Loading...
HomeMy WebLinkAbout20060717IPC to Staff 25, 75, part I.pdf~~,~,---~,~- IDAHO POWER COMPANY R E eEl V E 0O, BOX 70 BOISE, IDAHO 83707 2006 JUL I 1+ PH 4= 51 IDAHO PUBLIC UTILITIES COMMISSION Monica Moen AttorneyAn IDACORP Company July 14 , 2006 Jean D. Jewell, Secretary Idaho Public Utilities Commission 472 West Washington Street P. O. Box 83720 Boise, Idaho 83720-0074 Re:Case No. IPC-06- Idaho Power Company s Response to the First Production Request of Commission Staff Dear Ms. Jewell: Please find enclosed for filing an original and two (2) copies of Idaho Power Company s Response to the First Production Request of Commission Staff regarding the above-described case. I would appreciate it if you would return a stamped copy of this transmittal letter to me in the enclosed self-addressed stamped envelope. Very truly yours ~'- Monica B. Moen MBM:sh Enclosures Telephone (208) 388-2692 Fax (208) 388-6936, E-mail MMoen(g)idahopower.com BARTON L. KLINE ISB #1526 MONICA B. MOEN ISB #5734 Idaho Power Company P. O. Box 70 Boise , Idaho 83707 Telephone: (208) 388-2682 FAX Telephone: (208) 388-6936 RECE\VEO 100G JUL \ 4 PH 4: 5 , IDAHO PUBLIC UTILITIES COMMISSION Attorney for Idaho Power Company Street Address for Express Mail 1221 West Idaho Street Boise, Idaho 83702 BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION OF IDAHO POWER COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE RATE BASING OF THE EV ANDER ANDREWS POWERPLANT. CASE NO. IPC-06- IDAHO POWER COMPANY' RESPONSE TO THE FIRST PRODUCTION REQUEST OF COMMISSION STAFF COMES NOW , Idaho Power Company ("Idaho Power" or "the Company and in response to the First Production Request of the Commission Staff to Idaho Power Company dated June 16, 2006, herewith submits the following information: IDAHO POWER COMPANY'S RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page REQUEST NO. 25: Please provide information supporting the transmission costs assumed by Idaho Power for each of the bids considered. Include cost assumptions , transmission losses , and any other transmission factors considered. RESPONSE TO REQUEST NO. 25: Please refer to the documents attached hereto as "Response to Request No. 25. The response to this request was prepared by Monica Moen, Attorney II Idaho Power Company. IDAHO POWER COMPANY'S RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page 2 REQUEST NO. 75: For all intervenor requests , please provide the confidential responses to Staff even if the Company is unable to provide the information to that-party. RESPONSE TO REQUEST NO. 75: With respect to confidential information requested by Mountain View Power, Inc. ("MVP") that was not provided to MVP , Idaho Power has provided the requested confidential information to the Commission Staff as follows: Response to MVP Request No.1 (a)The confidential information requested by MVP in its Request No.1 (a) has been provided to the Commission Staff in Idaho Power s Response to Commission Staff Request No. Response to MVP Request No. : The confidential information requested by MVP in its Request No. 14 has been provided to the Commission Staff in Idaho Power Response to Commission Staff Request No. 45. The response to this request was prepared by Monica Moen, Attorney II , Idaho Power Company. (t. MONICA B. MOEN Attorney for Idaho Power Company IDAHO POWER COMPANY'S RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page 3 CERTIFICATE OF SERVICE I HEREBY CERTIFY that on this 14th day of July, 2006, I served a true and correct copy of the within and foregoing IDAHO POWER COMPANY'S RESPONSE TO THE FIRST PRODUCTION REQUEST OF COMMISSION STAFF upon the following named parties by the method indicated below, and addressed to the following: Commission Staff --2L Hand Delivered Donovan Walker US. Mail Deputy Attorney General Overnight Mail Idaho Public Utilities Commission FAX 472 W. Washington (83702)Email: Donovan.walker(g)puc.idaho.gov O. Box 83720 Boise, Idaho 83720-0074 Industrial Customers of Idaho Power Hand Delivered Peter 1. Richardson, Esq.u.S. Mail Richardson & O'Leary Overnight Mail 515 N. 27th Street FAX O. Box 7218 Email: peter(g)richardsonandoleary.com Boise, Idaho 83702 Don Reading Ben Johnson Associates Hand Delivered 6070 Hill Road u.S. Mail Boise, Idaho 83702 Overnight Mail FAX Email: dreading (g) mindspring.com Mountain View Power, Inc.Hand Delivered Ronald L. Williams --2L u.S. Mail Williams Bradbury, P.Overnight Mail O. Box 2128 FAX Boise, Idaho 83701 Email: ron(g)williamsbradbury.com Robert D. Looper, President Hand Delivered Mountain View Power, Inc.u.S. Mail 1015 W. Hays Street Overnight Mail Boise, Idaho 83702 FAX Email: rlooper(g)spellc.com ~ (3. Monica B. Moen CERTIFICATE OF SERVICE, Page IDAHO POWER COMPANY CASE NO. IPC-O6- FIRST PRODUCTION REQUEST OF COMMISSION STAFF RESPONSE TO REQUEST NO. 25 LARGE GENERATOR INTERCONNECTION FEASIBILITY STUDY REPORT for the 230 KV INTERCONNECTION OPTION EAST BOISE SITE for Idaho Power Company - Power Supply, Interconnection Customer for connection of A 200 MW OR 85 MW SIMPLE CYCLE GAS TURBINE PEAKING PROJECT EAST BOISE SITE IDAHO POWER COMPANY, Transmission Provider TRANSMISSION SYSTEM FINAL REPORT September 9, 2005 , . 1.0 Introduction Idaho Power Company - Power Supply has contracted with Idaho Power Company (IPC) to perform a Large Generator Interconnection Feasibility Study for Network Resource Interconnection Service at 230 kV for the integration of either a new 200 MW or 85 MW simple cycle gas turbine peaking project. The proposed location is the East Boise Site near the S. Eisenman Road Exit 59A on Interstate 84 just East of Boise, Idaho. This report documents the basis for and the results of this Feasibility Study. It describes the proposed interconnection alternatives, the study cases used, outage scenarios assumed and results of all work in the areas of concern. Summary The performance of a 230 kV interconnection alternative was evaluated to integrate a 200 MW simple cycle gas turbine, located at the East Boise Site, into the Idaho Power System. A detailed description of the location ofthe East Boise Site can be found in Section 5.0 of this report. Idaho Power Company - Power Supply has requested Interconnection Feasibility Studies for two units of different sizes at the East Boise Site. The larger unit is rated 200 MW 1$ -7 degrees C(winter rating) and 174 MW 1$ 32 degrees C(summer rating). The smaller unit is rated 85 MW 1$ -7 degrees C(winter rating) and 73.1 MW 1$ 32 degrees C(summer rating). It is. our understanding that only one unit will be selected for construction at this time. The same 230 kV interconnection alternative was selected for evaluation for each proposed unit. The 230 kV interconnection alternative performed acceptably for the 174/200 MW unit. This interconnection alternative is estimated to cost approximately $3 million. The smaller 73/85 MW unit will require the same interconnection facilities, thus have the same interconnection cost. We find no reason to believe the smaller unit would result in operational problems that were not apparent for the larger unit. These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. Summary of Interconnection Request A request was made to Idaho Power Co. by Idaho Power Company - Power Supply to study the interconnection of either a proposed 174/200 MW or a proposed 73/85 MW simple cycle gas turbine at the East Boise Site, near Boise, Idaho, to Idaho Power s transmission system at the 230 kV level for Network Resource Interconnection Service. Scope of Interconnection Feasibility Study The Interconnection Feasibility Study was done and prepared in accordance with the FERC Order 2003-, Standard Large Generator Interconnection Procedures , to provide a preliminary evaluation of the feasibility ofthe interconnection of the proposed large generating project to the Idaho Power transmission system. This study will only be concerned with the capabilities )" of the Idaho Power system to manage this new resource within the study area of the proposed interconnection. Description of Proposed Generating Project Idaho Power Company - Power Supply proposes to connect one or the other of two different sized simple cycle gas turbines to the Idaho Power 230 kV transmission system, at the East Boise Site. The East Boise Site is located at Boise Meridian Township 2N, Range 2E, NW1I4 ofNE1I4 of Section 13. The larger unit is rated 200 MW ~ - 7 degrees C(winter rating) and 174 MW ~ 32 degrees C(summer rating). The smaller unit is rated 85 MW ~ - 7 degrees C(winter rating) and 73.1 MW ~ 32 degrees C(summer rating). It is our understanding that only one unit will be selected for construction at this time. The equipment for the larger unit is described as being, a Siemens SGT6-5000F CT ECNO Pack. The general equipment description for the smaller unit is a GE 7F A Package. The proposed commercial operation date is April 1 , 2007, for either unit. Description of Existing Transmission Facilities The East Boise Site geographically lies under the Boise Bench to Caldwell 230 kV transmission line. The closest 138 kV line is approximately 1 mile away. At the Scoping Meeting for these Interconnection Requests, it was agreed that the interconnection voltage to be studied would be 230 kV. It was anticipated that the cost of a 138 kV alternative would be similar to the 230 kV alternative with no apparent performance advantage. The East Boise Site is approximately 8 circuit line miles out of the Boise Ben.ch Substation on the Boise Bench to Caldwell 230 kV line. ,';.. Description of Configurations Studied Since the most limiting operating conditions are expected during summer peak load conditions the injection of the simple cycle gas turbine s 174 MW summer rated output was inserted into a 2006 power flow case that would simulate peak summer loads in the Boise area. The interconnection alternative selected for evaluation was a fold of the Boise Bench to Caldwell 230 kV line and construction of a new 230 kV substation utilizing three 230 kV circuit breakers. The three terminal ring bus configuration would accommodate the generator terminal, the Boise Bench to East Boise Site 230 kV line terminal, and the Caldwell to East Boise Site line terminal. Post-transient Study Results This Interconnection Feasibility Study Report is for Network Resource Interconnection Service at 230 kV, for a 174/200 MW or 73/85 MW simple cycle gas turbine at the East Boise Site. The studies evaluate system performance for all levels of production ITom 0 MW output, up to its maximum rating for the summer season. For this study, there is no reason to believe the smaller unit would create operational problems, ifthe larger unit did not. N-O and N-1 outage performance for the existing system are recorded. For this alternative, the new generator output was taken to its maximum summer rating of 174 MW and system conditions recorded for both N-O and N-1 outages. Existing System The following one line diagram depicts the existing system with no outages. BROWNLEE043 u Existing System - No Outages Figure 1 174 MW East Boise Generator Added . The following one line diagram depicts the system with the East Boise Generator at full outputand with no outages. BROWNLEE1.043 u 174 MW (ID East Boise Site - No Outages Figure 2 'J' , ./ Single Contingency Line Outage Performance Four single contingency line outages (N-l) will be considered to evaluate system performance following the generator addition. The following one line depicts system performance following the loss of the Boise Bench to Locust 230 kV line, with the generator at 174 MW output. BROWNLEE044 u 174 MW (lY East Boise Site - Boise Bench to Locust 230 kV Line Outage Figure 3 For cowparison purposes, the following one-line depicts the existing system performance for the sallie Boise Bench to Locust 230 kV line outage. BROWNLEE044 u. Existing System - Boise Bench to Locust 230 kV Line Outage Figure 4 The following one line depicts system performance following the loss of the Brownlee to Ontario 230 kV line, with the generator at 174 MW output. BROWNLEE1.04 u 174 MW &J East Boise Site - Brownlee to Ontario 230 kV Line Outage Figure 5 For comparison purposes, the following one-line depicts the existing system performance for the same Brownlee to Ontario 230 kV line outage. BROWNLEE1.044 Existing System - Brownlee to Ontario 230 kV Line Outage Figure 6 The Brownlee to Ontario 230 kV line outage is critical in determining the timing of the next major transmission system improvement project required for Treasure Valley load growth. For the existing system with no generation at the East Boise Site, approximately 205 MW of Nampa/Caldwell area load growth can be accommodated before major transmission improvements are required. With 174 MW of generation at the East Boise Site, only about 185 MW ofload growth in the Nampa/Caldwell area can be accommodated before major transmission system improvements are required. As a result, the utilization of the East Boise Site will slightly accelerate the schedule for the next major transmission system improvement to accommodate load growth in the Nampa/Caldwell area. The following one line depicts system performance following the loss of the Boise Bench to East Boise Site 230 kV line, with the generator at 174 MW output. BROWNLEE1.043 u 174 MW ~ East Boise Site - Boise Bench to East Boise Site 230 kV Line Outage Figure 7 The foUowing one line depicts system performance following the loss of the Nampa Tap to East~kise Site 230 kV line, with the generator at 174 MW output. BROWNLEE1. "J. 174 MW ~ East Boise Site - Nampa Tap to East Boise Site 230kV Line Outage Figure 8 For comparison purposes, the following one-line depicts the existing system performance for the same Boise Bench to Nampa Tap 230 kV line outage. /,.' BROWNLEE1.044 u Existing System - Brownlee to Ontario 230 kV Line Outage Figure 9 The 230 kV interconnection alternative exhibits acceptable performance for all conditions studied. No single contingencies examined produced overloads or unacceptable voltage levels. Unfortunately, utilizing the East Boise Site will accelerate the schedule for the next major transmission system improvement to accommodate load growth in the NampaiCaldwell area. Estimated Cost of Proposed Improvements Cost estimates for the 230 kV interconnection alternative were generated for two categories of costs: Transmission Line Costs Substation Costs Approximate estimated costs for the East Boise Site interconnection alternative are: $ 115 000 010 000 $ 3 125 000 - Transmission Line Costs - Substation Costs - Total estimated generator interconnection cost These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). No tax gross-up is included in these estimates. These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. 