Loading...
HomeMy WebLinkAbout20031212Supplemental 1st Response of Idaho Power to Staff.pdfIDAHO POWER COMPANY O. BOX 70 BOISE, IDAHO B3707 F?ECE/VE r:- i:~ Iii: n ' '~'--U ZaU3 DEC I I P~f 4: 28 BARTON L. KLINE Senior Attorney An IDACORP Company ,.. iU;.;iU fUi;Lir'U IIUTIES COMrf/SSlfm December 11 2003 Jean D. Jewell, Secretary Idaho Public Utilities Commission 472 West Washington Street P. O. Box 83720 Boise , Idaho 83720-0074 Re:Case No. IPC-03- Idaho Power Company s Supplemental Response to First Production Request of Commission Staff (Production Request Nos. 1 , 4, and 20) Dear Ms. Jewell: In regard to the above-described response to the Commission Staff's production request which Idaho Power filed on December 8, 2003 , I inadvertently omitted the enclosed narratives. Enclosed with this letter are the narratives for the Responses to Request Nos. 1 , 4 and 20. Very truly yours OJ a( Barton L. Kline BLK:jb Enclosure Donald L. Howell , II Peter J. Richardson Eric L. Olsen Telephone (208) 388-2682, Fax (208) 388-6936 E-mail BKlinefiilidahopower.com IDAHO POWER COMPANY Case No. IPC-O3- f~ECEIVED r:-I ri ~..... 2003 DEC f I P11 4: 28 Supplemental Response To First Production Request of Commission Staff :' ;j " ,) I L,unuTiES cm'H'1IsSION REQUEST NO.1: Please provide a load-resource balance by month reflecting as accurately as possible Idaho Power s load-resource conditions for each of the next 10 years including consideration of the following: abandonment of the Garnet contract; addition of the PPL Montana contract; addition of the Danskin plant; changes in the load forecast considering economic factors; and any other material change in generation or load since the October 2002 Garnet report. Include load-resource balances for energy and peak hour, for median 70% and 90% water and load conditions as defined in the 2002 IRP. SUPPLEMENTAL RESPONSE TO REQUEST NO.1: As noted in our initial response to Request No 1 and Request No., the differences in peak-hour loads between the current and the 2002 IRP load forecasts were under review - specifically the increase in forecast June peak-hour loads. The outcome of the review was a decrease in forecast June peak-hour loads. The revised June peak-hour load forecast now more closely match historical data and the trend of June peak-hour load growth. The June peak-hour load reduction in 70% load case ranges from 111 MW in 2004 to IDAHO POWER COMPANY'S SUPPLEMENTAL RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page 1 127 MW in 2013. Updated monthly peak-hour load resource balance data and charts are attached. The Response to this Request was prepared by Karl Bokenkamp. General Manager Power Supply Planning, Idaho Power Company, in consultation with Barton L. Kline and Monica B. Moen , attorneys for Idaho Power Company. REQUEST NO.4: Please provide critical peak analysis data by month for each of the years 2005-2015 for the following conditions all assuming loads at the currently forecasted levels: 50% water, 50% load 70% water, 70% load 90% water, 70% load SUPPLEMENTAL RESPONSE TO REQUEST NO.4: As noted in our initial response to Request No 1 and Request No., the differences in peak-hour loads between the current and the 2002 IRP load forecasts were under review - specifically the increase in forecast June peak-hour loads. The outcome of the review was a decrease in forecast June peak-hour loads. The revised June peak-hour load forecast . now more closely match historical data and the trend of June peak-hour load growth. The June peak-hour load reduction in 70% load case ranges from 111 MW in 2004 to 127 MW in 2013. Updated monthly peak-hour Northwest transmission deficit data tables and charts are attached. The Response to this Request was prepared by Karl Bokenkamp, General Manager Power Supply Planning, Idaho Power Company, in consultation with Barton L. Kline and Monica B. Moen , attorneys for Idaho Power Company. IDAHO POWER COMPANY'S SUPPLEMENTAL RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page 2 REQUEST NO. 20: Please perform the following computer simulation runs for Idaho Power s system using the AURORA model. Before making any runs however, review all assumptions for the transmission interconnections to Idaho Power system, all assumptions for Idaho Power s existing generating plants, power purchase and sales contracts, load shape and any other necessary input assumptions and make any necessary adjustments so that the model corresponds as closely as possible to actual conditions. Insure that the load and fuel price forecasts assumed in the modeling runs are consistent with those of the 2002 )IRP. It may be desirable to