermal rating for eight hours. A prolonged outage of the Midpoint-Rattlesnake 230 kV line will require a reduction of transfers across the Midpoint West cutplane to prepare for the next contingency. The overload of the Midpoint-Boise Bench #3 Series Capacitor is less than its 8 hour rating, and will be resolved with the reduction in transfers. As a result, only the overloads on the 138 kV lines between Upper Salmon and Mountain Home Junction are problematic. The most effective and cost- efficient transmission improvement to alleviate these overloads is the installation of a series reactor on the Upper Salmon-Mountain Home Junction 138 kV line to better balance flows on the transmission network. A series reactor with an impedance of .042 pu(8 ohms) alleviates the overloads. Since this N-I overload condition pre-exists the addition of any new generation in the Twin Falls area, Idaho Power Company will take responsibility to fund this series reactor installation. The following one line diagram depicts the system with Phase #1 improvements added, no new generation in the Twin Falls area, and the same N-I as Figure 2. n1' :'" MldDolnt West = 1038 MW 'WN' '" - 'w'","'- '-," 1- "' "" :~:'.."" :~:", Phase #1 Transmission Improvements - Midpoint-Rattlesnake 230 kV Outage NoN ew Generation Figure 3 Phase #2 Transmission Improvements The following one line diagram depicts Phase #1 transmission improvements and 42 MW of new generation in the Twin Falls area, and the only N-l outage that results in loadings at or above 30 minute equipment ratings. 'OISE"" '-"'"~"" ~82 ::"":~\'" M;: rP . - "' ~'"O!~;: rP '"0""", fi' "~ MldDolnt West = 1077 MW ~fiiJ-1 "'u ~ " ""1~:'" "" 1~:'" Phase #1 Transmission Improvements - Rattlesnake-Boise Bench #2 230 kV Outage 42 MW of New Generation Figure 4 The most effective and cost-efficient transmission improvement to alleviate this overload is the installation of a series reactor on the Mountain Home Junction-Lucky Peak 138 kV line to better balance flows on the transmission network. A series reactor with an impedance of .021 pu( 4 ohms) was detennined to be the optimal size considering future generation additions. This overload is the result of the addition of new generation in the Twin Falls area, and as a result the costs of this improvement will be allocated to new generation interconnections. The following one line diagram depicts the system with Phase #2 improvements added, 42 MW of new generation in the Twin Falls area, and the same N-l as Figure 4. Please note that generation redispatch will be required following this contingency to reduce loadings to levels which can be accommodated continuously. n1' :'"~" ~g,':;' "1',j'" !~. ~ r1' .' '" ~'"O !~:'.r1' """" Vi~ Midpoint West = 1075 fj/~r 'w "'~ ~ '. "'1~~" ""1~~" Phase #2 Transmission Improvements - Rattlesnake-Boise Bench #2 230 kV Outage 42 MW of New Generation Figure 5 Phase #3 Transmission Im rovements The following one line diagram depicts Phase #2 transmission improvements and 94 MW of new generation in the Twin Falls area, and the only N-l outage that results in loadings at or above 30 minute equipment ratings. - 7- ?b\" :'" MldDolnt West = 1106 'W" " - sw'""~ ..,....".. ""3~~,, "" 3~~" Phase #2 Transmission Improvements - Midpoint-Rattlesnake 230 kV Outage 94 MW of New Generation Figure 6 To interconnect generation quantities greater than 94 MW will require additional transmission system improvements. The most effective and cost-efficient transmission improvements to alleviate these overloads is the installation of a new series reactor on the Lower Malad- Mountain Home Junction 138 kV line and an increase in the impedance of the Upper Salmon- Mountain Home Junction 138 kV line series reactor. These improvements, referred to as Phase , will better balance flows on the transmission network. A Lower Malad-Mountain Home Junction series reactor impedance of .065 pu(12.35 ohms) was detennined to be the optimal size considering future generation additions. The impedance of the Upper Salmon-Mountain Home Junction series reactor should be increased to .138 pu(26.2 ohms). This overload is the result of the addition of new generation in the Twin Falls area, and as a result the costs of this improvement will be allocated to new generation interconnections. The following one line diagram depicts the system with Phase #3 improvements added, 94 MW of new generation in the Twin Falls area, and the same N-l as Figure 6. n\' ,:." MldDolnt West .. 