Loading...
HomeMy WebLinkAbout20260709Appendix A - East Coeur d Alene Lake System Reinforcement.pdf �uY7STA' ImpactEast Coeur d'Alene Lake System Reinforcement System • teake ,�7 Carlin 1 Coeur diAene B� •i Etldyv,I!e j •Substation P:11 S oanyon Substation Ena� le - +►7 �J - - l y5. r Rockford Bay rJLane fi"�: � :BEND / IL f� StNI SC'_•ri�erda�e St Joe System • Avista Utilities • • MSC-1 • Spokane, WA 99220 TransmissionPlanning@avistacorp.com Prepared by: • TA Description Author Review oss 01/15/20257 Released K. Hausam East Coeur d'Alene Lake System Reinforcement 2024 Table of Contents 1. Project Overview......................................................................................................4 2. Project Description...................................................................................................4 2.1. Problem Statement ............................................................................................4 2.1.1. Risks............................................................................................................5 2.1.2. Need by Date............................................................................................... 5 2.1.3. Technical Prioritization................................................................................. 6 2.2. Project Scope and Requirements....................................................................... 6 2.2.1. System Modifications................................................................................... 6 2.2.2. Protection Requirements ............................................................................. 9 2.2.3. Communication Requirements .................................................................... 9 2.2.4. Metering Requirements ............................................................................. 10 2.3. Project Execution ............................................................................................. 10 2.3.1. Construction Schedule............................................................................... 10 2.3.2. Cost Estimate ............................................................................................ 10 2.3.3. Long Lead Time Equipment....................................................................... 10 2.4. Contingent Facilities......................................................................................... 11 3. Technical Analysis ................................................................................................. 11 3.1. Scope of Study................................................................................................. 11 3.2. Distribution Base Case Assumptions ............................................................... 11 3.2.1. Distribution Load Assumptions .................................................................. 12 3.3. Distribution Base Case Results........................................................................ 13 3.4. Mitigation Plan Results..................................................................................... 15 3.5. Simulation and Modeling Methodology ............................................................ 17 3.5.1. Transmission Base Case Assumptions ..................................................... 17 3.5.2. Transmission Projects Modeled................................................................. 17 3.6. Transmission Project Representation .............................................................. 17 3.7. Power Flow Model............................................................................................ 18 3.8. Steady State Contingency Analysis ................................................................. 20 3.8.1. Heavy Summer Scenario........................................................................... 20 3.8.2. Heavy Winter Scenario.............................................................................. 22 3.8.3. 2026 Light Spring Scenario ....................................................................... 25 3.9. Voltage Stability Analysis ................................................................................. 25 3.9.1. Power/Voltage (PV) Adequacy.................................................................. 25 3.9.2. Reactive/Voltage (QV) Stability Analysis ................................................... 26 I Page 2 of 44 East Coeur d'Alene Lake System Reinforcement 1 2024 3.9.3. Reactive Support Analysis......................................................................... 27 3.10. Stability Contingency Analysis...................................................................... 28 3.10.1 . Transient Performance........................................................................... 28 3.10.2. Maximum Clearing Times....................................................................... 29 3.11. Short Circuit Analysis.................................................................................... 29 3.12. Reliability Analysis ........................................................................................ 30 3.13. Redlined Scada Variable Limits.................................................................... 31 3.13.1 . Feeders.................................................................................................. 31 3.13.2. Transformers.......................................................................................... 31 3.13.3. Transmission Lines ................................................................................ 32 4. Appendix................................................................................................................ 36 4.1. Project Alternatives .......................................................................................... 37 4.1.1. Do Nothing................................................................................................. 37 4.1.2. Increase Distribution Voltage..................................................................... 37 4.1.3. Carlin Bay Station with Tap from O'Gara................................................... 38 4.1.4. Carlin Bay Station with O'Gara Switching Station...................................... 38 4.1.5. Star Point Configuration with O'Gara Switching Station ............................ 38 4.2. Distribution Integration .....................................................................................40 Page 3 of 44 East Coeur d'Alene Lake System Reinforcement 2024 1 . Project Overview Growth on the east side of Coeur d'Alene Lake is impacting the ability of the existing distribution system to reliably serve customer load. Operations are experiencing multiple concerns which are expected to worsen in the near-term planning horizon. The need for a plan to mitigate these concerns is evident. The identified concerns led to a necessity for the East Coeur d'Alene Lake System Reinforcement project. The complete scope will be executed in a phased approach so immediate concerns are mitigated and operational while the remainder of the scope can be completed. The complete scope includes the following: • Phase 1 includes: o Upgrade cable at lake crossing on BLU321 feeder from 350CN15 to 1000CN15 o Construction of 115/13kV Carlin Bay Station, 20 MVA Transformer 0 115kV transmission line tap from the Benewah — Pine Creek 115kV line near O'Gara Station to the Carlin Bay Station 0 328A (250kVA) Voltage Regulators will provide voltage regulation on CBY641 and CBY642 feeders o Distribution integration of Carlin Bay Station feeders • Phase 2 includes a rebuild of the O'Gara Station o Construction of 115/13kV Ogara Station, 20 MVA Transformer 0 115kV transmission bus breaker-and-a-half configuration 0 328A (250kVA) Voltage Regulators will provide voltage regulation on OGA611 feeder, KEC will provide voltage regulation on OGA612 feeder o Distribution integration of new O'Gara Station feeders. Phase 1 will relieve capacity constraints in the near term on adjacent distribution feeders, BLU321 and OGA611 . Phase 2 will address O'Gara Station capacity constraints and reliability for area customers. Technical analysis has been performed to confirm the project as proposed provides acceptable system performance and mitigates the critical system performance issues which exist on the distribution feeders, impacting customers on the east side of Lake Coeur d'Alene. 2. Project Description 2.1 . Prohlem Statement The population and load demand growth on the east side of Coeur d'Alene Lake has resulted in operational challenges for Avista to reliably support new customers at the far-reaching end of two distribution feeders. Currently, two distribution feeders serve the east side of Lake Coeur d'Alene, one originating from the Blue Creek Station and the other originates from the O'Gara Station. The associated feeders cannot support additional growth in the area considering the long distances are currently pushing limitations of the 13kV distribution system. Forecasted load in the area will further stress the existing infrastructure. Much of the new and forecasted load is concentrated at the far reaches for each distribution feeder. Additionally, several large developments, similar to the Gozzer Ranch development, have either been proposed or are under development. Table 1 provides the expected feeder and transformer loading over the next 10 years. Page 4 of 44 East Coeur d'Alene Lake System Reinforcement 2024 System performance criteria violations have emerged due to area load growth, including thermal capacity, current imbalance, and voltage performance. Blue Creek Station has existing and anticipated capacity constraints on the BLU321 feeder and Blue Creek Transformer 1 . O'Gara Station has multiple existing and anticipated thermal performance criteria violations. System protection challenges include low fault current availability and cold load pickup which contribute to decreased reliability in the area. BLU XFMR#1 50.54 54.07 58,15 62.49 67.33 72.23 77.77 83.61 '90.12 I 97.16 _I BLU321 70.56 75.31 81.01 89.24 96.66 PM BLU322 24.51 26.08 27.91 28.41 30.41 32.54 35.02 37.48 40.34 43.41 46.72 OGA XFMR#1 78.33 81.91 85.68 89.27 93.34 97.54 OGA611 84.23 88.05 92.66 109.38 114.31 119.91 125.91 132.14 138.39 144.86 OGA612* 111WI 3 139.95 145.93 152.13 158.65 165.45 172.53 179.92 Table 1: Blue Creek and O'Gara Station Forecasted Peak Loading (%) *Metering CT is the limiting equipment. KEC voltage regulators are next capacity limiting equipment at 86% loading. Several enhancements have been implemented to the distribution system to attempt to delay the need for a new station: • Reconductor four miles of the BLU321 feeder • Adjust locations of protective devices and sizes to best accommodate load • Addition of midline recloser devices • Balance feeders and laterals Despite system enhancements, the near-term planning horizon reveals existing infrastructure will be unable to reliably accommodate anticipated customer service requests and load growth in the area. The East Coeur d'Alene Lake System Reinforcement study identifies the recommended solutions to support future customer needs. 