use the AURORA Portfolio" feature to model Idaho Power for purposes of the following analyses. Perform an hourly simulation beginning June 1 , 2005 and extending through December 2020 under an operating mode in which no new capacity can be added within the Idaho Power system and supply deficiencies are met through power imports from outside Idaho Power s system. Based on the results of this run , identify the number and timing of any hours in which transmission constraints limit the amount of power that can be imported. In addition , identify those transmission interconnections on which constraints occur. Identify the timing and duration of any load curtailment predicted by the model. Report the results in graphical format , including any narrative necessary to interpret the results. Perform a long-term optimization (capacity addition) study for the period June 1 , 2005 through December 2020 (running five years beyond the conclusion of the period of interest as recommended by IDAHO POWER COMPANY'S SUPPLEMENTAL RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page 3 EPIS). Use hourly dispatch to fully capture peak load hours. Confirm that the new resource choices available match those identified in the Company s 2002 IRP and that the Bennett Mountain project is also available as a choice at the prices and terms assumed in the RFP analysis for the months of June , July, August, November and December. Assume also that market purchases are an available option. Based on the results of this run, identify the type , timing and location of new resources added along with the amount of capacity and energy associated with each new resource. Confirm whether the Bennett Mountain project is chosen as an alternative to meet load. Summarize the months and the hours within each month when the Bennett Mountain plant would be used to meet load. Identify any other resources selected by the model. Perform an hourly simulation beginning June 1 , 2005 and extending through December 2020 assuming that capacity and energy is available in accordance with the Bennett Mountain project but at zero cost. Compare the net power supply cost over the duration of the simulation to the net power supply cost for the model run conducted in part "b" above. Compare the difference in net power supply cost to the cost of the Bennett Mountain project. Perform an hourly simulation beginning June 1 2005 and extending through December 2020 assuming that capacity and energy is available in accordance with the Bennett Mountain project and that IDAHO POWER COMPANY'S SUPPLEMENTAL RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page 4 additional capacity and energy beyond that sought in the 2003 RFP can be purchased from the Bennett Mountain plant at predicted market prices (i.e. Bennett Mountain s output in all months other than June , July, August, November and December is modeled as a contract option available at prevailing market prices in the Idaho Power load-resource area). Report the amount, timing and cost of all additional capacity and energy purchased from the Bennett Mountain plant. RESPONSE TO REQUEST NO. 20: The requested information is attached. In responding to this request, Idaho Power has worked with EPIS (Developers of the Aurora Electric Market Model) and an outside consultant to perform the requested analyses. Comments are provided to assist in interpretation of the results and also to point out several important factors not addressed in the Aurora analysis. General Comments: Idaho Power does not believe that the Aurora model adequately address the transmission issues encountered in actual day-to-day operation of the Western grid. Several of our major concerns include; (1) Aurora does not model Capacity Benefit Margin (CBM) or Transmission Reliability Margin (TRM), (2) Aurora does not consider ownership of transmission rights , for example Aurora shows 337 MW of transmission capacity from Montana to Idaho , however, Idaho Power does not have contractual rights to use all of this import capacity yet the model uses it to serve the loads in the Idaho-South area, (3) PacifiCorp s South Idaho loads are not included in Aurora s Idaho-South area, and (4) we suspect that the Bridger plant is modeled as being in the Wyoming area with no limitation on the amount of energy Bridger can IDAHO POWER COMPANY'S SUPPLEMENTAL RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page 5 supply to the Wyoming area - in reality there is a limit. These are serious concerns that must be considered in a complete analysis of Idaho Power s need for additional resources. Idaho Power estimates that the overall impact of not