1099 'WN' '" - 'w'""~ .., 'MW","'M'" "'" g~:", Phase #3 Transmission Improvements - Midpoint-Rattlesnake 230 kV Outage 94 MW of New Generation Figure 7 Phase #4 Transmission Improvements The following one line diagram depicts Phase #3 transmission improvements and 153 MW of new generation in the Twin Falls area, and the only N-l outage that results in loadings at or above 30 minute equipment ratings. ~"' f&i::1" "('oj'"~t:P " " M'" t~:t. t:P 'OWMO" ~"~:' 'W'""~ ---.:.fr. MldDolnt West .. 1172 MIOW" MLO'CO"' "tn,sex:- "",".." It...." "tn,scx:-""pu MLO'CO"''/' 0, Phase #3 Transmission Improvements - Midpoint-Boise Bench #3 230 kV Outage 153 MW of New Generation Figure 8 To interconnect generation quantities greater than 153 MW will require additional transmission system improvements. Ifnew generation levels exceed 153 MW, and the Midpoint-Boise Bench #3230 kV line opens, the series capacitor bank on the Midpoint-Rattlesnake 230 kV transmission line may exceed its 30 minute overload capability of 135%. Presently, both the 230 kV series capacitor banks at Midpoint are configured to operate either fully inservice or fully by-passed. The most effective and cost-efficient transmission improvement to alleviate this overload is the re-configuration of the Midpoint-Rattlesnake 230 kV series capacitor bank to allow one third of the compensation to be bypassed. In addition, an automatic control scheme should be employed to bypass one third of the series capacitor bank when appropriate system conditions are detected. The re-configuration of the series capacitor bank and the addition of the automatic control scheme is referred to as Phase #4. The following one line diagram depicts the system with Phase #4 improvements added, 153 MW of new generation in the Twin Falls area, and the same N-l as Figure 8. n\' ,:."~?' ~" A~8J~' ~',,\'" ~~:!.cP. ~," M:!.cP. - ",,"'", fi" ~~~ MldDolnt West a 1145 MW :;?j(~~~" ::~::~~:::::::: ""'01" -- "./1 Woo 'W" "'- 'WA"Au.B I_BOO 'OW"",B"'" !~~"~"",,""' 00.. .. 0_98.. 0_ ".."'" L"OO Phase #4 Transmission Improvements - Midpoint-Boise Bench #3 230 kV Outage 153 MW of New Generation Figure 9 Phase #5 Transmission Im rovements The following one line diagram depicts Phase #4 transmission improvements and 156 MW of new generation in the Twin Falls area, and the only N-l outage that results in loadings at or above 30 minute equipment ratings. 10- '01"""L".. ~",' m:::""(~\", ,.~~ .,p .. .. ~:"O '~.~.,p ,"0'"'"' Yi' "': -:iF .:. MldDolnt West = 1151 Phase #4 Transmission Improvements - Rattlesnake-Boise Bench #2 230 kV Outage 156 MW of New Generation Figure 10 To interconnect generation quantities greater than 156 MW will require additional transmission system improvements. Ifnew generation levels exceed 156 MW, and the Rattlesnake-Boise Bench #2230 kV line opens, the Mountain Home Junction-Lucky Peak 138 kV transmission line may exceed its 30 minute overload capability of 115%. The required system improvements are referred to as "Phase #5" and include folding the Midpoint-DRAM #1 230 kV transmission line into and back out of the King Substation and installing a 230/138 kV 300 MV A transformer. This overload is the result of the addition of new generation in the Twin Falls area, and as a result the costs of this improvement will be allocated to new generation interconnections. The following one line diagram depicts the system with Phase #5 improvements added, 156 MW of new generation in the Twin Falls area, and the same N-l as Figure 10. 11- 'OIS"'" "'"~"' r~IW "j'oj'";~::: cf' .- '" ~- '"O ;~:::cf' "'EO'", ~~~ jf- MldDolnt West = 1165 ~&. '" ~~O . ~.'I~:::, ----- - ::if- , ---- . . -'- . - '--- . --I-- -~-,.,..