1.1 .1 . Risks The risk of not constructing the proposed project by the need by date is the inability to serve customers during heavy winter loading conditions. There are few operating procedures in place to mitigate equipment loading before the equipment reaches 100% of the applicable facility rating. Operational mitigation is required during heavy winter loading until Carlin Bay Station is energized. The Blue Creek Station transformer can briefly operate above 100% of the applicable facility rating until a major transformer alarm is triggered. O'Gara Station currently does not have SCADA, so real-time operation is not available. If the East Coeur d'Alene Lake System Reinforcement project is not completed by the winter of 2025, Avista will operate with the risk of turning customer's power off for 4-6 hours daily until heavy winter loading conditions have passed. 2.1 .2. Need by Date Technical studies show equipment ratings are exceeded during heavy winter conditions. Table 1 Table 2 shows the expected 80% and 90% need by dates. Page 5 of 44 East Coeur d'Alene Lake System Reinforcement 1 2024 Feeder/Sub 80% need by date 90% need by date BLU XFMR#1 2031 2032 BLU321 2026 2028 OGA XFMR#1 2025 2028 OGA611 Exceeded 2026 OGA612 Exceeded Exceeded Table 2: Station need by dates 2.1 .3 'echnical Prioritization Avista's Engineering Roundtable compares projects using a scoring matrix which evaluates both the technical importance and urgency of a project. Table 3 provides the suggested scoring for the Engineer Roundtable to use. The technical importance scoring accounts for the inability to serve load without experiencing capacity issues and the asset condition considerations of some equipment. The urgency scoring considers the need by date stated in Section 2.1.2. Tangential eliability P.erfor-"rsafeWlEnviron- Regula- mance mental tory Benefits Score 3 F::73 2 2 0 0 0 0 F 66 D. Number Urgency Flexible - Stations 3 3 3 1 1 2 88 Table 3: Engineering Roundtable prioritization scoring 2.2. Project Scope and Requirements 0.2.1 . System Modifications Following the technical analysis outlined in Section 3, the scope of the system upgrades shown below in Figure 1 and Figure 2 are necessary to improve system performance. The complete East Coeur d'Alene Lake System Reinforcement project scope will be implemented over two phases. Page 6 of 44 East Coeur d'Alene Lake System Reinforcement 2024 Feeder Feeder CBY642 CBY641 Phase 1 Project Notes Carlin Bay Substation Tap Benewah-Pine Creek 115kV line near ----------------------------- ----------- --------- - , O ; O'Gara and construct approximately 15 miles of new 115 KV transmission line with OPGW to Carlin Bay(min rating 150 MVA)_ OConstruct new Carlin Bay Substation with one 115/13-8kV distribution transformer and two distri bution feeders. 250 kVA M WA 250 kVA __.. _. Future to O Carlin Bay 115113-8kV distribution transformer BIUe Creek NLTC set to 115.5kV 1 O 115 kV to Pine Creek y 115113W 20 MVA --------------------------------------------------------------------------------- Legend: O Existing Facilities New 230 W New 115 W 115 kV to New Distribution / Benewah A11 Al2 KEC Distribution A13*1 A 29 5 O'Gara 115 kV to Substation St Maries Figure 1: Phase 1 Implementation Project Diagram Page 7 of 44 M East Coeur d'Alene Lake System Reinforcement 2024 Feeder Feeder CBY642 CBY641 Carlin B ay Substation Phase 2 Project Notes: ORebuild O'Gara lobe 115 kV,breaker and me halfsubstation with one 115/13.8kV tlistnbutlon transformer and Iw o distribution feetlers- IIIF--+I/ Illi�l/ 2 Design for an additional line position and space O for future capacitor bank or distribution 3 O'Gara 115/13.8kV 6slnbution transfornerNLTC kvA �2Eu kVA �29]kVA Future to set ID 115.5KV - -� Blue Creek • ®Voltage R r for Feetler 612 will be supplied V and installed letl by Dy KEC. 1 n O BPA to add metering for KEC feeder T 6 O'Gara Substation will include a microwave site O to establish a connection to Mica Peak y 115113kV 20 MVA --------------------------------------------------------------------------------- Legend: Existing Facilities - O'Gara Substation 1 New 230kV r--------------------------------------- New 115 W 115 W to New Distribution O Pine Creek KEC Distribution .._•. ._i...:_:�. 115 W to ` Benewah 115 W to Mica Peak St Maries ` 115113kV O 20 WA Feeder T O OGA612 O'Gara ILA rj (KEC) 25D WA Feeder OGA611 250 WA �6 Figure 2: Phase 2 Implementation Project Diagram I Carlin Bay Station Desigr The Carlin Bay Station project will include a new station at Avista-owned property on S. Elk Rd. Coeur d'Alene, ID. The station is fed from a 115kV transmission line tap from the Benewah — Pine Creek 115kV Transmission Line near O'Gara to the Carlin Bay Station. The distribution portion of the station will have a 115kV circuit switcher, a 115/13kV 20MVA transformer with two distribution feeders, and auxiliary feeder position. 328A (250kVA) Voltage regulators will provide feeder voltage regulation. A portion of load served by the existing Blue Creek Station 115/13kV Transformer 1 and O'Gara Station 115/13kV Transformer 1 will transfer to the new Carlin Bay Station. Page 8 of 44 East Coeur d'Alene Lake System Reinforcement 2024 ?.2.1 .? O'Gara Station Design O'Gara Station will be a greenfield rebuild of the existing O'Gara Station at Avista- owned property on S. Hwy 97 in Kootenai County, ID. The transmission portion of the station includes a four-position breaker-and-a-half bus configuration with space for a future bay. The distribution portion of the station will have a 115kV circuit breaker, a 115/13kV 20MVA transformer with two distribution feeders, and auxiliary feeder position. 328A (250kVA) Voltage regulators will provide feeder voltage regulation on the OGA611 feeder. KEC will provide voltage regulation on the OGA612 feeder. The load served by the existing O'Gara Station will be transferred to the new station. It is recommended to maintain the star point on the Benewah — O'Gara — Pine Creek 115kV transmission line until such a time the low voltage concerns, due to a loss of the Benewah 230/115kV Transformer, can be mitigated. 2.2.1 .3. Distribution Integration Desigr The following modifications to the distribution system are necessary to mitigate the identified performance issues and integrate the new Carlin Bay Station feeders: • Increase conductor size of the 9600' lake crossing from 350kCM to 1000kCM on BLU321 feeder. • Reconductor sections of feeder trunk to #556 AAC. • Add midline recloser devices to feeders CBY641, CBY642, BLU321 and OGA611. • Add phases to specified existing single-phase and two-phase laterals to balance per-phase loading. Distribution integration details are shown in Section 5.2. 2.2.2. PrntP(-tion Requirements Protection relay settings need to be modified at the Benewah A536 transmission line terminal to coordinate with the system modifications. Protection relays at the Pine Creek A292 transmission line terminal are obsolete and require upgrading with a new protection package. Typical distribution station protection schemes will need to be developed and deployed for both the O'Gara Station and the Carlin Bay Station. The Carlin Bay Station includes a 115/13kV 20MVA transformer and two distribution feeders. The O'Gara Station includes 115/13kV 20 MVA transformer and two distribution feeders. 2.2.3. C011 II 1 IUI 11t,6LIU1 I rm--qu11 CI I ICI IlJ Communication aided protection schemes are required on the Benewah — O'Gara and O'Gara — Pine Creek 115kV transmission lines. A new network communication path is required from O'Gara Station to Benewah and Pine Creek Stations. Redundant communications for the protection schemes are not required. The new O'Gara Station will include a microwave site to establish a connection to the existing Mica Peak tower. The O'Gara and Carlin Bay Stations will require communications to provide SCADA access to the sites. Carlin Bay Station can be connected by a radial fiber spur on the new transmission line from O'Gara to Carlin Bay. Secondary communications paths for SCADA backhaul may be provided by third-party cellular networks. Page 9 of 44 East Coeur d'Alene Lake System Reinforcement 2024 2.2.4. Metering Requirements No metering points related to Avista Balancing Authority Area will be impacted by the project scope. The Kootenai Electric feeder OGA612 from the O'Gara Station will require metering by BPA. 2.3. Project Execution 2.3.1 . Construction Schedule The full project scope is to be completed prior to 2028 winter operating season. The following timeline provides a high level, preliminary estimate of key milestones. Project Delivery will maintain the actual schedule used for proceeding with the project. Preliminary Carlin Bay Station project schedule is as follows: • Project Scoping - - - - - - Q1 2026 • Physical and Electrical Design - - Q2 2026 • Site Prep Q2 2026 • Physical and Electrical Transmittal - Q4 2026 • Physical Construction - - - - Q4 2026 • Electrical Construction - - - - Q1 2027 • Construction Commissioning - - - Q2 2028 Preliminary O'Gara Station project schedule is as follows: • Project Scoping - - - - - - Q3 2025 • Physical and Electrical Design - - Q4 2025 • Site Prep Q2 2026 • Physical and Electrical Transmittal - Q3 2026 • Physical Construction - - - - Q4 