10.Short Circuit Study Results Preliminary short circuit study results indicate five 138 kV circuit breakers at Boise Bench will need to be replaced to be able to accommodate the increased fault duty. More detailed short circuit analysis will be required to determine with certainty whether replacement of all five breakers will be required. Additional short circuit studies will be required if either of these generator interconnection projects proceed to a system impact study. If the additional short circuit analysis studies still require breaker replacements, cost estimates will be developed at that time. 11.Conclusions The feasibility of interconnecting either a 174/200 MW or 73/85 MW simple cycle gas turbine at the East Boise Site to Idaho Power 230 kV transmission system was studied. The 230 interconnection alternative evaluated was found to provide acceptable system performance for either of the proposed generators. The estimated total cost ofthe transmission improvements associated with the 230 kV interconnection alternative is approximately $3 Million. , , APPENDIX A 1.0 Method of Study The study methodology inserts the proposed generator up to the maximum requested output of 174 MW into the selected WECC power flow case and then, using the Power Wodd Simulator powerflow program, examines the impacts ofthe new resource on Idaho Power s transmission system (lines, transformers, etc.) within the study area under various operating/outage scenarios. The WECC and Idaho Power reliability criteria and Idaho Power operating procedures were used to determine the acceptability ofthe alternatives considered. The WECC case is a recent cases modified to simulate stressed but reasonable pre-contingency energy transfers utilizing the IPC system. Acceptability Criteria The following acceptability criteria were used in the power flow analysis to determine the acceptability of the alternatives: Loadings on transmission lines and transformers should not exceed 115% of the continuous rating, immediately flowing any N-l outage. Loading on the Midpoint 230 kV series capacitors should not exceed 135% of the continuous rating, immediately flowing any N-l outage. These loadings levels of 115% on transmission lines and transformers and 135% on Midpointseries capacitors correspond to IPCo s 30 minute emergency equipment ratings. Any loadings immediately following an N-l outage less than the 30 minute emergency rating is acceptable. Loadings which are less than the 30 minute emergency equipment ratings, but greater than the equipment continuous ratings, must be reduced to the continuous ratings by generation curtailments, re-dispatch, or some other operating procedure. Any remedial action schemes(RAS) or other transmission switching, must be judged to be reasonable before the alternatives performance can be deemed acceptable. The continuous rating of equipment is assumed to be the normal thermal rating of the equipment. This rating will be as determined by the manufacturer of the equipment or as determined by Idaho Power. Less than or equal to 100% of continuous rating for transmission lines and transformers is acceptable. Less than or equal to 110% of continuous rating for the Midpoint 230 kV series capacitors is acceptable. Transmission voltages, under normal operating conditions, are maintained within plus or minus 5% (0.05 per unit) of nominal. Therefore, voltages greater than or equal to 95 pu voltage and less than or equal to 1.05 pu voltage are acceptable. The stable operation of the transmission system requires an adequate supply of volt- amperes reactive (V ARs) to maintain a stable voltage profile under both steady-state and dynamic system conditions. An inadequate supply of V ARs will result in voltage decay or even collapse under the worst conditions. Idaho Power designs its system to integrate Network Resources at full capability during specified outage conditions. .. " ,. ' Equipment/line/path ratings used will be those that are in use at the time of the study or that are represented by IPC upgrade projects that are either currently under construction or whose budgets have been approved for construction in the near future. All other potential future ratings are outside the scope of this study. Future transmission changes may, however, affect current facility ratings used in the study. ~,.",. - T;5:;' 10- LARGE GENERATOR INTERCONNECTION FEASIBILITY STUDY REPORT for the 230 KV INTERCONNECTION OPTION EV ANDER ANDREWS PROJECT for Idaho Power Power Marketing, Interconnection Customer for connection of A 200 MW SIMPLE CYCLE GAS TURBINE PEAKING PROJECT EV ANDER ANDREWS PROJECT IDAHO POWER COMPANY, Transmission Provider TRANSMISSION SYSTEM FINAL REPORT August 4, 2005 1.0 ... Introduction Idaho Power Power Marketing has contracted with Idaho Power Company (IPC) to perform a Large Generator Interconnection Feasibility Study for Network Resource Interconnection Service at 230 kV for the integration of a new 200 MW simple cycle gas turbine peaking project. The proposed location is the Evander Andrews Project near Mountain Home, Idaho. This report documents the basis for and the results ofthis Feasibility Study. It describes the proposed interconnection alternatives, the study cases used, outage scenarios assumed and results of all work in the areas of concern. Summary The performance ofthree interconnection alternatives was evaluated to integrate a 200 MW simple cycle gas turbine, located at Evander Andrews Project, into the Idaho Power System. Alternative #3 is the recommended alternative. Alternative #1: Alternative #2: Alternative #3: Construct a radial 230 kV interconnection line, from a new 230 kV substation at Evander Andrews, to the Midpoint-Boise Bench #3 transmission line. Numerous N-l contingencies resulted in unacceptable overloads for this alternative. The additional improvement of a 230/138 kV transformer at Evander Andrews was evaluated in an unsuccessful attempt to achieve acceptable performance under N-l outage conditions. Construct two new 230 kV transmission lines from Bennett Mountain to Evander Andrews and Evander Andrews to Rattlesnake. These lines would complete a 230 kV loop from Rattlesnake to Bennett Mountain to Evander Andrews and back to Rattlesnake. In addition, the Dram-Midpoint #1230 kV line would be looped into Rattlesnake and rebuilt to support bundled 230 kV conductors west of Rattlesnake. Additional transmission modifications were also modeled at DRAM substation to make the "Old Midpoint to DRAM #1" 230 kV line bypass the DRAM Substation and terminate at Boise Bench. 230/138 kV transformer was modeled at Evander Andrews to improve system performance under N-l conditions. Alternative #2 has one N-l outage that produces an overload that exceeds 115% of continuous rating. In addition three N-l contingencies still require curtailments for Alternative #2. Alternative #2 is an unacceptable alternative due to the N-l outage that produces an overload that exceeds 115%. Alternative #2 is anticipated to be similar in cost to Alternative #3 , yet does not perform as well. Rebuild a de-energized 132 kV transmission line to 230 kV construction between Bennett Mountain and Mora Substations. This alternative utilizes the 406 line route which passes in the vicinity of Evander Andrews. The west end of the 230 kV line is assum~d to terminate at a new 230 kV Mora Substation which is folded into the Boise Bench-Caldwell 230 kV line. No 230/138 kV transformer is modeled to tie the two Mora busses. A 230/138 kV transformer was modeled at Evander Andrews to improve system performance under N- conditions. Studies revealed the need to reconductor/rebuild the Evander Andrews to Mountain Home Junction 138 kV line. With the previously mentioned additions in-service, two N-l outages produce overloads above equipment continuous ratings. One overload only requires a 2% reduction in loading to fall to a level that can be sustained continuously. Opening another lightly loaded line can mitigate the other overload. The estimated total cost for this alternative is approximately $26 Million, with approximately $22 Million allocated Idaho Power Power Marketing for the generator interconnection improvements and the remaining $4 Million allocated to Idaho Power Delivery to correct existing operational concerns. Following the execution of either a Large Generator Interconnection Agreement or a Engineering & Procurement Agreement by Idaho Power Power Marketing, Idaho Power Company estimates the time required to construct these facilities is approximately 18-21 months. These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). A cursory attempt has been made in this study to characterize each transmission improvement as either needed to integrate the proposed generator" or "needed to correct existing operational concerns . The proposed cost allocation is subject to change, as more information is known. These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. Summary of Interconnection Request A request was made to Idaho Power Co. by Idaho Power Power Marketing to study the interconnection of a proposed 200 MW simple cycle gas turbine at the Evander Andrews Project, near Mountain Home, Idaho, to Idaho Power s transmission system at the 230 kV level for Network Resource Interconnection Service. Scope of Interconnection Feasibility Study The Interconnection Feasibility Study was done and prepared in accordance with the FERC Order 2003-, Standard Large Generator Interconnection Procedures, to provide a preliminary evaluation of the feasibility of the interconnection of the proposed large generating project to the Idaho Power transmission system. This study will only be concerned with the capabilities of the Idaho Power system to manage this new resource within the study area of the proposed interconnection. Description of Proposed Generating Project Idaho Power Power Marketing proposes to connect a 200 MW simple cycle gas turbine to the Idaho Power 230 kV transmission system, at the existing Evander Andrews Power Complex 1862 NW Mashburn RD., Mountain Home, ID 83647. ThemaximUIn generating capacity of the proposed unit is estimated to be 200 MW for both summer and winter temperatures. The equipment is described as being, a Siemens Westinghouse 501F Econopac. The proposed commercial operation date is April 1 , 2007. Description of Existing Transmission Facilities At the Scoping Meeting for this Interconnection Request, it was agreed that the interconnection voltage to be studied would be 230 kV. The existing generating units at Evander Andrews Power Complex utilize the 138 kV transmission grid. No 230 kV transmission is present at Evander Andrews at this time. Evander Andrews has four 230 kV lines in relatively close proximity. Three ofthem run from the Midpoint Substation(north of Twin Falls, ill) to the east Boise area. The closest is the Midpoint- DRAM #1 line, which is approximately 4 miles Northeast of Evander Andrews. This line utilizes single 715.5 MCM conductors and has a continuous rating of339 MY A. The Rattlesnake-Boise Bench #2 line is approximately 5 miles Northeast ofEvander Andrews and utilizes a 2 conductor bundle of715.5 MCM. This line has a continuous rating of677 MYA. The Midpoint-Boise Bench #3 line is approximately 7 miles Northeast of Evander Andrews. This line has similar conductors and the same rating as the Rattlesnake-Boise Bench #2 line. The fourth 230 kV line in the area is the Rattlesnake-Bennett Mountain line. It is approximately 5 miles to the Southeast of Evander Andrews. This line utilizes single 1272 MCM conductors and has a continuous rating of 478 MYA. In addition to the three Midpoint to the east Boise area 230 kV lines previously mentioned, there are two 138 kV circuits which can carry power from the Mountain Home area to the Boise Area. They are: Mountain Home Junction-Lucky Peak-Micron 138 kV Line Mountain Home Junction-Evander Andrews-Strike-Swan Falls-Bowmont 138 kV Line Generators located in the Mountain Home area which are intended to serve load growth in the Treasure Valley area, will be adding new incremental flows on top of existing committed east-to- west transactions across the Midpoint West transmission cutplane. This feasibility study will model 1100 MW of transfers across the Midpoint West cutplane, prior to this proposed generator addition. For these studies, the flow level of the Midpoint west cutplane is defined as the sum of the flows on the following lines: . Midpoint-DRAM #1 230 kV line . Midpoint-Rattlesnake #2230 kV Line . Midpoint-Boise Bench #3 230 kV Line Lower Malad-Mountain Home Junction 138 kV Line Upper Salmon-Mountain Home Junction 138 kV Line Description of Configurations Studied Since the most limiting operating conditions are expected during heavy production on the upper and middle Snake and Boise River hydro plants, with heavy east-west transfers across the Idaho Power transmission system, the injection ofthe'simplecyc1e gas turbine s 200 MW output was inserted into a power flow case that would simulate committed (1100 MW) pre- contingency flows on the Midpoint West transmission path. In accordance with the Scoping Meeting for this Feasibility Study Request, three alternatives were studied, all of which employed a 230 kV interconnection voltage. Alternative #1 employed a radial 230 kV line to connect the generator to the Midpoint-Boise Bench #3 transmission line. The line was modeled as being 7.7 miles in length and utilized 1272 MCM single conductor construction. An additional improvement of a 230/138 kV 200 MY A transformer(duplicate of the Midpoint unit) was explored at Evander Andrews to improve the performance of this alternative. Alternative #2 calls for the construction of two new 230 kV transmission lines from Bennett Mountain to Evander Andrews, and Evander Andrews to Rattlesnake. These lines would complete a 1272 MCM single conductor 230 kV loop from Rattlesnake to Bennett Mountain to Evander Andrews and back to Rattlesnake. In addition, the Dram-Midpoint #1 230 kV line would be looped into Rattlesnake and rebuilt to support a two conductor bundle of715.5 MCM conductors west of Rattlesnake. Additional transmission modifications were also modeled outside of DRAM substation to make the "Old Midpoint to DRAM #1" 230 kV line bypass the DRAM Substation and terminate at Boise Bench. The combination of bundled conductors and folding the #1 line into Rattlesnake Substation necessitated the change to avoid overloads at DRAM associated with the loss ofthe DRAM to Boise Bench 230 kV line. A 230/138 kV 200 MY A transformer(duplicate of the Midpoint unit) was modeled at Evander Andrews to improve system performance under N-l conditions. Alternative #3 employed