HomeMy WebLinkAbout20060822Staff to IPC 91-103.pdfDONOV AN E. WALKER
DEPUTY ATTORNEY GENERAL
IDAHO PUBLIC UTILITIES COMMISSION
PO BOX 83720
BOISE, IDAHO 83720-0074
(208) 334-0312
IDAHO BAR NO. 5921
RECEIVED
200& AUG 22 PH 3: 24
IDF,HO FUBLIC
UTILITIES COMl.iISSIOI
Street Address for Express Mail:
472 W. WASHINGTON
BOISE, IDAHO 83702-5983
Attorney for the Commission Staff
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR A
CERTIFICATE OF PUBLIC CONVENIENCE
AND NECESSITY FOR THE RATE BASING OF
THE EV ANDER ANDREWS POWER PLANT.
CASE NO. IPC-06-
FOURTH PRODUCTION
REQUEST OF THE
COMMISSION STAFF TO
IDAHO POWER COMPANY
The Staff of the Idaho Public Utilities Commission, by and through its attorney of record
Donovan E. Walker, Deputy Attorney General, requests that Idaho Power Company (Company; IPC)
provide the following documents and information as soon as possible, but no later than MONDAY
SEPTEMBER 11, 2006.
This Production Request is to be considered as continuing, and Idaho Power Company is
requested to provide, by way of supplementary responses, additional documents that it or any person
acting on its behalf may later obtain that will augment the documents produced.
For each item, please indicate the name of the person(s) preparing the answers, along with the
job title of such person( s) and the witness who can sponsor the answer at hearing.
For purposes of clarification, the "Evander Andrews Plant" as referred to in this request means
the new proposed plant that would be constructed at the Evander Andrews site. The existing plant at
the Evander Andrews site is referred to as "Danskin.
FOURTH PRODUCTION REQUEST TO
IDAHO POWER COMPANY AUGUST 22, 2006
Questions 91-93 refer to the testimony of Greg Said beginning on pages 16 , line 22 and
continuing through page 17, line 19 wherein he discusses "other attributes of the Project that you (Greg
Said) believe are important to the Commission s consideration.
REQUEST NO. 91: Please explain in detail the transmission improvements that "will provide
capacity during all seasons and improve the reliability of the Company s transmission system." Please
quantify as accurately as possible the benefits of increased transmission capacity and of improved
reliability. If these attributes cannot be quantified, please explain why.
REQUEST NO. 92: Please explain in detail and quantify as accurately as possible the benefits
from the economies of centralizing operations at one location (Evander Andrews). If these attributes
cannot be quantified, please explain why.
REQUEST NO. 93: Please explain in detail and quantify as accurately as possible the benefits
from simplification of environmental compliance reporting as a result of locating the new generating
plant at the Evander Andrews location.
REQUEST NO. 94: Is Idaho Power willing to provide a commitment estimate for
transmission costs that will be incurred to integrate the proposed new Evander Andrews generating
plant, similar to the Commitment Estimate offered for the plant construction? If so , what is the
commitment estimate for transmission costs? If Idaho Power is not able or willing to agree to have the
transmission improvements subject to a commitment estimate, please explain why.
REQUEST NO. 95: A natural gas fired peaking plant was not selected as part of the preferred
portfolio chosen in the Draft 2006 IRP. If 2006 IRP assumptions are used and the proposed Evander
Andrews plant is assumed to be a resource option instead of part ofIdaho Power s existing generation
fleet, would the Evander Andrews plant be chosen as part of the preferred portfolio?
REQUEST NO. 96: In Request No.1 of the Commission Staff, Staff requested a copy of
load-resource balance data by month for each of the years 2006-2026 for six different assumed water
and load conditions, with and without the addition of the proposed Evander Andrews plant. The
FOURTH PRODUCTION REQUEST TO
IDAHO POWER COMPANY AUGUST 22, 2006
requested time period was chosen specifically to correspond to the time period covered by the 2006
IRP. 2006 IRP load-resource balance data has been in use by the Company for several months during
the preparation of the 2006 IRP; consequently, Staff assumed it could also be used to re-examine the
need for the Evander Andrews plant. In the Company s initial response to this request, Idaho Power
provided load-resource balance data for the period 2004-2013, apparently from the 2004 IRP.
Please provide a response to this request using load-resource balance data consistent with the
data that will be used in the 2006 IRP.