2026 • Electrical Construction - - - - Q2 2027 • Construction Commissioning - - - Q4 2028 2.3.2. Cost Estimate The work to be completed under the East Coeur d'Alene Lake System Reinforcement project requires budget allocated for Substation, Transmission, Distribution and Communication work. An estimate of total project cost is roughly $43.945M. iTotal Carlin Bay _`llllllllllllllllllll0'Gara'6MW7' Blue Creek Substation $21,895,000 $8,750,000 $13,145,000 - Transmission $15,400,000 $14,450,000 $950,000 - Distribution $4,000,000 $2,250,000 $750,000 $1,000,000 Communication $2,650,000 $1,550,000 $1,100,000 - Total $43,945,000 $27,000,000 $15,945,000 $1,000,000 Table 4: Project cost estimate 2.3.3. Lona Lead Time Equipment Any electric system expansion may be delayed by long-lead time requirements, such as equipment, land acquisition and/or outage windows. Known schedule constraints that may impact the proposed project schedule are detailed in Table 5. Page 10 of 44 Lim East Coeur d'Alene Lake System Reinforcement 1 2024 Potential Constraint Typical Extended Impact Procurement Procurement Distribution Transformer 9 months 36 months Yes 115kV Circuit Breaker 6 months 36 months Yes Table 5: Long-Lead Time Constraints 2.4. Contingent Facilities Contingent facilities are unbuilt facilities which if delayed or not built could cause a need for restudying the requested project. No contingent facilities were identified for the East Coeur d'Alene Lake System Reinforcement project. ScopeInitiative ERT# Project Name None Table 6: Contingent Facilities 3. Technical Analysis 3.1 . Scope of Study This study was performed to determine the transmission system and distribution system performance impacts and mitigation solutions for the addition of the Carlin Bay Station. Distribution system performance is compared against the criteria defined in DP-SPP-02 — Distribution System Performance. Distribution analysis performed included the following: • Multi-year Load Flow Analysis • Short Circuit Analysis Transmission system analysis performed included the following: • Steady State Contingency Analysis • Voltage Stability Analysis • Stability Contingency Analysis • Short Circuit Analysis • Reliability Analysis Transmission system performance is compared against the criteria defined in TP-SPP- 01 — Transmission System Performance. TP-SPP-01 contains criteria which encompasses at a minimum the criteria established through regulatory requirements of North American Electric Reliability Corporation (NERC) and Western Electric Coordinating Council (WECC). 3.2. Multi-Year Load Flow Analysis 3.2.1 . Distribution Base Case Assumptions Only data pertaining to the feeders and stations directly impacted by the selected project solution are listed in this section. Key Assumptions Page 11 of 44 East Coeur d'Alene Lake System Reinforcement 2024 • Peak loading at each feeder was set to operationally observed peak winter loading on 1/14/2024 and balanced per phase loading. • This analysis does not explicitly account for EV adoption or building electrification. • Relative load at service transformers was assumed to be proportional to the average loading over several days of data recorded during the cold event of 2024. • No block load additions were assumed - Growth rate was used in lieu of block load additions. • Growth rate was calculated using multivariate regression based on historical data 2021-2023. Due to O'Gara Station not having SCADA, ZC613R recloser was used to analyze the growth rate at this station. Based on the stated assumptions, the annual growth rates in Table 7 were applied to the stations impacted by the project work. Blue Creek Transformer 1 6.33% O'Gara Transformer 1 4.33% Table 7: Station growth rates 3.2.2. Distribution Load Assumptions Historical loading on the feeders at the O'Gara and Blue Creek Stations were analyzed to determine the appropriate base case loading assumptions for load flow simulations. The feeder loading shown in Table 8 was balanced and used in the distribution system model to represent the base year of 2024. Peak Demands Start 1/14/2024 7:30 Finish 1/14/2024 7:35 BEACON.TEMP -2.44 STATIONBLUE CREEK BLU XFMR#1 629.42 637.84 576.97 614.74 51.26% 51.94% 46.98% BLU321 462.08 499.92 443.13 468.38 69.17% 74.84% 66.34% BLU322 164.2 134.96 131 143.39 24.58% 20.20% 19.61% ZC869R 47.86 110.98 76.57 78.47 ZC150R 351.64 380.96 342.57 358.39 ZC883R 302.95 285.49 258.63 282.36 • STATION OGAXFMR#1(Insp) 383 249 369 333.67 87.24% 56.72% 84.05% OGA611(Insp) 215 116 191 174 94.30% 50.88% 83.77% OGA612(Insp) 168 133 178 159.67 88.67% ZC613R 143.06 81.9 159.29 128.08 62.75% 35.92% 69.86% ZC618R 77.9 32.82 90.51 67.08 Table 8: Station Peak Winter Loading Page 12 of 44 East Coeur d'Alene Lake System Reinforcement 2024 3.2.3. Distribution Base Case Results The results for the base case are shown in Table 9. This table is contextualized by noting that this is an all-lines in service, 1/14/2024 peak winter loading analysis with balanced per-phase loading. O'Gara Station has existing and anticipated capacity constraints. Blue Creek Station has existing capacity constraints on the distribution system and anticipated station capacity constraints. Feeder/Sub 1 . 2025 2026 2027 2028 ` BLU XFMR#1 50.54 54.07 58.15 62.49 67.33 72.23 77.77 83.61 90.12 97.16 _ BLU321 70.56 75.31 81.01 89.24 96.66 MMMI BLU322 24.51 26.08 27.91 28.41 30.41 32.54 35.02 37.48 40.34 43.41 46.72 OGA XFMR#1 78.33 81.91 85.68 89.27 f 93.34 97.54 P 101. OGA611 84.23 88.05 92.66 119.91 125.91 132.1 OGA612 _WM 1f 34.23 JW5 145.93 152.13 158.65 165.45 172.53 179.92 Table 9: Base Case Station % Loading Results The existing distribution system layout represented in the distribution system model for analysis is shown in Figure 3. Page 13 of 44 Gibbs CdA CS Coeur d'Alene— u �►� 1 BLu A ` F Wolf Lodge a � Ica Twin Beaches Edd'yville� F y3 d Bay , 71 e \'!�«! { Lane 1 ' ston S rin ►�' `�► _y4 _ P 9 ��..� Medimont j �► Harrison IN Conklmg Park OGAtfq • � J J • _ �• ,I,•:: Chatcolet �• +1 �r.9w• � � ',� �,• Ov Silvertip Landing Hawle s La ding ` Me- • �/ISTA' East Coeur d'Alene Lake System Reinforcement 2024 3.2.4. Mitigation Plan Results Implementation of the East Coeur d'Alene Lake System Reinforcement project results in significant improvements to system performance. The results of a multi-year analysis are shown in Table 10. The proposed Carlin Bay Station, energize year 2028, will have a portion of load transferred from feeders BLU321 and OGA611 to mitigate existing capacity constraints. The proposed O'Gara Station rebuild, energize year 2028 after Carlin Bay Station, will have load transferred from the existing O'Gara Station and mitigates the existing capacity constraints. To mitigate the high growth on BLU321 feeder, CBY641 feeder can pick up a portion of load at Gozzer Ranch during peak winter conditions if necessary to meet system performance criteria. This capacity for the CBY641 feeder to pick up a portion of Gozzer Ranch load increases as more sections of trunk conductor are upgraded to #556 AAC. Year Year Year 1rear--7'F91FwW Year Year I BLU XFMR#1 50.54 54.07 58.15 62.49 56.21 60.3 64.71 69.53 74.74 80.22 86.33 BLU321 70.56 75.31 81.01 89.24 73.35 79.05 85.25 W92.16 99.34 BLU322 24.51 26.08 27.91 28.4 30.39 32.52 34.81 37.25 39.86 42.66 45.91 OGA XFMR #1 78.33 81.91 85.68 89.27 0 0 0 0 0 0 0 OGA XFMR #1 NEW 0 0 0 0 25.03 26.12 27.25 28.46 29.7 31.04 32.4 OGA611 84.23 88.05 tlz.bb Z 0 0 0 0 0 0 0 OGA611 2 0 0 038 39.67 41.56 43.54 45.61 47.88 49.99 OGA612 1 128.54 0 0 0 0 0 0 0 OGA612 2 0 0 0 0 30.28 31.57 32.91 34.32 35.79 37.32 38.92 CBY XFMR #1 0 0 0 0 13.17 13.9 14.69 15.52 16.42 17.32 18.37 CBY641 0 0 0 0 16.91 17.97 19.11 20.39 21.75 23.13 24.74 CBY642 0 0 0 0 14.96 1 15.65 16.34 17.1 17.89 18.55 19.51 Table 10: Mitigation Case Winter% Loading Page 15 of 44 (fAS CdA CS t Coeur d'Alene- err ��°�1fb►, BLU t Wolf odge 1 KM, icad Twin Beaches ddyville� t rd Bay . . _ ,. #k '!Aw `. Springston Medimont A , Y -i�� * • .y.. Conkling Park ` OGA,, f Chatcolet �"✓ 1 �'i "- ' Silvertip Landing Hawleys Landing lager' 024.Au5us East Coeur d'Alene Lake System Reinforcement 2024 3.3. Simulation and Modeling Methodology Technical studies used to analyze the project's impact on the transmission system was performed. Transmission system analysis follows the methodology described in the TP- SPP-01 — Transmission System Performance. Distribution system analysis methodology was performed to determine expected feeder and transformer impacts. The following sections outline specific assumptions used for the East Coeur d'Alene Lake System Reinforcement project. 3.3.1 . Transmission Base Case Assumptions Project analysis was performed using transmission system models representing the scenarios listed in Table 11. Each scenario was used to determine existing transmission system performance as well as post project performance. Avista Planning cases are tailored from approved WECC cases, and each case includes a full suite of steady state power flow contingency scenarios that are run to analyze the impact of the project alternatives. These contingencies include outages within the Avista Transmission System as well as select outages in adjacent Planning Coordinator and Transmission Planner areas. Contingencies are also added or modified to include elements added to the Transmission System for the purposes of this study. Scenario WECC Case Five Year 2026 Heavy Summer 26HS2a1 PW Five Year 2026 Heavy Winter 26HW2a1 PW One Year 2022 Light Spring 21LW1a1PW Table 11: Scenario Studied Transmission Projects Modeled No unbuilt transmission system projects were identified to impact the analysis for the East Coeur d'Alene Lake System Reinforcement project and therefore not included in the models used for analysis. 3.4. Transmission Project Representation The East Coeur d'Alene Lake System Reinforcement project is represented in the transmission system model for analysis with two star point configuration options. Figure 5 shows the transmission system with the O'Gara — Plummer 115kV Transmission Line section open, as it operates today. Figure 6 shows the transmission system with the O'Gara — Plummer 115kV Transmission Line section closed. Page 17 of 44 East Coeur d'Alene Lake System Reinforcement 2024 4.QL1 w EASTFARM UCKROAD VOSi ELS PRAIRIU ,Ye vE ax ISw LA I 0. OU TM I2.11! 