the rebuild of a de-energized 132 kV transmission line to 230 kV bundled 795 MCM construction between Bennett Mountain and Mora Substations. This alternative utilizes the 406 line route (originally was the Upper Salmon to Caldwell line) which passes in the vicinity of Evander Andrews. The west end of this new 230 kV line is assumed to terminate at a new 230 kV Mora Substation, which is folded into the Boise Bench-Caldwell 230 kV line. No 230/138 kV transformer is modeled to tie the two Mora busses. A 230/138 kV 200 MY A transformer(duplicate of the Midpoint unit) was modeled at Evander Andrews to improve system performance under N-l conditions. Studies also revealed the need to reconductor/rebuild the Evander Andrews to Mountain Home Junction 138 kV line, with this alternative. Post-transient Study Results This Interconnection Feasibility Study Report is for Network Resource Interconnection Service at 230 kV, for a 200 MW simple cycle gas turbine at the Evander Andrews Power Project. System transfers across the Midpoint West cutplane are modeled at 1100 MW prior to the proposed transmission improvements or the proposed generator producing any power. Hydro generation production for the Boise & Snake plants, were modeled at heavy, but realistic levels. Ouput levels for the existing peakers at Evander Andrews and Bennett Mountain were varied over their operating ranges as appropriate. N-O and N-l outage performance for the existing system are recorded. As agreed in the Scoping Me~ting, three alternatives were . .. evaluated. For each alternative, the new generator s output was taken to its maximum level of 200 MW and system conditions recorded for both N-O and N-l outages. /'~ Existing System The following one line diagram depicts the existing system with no outages. Mid oint West = 1100 Existing System - No Outages Figure 1 For the existing system, seven N-l outages produce overloads that exceed the continuous rating of elements ofthe transmission system. The N-l 's that produce overloads with the existing system are included in Appendix B, Figures 9 - 15. Alternative #1 The following one line diagram depicts the system with Alternative #1 added, full output of the generator, and with no outages. Mid oint West = 1063 MW Alternative #1- No Outages Figure 2 Alternative #1 has multiple N-l outages that produce overloads that exceed 115% of continuous ratings. Some of the resulting overloads are reduced with the addition of the Evander Andrews 230/138 kV transformer, and others are increased. The largest overloads are produced by the Lockman Butte to Boise Bench #3 230 kV line outage. The following one line depicts a 128 % loading on the Mountain Home Junction to Lucky Peak 138 kV line without the Evander Andrews 230/138 kV transformer. Mid oint West = 910 MW Alternative #1 - Lockman Butte-Boise Bench #3 230 kV Outage Without the Evander Andrews 230/138 kV Transformer Figure 3 Adding the Evander Andrews 230/138 kV Transformer to the above outage, produces a 172% loading on the Mountain Home Junction to Lucky Peak 138 kV line. With the Evander Andrews 230/138 kV transformer in-service, only one other N-l outage produces overloads that exceed 115% loading and are also greater than existing system overloads for the same N-l. That N-l is loss of the Rattlesnake to Boise Bench #2230 kV line. Without the Evander Andrews 230/138 kV transformer in-service, four other N-l outages produces overloads that exceed 115% loading and are also greater than existing system overloads for the same N -1. They are: Rattlesnake - Boise Bench #2 230 kV Line outage Midpoint - Rattlesnake #2 230 kV line outage Evander Andrews - Strike 138 kV line outage Strike - Bowmont 138 kV line outage Several other N-l outages result in overloads below 115% that would require curtailments following the outage to get down to loadings that can be sustained continuously. In some cases, lowering the output ofthe proposed generator helps to lower the overload; but in 'one case (Lucky Peak - Micron 138 kV line outage), the overload increases as the proposed generators output is lowered. Alternative #1 is an unacceptable alternative, due to two N-l outages which produce overloads that exceed 115% of continuous ratings. The Network Rating for Alternative #1 is 0 MW. Alternative #2 The following one line diagram depicts the system with Alternative #2 added, full output of the generator, and with no outages. Mid Dint West = 1083 MW Alternative #2 - No Outages Figure 4 The addition ofthe Evander Andrews 230/138 kV transformer improves the performance of Alternative #2 for most N-l outages, but not all. Alternative #2 has one N-l outage that produces an overload that exceeds 115% of continuous rating and is also greater than existing system overloads for the same N-l. The outage is the Rattlesnake to Boise Bench #1 230 kV line. The following one line diagram depicts this outage at 200 MW of output on the proposed unit. BOISEBCHB1pu Mid ointWest = 1028 MW Alternative #2 - Rattlesnake to Boise Bench #1 Line Outage ~ 200MW of Output Figure 5 The output ofthe new unit needs to be restricted to approximately 163 MW to limit the overload to 115% on the Mountain Home Junction to Lucky Peak 138 kV line for this N- outage. For this reason, this alternative does not provide adequate performance for a Network Resource Rating of 200 MW. The following one line diagram depicts this condition. Mid olnt West = 1036 MW Alternative #2 - Rattlesnake to Boise Bench Line Outage (ID 163 MW of Output Figure 6 Curtailments are required for all three N-l outages ofthe 230 kV lines from the Mountain Home area into Boise Bench. Loss of the Rattlesnake to Boise Bench #1 or #2 lines require the proposed unit's output to be lowered to approximately 67 MW to reduce overloads 100% of the continuous rating or a level that the overload is no worse than it is for the existing system with the same N-l outage. These contingencies and resulting system performance determines the Network Resource Rating to be 67 MW for Alternative #2. The loss ofthe Midpoint to Boise Bench #3 230 kV line requires a curtailment to 10wer a 118% overload of the series capacitors on the Midpoint to Rattlesnake #2 230 kV line. This alternative does not permit the overload to be reduced by lowering the output of the proposed unit. Lowering the output of proposed unit will increase the overload on the series capacitors in question. Other generators would have to be curtailed to solve this overload scenario. Alternative #2 is an unacceptable alternative for the proposed unit at 200 MW for Network Resource Interconnection Service, due to the N-l outage that produces overloads that exceed 115% of continuous ratings. The Network Resource Rating for Alternative #2 is 67 MW. Alternative #2 is also believed to very similar in cost to AlternatIve #3 , yet it's performance is much more problematic than Alternative #3. 10- '- Alternative #3 The following one line diagram depicts the system with Alternative #3 added, full output ofthe generator, and with no outages. Mid oint West = 1103 MW Alternative #3 - No Outages Figure 7 The addition ofthe Evander Andrews 230/138 kV transformer improves the performance of Alternative #3, for all but one of the N-l outages. Alternative #3 has no N-l outages that produce overloads that exceed 115% of continuous ratings. Two N-l outages result in overloads below 115% and at a level that the overload is greater than it is for the existing system with the same N-l outage. The loss of the Midpoint to Boise Bench #3 230 kV line results in a 112% loading on the series capacitor of the Midpoint to Rattlesnake #2230 kV line. This series capacitor is capable of 110% loading continuously, so a 2% reduction in flow is required. Lowering generation in the Mountain Home area results in increased flow on the series capacitor bank, so transfers across the Midpoint West cutplane will need to be reduced to correct this overload, as well as prepare for the next contingency. The second N-l outage that results in an overload below 115%, is the Evander Andrews to Mora 230 kV line. This N-l outage results in a 106% loading on the Mountain Home Junction to Lucky Peak 138 kV line. This overload can be managed by opening the Evander Andrews to Mountain Home Junction 138 kV line. Alternative #3 changes the characteristics of the interconnected network enough to create the need to reconductor/rebuild the Evander Andrews to Mountain Home Junction 138 kV line. For the N-l outage of the Lucky Peak to Micron 138 kV line, the Evander Andrews to Mountain Home Junction 138 kV line loads to 109% of its rating with all the peaking generation in the Mountain Home area at full output. If the output ofthe peaking generation in the Mountain Home area is reduced, the overload increases in magnitude. The following one 11- line diagram depicts the Lucky Peak to Micron 138 kV line outage with all the Mountain Home area peaking generation offline. Mid oint West = 1157 Alternative #3 - Luck Peak to Micron 138 kV Line Outage With Peakers Off-line Figure 8 Alternative #3 is the recommended alternative for the proposed unit at 200 MW for Network Resource Interconnection Service. Cost Allocation of Proposed Improvements Alternative #3 contains the following five construction components: Bennett Mountain to Evander Andrews 230 kV line and terminals Evander Andrews to Mora 230 kV line and terminals 230 kV generator connection terminal at Evander Andrews Evander Andrews 230/138 kV transformer and terminals Reconductor/rebuild of the Evander Andrews to Mountain Home Junction 138 kV line A cursory attempt has been made in this study to characterize each transmission improvement as either "needed to integrate the proposed generator" or "needed to correct existing operational concerns . The costs associated with those improvements believed to be "needed to integrate the proposed generator" are allocated to the generator interconnection. The costs associated with those improvements believed to be "needed to correct existing operational concerns " are allocated to IPCo Delivery. 12- Approximate estimated costs allocated to the generator interconnection are: $ 4.1 Million - Bennett Mountain to Evander Andrews 230 kV line and terminals $17.3 Million - Evander Andrews to Mora 230 kV line and terminals $ 0.4 Million - 230 kV generator connection terminal at Evander Andrews $21.8 Million - Total estimated generator interconnection cost Approximate estimated costs allocated to the IPCo Delivery are: $2.1 Million - Evander Andrews 230/138 kV transformer and terminals $1.7 Million - Evander Andrews to Mountain Home Junction 138 kV line rebuild $3.8 Million - Total estimated allocation to IPCo Delivery These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). The proposed cost allocation is subject to change, as more information is known. These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. 10.Short Circuit Study Results Preliminary short circuit study results indicate the surrounding circuit breakers are believed to be able to accommodate the increased fault duty. No circuit breaker replacements are anticipated at this time. 11.Conclusions The feasibility of interconnecting a 200 MW simple cycle gas turbine at Evander Andrews Power Complex to Idaho Power s 230 kV transmission system was studied. Three interconnection alternatives were evaluated. Both Alternatives #1 & #2 were found to be unacceptable alternatives due to transmission system loadings that exceeded 115% for N-l outages. Alternative #3 was found to be an acceptable interconnection alternative. While Alternative #3 does require minimal redispatch/transmission switching for two N-l outages, they are minor in nature and deemed acceptable for this feasibility study. The estimated total cost of the transmission improvements associated with Alternative #3 is approximately $26 Million. At this time it is believed that approximately $22 Million of these estimated costs should be allocated to the generator interconnection. 13- APPENDIX A 1.0 Method of Study The study methodology inserts the proposed generator up to the maximum requested output of 200 MW into the selected WECC power flow case and then, using the PowerWorld Simulator powerflow program, examines the impacts of the new resource on Idaho Power s transmission system (lines, transformers, etc.) within the study area under various operating/outage ~cenarios. The WECC and Idaho Power reliability criteria and Idaho Power operating procedures were used to determine the acceptability of the alternatives considered. The WECC case is a recent cases modified to simulate stressed but reasonable pre-contingency energy transfers utilizing the IPC system. Acceptability Criteria The following acceptability criteria were used in the power flow analysis to determine the acceptability of the alternatives: Loadings on transmission lines and transformers should not exceed 115% of the continuous rating, immediately flowing any N-l outage. Loading on the Midpoint 230 kV series capacitors should not exceed 135% of the continuous rating, immediately flowing any N-l outage. These loadings levels of 115% on transmission lines and transformers and 135% on Midpoint series capacitors correspond to IPCo s 30 minute emergency equipment ratings. Any loadings immediately following an N-l outage less than the 30 minute emergency rating is acceptable. Loadings which are less than the 30 minute emergency equipment ratings, but greater than the equipment continuous ratings, must be reduced to the continuous ratings by generation curtailments, re-dispatch, or some other operating procedure. Any remedial action schemes(RAS) or other transmission switching, must be judged to be reasonable before the alternatives performance can be deemed acceptable. The continuous rating of equipment is assumed to be the normal thermal rating of the equipment. This rating will be as determined by the manufacturer of the equipment or as determined by Idaho Power. Less than or equal to 100% of continuous rating for transmission lines and transformers is acceptable. Less than or equal to 110% of continuous rating for the Midpoint 230 kV series capacitors is acceptable. Transmission voltages, under normal operating conditions, are maintained within plus or minus 5% (0.05 per unit) of nominal. Therefore, voltages greater than or equal to 95 pu voltage and less than or equal to 1.05 pu voltage are acceptable. The stable operation ofthe transmission system requires an adequate supply of volt- amperes reactive (V ARs) to maintain a stable voltage profile under both steady-state and dynamic system conditions. An inadequate supply of V ARs will result in voltage 14- decay or even collapse under the worst conditions. Idaho Power designs its system to integrate Network Resources at full capability during specified outage conditions. Equipment/line/path ratings used will be those that are in use at the time of the study or that are represented by IPC upgrade projects that are either currently under construction or whose budgets have been approved for construction in the near future. All other potential future ratings are outside the scope ofthis study. Future transmission changes may, however, affect current facility ratings used in the study. 