Clackamas Office: 11811 SE Hwy 212 ~ Clackamas, Oregon 97015 ▪ Phone 503.655.7191▪ Fax 503.650.2289
April 11, 2008
Sara Koeff
Avista Utilities
1411 East Mission Ave MSC 51
Spokane, Washington 99220
SENT VIA E-MAIL
Re: Transport Transformer – Boardman, Oregon to Gebze, Turkey
Emmert International Project C081549
Ms. Koeff,
Thank you for considering Emmert International for your upcoming project. With over 40 years
in the Engineered Transport and Specialized Rigging Industry, Emmert International has the
experience, expert personnel and equipment to get the job done in the safest most efficient
manner possible.
Emmert International is please to provide a budget estimate of Seven Hundred Seventy Five
Thousand Dollars ($775,000.00 USD) to remove one (1) transformer (31.16’ L x 11.48’ W x
16.4’ H 434,400 lbs) from foundation located in Boardman, Oregon, transport to on-site rail spur,
load and lash to railcar, transport via rail to the Port of Houston, Texas, offload to ocean heavy-
lift ship, transport via heavy lift ship to Turkey, offload directly to a suitable highway transporter,
and transport to final destination located in Gebze, Turkey.
A detailed route survey will be required to confirm this, and completion of this route survey will
require detailed shipping drawings. Please note that the price of performing utility work and
removal and reinstallation of overhead obstructions is not included in this price and will be
performed on an actual time and materials used plus 15% fee basis.
Our price includes permits, escorts, all management, labor, equipment, and material to perform
the work and is based upon:
¾ Mutually acceptable purchase order and/or contract terms. 50% payment is due upon
loading to ship, 50% due upon arrival at destination.
¾ Performing the work using open shop labor during a standard work week. Price does not
include overtime, weekend, or holiday work.
¾ Prices are quoted in today’s values and do not include any amounts for escalation.
Emmert International will reevaluate prices 30 days prior to the start of work.
¾ The price quoted assumes formal acceptance by the appropriate agencies using the
transporter configuration indicated above.
Transport Transformer – Boardman, Oregon to Gebze, Turkey
Emmert International Project C081549
Page 2
¾ Price is subject to current exchange rates at the actual time of all work performed outside
of the US.
¾ Duties, customs clearance charges, port charges at destination, port storage costs,
customs clearance documentation, marine insurance and import fees are by others.
Delays caused by customs, weather or others, is not included.
¾ Project is subject to equipment availability, vessel space allocation and sailing
schedule.
¾ The cost of utility work and removing overhead obstructions is not included. This work
will be performed on an actual time and materials used plus fee basis.
¾ Tarping and weather protection is not included.
¾ No demurrage time is included. Emmert International’s price is based on receiving cargos
on transport and unloading by others immediately upon arrival. Additional mobilizations
and demobilizations to perform the offloading work will be performed on an actual time
and materials, plus fees, basis.
¾ Published rail rates at the time of quotation. All rail charges are budgetary and will be re-
assessed on conditions after clearance and at the actual time of transport. This quotation
does not include special train charges, idler cars, counterweights, Rule 11 Charges, or any
other additional charges imposed by the railroad.
¾ This price does not include the cost for siding leases or site access costs.
¾ Rail clearances are included. Price to perform is $1,950.00. This amount is non-
refundable, but will be applied to the total contract amount stated above if awarded the
transportation of the project.
¾ Our standard cargo insurance is for a maximum value up to $1,000,000.00 per load based
on declared value. Emmert International maintains insurance up to $1,000,000.00.
However; all claims are limited to $2.50 per pound unless otherwise declared on the
shipping documents. If additional insurance is required, the cost for such will be quoted
separately upon request. Emmert International assumes no liability for cargo in excess of
insured amount. Emmert International’s insurance does not cover the cargo during
loading to ship or ocean transport.
¾ State, local, use taxes, fees, permits (other than trucking), additional licenses, additional
insurances, additional training, infrastructure improvements, overtime, utility charges,
fuel surcharges (fuel cost at $ 4.00/gal), liquidated damages, cost of right of way
clearances are not included.
If you have any questions, or require additional information, please contact me at 503.655.7191
ext. 242.
Respectfully,
Mark Hefty
Project Development Manager