7.7 „, 5]3IM M ROl OEE 2Q WII Mvar 1A W. ]UIIA ST - �.00 Olt F ILUEQK MI8 m .017W 00 Mvar 6.T IEYII 1.OMVLEWAY L00)11 OORw ,. 32 EIM Id3 4R HW OA MW T1. 2 9.6Hw9.9 Hvar U Hvr 11.2 Mvar O.O" 11.9MW 2.3 MW 36.3 HW 0.0 W. 2A Hqr 0.6 Hvar l2.7 Mvar 7A MW 2.2 Mvar 20.5 Mvar W SHW Hva I li Wr CAAUX SAY Mw -73. 1 Mwr O.906 VLUHHE0. w BENYYAH tc I.O HW TA EIEII / 1.6 HW r lA EIRI •.]' T ��-�.� 13 Hvar 0.1H \: O.O Hvar 5 HW �✓ 0 Hvar 1 1 0.9Ji w 23.0 HW S Figure 5: O'Gara — Plummer 115kV Line Section Open � H.. ..ECRK K9Mp ~ � SS Mrar w 6J3 Nrar 09%ws 200)��. LW1 pv RK 1101 II OTr � Haa 1 .sue lames _ Mra Lo . WTwFARM s1cKRo LWl � as Hw MEE111 1.3 MW aI MW 1 6.1 MW�w ' I �� Mus�m filOMq� 10[ �zz H.r a HKs ao Le HKs� �°o Jk Laa w o 0 99fi w LIBBTYLK 7.1 n21m 21 rnv 13.1 Mrr Ofi Hvar 120 Mrar 11 Mrar CARIlH MY PLUN6[ o6Rlu 19afiw OBELW n i n—rr uHla » uKnY of M�.r uMla sKm " SciT oELlw II IIQ aERS +a.9efi w 81MW y 2J MKs 81ENNEWAH I z Q OA llrr BAH y / F Figure 6: O'Gara - Pine Creek 115kV Line Closed 3.5. Power Flow Model Figure 7 depicts modeling the East Coeur d'Alene Lake System Reinforcement project in the 2026 Heavy Summer scenario with the star point configuration closed through. Page 18 of 44 East Coeur d'Alene Lake System Reinforcement 2024 O M r 0."s P. 1002 pu 3.5 ~0 M ar PINE fJIK M MW 8.1 MW DALTON A 1.00)p0 PEE W( 0 Mvar 5.5 Mvx PRA0VE8 67.3 Mvx 0.996 pu 1.031 W Mvx -M 0 M W r 0.996 ry• •,j, Os�1.0 ~D Mvzr 5.1 11W ~7� is lMva PU 9.5 Mvx TT 1.001 p BE 1.001 6.6 M 3.2 My/ 1.1 Mvvx I.8 51 BLUEC'W M; Ou 0.0 M�1002 �1.M00]2B.WMW DOWIRP7 T __ �0.99fi Ou T IlafYlL 1 1.001-1 7.2 MW I.a MW 1 OM pu ].0 Mwr Ir 0.99a Ou ].0 Mvar 0.5 Nvar 37.2 MW 2.4 MW 34.7 VM MW 13.1 W. 0.6 Mvx 12.0 Mvar Mvar 3.0 MW 1.4 Mvx GREE-m-S U RlJN BAY 1.002 pU MW Mvar PI UMMER � 1.006 pU 1.00D pu*O.l Mvx -0.1 Nwr ~ 1.]MW 0.3 M- 5MW 0 Mvar 099pµ �0986 pu as Mvar 22.4 MW 7.1 Mvx ■ 3 °Fl��i pN � � 2 i t T ^.. � OW.OpHMvx 1.012 W � Figure 7: 2026 Heavy Summer Power Flow Figure 8 depicts modeling the East Coeur d'Alene Lake System Reinforcement project in the 2026 Heavy Winter scenario with the star point configuration closed through. 0 Mvar 1.030 p 1.012 pv 1.3 Mva » MW I. Mvar PINE CRK » MW 6.1 MW DALTON A 1.010 W PINE CRK O Mvar 23 Mwr PRAIRIES 68A Mwr I.007 PU 1.036 pv 45.]Mvar ~O MWr I.OlO m• y S41.MW vL _ » MWY S.OM OTI5 O M- lA Mvar 1A13 p 1 IRIS pv EASTFARM aECKROAD 1.013 p• 1.012 pv 7.7 MW 42 MW 3ULIA 51 0.9 Mvar 1.013 pppyyy ��I t BUN- S 4.2 MW 5.5 MW I.J �Y�1 Mission 0.0M LOSS pu IS Mvar O.5 Mvar DOWER RD 0.6 Mva , pv 1 a,n M 1.008 A DDLEWAV DA 85 MW 3.3 MW L787Y1K 11.0 MW 1.012 pv 3 MW 1.009 P 14 Mvar 0.4 Mvar IA33 p 1.4 Mvar 1 Mvar 33.4 MW 23 MW 34.5 MW '. MW 6.1 Mvar 0.2 Mvar 6.4 Mvar Mva 3.0 MW f1A Mvar �EEMACRFS -.N BAV 3A32 p MW Tr pLUMMFR 06I1RA 1.6��1.011 W 1.004 w*� � O.S MW E • E� 0.2 Mvar O.1 Mwr 7.9 MW 2.2 MW 0.9 Mwr 0.2 Mwr O MWar ETFE S o.992 PO3u 9.]MW 1.2 Mvar 24.0 MW 3A Mwr RBEWAM • 1A34p / � _2 i T o.o Mwr � BENEWAH l.o1a p. Figure 8: Heavy Winter Power Flow Figure 9 depicts modeling the East Coeur d'Alene Lake System Reinforcement project in the 2022 Light Spring scenario with the star point configuration closed through. Page 19 of 44 East Coeur d'Alene Lake System Reinforcement 2024 �r W 1.00fiw MNE fJa _ QOMva MWr ai Mtiz �� aO flKat 01N006 WA I.OM�� LN�NEw n� 6.6MW IW6w •- N; Ll�w BfCKfID/1D � allN ARM I.aa uu � saMw Hw a— L]UIIRR;. Qw. �e WNKRHI .� f6V 0.1 FIW SSMWw BLUEQ6l JWr M590N QOIMy cc��a 1.009W alfNar 0.0fMar O�E1t1D al Mnr L T ` 1.001W -- 1/f, O.n pry �L006w � �L66w ♦7MW N1.61M�'• l LLI� 1'�w 3� LK Lm6w aoMv no Mvar S 16.6m L]MM 17.1M1 a7— aoMWr al MM LI M CANIIN 0A11 GNEFKA[IR6 LOOI W KUM M o66W .6mw » x9m I.I MR naMaar 'aG Maar 0MW RM.r RS srwwEs w Lonl ou 4.6 MW 0.1 M— 11.B fIW 0.9 FNar ` KW M .n o.o Erar F i 0Ffi ryF Wl1M Figure 9: 2022 Light Spring Power Flow 3.6. Steady State Contingency Analysis 3.6.1 . Heavy Summer Srpnarin The following sections describe some existing or newly identified performance issues influenced by the project in the heavy summer scenario. Steady state analysis was performed under two system configurations. The system was first analyzed with the Benewah — Pine Creek 115kV Transmission Line open, as it currently operates, followed by analysis with the Benewah — Pine Creek 115kV Transmission Line closed through. All performance/reliability issues, considering both system configurations, in the Heavy Summer scenario involve an outage of the Benewah 230/115kV Transformer. With the Benewah — Pine Creek 115kV Transmission Line open and using the current seasonal system configuration, 50.8MW of customer load and the 4.5MW generator in Plummer is dropped for a P1 contingency, loss of the Benewah 230/115kV Transformer. With the Benewah — Pine Creek 115kV Transmission Line closed and using the current seasonal system configuration the same P1 contingency result in low voltage concerns for the area served by the Benewah 230/115kV Transformer. Based on analysis of the two configuration alternatives, it is recommended to maintain the star point in an open configuration on the Benewah — O'Gara — Pine Creek 115kV transmission line until the low voltage concern can be mitigated. .1 R 1 1 :IPnPXniah TrangfnrmPr ni itan,, By closing the Benewah — Pine Creek 115kV Transmission Line, low voltage concerns appear under P1 contingency analysis which previously were not of concern. When the Benewah — Pine Creek 115kV Transmission Line is open the same P1 contingency Page 20 of 44 East Coeur d'Alene Lake System Reinforcement 2024 results in a loss of 50.8 MW of customer load and 4.5 MW of generation. Figure 10 shows the resulting system for a P1 outage of the Benewah 230/115kV Transformer. -�1��) - - : Figure 10: Benewah 230/115kV Transformer Outage, Heavy Summer 3.6.1 .2. Heavy Summer Summary Results HS GA I P1 • • T-1: Benewah 230/115 kV BENEWAH 48035 50.8 MW Load 0.94 HOPKINS# 47507 Dropped 0.93 LATAH 48181 0.94 MICA(47509) 0.93 ROCKFORD 48367 0.93 SETTERS(47376) 0.93 STMARIES 48417 0.95 TEKOA(48427) 0.94 P2 BF: R463 Benewah 230 kV Switched Shunt,Benewah 230/115 Transformer BENEWAH 48035 50.8 MW Load 0.94 HOPKINS#(47507) Dropped 0.93 LATAH 48181 0.94 MICA(47509) 0.93 ROCKFORD 48367 0.93 SETTERS(47376) 0.93 STMARIES 48417 0.95 TEKOA(48427) 0.94 BF: R468 Benewah-Boulder,Benewah 230/115 Transformer BENEWAH(48035) 50.8 MW Load 0.94 HOPKINS# 47507 Dropped 0.93 LATAH(48181) 0.94 MICA 47509 0.93 ROCKFORD(48367) 0.93 SETTERS 47376 0.93 STMARIES(48417) 0.95 TEKOA 48427 0.94 BF: R470 Benewah-Thornton,Benewah 230/115 Transformer BENEWAH 48035 50.8 MW Load 0.94 HOPKINS#(47507) Dropped 0.93 LATAH 48181 0.94 MICA(47509) 0.93 ROCKFORD 48367 0.93 SETTERS(47376) ` 0.93 Page 21 of 44 East Coeur d'Alene Lake System Reinforcement 2024 STMARIES 48417 0.95 TEKOA 48427 0.94 BF: R474 Benewah-Pine Creek,Benewah 230/115 Transformer BENEWAH 48035 50.8 MW Load 0.94 HOPKINS# 47507 Dropped 0.93 LATAH 48181 0.94 MICA 47509 0.93 PLUMMER 48323 0.95 ROCKFORD 48367 0.93 SETTERS 47376 0.93 STMARIES 48417 0.95 TEKOA 48427 0.94 BF: R476 Benewah-Moscow 230,Benewah 230/115 Transformer BENEWAH 48035 50.8 MW Load 0.94 HOPKINS# 47507 Dropped 0.93 LATAH 48181 0.94 MICA 47509 I 0.93 ROCKFORD 48367 0.93 SETTERS 47376 0.93 STMARIES 48417 I 0.95 TEKOA 48427 I 0.94 P6 N-1: Benewah-Pine Creek 230 kV+T-1: Benewah 230/115 kV 50.8 MW Load PLUMMER 48323 Dropped I 0.95 N-1: Burke-Pine Creek#3 115 kV BUR-LKY +T-1: Benewah 2301115 kV 150.8 MW Load PLUMMER 48323 I Dropped 0.95 N-1: Burke-Pine Creek#4 115 kV BUR-BIG +T-1: Benewah 230/115 kV �_ I 50.8 MW Load PLUMMER 48323 Dropped I 0.95 N-1: Burke-Thompson Falls B 115 kV+T-1: Benewah 2301115 kV 50.8 MW Load PLUMMER 48323 Dropped 0.95 N-1:Coeur dAlene 15th St-Ramsey 115 kV+T-1: Benewah 2301115 kV 50.8 MW Load PLUMMER 48323 Dropped 0.95 N-1: Noxon-Pine Creek 230 kV+T-1: Benewah 230/115 kV I 50.8 MW Load PLUMMER(48323) Dropped 0.95 A6 N-1: Burke-Pine Creek#3 115 kV Open @ BUR+T-1: Benewah 230/115 kV 50.8 MW Load PLUMMER(48323) 1 Dropped I 0.95 N-1: Burke-Thompson Falls B 115 kV Open @ BUR+T-1: Benewah 230/115 kV 50.8 MW Load PLUMMER 48323 Dropped 0.95 A7 IN-2:Appleway-Ramsey 115kV and Coeur dAlene-Ramsey 115kV+T-1: Benewah 230/115 kV _ _ I 157.2 MW Load PLUMMER(48323) Dropped 0.95 Table 12: Heavy Summer Steady State Contingency Results 3.6.2. Heavy Winter Scenario The following sections describe some existing or newly identified performance issues influenced by the project in the Heavy Winter scenario. Similar to the Heavy Summer Scenario, analysis was performed under the same two system configurations and performance/reliability issues in the Heavy Winter scenario also involve the loss of the Benewah 230/115kV Transformer. Page 22 of 44 East Coeur d'Alene Lake System Reinforcement 1 2024 With the Benewah — Pine Creek 115kV Transmission Line open and using the current seasonal system configuration, 66.8MW of customer load and the 4.5MW generator in Plummer is dropped in the P1 contingency of the loss of the Benewah 230/115kV Transformer. With the Benewah — Pine Creek 115kV Transmission Line closed and using the current seasonal system configuration the same P1 contingency result in low voltage concerns for the area served by the Benewah 230/115kV Transformer. Based on analysis of the two configuration alternatives, it is recommended to maintain the star point in an open configuration on the Benewah — O'Gara — Pine Creek 115kV transmission line until the low voltage concern can be mitigated. 