HomeMy WebLinkAbout20060706ICIP to IPC 20-30.pdf,':'
Peter Richardson
RECEIVED
200& JUL -6 AM 8: 04
IDAHO PUBLIC
UTILITIES COMMISSION
(C~;S~)JNf &: (I)!~YATTORNEYS AT LAW
Tel: 208-938-7901 Fax: 208-938-7904
peterlB' rich ardso nandoleary.com
O. Box 7218 Boise, 10 83707 - 515 N. 27th Sr. Boise, ID 83702
5 July 2006
Ms. Jean Jewell
Commission Secretary
Idaho Public Utilities Commission
POBox 83720
Boise ID 83720-0074
RE: Case No.lPC-O6-
Dear Ms. Jewell:
Enclosed please find three (3) copies of the SECOND PRODUCTION
REQUEST OF THE INDUSTRIAL CUSTOMERS OF IDAHO POWER TO IDAHO
POWER COMPANY in the above case. The original request has been sent to
Idaho Power Company.
Sincerely,
Nina Curtis
Administrative Assistant
end.
Peter J. Richardson
RICHARDSON & O'LEARY PLLC
515 N. 27th Street
Boise, Idaho 83702
Telephone: (208) 938-7901
Fax: (208) 938-7904
peter~richardsonando I eary. com
Attorneys for the Industrial Customers of Idaho Power
RECEWED
LOOn JUl-t) At' 8:
UT\~R~~~ J~J~\~S\ON
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION
OF IDAHO POWER COMPANY FOR A
CERTIFICATE OF CONVENIENCE AND
NECESSITY FOR THE EV ANDER ANDREWSPOWER PLANT
CASE NO. IPC-O6-
SECOND PRODUCTION
REQUEST OF THE
INDUSTRIAL
CUSTOMERS
OF IDAHO POWER TO
IDAHO POWER
COMPANY
Pursuant to Rule 225 of the Rules of Procedure of the Idaho Public Utilities
Commission (the "Commission ), the Industrial Customers of Idaho Power (ICIP) , by
and through their attorney of record, Peter J. Richardson, hereby requests that Idaho
Power Company ("Idaho Power ) provide the following documents.
This production request is to be considered as continuing, and Idaho Power is
requested to provide by way of supplementary responses additional documents that it or
any person acting on its behalf may later obtain that will augment the documents
produced.
Please provide one copy of your answer to Mr. Richardson at the address noted
above and one copy to Dr. Reading at 6070 Hill Road, Boise, Idaho 83703. Please
provide Dr. Reading s copy in electronic format, if available.
1 - SECOND PRODUCTION REQUEST OF ICIP TO IDAHO POWER
For each item, please indicate the name of the person(s) preparing the answers
along with the job title of such person(s) and the witness at hearing who can sponsor the
answer.
REQUEST FOR PRODUCTION NO. 20:
Please provide a copy of the most recent draft of Idaho Power s 2006 IRP.
REQUEST FOR PRODUCTION NO. 20-
Please explain the role gas fIred generation is expected to play in Idaho Power
2006 IRP. Please provide all work papers and documents in the Company s possession
that address the role natural gas will play in supplying the Company s load in the future.
REQUEST FOR PRODUCTION NO. 21:
On page 19 of Mr. Said's testimony, he states
While the Company is satisfied that the approximately $22.million estimate for
transmission and substation costs associated with this Project is a reasonable
upper limit estimate, no definitive studies have been completed and the Company
is not including transmission costs in its Commitment Estimate.
Please provide a timeline and description of the definitive studies that must be completed
before the Company will be able to determine the actual amounts of transmission and
substation costs associated with this Project.
REQUEST FOR PRODUCTION NO. 21-
Please explain and provide all documentation relied upon that allowed the Company to
conclude that it is "satisfied" that the $22.8 million estimate is "reasonable
REQUEST FOR PRODUCTION NO. 22
On page 18 of Mr. Said's testimony, he states that "(a)lthough the transmission
system will require additional investment in order to integrate the Project, those
2 - SECOND PRODUCTION REQUEST OF ICIP TO IDAHO POWER
improvements will provide capacity during all seasons and improve the reliability of the
Company s transmission system." Please provide all documents that Idaho Power relied
on in making the determination, or which demonstrate that the improvements will
provide capacity during all seasons and improve the reliability of the Company
transmission system.
REQUEST FOR PRODUCTION NO. 23
On page 15 ofMr. Said's testimony, he states that "(fJorecasted natural gas prices
from the 2004 IRP were used in the bid evaluation." At any time during its evaluation of
the various responses to Idaho Power s RFP, did Idaho Power use an updated forecast of
natural gas prices?
REQUEST FOR PRODUCTION NO. 24
Should the Commission deny Idaho Power s request for a certificate of public
convenience and necessity, what supply or demand reduction alternative options would
the company turn to in the summer of 2008? (If Idaho Power already answered, or
intends to answer this question in response to ICIP's Request for Production No. 18
please disregard this request.)