15- . . APPENDIX B 1.0 l Outages That Produce Overloads On The Existing System The following one line diagrams depict system performance following the seven N-l outages that produce overloads which exceed the continuous rating of facilities. Figure 1 on page 5 depicts the operation of the existing system with no outages. The combination of heavy hydro and peaker generation in the Mountain Home area, and 1100 MW east to west transfers on Midpoint West, results in the Mountain Home Junction to Lucky Peak and Lucky Peak to Micron 138 kV lines being loaded to 98% & 99% respectively, prior to any outages. Mid oint West = 981 Existing System - Midpoint to Boise Bench #3 230 kV Outage Figure 9 16- Mid oint West = 951 Existing System - Rattlesnake to Boise Bench #2 230 kV Outage Figure 10 Mid oint West = 997 Existing System - Midpoint to Rattlesnake #2 230 kV Outage Figure 11 17- , . MId oint West = 1053 Existing System - Midpoint to DRAM #1 230 kV Outage Figure 12 Mid oint West = 1085 Existing System - CJ Strike to Bowmont 138 kV Outage Figure 13 18- Mid oint West = 1072 Existing System - Lucky Peak to Micron 138 kV Outage Figure 14 Midpoint West = 1094 Existing System - Evander Andrews to CJ Strike 138 kV Outage Figure 15 19- LARGE GENERATOR INTERCONNECTION FEASIBILITY STUDY REPORT for the 230 KV INTERCONNECTION OPTION EV ANDER ANDREWS PROJECT for Idaho Power Company - Power Supply, Interconnection Customer for connection of A 100/124 MW SIMPLE CYCLE GAS TURBINE PEAKING PROJECT EV ANDER ANDREWS PROJECT IDAHO POWER COMPANY, Transmission Provider TRANSMISSION SYSTEM FINAL REPORT September 23, 2005 Introduction Idaho Power Company - Power Supply has contracted with Idaho Power Company (IPC) to perform a Large Generator Interconnection Feasibility Study for Network Resource Interconnection Service at 230 kV for the integration of a new 100/124 MW simple cycle gas turbine peaking project. The proposed location is the Evander Andrews Project near Mountain Home, Idaho. This report documents the basis for and the results of this Feasibility Study. It describes the proposed interconnection alternatives , the study cases used, outage scenarios assumed and results of all work in the areas of concern. Summary The performance of three interconnection alternatives was evaluated to integrate a simple cycle gas turbine with a summer rating of 100 MW and a winter rating of 124 MW, located at Evander Andrews Project, into the Idaho Power System. Alternative #3 is the recommended alternative. Alternative #1: Alternative #2: Construct a radial 230 kV interconnection line, from a new 230 kV substation at Evander Andrews, to the Midpoint-Boise Bench #3 transmission line. Several N-l contingencies resulted in unacceptable overloads for this alternative. The additional improvement of a 230/138 kV transformer at Evander Andrews was evaluated in an unsuccessful attempt to achieve acceptable performance under N-l outage conditions. Construct two new 230 kV transmission lines from Bennett Mountain to Evander Andrews and Evander Andrews to Rattlesnake. These lines would complete a 230 kV loop from Rattlesnake to Bennett Mountain to Evander Andrews and back to Rattlesnake. In addition, the Dram-Midpoint #1 230 kV line would be looped into Rattlesnake and rebuilt to support bundled 230 kV conductors west of Rattlesnake. Additional transmission modifications were also modeled at DRAM substation to make the "Old Midpoint to DRAM #1" 230 kV line bypass the DRAM Substation and terminate at Boise Bench. 230/138 kV transformer was modeled at Evander Andrews to improve system performance under N-l conditions. Alternative #2 has no N-l outages that produce overloads that exceeds 115% of continuous rating and are also greater than existing system overloads for the same N-l. Alternative #2 will require curtailments of the proposed generators output following multiple N- outages. The Network Resource Rating for Alternative #2 is 67 MW. Alternative #2 is anticipated to be similar in cost to Alternative #3 , yet does not perform as well. Alternative #3: Rebuild a de-energized 132 kV transmission line to 230 kV construction . between Bennett Mountain and Mora Substations. This alternative utilizes the 406 line route which passes in the vicinity of Evander Andrews. The west end of the 230 kV line is assumed to terminate at a new 230 kV Mora Substation which is folded into the Boise Bench-Caldwell 230 kV line. No 230/138 kV transformer is modeled to tie the two Mora busses. A 230/138 kV transformer was modeled at Evander Andrews to improve system performance under N- conditions. Studies revealed the need to reconductor/rebuild the Evander Andrews to Mountain Home Junction 138 kV line. With the previously mentioned additions in-service, one N-l outage produces an overload above equipment continuous ratings. This overload only requires a 6% reduction in loading to fall to a level that can be sustained continuously. The estimated total cost for this alternative is approximately $26 Million, with approximately $22 Million allocated Idaho Power Company - Power Supply for the generator interconnection improvements and the remaining $4 Million allocated to Idaho Power Delivery to correct existing operational concerns. Following the execution of either a Large Generator Interconnection Agreement or a Engineering & Procurement Agreement by Idaho Power Company - Power Supply, Idaho Power Company estimates the time required to construct these facilities is approximately 18-21 months. These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). A cursory attempt has been made in this study to characterize each transmission improvement as either needed to integrate the proposed generator" or "needed to correct existing operational concerns . The proposed cost allocation is subject to change, as more information is known. These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. Summary of Interconnection Request A request was made to Idaho Power Co. by Idaho Power Company - Power Supply to study the interconnection of a proposed 100/124 MW simple cycle gas turbine at the Evander Andrews Project, near Mountain Home, Idaho, to Idaho Power s transmission system at the 230 kV level for Network Resource Interconnection Service. Scope of Interconnection Feasibility Study The Interconnection Feasibility Study was done and prepared in accordance with the FERC Order 2003-, Standard Large Generator Interconnection Procedures, to provide a preliminary evaluation of the feasibility of the interconnection of the proposed large generating project to the Idaho Power transmission system. This study will only be concerned with the capabilities of the Idaho Power system to manage this new resource within the study area of the proposed interconnection. Description of Proposed Generating Project Idaho Power Company - Power Supply proposes to connect a 100/124 MW simple cycle gas turbine to the Idaho Power 230 kV transmission system, at the existing Evander Andrews Power Complex, 1862 NW Mashburn RD., Mountain Home, ill 83647. The maximum generating capacity of the proposed unit is estimated to be 100 MW for the summer and 124 MW for winter temperatures. The equipment is described as being, a Siemens SSC6- 3000E CT ECNO Pack. The proposed commercial operation date is April 1 , 2007. Description of Existing Transmission Facilities At the Scoping Meeting for this Interconnection Request, it was agreed that the interconnection voltage to be studied would be 230 kV. The existing generating units at Evander Andrews Power Complex utilize the 138 kV transmission grid. No 230 kV transmission is present at Evander Andrews at this time. Evander Andrews has four 230 kV lines in relatively close proximity. Three of them run from the Midpoint Substation(north of Twin Falls, ill) to the east Boise area. The closest is the Midpoint- DRAM #1 line, which is approximately 4 miles Northeast of Evander Andrews. This line utilizes single 715.5 MCM conductors and has a continuous rating of 339 MV A. The Rattlesnake-Boise Bench #2 line is approximately 5 miles Northeast of Evander Andrews and utilizes a 2 conductor bundle of 715.5 MCM. This line has a continuous rating of 677 MV A. The Midpoint-Boise Bench #3 line is approximately 7 miles Northeast of Evander Andrews. This line has similar conductors and the same rating as the Rattlesnake-Boise Bench #2 line. The fourth 230 kV line in the area is the Rattlesnake-Bennett Mountain line. It is approximately 5 miles to the Southeast of Evander Andrews. This line utilizes single 1272 MCM conductors and has a continuous rating of 478 MVA. In addition to the three Midpoint to the east Boise area 230 kV lines previously mentioned, there are two 138 kV circuits which can carry power from the Mountain Home area to the Boise Area. They are: Mountain Home Junction-Lucky Peak-Micron 138 kV Line Mountain Home Junction-Evander Andrews-Strike-Swan Falls-Bowmont 138 kV Line Generators located in the Mountain Home area which are intended to serve load growth in the Treasure Valley area, will be adding new incremental flows on top of existing committed east-to- west transactions across the Midpoint West transmission cutplane. This feasibility study will model 1100 MW of transfers across the Midpoint West cutplane, prior to this proposed generator addition. For these studies , the flow level of the Midpoint west cutplane is defined as the sum of the flows on the following lines: . Midpoint-DRAM #1 230 kV line . Midpoint-Rattlesnake #2 230 kV Line . Midpoint-Boise Bench #3 230 kV Line Lower Malad-Mountain Home Junction 138 kV Line Upper Salmon-Mountain Home Junction 138 kV Line Description of Configurations Studied Since the most limiting operating conditions are expected during heavy production on the upper and middle Snake and Boise River hydro plants, with heavy east-west transfers across the Idaho Power transmission system, the injection of the simple cycle gas turbine s 100 MW summer output was inserted into a power flow case that would simulate committed (1100 MW) pre-contingency flows on the Midpoint West transmission path. In accordance with the Scoping Meeting for this Feasibility Study Request, three alternatives were studied, all of which employed a 230 kV interconnection voltage. Alternative #1 employed a radial 230 kV line to connect the generator to the Midpoint-Boise Bench #3 transmission line. The line was modeled as being 7.7 miles in length and utilized 1272 MCM single conductor construction. An additional improvement of a 230/138 kV 200 MV A transformer( duplicate of the Midpoint unit) was explored at Evander Andrews to improve the performance of this alternative. Alternative #2 calls for the construction of two new 230 kV transmission lines from Bennett Mountain to Evander Andrews, and Evander Andrews to Rattlesnake. These lines would complete a 1272 MCM single conductor 230 kV loop from Rattlesnake to Bennett Mountain to Evander Andrews and back to Rattlesnake. In addition, the Dram-Midpoint #1230 kV line would be looped into Rattlesnake and rebuilt to support a two conductor bundle of 715.5 MCM conductors west of Rattlesnake. Additional transmission modifications were also modeled outside of DRAM substation to make the "Old Midpoint to DRAM #1" 230 kV line bypass the DRAM Substation and terminate at Boise Bench. The combination of bundled conductors and folding the #1 line into Rattlesnake Substation necessitated the change to avoid overloads at DRAM associated with the loss of the DRAM to Boise Bench 230 kV line. A 230/138 kV 200 MV A transformer(duplicate of the Midpoint unit) was modeled at Evander Andrews to improve system performance under N-l conditions. Alternative #3 employed the rebuild of a de-energized 132 kV transmission line to 230 kV bundled 795 MCM construction between Bennett Mountain and Mora Substations. This alternative utilizes the 406 line route (originally was the Upper Salmon to Caldwell line) which passes in the vicinity of Evander Andrews. The west end of this new 230 kV line is assumed to terminate at a new 230 kV Mora Substation, which is folded into the Boise Bench-Caldwell 230 kV line. No 230/138 kV transformer is modeled to tie the two Mora busses. A 230/138 k V 200 MV A transformer( duplicate of the Midpoint unit) was modeled at Evander Andrews to improve system performance under N-l conditions. Studies also revealed the need to reconductor/rebuild the Evander Andrews to Mountain Home Junction 138 kV line, with this alternative. Post-transient Study Results This Interconnection Feasibility Study Report is for Network Resource Interconnection Service at 230 kV, for a 100/124 MW simple cycle gas turbine at the Evander Andrews Power Project. System transfers across the Midpoint West cutplane are modeled at 1100 MW prior to the proposed transmission improvements or the proposed generator producing any power. Hydro generation production for the Boise & Snake plants , were modeled at heavy, but realistic levels. Ouput levels for the existing peakers at Evander Andrews and Bennett Mountain were varied over their operating ranges as appropriate. N-O and N-l outage performance for the existing system are recorded. As agreed in the Scoping Meeting, three alternatives were evaluated. For each alternative, the new generator s output was taken to its summer temperature maximum level of 100 MW and system conditions recorded for both N-O and N- outages. Existine: System The following one line diagram depicts the existing system with no outages. MldDolnt West = 1100 MW Existing System - No Outages Figure 1 For the existing system, seven N-l outages produce overloads that exceed the continuous rating of elements of the transmission system. The N-l' s that produce overloads with the existing system are included in Appendix B , Figures 7 - 13. Alternative #1 The following one line diagram depicts the system with Alternative #1 added, full summer output of the generator, and with no outages. Mid oint West = 1080 Alternative #1 - No Outages Figure 2 Alternative #1 has multiple N-l outages that produce overloads that exceed 115% of continuous ratings. Some of the resulting overloads are reduced with the addition of the Evander Andrews 230/138 kV transformer, and others are