3.6.2.1 . Benewah Transformer Outaor By closing the Benewah — Pine Creek 115kV Transmission Line, low voltage concerns appear under P1 contingency analysis which previously were not of concern. When the Benewah — Pine Creek 115kV Transmission Line is open the same P1 contingency results in a loss of 66.8MW of customer load and 4.5MW of generation. Figure 11 shows the resulting system for a P1 outage of the Benewah 230/115kV Transformer. = w Figure 11: Benewah 230/115kV Transformer Outage, Heavy Winter 3.6.2.2. Heavy Winter Summary Results HW CLOSEOGA HW—BASE —PIN P1 T-1: Benewah 230/115 kV BENEWAH 48035 66.8 MW Load 0.94 HOPKINS#(47507) Dropped 0.92 LATAH 48181 0.94 MICA(47509) 0.92 PLUMMER 48323 0.95 ROCKFORD(48367) 0.93 SETTERS 47376 0.93 TEKOA(48427) 0.94 P2 BF: R463 Benewah 230 kV Switched Shunt, Benewah 230/115 Transformer BENEWAH 48035 66.8 MW Load 0.94 HOPKINS#(47507) Dropped 0.92 LATAH 48181 0.94 MICA(47509) 0.92 Page 23 of 44 East Coeur d'Alene Lake System Reinforcement 2024 PLUMMER 48323 0.95 ROCKFORD 48367 0.93 SETTERS 47376 I 0.93 TEKOA 48427 _ 0.94 BF: R468 Benewah-Boulder,Benewah 230/115 Transformer BENEWAH 48035 66.8 MW Load 0.94 HOPKINS#(47507) Dropped 0.92 LATAH(48181) 1 0.94 MICA(47509) 0.92 PLUMMER 48323 0.95 ROCKFORD(48367) 0.93 SETTERS(47376) 0.93 TEKOA(48427) I 0.94 BF: R470 Benewah-Thornton,Benewah 2301115 Transformer BENEWAH(48035) 166.8 MW Load 0.94 HOPKINS# 47507 I Dropped 0.92 LATAH(48181) I 0.94 MICA(47509) 0.92 PLUMMER 48323 0.95 ROCKFORD 48367 0.93 SETTERS 47376 0.93 TEKOA 48427 �_ 0.94 BF: R474 Benewah-Pine Creek,Benewah 230/115 Transformer BENEWAH 48035 66.8 MW Load 0.94 HOPKINS# 47507 j Dropped 0.92 LATAH 48181 0.93 MICA 47509 0.92 PLUMMER 48323 0.95 ROCKFORD 48367 0.92 SETTERS 47376 0.92 STMARIES 48417 I 0.95 TEKOA 48427 I 0.93 BF: R476 Benewah-Moscow 230,Benewah 230/115 Transformer BENEWAH 48035 166.8 MW Load 0.94 HOPKINS# 47507 Dropped 0.92 LATAH(48181) 0.94 MICA 47509 0.92 PLUMMER 48323 I 0.95 ROCKFORD 48367 0.93 SETTERS 47376 0.93 TEKOA 48427 I 0.94 P6 N-1: Benewah-Pine Creek 230 kV+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 Dropped 0.95 N-1: Burke-Pine Creek#3 115 kV BUR-LKY +T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 Dropped 0.95 N-1: Burke-Pine Creek#3 115 kV(PIN-LKY)+T-1:Benewah 230/115 kV 66.8 MW Load STMARIES 48417 I Dropped 0.95 N-1: Burke-Pine Creek#4115 kV BUR-BIG +T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 Dropped 0.95 N-1: Burke-Pine Creek#4 115 kV(PIN-BIG)+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 Dropped 0.95 N-1: Burke-Thompson Falls B 115 kV+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 I Dropped 0.95 N-1:Coeur dAlene 15th St-Ramsey 115 kV+T-1:Benewah 230/115 kV 66.8 MW Load STMARIES 48417 Dropped 0.95 N-1: Hatwai-Moscow 230 230 kV+T-1: Benewah 230/115 kV Page 24 of 44 East Coeur d'Alene Lake System Reinforcement 2024 PIN 66.8 MW Load STMARIES 48417 Dropped 0.95 N-1: Noxon-Pine Creek 230 kV+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 Dropped 0.95 S-1: Ramsey 115kV Switched Shunt+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 I Dropped 0.95 A7 N-2:Appleway-Ramsey 115kV and Coeur dAlene-Ramsey 115kV+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 I Dropped 0.95 A6 N-1: Burke-Pine Creek#3 115 kV Open @ BUR+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 Dropped 0.95 N-1: Burke-Pine Creek#3 115 kV Open @ PIN+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 I Dropped 0.95 N-1: Burke-Pine Creek#4 115 kV Open @ PIN+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 I Dropped 0.95 N-1: Burke-Thompson Falls B 115 kV Open @ BUR+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 Dropped 0.95 N-1:Coeur dAlene 15th St-Pine Creek 115 kV Open @ CDA+T-1: Benewah 230/115 kV 66.8 MW Load STMARIES 48417 Dropped 0.95 Table 13: Heavy Winter Steady State Contingency Results 3.6.3. 2026 Light Spring Scenario Steady state analysis using the Light Spring scenario did not identify any new performance issues for the subject area. The same load loss reliability concern, as with the Heavy Summer and Heavy Winter scenarios, transpire with the loss of the Benewah 230/115kV Transformer. 3.7. Voltage Stability Analysis 3.7.1 . Power/Voltage (PV) Adequacy With the necessary network upgrades represented in the model, a Load Ramp PV Curve analysis was conducted while monitoring all buses in the local area. The PV curve process automatically solves a sequence of power flows at incremental levels of power transfer between a source Injection Group and a sink Injection Group. The source Injection Group, supplying the generation necessary for the incremental load increase, was configured to be sourced from all generation in WECC. Power transfer of load in the Coeur D'Alene and Palouse areas was incrementally increased, while performing contingency analysis for a pre-defined set of contingencies at each load increment, until voltage collapse occurred. This process provides the resulting PV Curve as shown in Figure 12. Analysis was performed assuming the 115kV transmission line is closed through from Benewah to Pine Creek. Any breaker failure at Benewah or loss of the Benewah 230/115kV Transformer have a similar response to increase in load. The most limiting contingency is the R474 breaker Page 25 of 44 East Coeur d'Alene Lake System Reinforcement 2024 failure at Benewah. Voltage in the area quickly decreased for the breaker failure outage as load in the area is increased. 0.9T 0- _ 091 090 091 09 009 0,87 OBfi 001 0� n 0.01 OB BM 0T8 0]1 OB] 0.% 000 1,090 1,300 1,100 1,600 1,000 3,000 �__., _.�_ 3,6W 20W ­. O.a nnv:coevvamema Palouse — 50(1 T) — 5.0(ae1n, —BF:RIfiBBmexeM1-Boultler,BmcxeM1 330I115Trensl0rmer:STM1VRIES_115.0(1811T) -RI]IBmexeM1-Pine Geek.Be---M1 3501115Trenslarmer:STMMIES_1150(1811') Build Date:December 9,2021 Figure 12: PV Analysis Results 3.7.2. Reactive/Voltage (QV) Stability Analysis The reactive power and voltage relationship show the sensitivity and variation of bus voltages with respect to reactive power injections or absorptions. A system is considered stable, with respect to voltage, if VQ sensitivity is positive for every bus. Positive reactive margin is an indication of how far a transmission system is from voltage instability. Low reactive margin (below 200Mvar at any 230kV bus or any 230/115kV source on the low side) is considered marginal and is indicative of potential system concerns. Voltage adequacy studies were performed to determine the relative strength of the local transmission system. Several buses in the area were selected as an injection bus where reactive load was increased until the voltage collapsed (i.e., the case became numerically unstable) for each contingency. Analysis was performed assuming the 115kV transmission line is closed through from Benewah to Pine Creek. The results provided in Table 14 show improved reactive margin in some areas and very little change in reactive margin in other areas. A notable improvement is made at the St. Maries bus under the base case. The reactive margin improved from 85Mvar to almost 152Mvar. The pre-project contingencies at Benewah 115kV bus and the St. Maries bus result in an outage for the area, therefore no reactive margin was calculated for these instances. Reactive Margin Bus/Contingency Pre-Project Post-Project Percent Change BENEWAH 115 BASECASE -313.77 -385.09 22.73% BF:R463 BENEWAH 230 KV SWITCHED SHUNT,BENEWAH 230/115 TRANSFORMER 0 -62.98 BF:R468 BENEWAH-BOULDER,BENEWAH 230/115 TRANSFORMER 0 -63.15 Page 26 of 44 East Coeur d'Alene Lake System Reinforcement 1 2024 Reactive Margin Bus/Contingency Pre-Project Post-Project Percent Change BF:R474 BENEWAH-PINE CREEK,BENEWAH 230/115 TRANSFORMER 0 -62.27 BF:R476 BENEWAH-MOSCOW 230,BENEWAH 230/115 TRANSFORMER 0 I -63.22 T-1:BENEWAH 230/115 KV 0 -62.98 BENEWAH 230 BASECASE -1035.17 -1068.58 3.23% BF:R463 BENEWAH 230 KV SWITCHED SHUNT,BENEWAH 230/115 TRANSFORMER -1168.84 -1160.88 -0.68% BF:R468 BENEWAH-BOULDER,BENEWAH 230/115 TRANSFORMER -687.1 -682.44 -0.68% BF:R474 BENEWAH-PINE CREEK,BENEWAH 230/115 TRANSFORMER -958.03 -957.96 -0.01% BF:R476 BENEWAH-MOSCOW 230,BENEWAH 230/115 TRANSFORMER -944.88 -936.84 -0.85% T-1:BENEWAH 230/115 KV -1168.84 -1160.88 -0.68% PINE CRK 115 BASECASE -582.74 1 -619.74 6.35% BF:R463 BENEWAH 230 KV SWITCHED SHUNT,BENEWAH 230/115 TRANSFORMER -592.58 -528.46 -10.82% BF:R468 BENEWAH-BOULDER,BENEWAH 230/115 TRANSFORMER -607.35 -553.75 -8.83% BF:R474 BENEWAH-PINE CREEK,BENEWAH 230/115 TRANSFORMER -471.63 -416.84 -11.62% BF:R476 BENEWAH-MOSCOW 230,BENEWAH 230/115 TRANSFORMER -608.94 -555.1 -8.84% T-1:BENEWAH 230/115 KV -615.45 -559.55 -9.08% PINE CRK 230 BASECASE -754.59 -765.83 1.49% BF:R463 BENEWAH 230 KV SWITCHED SHUNT,BENEWAH 230/115 TRANSFORMER -804.35 -768.09 -4.51% BF:R468 BENEWAH-BOULDER,BENEWAH 230/115 TRANSFORMER -782.2 -752.77 -3.76% BF:R474 BENEWAH-PINE CREEK,BENEWAH 230/115 TRANSFORMER -520.16 -489 -5.99% BF:R476 BENEWAH-MOSCOW 230,BENEWAH 230/115 TRANSFORMER -810.43 -772.68 -4.66% T-1:BENEWAH 230/115 KV -824.86M-87.14 -3.84% STMARIES BASECASE -85.27 77.91% BF:R463 BENEWAH 230 KV SWITCHED SHUNT,BENEWAH 230/115 TRANSFORMER 0BF:R468 BENEWAH-BOULDER,BENEWAH 230/115 TRANSFORMER 0BF:R474 BENEWAH-PINE CREEK,BENEWAH 230/115 TRANSFORMER I 0 BF:R476 BENEWAH-MOSCOW 230,BENEWAH 230/115 TRANSFORMER 0 -86.96 T-1:BENEWAH 230/115 KV 1 0 I -87.14 Table 14: QV Analysis Results 3.7.3. Reactive SUDDort Analysi, Steady state contingency analysis results in low voltage concerns in both the heavy summer and heavy winter scenarios with the loss of the Benewah 230/115kV transformer. The star network around Benewah can be rearranged post contingency to transfer load thus mitigating low voltage concerns. Should future studies or operations deem load transfers unacceptable, additional analysis was performed to evaluate the size and optimal location for future capacitors. The following table shows post contingency reactive support in the area. Various size capacitor banks were evaluated, considering locations at either O'Gara or Benewah. Two steps of 6.7Mvar at Benewah is recommended to mitigate post contingency undervoltage concerns. Page 27 of 44 East Coeur d'Alene Lake System Reinforcement 1 2024 SupportOGA @ OGA @ • P1 T-1: Benewah 230/115 W BENEWAH 48035 0.94 1 0.959 0.971 0.984 0.967 0.987 1.013 HOPKINS# 47507 0.92 I 942 0.954 0.967 0.949 0.97 0.997 LATAH 48181 0.94 0.956 0.968 0.98 0.963 0.984 1.010 MICA 47509 0.92 943 0.955 0.968 0.951 0.971 0.998 OGARA 48297 0.97 0.983 0.995 1.008 0.983 0.994 1.009 PLUMMER 48323 0.95 0.968 0.979 0.992 0.972 0.988 1.009 ROCKFORD 48367 0.93 0.946 0.959 0.971 0.954 0.975 1.001 SETTERS 47376 0.93 0.945 0.958 0.97 0.953 0.973 0.999 ST MARIES 48417 0.96 0.97 0.982 0.995 0.969 0.981 0.996 TEKOA(48427) 0.94 0.955 0.967 0.98 0.962 0.983 1.009 Table 15: Reactive Support Analysis 3.8. Stability Contingency Analysis Modifications to the transmission system may impact the transient stability performance of the transmission system. An analysis is necessary to determine if the completion of the East Coeur d'Alene Lake System Reinforcement project will introduce new transient stability issues. Additionally, an analysis can be performed to determine the maximum clearing time at stations impacted by the project. Analysis was performed assuming the 115kV transmission line is closed through from Benewah to Pine Creek. 