REQUEST FOR PRODUCTION NO. 25
On page 21 of Mr. Said's testimony, he explains that "Siemens has located an
existing, new Generator Step-Up Transformer (GSU) that is available for the Project at
significant cost savings in comparison to identical transformers that are being
manufactured today." He also states that "(i)n order to take advantage of the cost
3 - SECOND PRODUCTION REQUEST OF ICIP TO IDAHO POWER
savings, the Company must act expeditiously." Please provide copies of all documents
that Idaho Power or its employees have reviewed that demonstrate that the GSU is
available at a significant cost savings in comparison to identical transformers that are
being manufactured today.
REQUEST FOR PRODUCTION NO. 26:
Please provide all documents that have been in the possession of Idaho Power
which relate to the GSU referenced on page 21 of Mr. Said's testimony.
REQUEST FOR PRODUCTION NO. 27
In Response to Request No. 41 of Staff's First Production Request , the Company
stated "(l)ast year during normal operations, the existing Danskin Power plant emitted a
total of 0 tons Sulfur Dioxide, 5.72 tons of NO x and 1.5 tons of CO." Please indicate the
estimates of pollutant emissions for each plant if both were operated to their full capacity
under the existing air permits. Please indicate the hours of operation for each plant if
both were operated to their full capacity under the existing air permits.
REQUEST FOR PRODUCTION NO. 28:
In Response to Request No. 61 of Staffs First Production Request, the Company
stated "Idaho Power did not receive any bids in this RFP that would require energy to
cross the Borah-West transmission constraint." Assuming the plant is constructed, does
the Company anticipate there will be any impact on the Borah- West transmission
constraint? If so, how much and what kind? Please explain the answer fully.
REQUEST FOR PRODUCTION NO. 29
In Response to Request No. 15 of Staffs First Production Request, Idaho Power
states
4 - SECOND PRODUCTION REQUEST OF ICIP TO IDAHO POWER
With the 2005 RFP, the Company was convinced that based upon recent
experience with the 2003 RFP process, it would receive sufficient competitive
bids, the Company had reasonable benchmarks for peaking unit prices and that
expenses associated with self-build preparation could be avoided
Please provide the "reasonable benchmarks for peaking unit prices" that the Company
had. Please provide a copy of all related documents, or, if none are available, a
description of what the reasonable benchmarks were and how they were calculated.
REQUEST FOR PRODUCTION NO. 30:
In Response to Request No. 40 of Staff's First Production Request , Idaho Power
describes the new permits that will need to be obtained before constructing the Evander
Andrews plant. Is the cost of obtaining these permits included in the Company
Commitment Estimate of $60 million? Are the expected costs of complying with permit
conditions included in the Company s Commitment Estimate of$60 million?
DATED this 5th day of July 2006.
RICHARDSON & O'LEARY PLLC
By: f24, Peter J. Richardson, ISB #3195
Attorneys for the Industrial
Customers of Idaho Power
5 - SECOND PRODUCTION REQUEST OF ICIP TO IDAHO POWER
CERTIFICATE OF SERVICE
I HEREBY CERTIFY that on this 5th day of July, 2006, I caused a true and
correct copy ofthe foregoing SECOND PRODUCTION REQUEST OF THE INDUSTRIAL
CUSTOMERS OF IDAHO POWER to be served by the method indicated below, and
addressed to the following:
Jean Jewell
Idaho Public Utilities Commission
472 West Washington Street (83702)
Post Office Box 83720
Boise, Idaho 83720-0074
(X) U.S. Mail, Postage Prepaid
( ) Hand Delivered
( ) Overnight Mail
( ) Facsimile
( ) Electronic Mail
Barton L. Kline
Idaho Power Company
1221 W. Idaho St. (83702)
PO Box 70
Boise, Idaho 83707
bkline(~jdahopower .com
mmoen~idahopower. com
( ) U.S. Mail, Postage Prepaid
( )
Hand Delivered
( ) Overnight Mail
( ) Facsimile
(X) Electronic Mail
Donovan Walker
Deputy Attorney General
Idaho Public Utilities Commission
472 W. Washington (83702)
PO Box 83720
Boise, ID 83720-0074
Donovan. walker~puc.idaho. gov
( ) U.S. Mail, Postage Prepaid
( ) Hand Delivered
( ) Overnight Mail
( ) Facsimile
(X) Electronic Mail
James C. Miller
Sr. Vice President, Generation
Idaho Power Company
1221 W. Idaho St. (83702)
PO Box 70
Boise, Idaho 83707
i immiller~idahopower .com
( ) U.S. Mail, Postage Prepaid
( ) Hand Delivered
( ) Overnight Mail
( )
Facsimile
(X) Electronic Mail
CERTIFICATE OF SERVICE - 1
Ronald L. Williams
Williams Bradbury, P.
PO Box 2128
Boise, ID 83701
ron~williamsbradbury .com
( ) U.S. Mail, Postage Prepaid
( ) Hand Delivered
( ) Overnight Mail
( ) Facsimile
(X) Electronic Mail
Robert D. Looper
President
Mountain View Power, Inc.
1015 W Hays Street
Boise, ID 83702
rlooper~spellc.com
( ) U.S. Mail, Postage Prepaid
( )
Hand Delivered
( )
Overnight Mail
( ) Facsimile
(X) Electronic Mail
Signed: ~.a.Jn CuJ\~~
Nina M. Curtis
CERTIFICATE OF SERVICE - 2