modeling CBM , TRM and PacifiCorp s South Idaho load is on the order of 1000 MW during peak-load hours. These three items can be thought of as a 1000 MW worth of additional load and reductions in transmission capacity not currently considered in the Aurora analysis. There may be ways to configure Aurora to address these issues. One possibility is to increase the Idaho-South load forecast and to reduce the transmission capacity into Idaho-South; however, Idaho Power does not believe these transmission issues are adequately addressed in the attached results. Idaho Power will continue to work with EPIS to investigate ways to address these transmission related issues in future Aurora analyses. Part A. The requested analysis was performed. An Aurora simulation was performed for the Idaho Power Company (IPC) system modeling with no new capacity being added and deficiencies met through power imports and DSM curtailments if necessary. The simulation was performed for years 2005 through 2020 with 70 percentile water and 70 percentile loads, BPA transmission loads included and the Bennett Mountain Plant removed from the simulation. Aurora calculated the transmission path loadings for the following transmission interconnections: . Oregon/Washington/ldaho-North to IPC Montana to I Wyoming to IPC Utah to IPC IDAHO POWER COMPANY'S SUPPLEMENTAL RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page 6 . Nevada-North to I Charts showing the transmission path loadings and the path limit are included for each of the above transmission interconnections. Aurora will not violate the reserve margin requirements within an area (Idaho-South for example), so , if the transmission interconnections are full , Aurora will dispatch Demand Side Curtailment units to meet load. This simulation produced Demand Side Curtailments beginning in 2010. This information is included in chart form. A chart showing the Demand Side Curtailments in the Nevada-North area is also included - both regions are experiencing curtailments at the same time. Another point of interest is the Nevada-North to IPC transmission path loading. While the path has directional limits, the Aurora model's results are for the net loading of the Nevada-North to IPC path. For example , if IPC is importing 200 MW from Valmy to IPC and there is a simultaneous export of 150 MW from IPC to Nevada- North , the net flow on the Nevada-North to IPC path would show as 50 MW. This explains why the Nevada-North to IPC transmission path appears to be lightly loaded during nearly all hours. The simultaneous curtailments in Nevada -North and IPC explain why the I PC curtailments could not be served via imports from Nevada-North. And finally, Idaho Power does not understand some of the transmission flows predicted in this analysis - specifically the sustained flows on the Montana to IPC interconnection. The results do not correspond to typical usage of this line. Part B. The requested data is attached. The Bennett Mountain project was selected as an alternative to meet load, however, the project was not selected until 2011. The first resource added to the area Idaho-South was added in 2011. A six IDAHO POWER COMPANY'S SUPPLEMENTAL RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page 7 page table of resources added in the WECC is included as well as a table and two graphs summarizing the months and hours that the Bennett Mountain was dispatched. As noted earlier, Idaho Power believes that if the transmission system were modeled more accurately, a resource would have been required in the Idaho-South area prior to 2011. In fact, Idaho Power utilized its TRM and CBM during the summer of 2004, and summer peak loads are expected to continue to grow. Part C. The requested data is attached. As previously noted , the Bennett Mountain project does not come on-line in this simulation until 2011. The differences in net power supply costs are summarized in a table. Part D. The requested data is attached. Bennett Mountain output in MWh , average megawatts (aMW) and dispatch costs are tabulated for all months other June , July, August, November and December. In this instance Bennett Mountain was modeled as Resource Market Price contract. The cost of energy for the Resource Market Price contract is calculated by multiplying the resource output times the market price. The Response to this Request was prepared by Karl Bokenkamp, General Manager, Power Supply Planning, Idaho Power Company, in consultation with Barton L. Kline and Monica B. Moen , attorneys for Idaho Power Company. IDAHO POWER COMPANY'S SUPPLEMENTAL RESPONSE TO FIRST PRODUCTION REQUEST OF COMMISSION STAFF Page 8