increased. The largest overloads are produced by the Lockman Butte to Boise Bench #3 230 kV line outage. The following one line depicts a 124 % loading on the Mountain Home Junction to Lucky Peak 138 kV line, without the Evander Andrews 230/138 kV transformer. DNPRCT! IR0J) 1O0MWcr 11M", Mid oint West = 946 MW Alternative #1- Lockman Butte-Boise Bench #3230 kV Outage Without the Evander Andrews 230/138 kV Transformer Figure 3 Adding the Evander Andrews 230/138 kV Transformer to the above outage, produces a 158% loading on the Mountain Home Junction to Lucky Peak 138 k V line. With the Evander Andrews 230/138 kV transformer in-service, there are no other N-l outages that produce overloads that exceed 115% loading. Without the Evander Andrews 230/138 kV transformer in-service, four other N-l outages produces overloads that exceed 115% loading and are also greater than existing system overloads for the same N-l. They are: Rattlesnake - Boise Bench #2 230 kV Line outage Midpoint - Rattlesnake #2 230 kV line outage Evander Andrews - Strike 138 kV line outage Strike - Bowmont 138 kV line outage Several other N-l outages result in overloads below 115% that would require curtailments following the outage to get down to loadings that can be sustained continuously. In some cases , lowering the output of the proposed generator helps to lower the overload, but in one case (Lucky Peak - Micron 138 kV line outage), the overload increases as the proposed generators output is lowered. Alternative #1 is an unacceptable alternative, due to the N-l outage that produces an overload that exceeds 115% of continuous ratings. The Network Rating for Alternative #1 is 0 MW. Alternative #2 The following one line diagram depicts the system with Alternative #2 added, full output of the generator, and with no outages. Alternative #2 - No Outages Figure 4 The addition of the Evander Andrews 230/138 kV transformer improves the performance of Alternative #2 for most N-l outages , but not all. Without the Evander Andrews 230/138 kV transformer, Alternative #2 has four N-l outages that produce overloads that exceeds 115% of continuous rating, however, all the overloads are less than existing system overloads for the same N-l and as a result are judged to provide acceptable performance. With the Evander Andrews 230/138 kV transformer, Alternative #2 has no N-l outages that produce overloads that' exceed 115 % of continuous rating. Curtailments are required for all three N-l outages of the 230 kV lines from the Mountain Home area into Boise Bench. Loss of the Rattlesnake to Boise Bench #1 or #2 lines require the proposed unit's output to be lowered to approximately 67 MW to reduce overloads to 100% of the continuous rating or a level that the overload is no worse than it is for the existing system with the same N-l outage. These contingencies and resulting system performance determines the Network Resource Rating to be 67 MW for Alternative #2. The loss of the Midpoint to Boise Bench #3230 kV line requires a curtailment to lower a 118% overload of the series capacitors on the Midpoint to Rattlesnake #2 230 kV line. This alternative does not permit the overload to be reduced by lowering the output of the proposed unit. Lowering the output of proposed unit will increase the overload on the series capacitors in question. Other generators would have to be curtailed to solve this overload scenario. Alternative #2 will require curtailments of the proposed generators output following multiple loutages. As a result, Alternative #2 does not provide acceptable performance for Network Resource Interconnection Service for the proposed unit at full output. The Network Resource Rating for Alternative #2 is 67 MW. Alternative #2 is also believed to very similar in cost to Alternative #3 , yet it's performance is much more problematic than Alternative #3. Alternative #3 The following one line diagram depicts the system with Alternative #3 added, full output of the generator, and with no outages. Mld olnt West = 1118 MW Alternative #3 - No Outages Figure 5 The addition of the Evander Andrews 230/138 kV transformer improves the performance of Alternative #3 , for all but one of the N-l outages. With the Evander Andrews 230/138 kV transformer in service, alternative #3 has no N-l outages that produce overloads that exceed 115% of continuous ratings. One N-l outage results in an overload below 115% and at a level that the overload is greater than it is for the existing system with the same N-l outage. The loss of the Midpoint to Boise Bench #3 230 kV line results in a 116% loading on the series capacitor of the Midpoint to Rattlesnake #2 230 kV line. This series capacitor is capable of 110% loading continuously, so a 6% reduction in flow is required. Lowering generation in the Mountain Home area results in increased flow on the series capacitor bank, so transfers across the Midpoint West cutplane will need to be reduced to correct this overload, as well as prepare for the next contingency. Alternative #3 changes the characteristics of the interconnected network enough to create the need to reconductor/rebuild the Evander Andrews to Mountain Home Junction 138 kV line. For the N -1 outage of the Lucky Peak to Micron 138 k V line, the Evander Andrews to Mountain Home Junction 138 kV line loads to 113% of its rating with all the peaking generation in the Mountain Home area at full output. If the output of the peaking generation in the Mountain Home area is reduced, the overload increases in magnitude. The following one line diagram depicts the Lucky Peak to Micron 138 kV line outage with all the Mountain Home area peaking generation offline. Mld olnt West.. 1157 Alternative #3 - Luck Peak to Micron 138 kV Line Outage With Peakers Off-line Figure 6 Alternative #3 is the recommended alternative for the proposed unit at 100/124 MW for Network Resource Interconnection Service. Cost Allocation of Proposed Improvements Alternative #3 contains the following five construction components: Bennett Mountain to Evander Andrews 230 kV line and terminals Evander Andrews to Mora 230 kV line and terminals 230 kV generator connection terminal at Evander Andrews Evander Andrews 230/138 kV transformer and terminals Reconductorlrebuild of the Evander Andrews to Mountain Home Junction 138 kV line A cursory attempt has been made in this study to characterize each transmission improvement as either "needed to integrate the proposed generator" or "needed to correct existing operational concerns . The costs associated with those improvements believed to be "needed to integrate the proposed generator" are allocated to the generator interconnection. The costs 10- associated with those improvements believed to be "needed to correct existing operational concerns " are allocated to IPCo Delivery. Approximate estimated costs allocated to the generator interconnection are: $ 4.1 Million - Bennett Mountain to Evander Andrews 230 kV line and terminals $17.3 Million - Evander Andrews to Mora 230 kV line and terminals $ 0.4 Million - 230 kV generator connection terminal at Evander Andrews $21.8 Million - Total estimated generator interconnection cost Approximate estimated costs allocated to the IPCo Delivery are: $2.1 Million - Evander Andrews 230/138 kV transformer and terminals $1.7 Million - Evander Andrews to Mountain Home Junction 138 kV line rebuild $3.8 Million - Total estimated allocation to IPCo Delivery These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). The proposed cost allocation is subject to change, as more information is known. These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. 10.Short Circuit Study Results Preliminary short circuit study results indicate the surrounding circuit breakers are believed to be able to accommodate the increased fault duty. No circuit breaker replacements are anticipated at this time. 11.Conclusions The feasibility of interconnecting a 100/124 MW simple cycle gas turbine at Evander Andrews Power Complex to Idaho Power s 230 kV transmission system was studied. Three interconnection alternatives were evaluated. Alternative #1 was found to be an unacceptable alternative due to transmission system loadings that exceeded 115% for N-l outages. Alternative #2 did not provide acceptable performance for Network Resource Interconnection Service for the proposed unit at full output. The Network Resource Rating for Alternative #2 is 67 MW. Alternative #3 was found to be an acceptable interconnection alternative. While Alternative #3 does require minimal redispatchltransmission switching for one N-l outage, it is minor in nature and deemed acceptable for this feasibility study. The estimated total cost of the transmission improvements associated with Alternative #3 is approximately $26 Million. At this time it is believed that approximately $22 Million of these estimated costs should be allocated to the generator interconnection. 11- APPENDIX A Method of Study The study methodology inserts the proposed generator up to the maximum requested output of 100 MW into the selected WECC power flow case and then, using the PowerWorld Simulator powerflow program, examines the impacts of the new resource on Idaho Power s transmission system (lines, transformers, etc.) within the study area under various operating/outage scenarios. The WECC and Idaho Power reliability criteria and Idaho Power operating procedures were used to determine the acceptability of the alternatives considered. The WECC case is a recent cases modified to simulate stressed but reasonable pre-contingency energy transfers utilizing the IPC system. Acceptability Criteria The following acceptability criteria were used in the power flow analysis to determine the acceptability of the alternatives: Loadings on transmission lines and transformers should not exceed 115% of the continuous rating, immediately flowing any N-l outage. Loading on the Midpoint 230 kV series capacitors should not exceed 135% of the continuous rating, immediately flowing any N-l outage. These loadings levels of 115% on transmission lines and transformers and 135% on Midpoint series capacitors correspond to IPCo s 30 minute emergency equipment ratings. Any loadings immediately following an N-l outage less than the 30 minute emergency rating is acceptable. Loadings which are less than the 30 minute emergency equipment ratings, but greater than the equipment continuous ratings, must be reduced to the continuous ratings by generation curtailments, re-dispatch, or some other operating procedure. Any remedial action schemes(RAS) or other transmission switching, must be judged to be reasonable before the alternatives performance can be deemed acceptable. The continuous rating of equipment is assumed to be the normal thermal rating of the equipment. This rating will be as determined by the manufacturer of the equipment or as determined by Idaho Power. Less than or equal to 100% of continuous rating for transmission lines and transformers is acceptable. Less than or equal to 110% of continuous rating for the Midpoint 230 kV series capacitors is acceptable. Transmission voltages, under normal operating conditions, are maintained within plus or minus 5% (0.05 per unit) of nominal. Therefore, voltages greater than or equal to 95 pu voltage and less than or equal to 1.05 pu voltage are acceptable. The stable operation of the transmission system requires an adequate supply of volt- amperes reactive (V ARs) to maintain a stable voltage profile under both steady-state and dynamic system conditions. An inadequate supply of V ARs will result in voltage 12- decay or even collapse under the worst conditions. Idaho Power designs its system to integrate Network Resources at full capability during specified outage conditions. Equipment/line/path ratings used will be those that are in use at the time of the study or that are represented by IPC upgrade projects that are either currently under construction or whose budgets have been approved for construction in the near future. All other potential future ratings are outside the scope of this study. Future transmission changes may, however, affect current facility ratings used in the study. 13- APPENDIX B 1 Outages That Produce Overloads On The Existing System The following one line diagrams depict system performance following the seven N-l outages that produce overloads which exceed the continuous rating of facilities. Figure 1 on page 5 depicts the operation of the existing system with no outages. The combination of heavy hydro and peaker generation in the Mountain Home area, and 1100 MW east to west transfers on Midpoint West, results in the Mountain Home Junction to Lucky Peak and Lucky Peak to Micron 138 kV lines being loaded to 98% & 99% respectively, prior to any outages. Midpoint West II 981 Existing System - Midpoint to Boise Bench #3230 kV Outage Figure 7 14- MldDolnt West = 951 Existing System - Rattlesnake to Boise Bench #2 230 kV Outage Figure 8 Mld olnt West = 997 Existing System - Midpoint to Rattlesnake #2230 kV Outage Figure 9 15- Midpoint West = 1053 Existing System - Midpoint to DRAM #1 230 k V Outage Figure 10 Mid oint West = 1085 Existing System - CJ Strike to Bowmont 138 kV Outage Figure 11 16- MldDolnt West = 1072 Existing System - Lucky Peak to Micron 138 kV Outage Figure 12 Mld olnt West = 1094 Existing System - Evander Andrews to CJ Strike 138 kV Outage Figure 13 17- LARGE GENERATOR INTERCONNECTION FEASIBILITY STUDY REPORT for the 230 KV INTERCONNECTION OPTION EV ANDER ANDREWS PROJECT for Idaho Power Company - Power Supply, Interconnection Customer for connection of A 91/100 MW SIMPLE CYCLE GAS TURBINE PEAKING PROJECT EV ANDER ANDREWS PROJECT IDAHO POWER COMPANY, Transmission Provider TRANSMISSION SYSTEM FINAL REPORT September 23, 2005 1.0 Introduction Idaho Power Company - Power Supply has contracted with Idaho Power Company (IPC) to perform a Large Generator Interconnection Feasibility Study for Network Resource Interconnection Service at 230 kV for the integration of a new 91/100 MW simple cycle gas turbine peaking proj ect. The proposed location is the Evander Andrews Proj ect near Mountain Home, Idaho. This report documents the basis for and the results ofthis Feasibility Study. It describes the proposed interconnection alternatives, the study cases used, outage scenarios assumed and results of all work in the areas of concern. Summary The performance of three interconnection alternatives was evaluated to integrate a simple cycle gas turbine with a summer rating of91 MW and a winter rating of 100 MW, located at Evander Andrews Project, into the Idaho Power System. Alternative #3 is the recommended alternative. Alternative #1: Alternative #2: Alternative #3: Construct a radial 230 kV interconnection line, from a new 230 kV substation at Evander Andrews, to the Midpoint-Boise Bench #3 transmission line. Several N-l contingencies resulted in unacceptable overloads for this alternative. The additional improvement of a 230/138 kV transformer at Evander Andrews was evaluated in an unsuccessful attempt to achieve acceptable performance under N-l outage conditions. Construct two new 230 kV transmission lines from Bennett Mountain to Evander Andrews and Evander Andrews to Rattlesnake. These lines would complete a 230 kV loop from Rattlesnake to Bennett Mountain to Evander Andrews and back to Rattlesnake. In addition, the Dram-Midpoint #1 230 kV line would be looped into Rattlesnake and rebuilt to support bundled 230 kV conductors west of Rattlesnake. Additional transmission modifications were also modeled at DRAM substation to make the "Old Midpoint to DRAM #1" 230 kV line bypass the DRAM Substation and terminate at Boise Bench. 