-~- GU'","~OM' """",BE"'" """" "'" . ~'O,"8", '-" pu 1-02pu 1-02", Phase #5 Transmission Improvements - Rattlesnake-Boise Bench #2 230 kV Outage 156 MW of New Generation Figure 11 Phase #5 transmission improvements are capable of accommodating approximately 330 MW of new generation in the Twin Falls area. The following one line diagram depicts the system with Phase #5 improvements added, 330 MW of new generation in the Twin Falls area, and the loss of the Midpoint-Rattlesnake 230 kV transmission line. At 330 MW of new generation in the Twin Falls area, two other outages also result in transmission system components loaded at their 30 minute emergency equipment ratings. """""'" MldDolnt West.. 1272 l'litiIJ ,,~- """"!~~""'" !~~";'( Phase #5 Transmission Improvements - Midpoint-Rattlesnake #2 230 kV Outage 330 MW of New Generation Figure 12 12- Generation Redispatch Requirements Generators which have chosen to be dispatchable are allowed to operate at levels which may create overloads at or below 30 minute emergency equipment ratings following N- contingencies. Following any N -1 outage, transmission line and transformer loadings which are less than or equal to the 30 minute emergency equipment ratings (115%), but greater than the equipment continuous ratings (100%), must be reduced to the continuous ratings by generation curtailments, redispatch, or some other operating procedure. For the Midpoint series capacitor banks, following any N -1 outage, similar corrective actions are required for loadings which are less than or equal to the 30 minute emergency equipment ratings(135%), but greater than the equipment 8 hour rating( 110%). The following table summarizes generation curtailment requirements for the proposed generation projects modeled at King 138 kV Substation; for various timeframes, and for numerous transmission system single contingencies. The fourth column of the table provides information regarding potential benefits of requesting and funding an optional improvement. The improvement evaluated is the re-configuration of the Midpoint-Boise Bench #3230 kV series capacitor bank to allow one third of the compensation to be bypassed. Unlike Phase #4, no automatic control scheme is contemplated. This Optional Improvement may reduce the magnitude of generation which must be redispatched during a Midpoint-Rattlesnake 230 kV Transmission Line outage. The Optional Improvement is estimated at approximately $50 000. The fifth column of the table provides information regarding potential benefits of completing a portion of Phase #4 improvements early. Phase #4 improvements can be separated into two components. The first component is the "re-configuration" of the Midpoint-Rattlesnake 230 kV series capacitor so it can be operated "fully inservice , " 1/3 bypassed" , " 2/3 bypassed", or fully bypassed". The second component was the "automatic control scheme . The Phase #4a improvement contained in the fifth column is for expediting only the "re-configuration component. Expediting the phase #4a improvement may reduce the magnitude of generation which must be redispatched during a Midpoint-Boise Bench #3230 kV Transmission Line outage. The Phase #4a improvement is estimated at approximately $50 000. 13- Maximum Maximum Maximum Allowable Allowable Allowable Maximum Generation Generation Generation Allowable After N-After N- Before Generation w/Optional w/Phase #4a Contin2ency After N-Improvement Improvement After Phase #1 , but before Phase #2 Midpoint-Boise Bench #3230 kV Line 42MW OMW OMW 42MW Midpoint-Rattlesnake 230 kV Line 42MW 7MW 7MW 7MW Rattlesnake-Boise Bench 230 kV Line, also open Mountain Home Junction-Danskin 138 42MW 9MW 9MW 9MW kV Line Danskin-Mora 230 kV Line, also open Mountain Home Junction-Danskin 138 kV 42MW 42MW 42MW 42MW Line After Phase #2, but before Phase #3 Midpoint-Boise Bench #3 230 kV Line 94MW OMW OMW 94MW Midpoint-Rattlesnake 230 kV Line 94MW 9MW 9MW 9MW Rattlesnake-Boise Bench 230 kV Line, also open Mountain Home Junction-Danskin 138 94MW 32MW 32MW 32MW kV Line Danskin-Mora 230 kV Line, also open Mountain Home Junction-Danskin 138 kV 94MW 80MW 80MW 80MW Line Mountain Home Junction-Lower Malad 138 94MW 49MW 49MW 49MWkV Line Lucky Peak-Micron 138 kV Line 94MW 45MW 45MW 