REQUEST NO. 97: In response to Request No.2 of the Commission Staff, the Company
states "Peak load surpluses/deficiencies are evaluated using 90th percentile water and 95th percentile
peak load conditions." Has the Company changed its capacity planning criteria for the 2006 IRP, or
should the response be corrected to refer to the "90th percentile water and 70th percentile peak load
conditions. "
REQUEST NO. 98: Assuming, hypothetically, that the Evander Andrews plant is constructed
and that Idaho Power is fully utilizing all of its own resources and purchase contracts, if water and load
conditions are such that Idaho Power is still unable to meet load, what other alternatives will be
pursued to meet load? At what point will load curtailment be considered?
REQUEST NO. 99: Staff Request No. 18 specifically asked that the load and fuel price
forecasts used to perform the AURORA analysis be consistent with those of the 2006 IRP. Based on
the Company s response, it appears that 2004 IRP assumptions were used with perhaps some update to
fuel price forecasts. Please provide responses to parts a, b, and c of Request No. 18 using 2006 IRP
assumptions, or explain why 2006 IRP assumptions cannot be used.
REQUEST NO. 100: Staff Request No. 26 asked for monthly estimates for the period June
2007-December 2027 ofthe number of hours the Evander Andrews plant will be expected to operate
to serve Idaho Power s load. Idaho Power did not provide any estimate of expected operating hours.
For the purposes of answering this request, Staff assumed that the Evander Andrews plant would be
added to Idaho Power s portfolio and dispatched in an AURORA simulation using the portfolio
FOURTH PRODUCTION REQUEST TO
IDAHO POWER COMPANY AUGUST 22 , 2006
selected in the 2006 IRP. Please provide monthly estimates as requested, or if this cannot be done
please explain why.
REQUEST NO. 101: Staff Request No. 51 asked for Idaho Power s current forecast of firm
wholesale electric energy prices for the next five and 1 O-year periods for heavy and light load hours.
In response to the request, Idaho Power provided monthly heavy and light load hour prices for three
market hubs from July 2006-December 2012 (approximately a six-year period). Does the Company
prepare or purchase a forecast that extends beyond 2012? If so, please provide a copy.
REQUEST NO. 102: Staff request No. 61 asked for an update on the status on the Company
plans to upgrade the Borah-West transmission path. Neither in its initial or its supplemental answers to
this request did Idaho Power provide an actual update on the project status as requested. Staff would
like to know, for example, is the project under construction, when is completion expected, how much
has/will the rated transmission capacity of the path been increased, etc.
REQUEST NO. 103: In Staff Request No. 74, Staff asked Idaho Power to describe any
additional costs Idaho Power expects it will incur as a result of delaying completion of the project from
June 1 2007 until April 1 , 2008. If the answer to the question can be determined simply by subtracting
the winning bidder s 2008 online date price from its 2007 online date price, then Staff can develop an
answer without assistance. However, if there are other costs because of delaying the online date until
April 2008, such as costs for acquiring replacement power for 2007 for example, then Staff requests
that Idaho Power provide an answer.
DATED at Boise, Idaho thiS?t~ day of August 2006.
onovan E. Walker
Deputy Attorney General
Technical Staff: Rick Sterling
i:umisc:prodreqlipceO6.09dwrps ipc4
FOURTH PRODUCTION REQUEST TO
IDAHO POWER COMPANY AUGUST 22, 2006
CERTIFICATE OF SERVICE
I HEREBY CERTIFY THAT I HAVE THIS 22ND DAY OF AUGUST 2006
SERVED THE FOREGOING FOURTH PRODUCTION REQUEST OF THE
COMMISSION STAFF TO IDAHO POWER COMPANY IN CASE NO. IPC-06-
BY MAILING A COpy THEREOF, POSTAGE PREPAID, TO THE FOLLOWING:
BARTON L KLINE
MONICA MOEN
IDAHO POWER COMPANY
PO BOX 70
BOISE ID 83707-0070
JAMES C MILLER
SR. VICE PRESIDENT, GENERATION
IDAHO POWER COMPANY
PO BOX 70
BOISE ID 83707-0070
PETER J RICHARDSON
RICHARDSON & O'LEARY
515 N 27TH ST
PO BOX 7218
BOISE ID 83702
DR DON READING
6070 HILL ROAD
BOISE ID 83703
SECRET
CERTIFICATE OF SERVICE