230/138 kV transformer was modeled at Evander Andrews to improve system performance under N-l conditions. Alternative #2 has no N-l outages that produce overloads that exceeds 115% of continuous rating and are also greater than existing system overloads for the same N-l. Alternative #2 will require curtailments of the proposed generators output following multiple N- outages. The Network Resource Rating for Alternative #2 is 67 MW. Alternative #2 is anticipated to be similar in cost to Alternative #3, yet does not perform as well. Rebuild a de-energized 132 kV transmissionline to 230 kV construction between Bennett Mountain and Mora Substations. This alternative utilizes the 406 line route which passes in the vicinity of Evander Andrews. The west end of the 230 kV line is assumed to terminate at a new 230 kV Mora Substation --' which is folded into the Boise Bench-Caldwell 230 kV line. No 230/138 kV transformer is modeled to tie the two Mora busses. A 230/138 kV transformer was modeled at Evander Andrews to improve system performance under N- conditions. Studies revealed the need to reconductor/rebuild the Evander Andrews to Mountain Home Junction 138 kV line. With the previously mentioned additions in-service, one N-l outage produces an overload above equipment continuous ratings. This overload only requires a 6% reduction in loading to fall to a level that can be sustained continuously. The estimated total cost for this alternative is approximately $26 Million, with approximately $22 Million allocated Idaho Power Company - Power Supply for the generator interconnection improvements and the remaining $4 Million allocated to Idaho Power Delivery to correct existing operational concerns. Following the execution of either a Large Generator Interconnection Agreement or a Engineering & Procurement Agreement by Idaho Power Company - Power Supply, Idaho Power Company estimates the time required to construct these facilities is approximately 18-21 months. These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). A cursory attempt has been made in this study to characterize each transmission improvement as either needed to integrate the proposed generator" or "needed to correct existing operational concerns . The proposed cost allocation is subject to change, as more information is known. These are cost estimates only and final charges to the customer will be based on the actual constrUction costs incurred. Summary of Interconnection Request A req4est was made to Idaho Power Co. by Idaho Power Company - Power Supply to study the interconnection of a proposed 91/100 MW simple cycle gas turbine at the Evander Andrews Project, near Mountain Home, Idaho, to Idaho Power s transmission system at the 230 kV level for Network Resource Interconnection Service. Scope of Interconnection Feasibility Study The Interconnection Feasibility Study was done and prepared in accordance with the FERC Order 2003-, Standard Large Generator Interconnection Procedures, to provide a preliminary evaluation ofthe feasibility ofthe interconnection ofthe proposed large generating project to the Idaho Power transmission system. This study will only be concerned with the capabilities ofthe Idaho Power system to manage this new resource within the study area of the proposed interconnection. Description of Proposed Generating Project Idaho Power Company - Power Supply prop,oses to connect a 91/100 MW simple cycle gas turbine to the Idaho Power 230 kV transmission system, at the existing Evander Andrews Power Complex, 1862 NW Mashburn RD., Mountain Home, ill 83647. The maximum generating capacity of the proposed unit is estimated to be 91 MW for the summer and 100 MW for winter temperatures. The equipment is described as being, 2 GE LM 6000 Packages, or a GE7F A, or a GE LMS 1 00 Package. The proposed commercial operation date is April 1 , 2007. Description of Existing Transmission Facilities At the Scoping Meeting for this Interconnection Request, it was agreed that the interconnection voltage to be studied would be 230 kV. The existing generating units at Evander Andrews Power Complex utilize the 138 kV transmission grid. No 230 kV transmission is present at Evander Andrews at this time. Evander Andrews has four 230 kV lines in relatively close proximity. Three of them run ITom the Midpoint Substation(north of Twin Falls, ill) to the east Boise area. The closest is the Midpoint- DRAM #1 line, which is approximately 4 miles Northeast of Evander Andrews. This line utilizes single 715.5 MCM conductors and has a continuous rating of339 MV A. The Rattlesnake-Boise Bench #2 line is approximately 5 miles Northeast of Evander Andrews and utilizes a 2 conductor bundle of715.5 MCM. This line has a continuous rating of 677 MV A. The Midpoint-Boise Bench #3 line is approximately 7 miles Northeast of Evander Andrews. This line has similar conductors and the same rating as the Rattlesnake-Boise Bench #2 line. The fourth 230 kV line in the area is the Rattlesnake-Bennett Mountain line. It is approximately 5 miles to the Southeast of Evander Andrews. This line utilizes single 1272 MCM conductors and has a continuous rating of 478 MVA. In addition to the three Midpoint to the east Boise area 230 kV lines previously mentioned, there are two 138 kV circuits which can carry power ITom the Mountain Home area to the Boise Area. They are: Mountain Home Junction-Lucky Peak-Micron 138 kV Line Mountain Home Junction-Evander Andrews-Strike-Swan Falls-Bowmont 138 kV Line Generators located in the Mountain Home area which are intended to serve load growth in the Treasure Valley area, will be adding new incremental flows on top of existing committed east-to- west transactions across the Midpoint West transmission cutplane. This feasibility study will model 1100 MW oftransfers across the Midpoint West cutplane, prior to this proposed generator addition. For these studies, the flow level of the Midpoint west cutplane is defined as the sum of the flows on the following lines: . Midpoint-DRAM #1 230 kV line . Midpoint-Rattlesnake #2230 kV Line . Midpoint-Boise Bench #3230 kV Line Lower Malad-Mountain Home Junction 138 kV Line Upper Salmon-Mountain Home Junction 138 kV Line Description of Configurations Studied Since the most limiting operating conditions are expected during heavy production on the upper and middle Snake and Boise River hydro plants, with heavy east-west transfers across the Idaho Power transmission system, the injection of the simple cycle gas turbine s 91 MW summer output was inserted into a power flow case that would simulate committed (1100 MW) pre-contingency flows on the Midpoint West transmission path. In accordance with the Scoping Meeting for this Feasibility Study Request, three alternatives were studied, all of which employed a 230 kV interconnection voltage. Alternative #1 employed a radial 230 kV line to connect the generator to the Midpoint-Boise Bench #3 transmission line. The line was modeled as being 7.7 miles in length and utilized 1272 MCM single conductor construction. An additional improvement of a 230/138 kV 200 MV A transformer(duplicate of the Midpoint unit) was explored at Evander Andrews to improve the performance of this alternative. Alternative #2 calls for the construction of two new 230 kV transmission lines from Bennett Mountain to Evander Andrews, and Evander Andrews to Rattlesnake. These lines would complete a 1272 MCM single conductor 230 kV loop from Rattlesnake to Bennett Mountain to Evander Andrews and back to Rattlesnake. In addition, the Dram-Midpoint #1230 kV line would be looped into Rattlesnake and rebuilt to support a two conductor bundle of715.5 MCM conductors west of Rattlesnake. Additional transmission modifications were also modeled outside of DRAM substation to make the "Old Midpoint to DRAM #1" 230 kV line bypass the DRAM Substation and terminate at Boise Bench. The combination of bundled conductors and folding the #lline into Rattlesnake Substation necessitated the change to avoid overloads at DRbM associated with the loss of the DRAM to Boise Bench 230 kV line. A 230/138 kV 200 My A transformer(duplicate of the Midpoint unit) was modeled at Evander Andrews to improve system performance under N-l conditions. Alternative #3 employed the rebuild of a de-energized 132 kV transmission line to 230 kV bundled 795 MCM construction between Bennett Mountain and Mora Substations. This alternative utilizes the 406 line route (originally was the Upper Salmon to Caldwell line) which passes in the vicinity of Evander Andrews. The west end of this new 230 kV line is assumed to terminate at a new 230 kV Mora Substation, which is folded into the Boise Bench-Caldwell 230 kV line. No 230/138 kV transformer is modeled to tie the two Mora busses. A 230/138 kV 200 MV A transformer(duplicate of the Midpoint unit) was modeled at Evander Andrews to improve system performance under N-l conditions. Studies also revealed the need to reconductor/rebuild the Evander Andrews to Mountain Home Junction 138 kV line, with this alternative. Post-transient Study Results This Interconnection Feasibility Study Report is for Network Resource Interconnection Service at 230 kV, for a 91/100 MW simple cycle gas turbine at the Evander Andrews Power Project. System transfers across the Midpoint West cutplane are modeled at 1100 MW prior to the proposed transmission improvements or the proposed generator producing any power. Hydro generation production for the Boise & Snake plants, were modeled at heavy, but realistic levels. Ouput levels for the existing peakers at Evander Andrews and Bennett Mountain were varied over their operating ranges as appropriate. N-O and N-l outage performance for the existing system are recorded. As agreed in the Scoping Meeting, three alternatives were evaluated. For each alternative, the new generator s output was taken to its summer temperature maximum level of91 MW and system conditions recorded for both N-O and N- outages. Existin2 System The following one line diagram depicts the existing system with no outages. Mid oint West = 1100 Existing System - No Outages Figure 1 For the existing system, seven N-l outages produce overloads that exceed the continuous rating of elements ofthe transmission system. The N-s that produce overloads with the existing system are included in Appendix B, Figures 7 - 13. Alternative #1 The following one line diagram depicts the system with Alternative #1 added, full summer output of the generator, and with no outages. Mid oint West = 1081 MW Alternative #1- No Outages Figure 2 Alternative #1 has multiple N-l outages that produce overloads that exceed 115% of continuous ratings. Some of the resulting overloads are reduced with the addition of the Evander Andrews 230/138 kV transformer, and others are increased. Some of the larger overloads are produced by the Lockman Butte to Boise Bench #3230 kV line outage. The following one line depicts a 123 % loading on the Mountain Home Junction to Lucky Peak 138 kV line, without the Evander Andrews 230/138 kV transformer. '- Mid oint West = 949 MW . Alternative #1 - Lockman Butte-Boise Bench #3 230 kV Outage Without the Evander Andrews 230/138 kV Transformer Figure 3 Adding the Evander Andrews 230/138 kV Transformer to the above outage, produces a 156% loading on the Mountain Home Junction to Lucky Peak 138 kV line. With the Evander Andrews 230/138 kV transformer in-service, there are no other N-l outages that produce overloads that exceed 115% loading. Without the Evander Andrews 230/138 kV transformer in-service, four otherN-l outages produces overloads that exceed 115% loading and are also greater than existing system overloads for the same N-l. They are: Rattlesnake - Boise Bench #2 230 kV Line outage Midpoint - Rattlesnake #2 230 kV line outage Evander Andrews - Strike 138 kV line outage Strike - Bowmont 138 kV line outage Several other N-l outages result in overloads below 115% that would require curtailments following the outage to get down to loadings that can be sustained continuously. In some cases, lowering the output of the proposed generator helps to lower the overload, but in one case (Lucky Peak - Micron 138 kV line outage), the overload increases as the proposed generators output is lowered. Alternative #1 is an unacceptable alternative, due to the N-l outage that produces an overload that exceeds 115% of continuous ratings. The Network Rating for Alternative #1 is 0 MW. Alternative #2 The following one line diagram depicts the system with Alternative #2 added, full output of the generator, and with no outages. Mid oint West = 1101 MW Alternative #2 - No Outages Figure 4 The aq,gition ofthe Evander Andrews 230/138 kV transformer improves the performance of Alternative #2 for most N-l outages, but not all. Without the Evander Andrews 230/138 kV transformer, Alternative #2 has four N-l outages that produce overloads that exceeds 115% of continuous rating, however, all the overloads are less than existing system overloads for the same N-l and as a result are judged to provide acceptable performance. With the Evander Andrews 230/138 kV transformer, Alternative #2 has no N-l outages that produce overloads that exceed 115% of continuous rating. Curtailments are required for all three N-l outages ofthe 230 kV lines from the Mountain Home area into Boise Bench. Loss of the Rattlesnake to Boise Bench #1 or #2 lines require the proposed unit's output to be lowered to approximately 67 MW to reduce overloads to 100% ofthe continuous rating or a level that the overload is no worse than it is for the existing system with the same N-l outage. These contingencies and resulting system performance determines the Network Resource Rating to be 67 MW for Alternative #2. The loss ofthe Midpoint to Boise Bench #3230 kV line requires a curtailment to lower a 120% overload of