45MW Danskin 230/138 kV Transformer 94MW 90MW 90MW 90MW After Phase #3, but before Phase #4 Midpoint-Boise Bench #3230 kV Line 153 MW OMW OMW 153 MW Midpoint-Rattlesnake 230 kV Line 153 MW l7MW 53MW l7MW Rattlesnake-Boise Bench 230 kV Line, also open Mountain Home Junction-Danskin 138 153 MW 71MW 71MW 71MW kV Line Danskin-Mora 230 kV Line, also open Mountain Home Junction-Danskin 138 kV 153 MW 120 MW 120 MW 120 MW Line Mountain Home Junction-Lower Malad 138 153 MW 129 MW 129 MW 129 MWkV Line Lucky Peak-Micron 138 kV Line 153 MW 84MW 84MW 84MW Danskin 230/138 kV Transformer 153 MW 125 MW 125 MW 125 MW 14- Maximum Maximum Maximum Allowable Allowable Allowable Maximum Generation Generation Generation Allowable After N-After N- Before Generation w/Optional w/Phase #4a Contin2ency After N-Improvement Improvement After Phase #4 but before Phase #5 Midpoint-Boise Bench #3230 kV Line 156 MW 156 MW 156 MW N/A Midpoint-Rattlesnake 230 kV Line 156 MW 18MW 53MW N/A Rattlesnake-Boise Bench 230 kV Line, also open Mountain Home Junction-Danskin 138 156 MW 71MW 71MW N/A kV Line Danskin-Mora 230 kV Line, also open Mountain Home Junction-Danskin 138 kV 156 MW 120 MW 120 MW N/A Line Mountain Home Junction-Lower Malad 138 156 MW 129 MW 129 MW N/AkV Line Lucky Peak-Micron 138 kV Line 156 MW 84MW 84MW N/A Danskin 230/138 kV Transfonner 156 MW 125 MW 125 MW N/A After Phase #5 Midpoint-Boise Bench #3 230 kV Line 330 MW 140 MW 140 MW N/A Midpoint-Rattlesnake 230 kV Line 330 MW 25MW 123 MW N/A Rattlesnake-Boise Bench 230 kV Line, also open Mountain Home Junction-Danskin 138 330 MW 254 MW 254 MW N/A kV Line Danskin-Mora 230 kV Line, also open Mountain Home Junction-Danskin 138 kV 330 MW 310 MW 31OMW N/A Line Mountain Home Junction-Lower Ma1ad 138 330 MW 280 MW 280 MW N/AkV Line Lucky Peak-Micron 138 kV Line 330 MW 265 MW 265 MW N/A Danskin 230/138 kV Transfonner 330 MW 295 MW 295 MW N/A King 230/138 kV Transfonner 330 MW 245 MW 245 MW N/A Fault Study Results Since this System Impact Study lumps all the proposed generation additions at King 138 kV bus, this Draft Report makes no attempt to address fault study concerns. Each proposed generation project will have to be evaluated individually based on its specific location. 10.Transient Stability Study Results The Midpoint West Transmission System is not transient stability limited. Therefore, no transient stability studies were perfonned. 15- 11.0 Conclusions The System Impact of interconnecting up t0304 MW of new generation in the Twin Falls area to Idaho Power s 138 kV transmission system was studied. Five phases of transmission system improvements are required to provide Network Resource Interconnection Service to 304 MW of new generation, on a dispatchable basis. Phase #1 is the installation ofa 8 ohm 138 kV Series Reactor on the Upper Salmon-Mountain Home Junction 138 kV transmission line. This improvement corrects a N-1 overload that exists before any new generation is added in the Twin Falls area. As a result, the estimated $290 000 cost of this improvement will be borne by Idaho Power Company. After approximately 42 MW of new generation is added, Phase #1 improvements are no longer sufficent. Phase #2 improvements require the installation of a 4 ohm 138 kV Series Reactor on the Mountain Home Junction-Lucky Peak 138 kV transmission line. The estimated $290 000 cost of this improvement should be allocated to new generator interconnections. Following the addition of approximately 94 MW of new generation, Phase #3 transmission improvements are required. Phase #3 improvements require the installation a 12.35 ohm 138 kV Series Reactor on the Lower Malad-Mountain Home Junction 138 kV transmission line, and increasing the impedance of the existing Upper Salmon-Mountain Home Junction 138 kV Series Reactor to 26.2 ohms. The estimated $290 000 cost of Phase #3 improvements should be allocated to new generator interconnections. Following the addition of approximately 153 MW of new generation, Phase #4 transmission improvements are required. Phase #4 involves re-configuring the Midpoint-Rattlesnake 230 kV series capacitor bank to allow 1/3 of the compensation