Loading...
HomeMy WebLinkAbout20230505122 Supplemental Attachment J.pdfInternal Use Only 2023 Distribution Wood Pole Management ER2060 Results Thru March 31st Wood Pole Management inspects and maintains Avista’s poles on a 20 year cycle. The major drivers are system reliability, improved cost performance, reduced outages safely, responsibly, & affordably. WPM Updates •In-house Crews working on WAL542, GRA12F2, SPT4S30, l&S12F4 •20 year cycle being accelerated in 2021 to accommodate the Grid Hardening Efforts •WPM will complete LTF34F1, PIN441 & GRA12F2-SEC2 under the GH Budget •Slowing inspections down because the inspection rate is 1.7 years ahead of the follow-up completion rate. 67% 33% 0 0 0 0 0 Poles Replaced Equipment Replaced DX Trussing TX Trussing Transformers 0 500 1000 1500 WPM Contractor Assets Replaced YTD 2023 30% 0% 20% 40% 60% 80% 100% 120% 2023 QUALITY -ILB % Work to STD Acceptable % Units Billed Acceptable FEBRUARY Grand Total Distribution Poles Inspected Transmission Poles Inspected Follow up Poles Completed YTD Actual 1,809 788 1,714 YE GOAL 9,369 1,538 11,400 1809 788 1714 9,369 1,538 11,400 0 2,000 4,000 6,000 8,000 10,000 12,000 $1,441,516 $13,000,000 $1,649,610 $3,000,000 $500,000 $2,500,000 $4,500,000 $6,500,000 $8,500,000 $10,500,000 $12,500,000 YTD ACTUAL YE TARGET WPM/GH YTD ACTUAL WPM/GH YE TARGET WPM Capital Budget YTD ACTUAL YE TARGET O&M Budget $173,454 $729,184 $173,454 $729,184 $- $100,000 $200,000 $300,000 $400,000 $500,000 $600,000 $700,000 $800,000 WPM O&M Budget 184,046 171,000 43,954 0250005000075000100000125000150000175000200000 Completed Inspections Goal Remaining 20 Year Cycle O&M Inspection Progress 19% 75% 75% Pole Inspection Results -2023 0% 20% 40% 60% 80% 100% 120% February Grand Total 2023 QUALITY -TITAN %Units Billed Acceptable % Work to STD Acceptable Staff_PR_122 Supplemental Attachment J Page 1 of 1