the series capacitors on the Midpoint to Rattlesnake #2 230 kV line. This alternative does not permit the overload to be reduced by lowering the output ofthe proposed unit. Lowering the output of proposed unit will increase the overload on the series capacitors in question. Other generators would have to be curtailed to solve this overload scenario. ' -'- Alternative #2 will require curtailments of the proposed generators output following multiple l outages. As a result, Alternative #2 does not provide acceptable performance for Network Resource Interconnection Service for the proposed unit at full output. The Network Resource Rating for Alternative #2 is 67 MW. Alternative #2 is also believed to very similar in cost to Alternative #3, yet it's performance is much more problematic than Alternative #3. Alternative #3 The following one line diagram depicts the system with Alternative #3 added, full output of the generator, and with no outages. Mid oint West = 1119 Alternative #3 - No Outages Figure 5 The addition of the Evander Andrews 230/138 kV transformer improves the performance of Alternative #3, for all but one ofthe N-l outages. With the Evander Andrews 230/138 kV transformer in service, alternative #3 has no N-l outages that produce overloads that exceed 115% of continuous ratings. One N-l outage results in an overload below 115% and at a level that the overload is greater than it is for the existing system with the same N-l outage. The loss of the Midpoint to Boise Bench #3230 kV line results in a 116% loading on the series capacitor of the Midpoint to Rattlesnake #2 230 kV line. This series capacitor is capable of 110% loading continuously, so a 6% reduction in flow is required. Lowering generation in the Mountain Home area results in increased flow on the series capacitor bank, so transfers across the Midpoint West cutp1ane will need to be reduced to correct this overload, as well as prepare for the next contingency. Alternative #3 changes the characteristics of the interconnected network enough to create the need to reconductor/rebui1d the Evander Andrews to Mountain Home Junction 138 kV line. For the N-l outage of the Lucky Peak to Micron 138 kV line, the Evander Andrews to Mountain Home Junction 138 kV line loads to 113% of its rating with all the peaking generation in the Mountain Home area at full output. lithe output of the peaking generation in the Mountain Home area is reduced, the overload increases in magnitude. The following one line diagram depicts the Lucky Peak to Micron 138 kV line outage with all the Mountain Home area peaking generation offline. Mid oint West = 1157 Alternative #3 - Luck Peak to Micron 138 kV Line Outage With Peakers Off-line Figure 6 Alternative #3 is the recommended alternative for the proposed unit at 91/100 MW for Network Resource Interconnection Service. Cost Allocation of Proposed Improvements Alternative #3 contains the following five construction components: Bennett Mountain to Evander Andrews 230 kV line and terminals Evander Andrews to Mora 230 kV line and terminals 230 kV generator connection terminal at Evander Andrews Evander Andrews 230/138 kV transformer and terminals Reconductor/rebuild of the Evander Andrews to Mountain Home Junction 138 kV line A cursory attempt has been made in this study to characterize each transmission improvement as either "needed to integrate the proposed generator" or "needed to correct existing operational concerns . The costs associated with those improvements believed to be "needed to integrate the proposed generator" are allocated to the generator interconnection. The costs 10- associated with those improvements believed to be "needed to correct existing operational concerns " are allocated to IPCo Delivery. Approximate estimated costs allocated to the generator interconnection are: $ 4.1 Million - Bennett Mountain to Evander Andrews 230 kV line and terminals $17.3 Million - Evander Andrews to Mora 230 kV line and terminals $ 0.4 Million - 230 kV generator connection terminal at Evander Andrews $21.8 Million - Total estimated generator interconnection cost Approximate estimated costs allocated to the IPCo Delivery are: $2.1 Million - Evander Andrews 230/138 kV transformer and terminals $1.7 Million - Evander Andrews to Mountain Home Junction 138 kV line rebuild $3.8 Million - Total estimated allocation to IPCo Delivery These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). The proposed cost allocation is subj ect to change, as more information is known. These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. 10.Short Circuit Study Results Preliminary short circuit study results indicate the surrounding circuit breakers are believed to be able to accommodate the increased fault duty. No circuit breaker replacements are anticipated at this time. 11.Conclusions The feasibility of interconnecting a 91/100 MW simple cycle gas turbine at Evander Andrews Power Complex to Idaho Power s 230 kV transmission system was studied. Three interconnection alternatives were evaluated. Alternative #1 was found to be an unacceptable alternative due to transmission system loadings that exceeded 115% for N-l outages. Alternative #2 did not provide acceptable performance for Network Resource Interconnection Service for the proposed unit at full output. The Network Resource Rating for Alternative #2 is 67 MW. Alternative #3 was found to be an acceptable interconnection alternative. While Alternative #3 does require minimal redispatch/transmission switching for one N-l outage, it is minor in nature and deemed acceptable for this feasibility study. The estimated total cost of the transmission improvements associated with Alternative #3 is approximately $26 Million. At this time it is believed that approximately $22 Million of these estimated costs should be allocated to the generator interconnection. 11- '-, APPENDIX A 1.0 Method of Study The study methodology inserts the proposed generator up to the maximum requested summer output of91 MW into the selected WECC power flow case and then, using the PowerWorld Simulator powerflow program, examines the impacts of the new resource on Idaho Power transmission system (lines, transformers, etc.) within the study area under various operating/outage scenarios. The WECC and Idaho Power reliability criteria and Idaho Power operating procedures were used to determine the acceptability of the alternatives considered. The WECC case is a recent cases modified to simulate stressed but reasonable pre-contingency energy transfers utilizing the IPC system. Acceptability Criteria The following acceptability criteria were used in the power flow analysis to determine the acceptabilityofthe alternatives: Loadings on transmission lines and transformers should not exceed 115% of the continuous rating, immediately flowing anyN-l outage. Loading on the Midpoint 230 kV series capacitors should not exceed 135% of the continuous rating, immediately flowing anyN-l outage. These loadings levels of 115% on transmission lines and transformers and 135% on Midpoint series capacitors correspond to IPCo s 30 minute ~~emergency equipment ratings. Any loadings immediately following an N-l outage less than the 30 minute emergency rating is acceptable. Loadings which are less than the 30 minute emergency equipment ratings, but greater than the equipment continuous ratings, must be reduced to the continuous ratings by generation curtailments, re-dispatch, or some other operating procedure. Any remedial action schemes(RAS) or other transmission switching, must be judged to be reasonable before the alternatives performance can be deemed acceptable. The continuous rating of equipment is assumed to be the normal thermal rating of the equipment. This rating will be as determined by the manufacturer of the equipment or as determined by Idaho Power. Less than or equal to 100% of continuous rating for transmission lines and transformers is acceptable. Less than or equal to 110% of continuous rating for the Midpoint 230 kV series capacitors is acceptable. Transmission voltages, under normal operating conditions, are maintained within plus or minus 5% (0.05 per unit) of nominal. Therefore, voltages greater than or equal to 95 pu voltage and less than or equal to 1.05 pu voltage are acceptable. The stable operation of the transmission system requires an adequate supply of volt- amperes reactive (V ARs) to maintain a stable voltage profile under both steady-state and dynamic system conditions. An inadequate supply of V ARs will result in voltage 12- decay or even collapse under the worst conditions. Idaho Power designs its system to integrate Network Resources at full capability during specified outage conditions. Equipment/line/path ratings used will be those that are in use at the time of the study or that are represented by IPC upgrade projects that are either currently under construction or whose. budgets have been approved for construction in the near future. All other potential future ratings are outside the scope ofthis study. Future transmission changes may, however, affect current facility ratings used in the study. 13- APPENDIX B 1.0 l Outages That Produce Overloads On The Existing System The following one line diagrams depict system performance following the seven N-l outages that produce overloads which exceed the continuous rating of facilities. Figure 1 on page 5 depicts the operation of the existing system with no outages. The combination of heavy hydro and peaker generation in the Mountain Home area, and 1100 MW east to west transfers on Midpoint West, results in the Mountain Home Junction to Lucky Peak and Lucky Peak to Micron 138 kV lines being loaded to 98% & 99% respectively, prior to any outages. Mid oint West = 981 Existing System - Midpoint to Boise Bench #3 230 kV Outage Figure 7 14- Mid oint West = 951 Existing System - Rattlesnake to Boise Bench #2 230 kV Outage Figure 8 Mid oint West = 997 Existing System - Midpoint to Rattlesnake #2 230 kV Outage Figure 9 15- Mid oint West = 1053 MW Existing System - Midpoint to DRAM #1 230 kV Outage Figure 10 Mid oint West = 1085 Existing System - CJ Strike to Bowmont 138 kV Outage Figure 11 16- Mid oint West = 1072 Existing System - Lucky Peak to Micron 138 kV Outage Figure 12 MIdpoint West = 1094 Existing System - Evander Andrews to CJ Strike 138 kV Outage Figure 13 17- - , LARGE GENERATOR INTERCONNECTION FEASIBILITY STUDY REPORT for the 138 KV INTERCONNECTION OPTION EV ANDER ANDREWS PROJECT for Idaho Power Company - Power Supply, Interconnection Customer for connection of A 73/86 MW SIMPLE CYCLE GAS TURBINE PEAKING PROJECT EV ANDER ANDREWS PROJECT IDAHO POWER COMPANY, Transmission Provider TRANSMISSION SYSTEM FINAL REPORT October 14, 2005 1.0 Introduction Idaho Power Company - Power Supply has contracted with Idaho Power Company (IPC) to perform a Large Generator Interconnection Feasibility Study for Network Resource Interconnection Service at 138 kV for the integration of a new 73/86 MW simple cycle gas turbine peaking project. The proposed location is the Evander Andrews Project near Mountain Home, Idaho. This report documents the basis for and the results of this Feasibility Study. It describes the proposed interconnection alternatives, the study cases used, outage scenarios assumed and results of all work in the areas of concern. Summary The performance of a 138 kV interconnection alternative was evaluated to integrate a simple cycle gas turbine with a summer rating of 73 MW and a winter rating of 86.3 MW, located at Evander Andrews Project, into the Idaho Power System. Several system performance problems for N-l outages , necessitated additional facility additions, but ultimately a 138 kV interconnection alternative was found that performed acceptably. The addition of a new 138 kV transmission line from Evander Andrews to the Mora Substation was the initial interconnection alternative that was evaluated. It did not perform acceptably for its own N-l outage. To correct this performance shortcoming, a 230/138 kV 200 MV A transformer at Rattlesnake Substation and a new 138 kV transmission line from Rattlesnake to Mountain Home Junction was added to the alternative. The additional facilities resulted in acceptable performance for the N-l outage ofthe proposed Evander Andrews to Mora 138 kV line. However, the 230/138 kV transformer addition resulted in performance problems for a different N-l outage. As a result, the reconductor/rebuild of the Evander Andrews to Mountain Home Junction 138 kV transmission line was added to the necessary facility additions for the 138 kV interconnection alternative. The estimated total cost for this alternative is approximately $23.1 Million, with all the costs allocated to Idaho Power Company - Power Supply for the generator interconnection improvements. Following the execution of either a Large Generator Interconnection Agreement or a Engineering & Procurement Agreement by Idaho Power Company - Power Supply, Idaho Power Company estimates the time required to construct these facilities is approximately 18-21 months. These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. Summary of Interconnection Request A request was made to Idaho Power Co. by Idaho Power Company - Power Supply to study the interconnection of a proposed 73/86 MW simple cycle gas turbine at the Evander Andrews Project, near Mountain Home, Idaho, to Idaho Power s transmission system at the 138 kV level for Network Resource Interconnection Service. Scope of Interconnection Feasibility Study The Interconnection Feasibility Study was done and prepared in accordance with the FERC Order 2003-, Standard Large Generator Interconnection Procedures , to provide a preliminary evaluation of the feasibility of the interconnection of the proposed large generating project to the Idaho Power transmission system. This study will only be concerned with the capabilities of the Idaho Power system to manage this new resource within the study area of the proposed interconnection. Description of Proposed Generating Project Idaho Power Company - Power Supply proposes to connect a 73/86 MW simple cycle gas turbine to the Idaho Power 138 kV transmission system, at the existing Evander Andrews Power Complex, 1862 NW Mashburn RD., Mountain Home, ill 83647. The maximum generating capacity of the proposed unit is estimated to be 73 MW for the summer and 86.3 MW for winter temperatures. The equipment is described as being, two GE LM 6000 packages , or a GE7FA, or a GE LMSlOO package. The proposed commercial operation date is April 1 2007. Description of Existing Transmission Facilities At the Scoping Meeting for this Interconnection Request, it was agreed that the interconnection voltage to be studied would be 138 kV. The existing