3.8.1 . Transient Performance A high generation, light load scenario where power angles across transmission lines are relatively large will typically create the highest potential for transient performance issues. Spring runoff for the hydroelectric facilities in north Idaho and eastern Montana is the scenario historically studied. Combining spring runoff with high output from Colstrip and the gas plants at Lancaster and Rathdrum stresses the performance concerns. The retirement of Colstrip units 1 and 2 has led to a lower probability of having the high-power angle spreads historically studied. The scenario studied for the Carlin Bay Station project represents a realistic operating condition. No new transient performance issues were identified. Figure 13 shows the rotor angle and real power output trajectory for a fault on the Pine Creek 115kV bus with a protection system failure contingency. The simulated fault represents one of the larger impacts to the system for this area but no material changes in performance to the simulation was observed. The transient performance was equal to or better under various contingencies in the region. Page 28 of 44 East Coeur d'Alene Lake System Reinforcement 2024 Local Generators 90 80 70 60 in 50 $D rn v 3° y 20 10 Q o `o p -10 -20 -30 -40 -50 -60 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 Time(s) 130 120 110 100 _ so 80 70 r a 0 50 a 4o v 0 � 20 10 - 0 -10 -20 -30 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 Time(s) PSF:Pine Creek 115 W 3P PowerWorkl euld lanuary 25,2022 February 24,2022 08:42:56 Figure 13: Transient Response to Fault and PSF at Pine Creek 115kV Bus 3.8.2. Maximum Clearing Times Simulations defined did not have communication aided protection schemes and the resulting transient performance was adequate. No further analysis for maximum clearing times was required for East Coeur d'Alene Lake System Reinforcement project. 3.9. Short Circuit Analysis Short circuit analysis for a three-phase and single-line-to-ground bus fault was performed to determine circuit breaker interrupting capacity requirements for expected fault current at Carlin Bay and O'Gara Stations. Analysis was performed assuming the 115kV transmission line is closed through from Benewah to Pine Creek. New equipment shall have an interrupting capacity greater than the available fault current at the stations. The expected available fault current at Carlin Bay Station and Thevenin equivalent impedance are show in Table 16 and Table 17. The expected available fault Page 29 of 44 East Coeur d'Alene Lake System Reinforcement 2024 current and Thevenin equivalent impedance for O'Gara Station are shown in Table 18 and Table 19. Fromcman t 1pomnm Three Single Line Phase to Ground Fault 115 kV Bus 3065.6 A 1951 A 13 kV Bus 5080.3 A 5498.7 A Table 16: Expected Carlin Bay Station available fault current i 115 kV Bus 5.21834+j21.8122 13.306+j59.3829 I 13kVBus 0.12405+j1.61928 0.0489+j1.25277 Table 17: Expected Carlin Bay Station Thevenin Impedance Location Three Single Line Phase to Ground Fault I115 kV Bus 4947.8 A 3238.3 A 13 kV Bus 5494.3 A 5814.5 A Table 18: Expected O'Gara Station available fault current I115 kV Bus 3.67065+j13.4005 6.97164+j35.247 13 kV Bus 0.10184+j1.49815 0.0489+j1.25277 Table 19: Expected O'Gara Station Thevenin Impedance 3.10. Reliability Analysis Exhaustive reliability metrics are not readily available for Avista's electrical system. Reliability is therefore discussed in a relative, qualitative manner. However, there are perceived impacts to reliability with completion of the project. The Benewah — Pine Creek 115kV Transmission Line is currently operated open between O'Gara and Plummer. The open point reduces customer exposure to the transmission line between O'Gara and Pine Creek. With the addition of a switching station at O'Gara, the Benewah — Pine Creek line will become two separate lines, O'Gara — Pine Creek 115kV Transmission Line and Benewah — O'Gara 115kV Transmission Line, increasing reliability to customers in the area. The Carlin Bay Station will initially have only one 115kV transmission line to the station. If warranted in the future, increased reliability can be achieved with a second 115kV transmission line into Carlin Bay, sourced from Blue Creek. The Carlin Bay Station initial construction will include one 20MVA transformer with two feeders and an auxiliary feeder position. Following the Distribution Substation Planning procedure in DP-SPP-01, the Carlin Bay Station will be designed as a Stage 1 configuration and will not include 115kV circuit breakers in the initial construction. Motor operated switches should be installed, and allocations made for breakers in the future. Page 30 of 44 East Coeur d'Alene Lake System Reinforcement 2024 A Stage 2 configuration at Carlin Bay Station will be considered as a future option should current conditions change. 3.11 . Redlined Scada Variable Limits Preliminary SCADA Variable Limits (SVL's) are prepared with the intent of identifying constraints of existing equipment and identifying requirements for new equipment. 3.11 .1 .Feeders The new feeders at Carlin Bay and new O'Gara Station are expected to have a minimum 512A rating at 400C ambient temperature. The new feeders at the stations will have an expected winter SVL rating of 668 amps. The existing feeders at Blue Creek Station and O'Gara Station will not have a change to their facility ratings. CARLIN BAY-COEUR D'ALENE,IDAHO--13.2kV FDR CBY641, CBY642 (via 115-13.8kV XFMR NO.1) LOCATION DEVICE TYPE RATING(A) AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS V.C.B. FVR 1200 1200 1200 1200 1200 1200 1200 1200 1200 1094 CURRENT XFMR 1200/5 M.R. coon.800/5(TRF=1.33) 1064 1064 1064 1064 1064 1064 1064 1064 1064 DISCONN.SW. S&C SPST(B02) 600 1070 1018 963 905 842 775 701 618 522 S&C SPTT(B02) 600 1070 1018 963 905 842 775 701 618 522 CONDUCTOR 1000 MCM CU(75°C) 1862 1763 1653 1534 1420 1293 1150 983 778 500 MCM CU(75-C) 1222 1157 1087 1010 936 853 761 654 523 PROTECTION SEL 351S 2400 2400 2400 2400 2400 2400 2400 2400 2400 2400 (50P1P) 1104 1104 1104 1104 1104 1104 1104 1104 1104 (50P2P) 1104 1104 1104 1104 1104 1104 1104 1104 1104 5%VOLT.REG. 250KVA 525 668 668 668 668 668 643 590 512 433 -------(7.5%) MAX CURRENT= 394 561 561 561 561 522 482 443 384 325 -------(10%) 668 A 328 467 467 467 467 435 402 369 320 271 DISTRIBUTION LINE 556 AAC"D.M."(80°C) 1059 1006 948 886 825 759 685 601 502 643 600 512" ON. *NOTE: FOR SYSTEM CURRENT LIMITS,IT IS ASSUMED THAT VOLTAGE REGULATORS ARE OPERATING WITHIN A RANGE OF 5%BUCK TO 5%BOOST, AMPACITY LIMITS FOR THE RANGES OF(+/-)7.5%AND(+/-)10%,HOWEVER,HAVE ALSO BEEN LISTED TO AID ACTUAL OPERATING DECISIONS. Figure 14: Expected Carlin Bay Feeder SVL OGARA-COEUR D'ALENE,ID-- 13.2kV FDR 611 (via 115-13.8KV XFMR NO. 1) LOCATION DEVICE TYPE RATING(A) AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS V.C.B. FVR 1200 1200 1200 1200 1200 1200 1200 1200 1200 1094 CURRENT XFMR 120015 M.R. conn.800/5(TRF=1.33) 1064 1064 1064 1064 1064 1064 1064 1064 1064 DISCONN.SW. S&C SPST(B02) 600 1070 1018 963 905 842 775 701 618 522 S&C SPTT(B02) 600 1070 1018 963 905 842 775 701 618 522 CONDUCTOR 1000 MCM CU(75°C) 1862 1763 1653 1534 1420 1293 1150 983 778 500 MCM CU(75-C) 1222 1157 1087 1010 936 853 761 654 523 PROTECTION SEL 351S 2400 2400 2400 2400 2400 2400 2400 2400 2400 2400 (50P1P) 1104 1104 1104 1104 1104 1104 1104 1104 1104 (50P2P) 1104 1104 1104 1104 1104 1104 1104 1104 1104 5%VOLT.REG. 250KVA 525 668 668 668 668 668 643 590 512 433 -------(7.5%) MAX CURRENT= 394 561 561 561 561 522 482 443 384 325 -------(10%) 668 A 328 467 467 467 467 435 402 369 320 271 DISTRIBUTION LINE 556 AAC"D.M."(80°C) 1059 1006 948 886 825 759 685 601 502 YSTEM:CURRENT..!MtT:FORSPEGIFkCIEMRERAT.URE ;:i'. .i?! .:'> ..'> .668 . '>668. .668. .668>:i. 668..>::643 S90 5121' 433' *NOTE: FOR SYSTEM CURRENT LIMITS,IT IS ASSUMED THAT VOLTAGE REGULATORS ARE OPERATING WITHIN A RANGE OF S%BUCK TO 5%BOOST. AMPACITY LIMITS FOR THE RANGES OF(+/-)7.5%AND(+/-)10%,HOWEVER,HAVE ALSO BEEN LISTED TO AID ACTUAL OPERATING DECISIONS. Figure 15: Expected O'Gara Feeder SVL 3.11 .2.Transformers The new transformers at O'Gara and Carlin Bay will have an expected SVL of 29.3 MVA (20 MVA nominal) at 0°C ambient temperature. Page 31 of 44 East Coeur d'Alene Lake System Reinforcement 2024 The existing transformer at Blue Creek Station will not have a change to its facility ratings. CARLIN BAY-COEUR D'ALENE,IDAHO--115-13.8kV XFMR NO. 1 (and ASSOCIATED 115& 13.8kV BUSES) LOCATION DEVICE TYPE RATING(Amps.) AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS PRIMARY SIDE XFMR AIR SWITCH USCO AGCH5V-11512(D06) 1200 1915 1843 1768 1689 1607 1520 1417 1294 1157 CKT.SWR.A-# S&C 2030 1200 1200 1200 1200 1200 1200 1200 1200 1200 1094 CONDUCTOR 3"AL Pipe(85"C) 3591 3432 3262 3079 2879 2659 2414 2133 2000 2"AL Pipe(850C) 2196 2099 1995 1883 1762 1629 1481 1313 1114 CURRENT XFMR 120015 M.R. conn.600/5(TRF=1) 600 600 600 600 600 600 600 600 600 (55/65°C) XFMR OA/FA/FOA 112 147 147 147 147 140 133 124 114 102 22400000 115500 LOCATION DEVICE TYPE RATING(Amps.) AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS PRIMARY SIDE XFMR AIR SWITCH USCO AGCH5V-11512(D06) 10043 16028 15425 14797 14136 13450 12722 11860 10830 9684 CKT.SWR.A-# S&C 2030 10043 10043 10043 10043 10043 10043 10043 10043 10043 9156 (@ 13kV) CONDUCTOR 3"AL Pipe(85°C) 30055 28724 27302 25770 24096 22255 20204 17852 16739 2"AL Pipe(850C) 18380 17568 16697 15760 14747 13634 12395 10989 9324 CURRENT XFMR 1200/5 M.R. 5022 5022 5022 5022 5022 5022 5022 5022 5022 SECONDRY SIDE XFMR DISCONNECT SW ROYAL VT1520(D06) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 CONDUCTOR 2"Al.Pipe(85°C) 2196 2099 1995 1883 