to be bypassed via IPCo s SCADA system and install a automatic 1/3 bypass scheme" for overloads exceeding the series capacitor s 30 minute emergency equipment rating of 135%. The estimated $100 000 cost of this improvement should be allocated to new generator interconnections. Following the addition of approximately 156 MW of new generation, Phase #5 transmission improvements are required. Phase #5 involves folding the Midpoint-DRAM #1 230 kV transmission line into and back out of the King Substation and installing a 230/138 kV 300 MV A transfonner. The estimated $10 320 000 cost of this improvement should be allocated to new generator interconnections. Phase #5 transmission improvements are adequate to interconnect approximately 330 MW of new generation in the Twin Falls area, on a dispatchable basis, before additional improvements are required. 16- APPENDIX A 1.0 Method of Study The study methodology inserts the proposed generators up to the maximum requested output of 304 MW into the selected WECC power flow case and then, using the PowerWorid Simulator powerflow program, examines the impacts of the new resource on Idaho Power s transmission system (lines, transformers, etc.) within the study area under various operating/outage scenarios. The WECC and Idaho Power reliability criteria and Idaho Power operating procedures were used to determine the acceptability of the alternatives considered. The WECC case is a recent cases modified to simulate stressed but reasonable pre-contingency energy transfers utilizing the IPC system. Acceptability Criteria The following acceptability criteria were used in the power flow analysis to determine the acceptability of the alternatives: Loadings on transmission lines and transformers should not exceed 115% of the continuous rating, immediately following any N-l outage. Loading on the Midpoint 230 kV series capacitors should not exceed 135% of the continuous rating, immediately following any N-l outage. These loadings levels of 115% on transmission lines and transformers and 135% on Midpoint series capacitors correspond to IPC's 30 minute emergency equipment ratings. Any loadings immediately following an N-l outage less than the 30 minute emergency rating is acceptable. Loadings which are less than the 30 minute emergency equipment ratings, but greater than the equipment continuous ratings, must be reduced to the continuous ratings by generation curtailments, re-dispatch, or some other operating procedure. Any remedial action schemes(RAS) or other transmission switching, must be judged to be reasonable before the alternatives performance can be deemed acceptable. The continuous rating of equipment is assumed to be the normal thermal rating of the equipment. This rating will be as determined by the manufacturer of the equipment or as determined by Idaho Power. Less than or equal to 100% of continuous rating for transmission lines and transformers is acceptable. Less than or equal to 110% of continuous rating for the Midpoint 230 kV series capacitors is acceptable. Transmission voltages, under normal operating conditions, are maintained within plus or minus 5% (0.05 per unit) of nominal. Therefore, voltages greater than or equal to 95 pu voltage and less than or equal to 1.05 pu voltage are acceptable. The stable operation of the transmission system requires an adequate supply of volt- amperes reactive (V ARs) to maintain a stable voltage profile under both steady-state and dynamic system conditions. An inadequate supply of V ARs will result in voltage decay or even collapse under the worst conditions. Idaho Power designs its system to integrate Network Resources at full capability during specified outage conditions. 17- Equipment/line/path ratings used will be those that are in use at the time of the study or that are represented by IPC upgrade projects that are either currently under construction or whose budgets have been approved for construction in the near future. All other potential future ratings are outside the scope of this study. Future transmission changes may, however, affect current facility ratings used in the study. 18-