generating units at Evander Andrews Power Complex utilize the 138 kV transmission grid. No 230 kV transmission is present at Evander Andrews at this time. Evander Andrews has four 230 kV lines in relatively close proximity. Three of them run from the Midpoint Substation(north of Twin Falls, ill) to the east Boise area. The closest is the Midpoint- DRAM #1 line, which is approximately 4 miles Northeast of Evander Andrews. This line utilizes single 715.5 MCM conductors and has a continuous rating of 339 MV A. The Rattlesnake-Boise Bench #2 line is approximately 5 miles Northeast of Evander Andrews and utilizes a 2 conductor bundle of 715.5 MCM. This line has a continuous rating of 677 MV A. The Midpoint-Boise Bench #3 line is approximately 7 miles Northeast of Evander Andrews. This line has similar conductors and the same rating as the Rattlesnake-Boise Bench #2 line. The fourth 230 kV line in the area is the Rattlesnake-Bennett Mountain line. It is approximately 5 miles to the Southeast of Evander Andrews. This line utilizes single 1272 MCM conductors and has a continuous rating of 478 MVA. In addition to the three Midpoint to the east Boise area 230 kV lines previously mentioned, there are two 138 kV circuits which can carry power from the Mountain Home area to the Boise Area. They are: Mountain Home Junction-Lucky Peak-Micron 138 kV Line Mountain Home Junction-Evander Andrews-Strike-Swan Falls-Bowmont 138 kV Line Generators located in the Mountain Home area which are intended to serve load growth in the Treasure Valley area, will be adding new incremental flows on top of existing committed east-to- west transactions across the Midpoint West transmission cutplane. This feasibility study will model 1100 MW of transfers across the Midpoint West cutplane, prior to this proposed generator addition. For these studies, the flow level of the Midpoint west cutplane is defined as the sum of the flows on the following lines: . Midpoint-DRAM #1 230 kV line . Midpoint-Rattlesnake #2 230 kV Line . Midpoint-Boise Bench #3230 kV Line Lower Malad-Mountain Home Junction 138 kV Line Upper Salmon-Mountain Home Junction 138 kV Line Description of Configurations Studied Since the most limiting operating conditions are expected during heavy production on the upper and middle Snake and Boise River hydro plants , with heavy east-west transfers across the Idaho Power transmission system, the injection of the simple cycle gas turbine s 73 MW summer output was inserted into a power flow case that would simulate committed (1100 MW) pre-contingency flows on the Midpoint West transmission path. In accordance with the Scoping Meeting for this Feasibility Study Request a 138 kV alternative was studied. A new Evander Andrews to Mora 138 kV transmission line, utilizing 1272 MCM single conductor construction, was explored in the initial powerflow studies. This line is assumed to be 36.4 miles in length. The initial powerflow studies indicated additional facility improvements would be required to achieve satisfactory system performance under N-l outage conditions. As a result, the addition of a 230/138 kV 200 MV A transformer at Rattlesnake Substation and a 138 kV transmission line from Rattlesnake to Evander Andrews was incorporated into the configuration studied. The Rattlesnake to Evander Andrews 138 kV line was assumed to be 1 mile in length and utilized 954 MCM single conductor construction. Subsequent powerflow studies indicated additional facility improvements would be required to achieve satisfactory system performance under different N -1 outage conditions. The final facility addition to the configuration studied was a reconductor/rebuild of the Evander Andrews to Mountain Home Junction 138 kV line. This line is approximately 5.6 miles in length and the existing 397.5 MCM conductors were upgraded to 954 MCM. The facility additions employed in the final configuration of this study are listed below: A new 138kV transmission line from Evander Andrews to Mora Substation. A new 230/138 kV 200 MV A transformer at Rattlesnake Substation. A new 138 kV transmission line from Rattlesnake to Mountain Home Junction. A reconductor/rebuild of the Evander Andrews to Mountain Home Junction 138 k transmission line. Post-transient Study Results This Interconnection Feasibility Study Report is for Network Resource Interconnection Service at 138 kV, for a 73/86 MW simple cycle gas turbine at the Evander Andrews Power Project. System transfers across the Midpoint West cutplane are modeled at 1100 MW prior to the proposed transmission improvements or the proposed generator producing any power. Hydro generation production for the Boise & Snake plants , were modeled at heavy, but realistic levels. Output levels for the existing peakers at Evander Andrews and Bennett Mountain were varied over their operating ranges as appropriate. N-O and N-l outage performance for the existing system are recorded. As agreed in the Scoping Meeting, a 138 kV alternative was evaluated. For the 138 kV alternative, the new generator s output was taken to its summer temperature maximum level of 73 MW and system conditions recorded for both N-O and N- outages. Existing System The following one line diagram depicts the existing system with no outages. BOISEBCH1.02," Mld olnt West = 1100 Existing System - No Outages Figure 1 For the existing system, seven N-l outages produce overloads that exceed the continuous rating of elements of the transmission system. The N-l' s that produce overloads with the existing system are included in Appendix B , Figures 9 - 15. Additional Facilities Added The following one line diagram depicts the system with full summer output of the generator only the Evander Andrews- Mora 138 kV line added, and with no outages. n1E,", Mid oint West = 1100 Evander Andrews to Mora Line & Generator Added - No Outages Figure 2 With the generator and the Evander Andrews to Mora 138 kV line added, one N-l outage produces an overload that exceeds 115% of continuous ratings. The N-l outage with unacceptable performance is loss of the new Evander Andrews to Mora 138 kV line. The following one line diagram depicts the system performance with full summer output of the generator and loss of the Evander Andrews to Mora 138 kV line. ,,\,Iij' MidDoint West 1089 MW Loss of Evander Andrews to Mora 138 kV Line, when it was the only proposed transmission improvement Figure 3 The 119% loading on the Mountain Home Junction to Lucky Peak 138 kV line, requires additional transmission improvements be added to this proposal in an attempt to achieve acceptable performance for a 138 kV interconnection alternative. The least expensive transmission addition that will relieve the Mountain Home Junction to Lucky Peak 138 kV overload, is installation of a 230/138 kV 200 MV A transformer at Rattlesnake Substation along with a new one-mile long 954 MCM 138 kV line from the low side of the transformer to Mountain Home Junction. The following one line depicts system performance with transmission improvements including, the Evander Andrews to Mora 138 kV line, a 230/138 k V 200 MV A transformer at Rattlesnake, and a new 138 k V line from Rattlesnake to Mountain Home Junction, with no outages. n,!!'.", MidDoint West = 1101 MW Evander Andrews to Mora 138 kV Line, Rattlesnake 230/138 k V Transformer, Rattlesnake to Mountain Home Junction 138 kV Line, & Generator Added - No Outages Figure 4 For the transmission facilities shown above, three N-l outages produce overloads that exceed 115 % of continuous ratings. All three outages create overloads on the Evander Andrews to Mountain Home Junction 138 kV line. The following one line depicts system performance with transmission improvements including, the Evander Andrews to Mora 138 kV line, a 230/138 kV 200 MV A transformer at Rattlesnake, and a new 138 kV line from Rattlesnake to Mountain Home Junction. The outage for this one line diagram is the 230 kV Boise Bench to Rattlesnake #2 line, with all the peakers off-line at Evander Andrews. Bn~'j,"" MidDoint West = 1033 MW Evander Andrews to Mora 138 k V Line added, Rattlesnake 230/138 kV Transformer added Rattlesnake to Mountain Home Junction 138 kV Line added, & Evander Andrews Peakers Off-line - with Boise Bench to Rattlesnake #2 230 k V Line Outage Figure 5 The overloads experienced on the Evander Andrews to Mountain Home Junction 138 kV line for all three problem N -1' s , mandates the need to reconductorlrebuild the line with a minimum of 954 MCM conductor. The following one line diagram depicts system performance with no outages for the following additions: Evander Andrews to Mora 1272 MCM 138 kV Line Rattlesnake 230/138 kV 200 MV A Transformer Rattlesnake to Mountain Home Junction 954 MCM 138 kV Line Evander Andrews to Mountain Home Junction reconductorlrebuild from 397. MCM conductor to 954 MCM conductor bW" Mid oint West = 1101 Evander Andrews to Mora 138 k V Line added Rattlesnake 230/138 k V Transformer added, Rattlesnake to Mountain Home Junction 138 kV Line added, & Mountain Home Junction to Evander Andrews 138 kV Line Reconductored - No Outages Figure 6 Two N-l outages result in performance concerns for the addition of the generator and the other transmission facilities listed above. The most serious concern is for the outage of the Boise Bench to Rattlesnake #2 230 kV line, with all the peaking generation on-line at Evander Andrews. The following one line diagram depicts system performance for this outage. nl'iJ', Mld oint West 1003 MW Evander Andrews to Mora 138 k V Line added Rattlesnake 230/138 kV Transformer added, Rattlesnake to Mountain Home Junction 138 kV Line added, & Mountain Home Junction to Evander Andrews 138 kV Line Reconductored - Boise Bench to Rattlesnake #2 230 kV Line Outage Figure 7 The 136% loading on the Mountain Home Junction to Lucky Peak 138 kV line will require a remedial action scheme(RAS) to provide acceptable performance. Following the loss of the Boise Bench to Rattlesnake #2 230 kV line, either the Rattlesnake 230/138 kV transformer or the Mountain Home Junction to Lucky Peak 138 kV line could be opened to relieve the overload. The following one line diagram depicts system performance for a remedial action scheme that opens the Rattlesnake 230/138 kV transformer following the loss of the Boise Bench to Rattlesnake #2 230 kV line. 10- BOISEBeH00p" Mid oint West = 957 Evander Andrews to Mora 138 kV Line added Rattlesnake 230/138 kV Transformer added, Rattlesnake to Mountain Home Junction 138 kV Line added & Mountain Home Junction to Evander Andrews 138 kV Line Reconductored - Boise Bench to Rattlesnake #2 230 kV Line Outage with RAS opening Rattlesnake 230/138 k V Transformer Figure 8 The N-l outage of the Rattlesnake to Midpoint #2 230 kV line, with the Evander Andrews peaking generation off-line, creates a 2% overload of the Upper Salmon to Mountain Home Junction 138 kV line. An operating procedure will be required to relieve this minor overload. Opening the Rattlesnake 230/138 kV transformer is a possible solution. Both the remedial action scheme and the operating procedure can be further investigated if this project proceeds to a system impact study. The Brownlee to Ontario 230 kV line outage is critical in determining the timing of the next major transmission system improvement project required for Treasure Valley load growth. For the existing system approximately 205 MW of NampalCaldwell area load growth can be accommodated before major transmission improvements are required. With 73 MW of new generation at the Evander Andrews Site and the associated transmission facility improvements for a 138 kV interconnection, approximately 228 MW of load growth in the NampalCaldwell area can be accommodated before major transmission system improvements are required. As a result, the utilization of the 138 kV interconnection alternative for a 73 MW generator at the Evander Andrews Site will slightly delay the schedule for the next major transmission system improvement to accommodate load growth in the NampalCaldwell area. 11- ,.. A 138 kV interconnection alternative is feasible for Network Resource Interconnection Service for the proposed 73/86 MW simple cycle gas turbine at the Evander Andrews Project. With the following transmission facility additions, marginally acceptable system performance is possible: Evander Andrews to Mora 1272 MCM 138 kV Line Rattlesnake 230/138 kV 200 MV A Transformer Rattlesnake to Mountain Home Junction 954 MCM 138 kV Line Evander Andrews to Mountain Home Junction reconductorlrebuild from 397. MCM conductor to 954 MCM conductor Cost Estimates of Proposed Improvements Approximate estimated costs for the proposed transmission improvements are: $16.9 Million - Evander Andrews to Mora 138 kV line and terminals $ 4.0 Million - Rattlesnake 230/138 kV Transformer and Rattlesnake to Mountain Home Junction 138 kV Line & associated terminals $ 1.7 Million - Evander Andrews to Mountain Home Junction 138 k V Line Reconductorlrebuild $ 0.5 Million - Generator 138 kV Connection Terminal at Evander Andrews $23.1 Million - Total estimated generator interconnection cost All of these interconnection costs would be allocated to the generator interconnection. These cost estimates include direct equipment and installation labor costs, indirect labor costs and overheads, and allowance for funds used during construction (AFUDC). These are cost estimates only and final charges to the customer will be based on the actual construction costs incurred. 10.Short Circuit Study Results Preliminary short circuit study results indicate the surrounding circuit breakers are believed to be able to accommodate the increased fault duty. No circuit breaker replacements are anticipated at this time. 11.Conclusions The feasibility of interconnecting a 73/86 MW simple cycle gas turbine at Evander Andrews Power Complex to Idaho Power s 138 kV transmission system was studied. Initial studies found adding only a Evander Andrews to Mora 138 kV line would not yield acceptable performance. Several successive rounds of adding additional transmission improvements did eventually yield marginally acceptable performance. The required transmission improvements are: 12- A new 138 kV transmission line from Evander Andrews to Mora Substation. A new 230/138 kV 200 MV A transformer at Rattlesnake Substation. A new 138 kV transmission line from Rattlesnake to Mountain Home Junction. A reconductorlrebuild of the Evander Andrews to Mountain Home Junction 138 kV transmission line. The estimated total cost of the transmission improvements associated with the 138 k interconnection alternative is approximately $23.1 Million. At this time, it is believed that the entire $23.1 Million should be allocated to the generator interconnection. 13-