1762 1629 1481 1313 1114 CURRENT XFMR GE JCW-5 1200/5 S.R. conn.1200/5(TRF=1.33) 1596 1596 1596 1596 1596 1596 1596 1596 1596 2000/5 M.R. coon.1200/5(TRF=1.33) 1596 1596 1596 1596 1596 1596 1596 1596 1596 (55/65°C) XFMR CA/FA/FOA r 937 1228 1228 1228 1228 1171 1115 1040 956 853 22400000 13800 Figure 16: Expected Carlin Bay Transformer SVL OGARA-COEUR D'ALENE,ID--115-13.8kVXFMR NO. 1 (and ASSOCIATED 115& 13.8kV BUSES) LOCATION DEVICE TYPE RATING(Amps.) AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS PRIMARY SIDE XFMR AIR SWITCH USCG AGCH5V-11512(D06) 1200 1915 1843 1768 1689 1607 1520 1417 1294 1157 CKT.SWR.A-# S&C 2030 1200 1200 1200 1200 1200 1200 1200 1200 1200 1094 CONDUCTOR 3"AL Pipe(85°C) 3591 3432 3262 3079 2879 2659 2414 2133 2000 2"AL Pipe(85°C) 2196 2099 1995 1883 1762 1629 1481 1313 1114 CURRENT XFMR 120015 M.R. conn.600/5(TRI 600 600 600 600 600 600 600 600 600 (55/65°C) XFMR OA/FA/FOA 1 112 147 147 147 147 140 133 124 114 102 22400000 115500 LOCATION DEVICE TYPE RATING(Amps.) AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS PRIMARY SIDE XFMR AIR SWITCH USCG AGCHSV-11512(D06) 10043 16028 15425 14797 14136 13450 12722 11860 10830 9684 CKT.SWR.A-# S&C 2030 10043 10043 10043 10043 10043 10043 10043 10043 10043 9156 (@ 131,V) CONDUCTOR 3"AL Pipe(85°C) 30055 28724 27302 25770 24096 22255 20204 17852 16739 2"AL Pipe(85°C) 18380 17568 16697 15760 14747 13634 12395 10989 9324 CURRENT XFMR 120D/5 M.R. 5022 5022 5022 5022 5022 5022 5022 5022 5022 SECONDRY SIDE XFMR DISCONN.SW. ROYAL VT1520(DO6) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 CONDUCTOR 2"Al.Pipe(85°C) 2196 2099 1995 1883 1762 1629 1481 1313 1114 CURRENT XFMR GE JCW-5 1200/5 S.R. corm.1200/5(TRF=1.33) 1596 1596 1596 1596 1596 1596 1596 1596 1596 200015 M.R. onn.1200/5(TRF=1.33) 1596 1596 1596 1596 1596 1596 1596 1596 1596 (55/65°C) XFMR CA/FA/FOA r 937 1228 1228 1228 1228 1171 1115 1040 956 853 22400000 13800 Figure 17: Expected O'Gara Transformer SVL 3.11 .3.Trans mission Lines Phase one reinforcements include the new Carlin Bay— O'Gara 115kV Transmission Line which will have minimum 239MVA rating. New station equipment for phase one at O'Gara and Carlin Bay should have standard 2000A ratings. The Benewah — Pine Creek 115kV line will have no changes to the SVL ratings for phase one. The single SVL for the Benewah — Pine Creek 115kV Transmission Line will be split into four new SVL spreadsheets with the new O'Gara 115kV Station for phase two. Proposed SVL's shown below include the following impacted 115kV transmission lines- • Carlin Bay— O'Gara 115kV Transmission Line • Benewah — O'Gara 115kV Transmission Line Page 32 of 44 East Coeur d'Alene Lake System Reinforcement 2024 • O'Gara — St. Maries 115kV Transmission Line • O'Gara — Pine Creek 115kV Transmission Line CARLIN BAY-O'GARA 115kV A-XXX A-XXX,A-XXX AMBIENT TEMPERATURE (C) -30 -20 -10 0 10 20 30 40 50' LOCATION DEVICE TYPE RATING Am AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS CARLIN BAY AIR SWITCH (2)USCO AGCH5V-11520(DO6) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 (O'GARA LINE) TRANSMISSION LINE CONDUCTOR 795 ACSS"Drake" 200'C 1864 1816 1777 1736 1699 1660 1620 1578 1s34 O'GARA 115KV SUBSTATION G.C.B.A-XXX SIEMENS SPS2S-145-40-1 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (CARLIN BAY LINE) CONDUCTOR 3"AI.Pipe(85°C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 x 1272 kCM AAC"Narcissus"(80'C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (2)2000/5 M.R. conn.2000/5(TRF=2) 4000 4000 4000 4000 4000 4000 4000 4000 4000 (2)2000/5 M.R. conn.120015(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-11520(D06) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 O'GARA 115KV SUBSTATION G.C.B.A-XXX SIEMENS SPS2S-145-40-1 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (115kV LINE TIE) CONDUCTOR 3"Al.Pipe(85'C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 x 1272 kCM AAC"Narcissus"(80'C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (4)2000/5 M.R. conn.120015(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-11520(DO6) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 O'GARA 115KV SUBSTATION G.C.B.A-XXX SIEMENS SPS2 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (PINE CREEK LINE) CONDUCTOR 3"AI.Pipe(85'C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 x 1272 AAC"Narcissus"(80'C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (2)2000/5 M.R. conn.2000/5(TRF=2) 4000 4000 4000 4000 4000 4000 4000 4000 4000 (2)2000/5 M.R. conn.120015(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-11520(DO6) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 PROTECTION SEL-421(Z1MP) 3600 30881 30881 30881 30881 30881 30881 30881 30881 30881 (Z2MP) 19004 19004 19004 19004 19004 19004 19004 19004 19004 (ZLF) 2447 2447 2447 2447 2447 2447 2447 2447 2447 (50P1) 1920 1920 1920 1920 1920 1920 1920 1920 1920 (67P2)*'* 1920 1920 1920 1920 1920 1920 1920 1920 1920 SEL-311L(Z1P) 3600 30881 30881 30881 30881 30881 30881 30881 30881 30881 (Z2P) 19004 19004 19004 19004 19004 19004 19004 19004 19004 (ZLF) 2447 2447 2447 2447 2447 2447 2447 2447 2447 (50P1) 1920 1920 1920 1920 1920 1920 1920 1920 1920 67P2"' 1920 1920 1920 1920 1920 1920 1920 1920 1920 SYSTEM CURRENT LIMIT FOR SPECIFIC TEMPERATURE 1854 1818 1777 1738.. 1889 ..IND. 1620 1578 1634' Figure 18: Preliminary Carlin Bay - O'Gara 115kV SVL Page 33 of 44 East Coeur d'Alene Lake System Reinforcement 2024 BENEWAH-O'GARA 115kV A-536 A-XXX,A-XXX AMBIENT TEMPERATURE (C) .30 -20 .10 0 10. 20 30 40 50 LOCA71ON DEVICE TYPE RATING Am AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS BENEWAH SUB. G.C.B.A-536 MITSUBISHI 100SFMT40HEI 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (O'GARA LINE) CONDUCTOR 3"Al.Pipe(85'C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 CURRENT XFMR. (2)2000/5 M.R. conn 800/5(TRF-2) 1600 1600 1600 1600 1600 1600 1600 1600 1600 2000/5 M.R. conn 2000/5(TRF=2) 4000 4000 4000 4000 4000 4000 4000 4000 4000 AIR SWITCH (2)USCO AGCH5V(DO6) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 PROTECTION SEL421(ZIMP) 2400 2195 2195 2195 2195 2195 2195 2195 2195 2195 (Z2MP) 1518 1518 1518 1518 1518 1518 1518 1518 1518 (Z4MP) 1458 1458 1458 1458 1458 1458 1458 1458 1458 (ZLF) 690 690 690 690 690 690 690 690 690 (501 584 584 584 584 584 584 584 584 584 (67P2)"' 584 584 584 584 584 584 584 584 584 SEL-311L(Z1 P) 2400 2195 2195 2195 2195 2195 2195 2195 2195 2195 (Z2P) 1518 1518 1518 1518 1518 1518 1518 1518 1518 (ZLF) 762 762 762 762 762 762 762 762 762 (50P1) 584 584 584 584 584 584 584 584 584 67P2"' 584 584 584 584 584 584 584 584 584 TRANSMISSION LINE CONDUCTOR 7#7 CU(80-C) 572 544 513 481 448 413 374 330 278 210 CU 7S(85-C) 549 524 496 466 437 406 371 332 288 551 ACSR"Parakeef'(100`C) 1159 1111 1060 1005 953 896 836 769 695 556.5 AAC"Dahlia"(100°C) 1130 1083 1033 980 929 874 815 750 678 1622 ACSSITW"Pecos"(80"C) 2088 1981 1864 1738 1617 1485 1337 1167 963 AIR SWITCH A-10 USCO AGCH5V(006) 1200 1915 1843 1768 1689 1607 1520 1417 1294 1157 A-11 SIEMENS CBL-2(B02) 1200 2141 2036 1926 1809 1684 1549 1401 1236 1044 A-161 PATTON 8 COOKE V311512 B02 1200 2141 2036 1926 1809 1684 1549 1401 1236 1044 O'GARA 1151KV SUBSTATION G.C.B.A-XXX SIEMENS SPS2S-14540-1 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (BENEWAH LINE) CONDUCTOR 3"Al.Pipe(85°C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 x 1272 kCM AAC"Narcissus"(80°C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (2)20D0/5 M.R. conn.200015(TRF=2) 4000 4000 4000 4000 4000 4000 4000 4000 4000 (2)20D0/5 M.R. conn.120015(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-1 1520(006) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 O'GARA 1151KV SUBSTATION G.C.B.A-XXX SIEMENS SPS2S-145-40-1 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (115kV LINE TIE) CONDUCTOR 3"Al.Pipe(85'C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 x 1272 kCM AAC"Narcissus"(80°C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (4)20D0/5 M.R. conn.120015(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-1 1520(006) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 O'GARA 115KV SUBSTATION G.C.B.A-XXX SIEMENS SPS2 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (ST.MARIES LINE) CONDUCTOR 3"Al.Pipe(85"C)" 3591 3432 3262 3079 2879 2659 2414 2133 2D00 2 x 1272 AAC"Narcissus"(80'C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (2)200015 M.R. conn.200015(TRF=2) 4000 4000 4000 4000 4000 4000 4000 4000 4D00 (2)20D0/5 M.R. conn.120015(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-11520(DO6) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 PROTECTION SEL-421(Z1MP) 3600 30881 30881 30881 30881 30881 30881 30881 30881 30881 (Z2MP) 19004 19004 19004 19004 19004 19004 19004 19004 19004 (ZLF) 2447 2447 2447 2447 2447 2447 2447 2447 2447 (501 1920 1920 1920 1920 1920 1920 1920 1920 1920 (67P2)"' 1920 1920 1920 1920 1920 1920 1920 1920 1920 SEL-311L(Z1 P) 3600 30881 30881 30881 30881 30881 30881 30881 30881 30881 (Z2P) 19004 19004 19004 19004 19004 19004 19004 19004 19004 (ZLF) 2447 2447 2447 2447 2447 2447 2447 2447 2447 (50P1) 1920 1920 1920 1920 1920 1920 1920 1920 1920 67P2-'- 1920 1920 1920 1920 1920 1920 1920 1920 1920 SYSTEM CURRENT LIMIT FOR SPECIFIC TEMPERATURE 549 524 496 466 437 406 371 330 278 Figure 19: Preliminary Benewah - O'Gara 115V SVL Page 34 of 44 East Coeur d'Alene Lake System Reinforcement 2024 O'GARA-ST. MARIES 115kV A-XXX,A-XXX A-295 AMBIENT TEMPERATURE (C) -30 -20 -10 0 10 20 30 40 50. LOCATION DEVICE TYPE RATING Am AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS O'GARA 115KV SUBSTATIOI G.C.B.A-XXX SIEMENS SPS2S-145-40-1 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (ST MARIES LINE) CONDUCTOR 3"AI.Pipe(85'C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 x 1272 kCM AAC"Narcissus"(80`C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (2)200015 M.R. Conn.2000/5(TRF=2) 4000 4000 4000 4000 4000 4000 4000 4000 4000 (2)200015 M.R. conn.1200/5(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-11520(DO13) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 O'GARA 115KV SUBSTATIOI G.C.B.A-XXX SIEMENS SPS2S-14540-1 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (115kV LINE TIE) CONDUCTOR 3"AI.Pipe(85°C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 x 1272 kCM AAC"Narcissus"(80'C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (4)2000/5 M.R. conn.1200/5(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCHSV-11520(D06) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 O'GARA 115KV SUBSTATIOFG.C.B.A-XXX SIEMENS SPS2 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (BENEWAH LINE) CONDUCTOR 3"AI.Pipe(85'C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 x 1272 AAC"Narcissus"(80'C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (2)200015 M.R. conn.2000/5(TRF=2) 4000 4000 4000 4000 4000 4000 4000 4000 4000 (2)200015 M.R. conn.1200/5(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-11520(DO6) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 PROTECTION SEL421(Z1MP) 3600 30881 30881 30881 30881 30881 30881 30881 30881 30881 (Z2MP) 19004 19004 19004 19004 19004 19004 19004 19004 19004 (ZLF) 2447 2447 2447 2447 2447 2447 2447 2447 2447 (50P1) 1920 1920 1920 1920 1920 1920 1920 1920 1920 (67P2)"' 1920 1920 1920 1920 1920 1920 1920 1920 1920 SEL-311L(Z1 P) 3600 30881 30881 30881 30881 30881 30881 30881 30881 30881 (Z2P) 19004 19004 19004 19004 19004 19004 19004 19004 19004 (ZLF) 2447 2447 2447 2447 2447 2447 2447 2447 2447 (50P1) 1920 1920 1920 1920 1920 1920 1920 1920 1920 67P2"' 1920 1920 1920 1920 1920 1920 1920 1920 1920 TRANSMISSION LINE CONDUCTOR 2/0 ACSR"Quail"(80°C) 412 392 370 346 323 297 269 238 200 ST.MARIES SUB AIR SWITCH A-295 1200 1915 1843 1768 1689 1607 1520 1417 1294 1157 (O'GARA LINE) SYSTEM CURRENT LIMIT FOR SPECIFIC TEMPERATURE 412 392 370 348 323 297 289 238 200 Figure 20: Preliminary O'Gara - St. Maries 115kV SVL Page 35 of 44 East Coeur d'Alene Lake System Reinforcement 2024 O'GARA -PINE CREEK 115kV A-XXX,A-XXX A-292 AMBIENT TEMPERATURE (C) -20 -1^ 0 10 20 �0 50 LOCATION DEVICE TYPE RATING(Amps.) AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS AMPS O'GARA 115KV SUBSTATI(G.C.B.A-XXX SIEMENS SPS2S-145-40-1 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (PINE CREEK LINE) CONDUCTOR 3"Al.Pipe(85'C)"" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 z 1272 kCM AAC"Narcissus"(80'C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (2)200015 M.R. coon.2000/5(TRF=2) 4000 4000 4000 4000 4000 4000 4000 4000 4000 (2)200015 M.R. coon.1200/5(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-11520(DO6) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 O'GARA 115KV SUBSTATI(G.C.B.A-XXX SIEMENS SPS2S-14540-1 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (115kV LINE TIE) CONDUCTOR 3"Al.Pipe(85'C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 a 1272 kCM AAC"Narcissus"(80'C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (4)200015 M.R. corn.120015(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-11520(DO6) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 O'GARA 115KV SUBSTATI(G.C.B.A-XXX SIEMENS SPS2 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (CARLIN BAY LINE) CONDUCTOR 3"Al.Pipe(85'C)" 3591 3432 3262 3079 2879 2659 2414 2133 2000 2 x 1272 AAC"Narcissus"(80"C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (2)200015 M.R. coon.2000/5(TRF=2) 4000 4000 4000 4000 4000 4000 4000 4000 4000 (2)200015 M.R. coon.120015(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 AIR SWITCH (2)USCO AGCH5V-11520(DO6) 2000 3192 3071 2946 2815 2678 2533 2362 2157 1929 PROTECTION SEL421(Z1MP) 3600 30881 30881 30881 30881 30881 30881 30881 30881 30881 (Z2MP) 19004 19004 19004 19004 19004 19004 19004 19004 19004 (ZLF) 2447 2447 2447 2447 2447 2447 2447 2447 2447 (50P1) 1920 1920 1920 1920 1920 1920 1920 1920 1920 (67P2)"" 1920 1920 1920 1920 1920 1920 1920 1920 1920 SEL-311L(Z1P) 3600 30881 30881 30881 30881 30881 30881 30881 30881 30881 (Z2P) 19004 19004 19004 19004 19004 19004 19004 19004 19004 (ZLF) 2447 2447 2447 2447 2447 2447 2447 2447 2447 (50P1) 1920 1920 1920 1920 1920 1920 1920 1920 1920 67P2'"' 1920 1920 1920 1920 1920 1920 1920 1920 1920 TRANSMISSION LINE CONDUCTOR 413.7 ACSR/AW"Ids"(100'C) 1010 969 924 877 831 782 729 671 607 556.5 ACSR"Parakeet' 100°C 1159 1111 1060 1005 953 896 836 769 695 PINE CREEK SUB. G.C.B.A-292 MITSUBISHI 100SFMT40E 2000 3002 2876 2746 2611 2469 2321 2165 2000 1823 (O'GARA LINE) CONDUCTOR 2"AI.Pipe(85'C) 2196 2099 1995 1883 1762 1629 1481 1313 1114 3"Al.Pipe(85"C)'" 3591 3432 3262 3079 2879 2659 2414 2133 2000 (2)1272 AAC"Narcissus"(80"C) 3556 3376 3176 2962 2758 2532 2282 1994 1650 CURRENT XFMR. (2)200015 M.R. corm 1200/5(TRF=2) 2400 2400 2400 2400 2400 2400 2400 2400 2400 2000/5 M.R. coon 200015(TRF=2) 4000 4000 4000 4000 4000 4000 4000 4000 4000 AIR SWITCH (2)WEST RL(802) 600 1070 1018 963 905 842 775 701 618 522 PROTECTION SEL-321(Z1MP) 3600 2194 2194 2194 2194 2194 2194 2194 2194 2194 (Z2MP) 1853 1853 1853 1853 1853 1853 1853 1853 1853 (Z4MP) 1498 1498 1498 1498 1498 1498 1498 1498 1498 (ZLF) 1145 1145 1145 1145 1145 1145 1145 1145 1145 (50H) 1824 1824 1824 1824 1824 1824 1824 1824 1824 (50MF)"" 1200 1200 1200 1200 1200 1200 1200 1200 1200 SEL-321(Z1MP) 3600 2194 2194 2194 2194 2194 2194 2194 2194 2194 (Z2MP) 1806 1806 1806 1806 1806 1806 1806 1806 1806 (Z3MP) 1498 1498 1498 1498 1498 1498 1498 1498 1498 (ZLF) 1145 1145 1145 1145 1145 1145 1145 1145 1145 (50H) 1824 1824 1824 1824 1824 1824 1824 1824 1824 (50MF)"" 1200 1200 1200 1200 1200 1200 1200 1200 1200 SEL-351 50BF)"- 3600 3600 3600 3600 3600 3600 3600 3600 3600 3600 SYSTEM CURRENT UMIT'FOR'SPECIFIC TEMPERATURE _1010 969 924 877 831 776 701 618 ' 627 Figure 21: Preliminary O'Gara - Pine Creek 115kV SVL 4. Stakeholder Acknowledgement The Avista stakeholders listed in Table 20 have acknowledged they were informed and consulted during the development of the proposed project. Function Name 1. Substation Engineering Brian Chain 12/5/2024 Transmission Engineering Ken Sweigart 12/5/2024 Distribution Engineering Marshall Law 12/5/2024 Protection Engineering Kevin Damron 12/5/2024 Project Delivery Katie Pru h 12/5/2024 SCADA/EMS Craig Fi art 1/13/2025 Transmission Operations Rich H dzik 1/14/2025 Distribution Operations Kaitl n Richardson/Jill Ham 1/13/2025 Network Engineering - - Table 20: Avista stakeholder acknowledgement Page 36 of 44 East Coeur d'Alene Lake System Reinforcement 2024 5. Appendix 5.1 . Project Alternatives The following information provides the technical analysis results for alternatives considered. The body of the report contains the preferred alternative to address the performance issues identified in the problem statement. Providing the alternative technical analysis results is intended to be informative to System Planners and demonstrate, in part, how the preferred alternative was selected. 5.1 .1 . Do Nothinr The expected system performance if no mitigation alternatives are executed were previously discussed in the Problem Statement in Section 1. BLU321 is at capacity to accommodate existing loading levels as it relates to maintaining adequate feeder protection. Both BLU321 and OGA611 each have 3 stages of voltage regulation (including station regulators). Providing sufficient voltage regulation is already a challenge and will become more difficult as load continues to increase. Represented below are previous recorded winter peak loading values compared to the last cold load pickup event recorded. The following data was recorded for the BLU321 feeder. • The highest cold load pickup was recorded on 1/13/2024. 80T trunk fuses melted under heavy loading conditions and required 100T fuses to be temporarily installed to serve load. 100T fuses do not coordinate with midline recloser settings. • The winter peak load on 1/14/2024 was 500A. • Using 500A as a potential pre-outage load, the cold load pickup is expected to be 2.5 x 500A = 1250A. The cold load pickup surpasses the phase pickup setting of 600A for the ZC150R. The following data was recorded for the OGA611 feeder. • The winter peak load on 1/13/2024 was 215A. • Using 215A as a potential pre-outage load, the cold load pickup is expected to be 2.5 x 215A = 537.5A. The potential cold load pickup is more than the phase pickup of 420A for ZC613R. The "do nothing" alternative is not valid for the East Coeur d'Alene Lake System Reinforcement project as protection challenges will continue to increase as load in the area increases. 5.1 .2. Increase Distribution Voltag(c Distribution voltage for BLU321 and OGA611 could be increased from 13.8kV, as it operates today, to 25kV. This option would improve distribution reliability for customers on the east side of Lake Coeur d'Alene and eliminate the existing voltage drop, reduced fault current, and cold load pickup concerns. The conversion would be very involved and complicated. The option would include reconductoring the feeder from 15kV cable to 25kV. This alternative would not address the 10MVA capacity limit of Avista feeders. Page 37 of 44 East Coeur d'Alene Lake System Reinforcement 2024 This alternative will address the protection challenges however the significant cost of this option has deemed the option invalid. 5.1 .3. marlin Bay Station with Tap from O'Gara A new Carlin Bay Station could be fed from a tap of the Benewah — Pine Creek 115kV Transmission Line near O'Gara. This option would reduce modifications needed at O'Gara to just distribution upgrades, thus reducing the overall cost of the project by almost $10 million. Alternatively, this option increases customer exposure to outages on the Benewah — Pine Creek 115kV line thus reducing customer reliability in the area. SP- SPP-02 Facility Interconnection Requirements requires circuit breakers be installed for tap lines greater than 50% of the existing line length. This is intended to minimize line exposure to existing customers. The proposed Carlin Bay — O'Gara Transmission Line exceeds the 50% line-length requirement. >.1 .4. Carlin Bay Station with O'Gara Switching Station In addition to development of the Carlin Bay Station, this option includes re-building the O'Gara station to be a switching station. This option increases the overall cost of the project however provides benefits for the reliability of the system. Existing customer exposure to outages, due to the O'Gara — St. Maries 115kV line section and O'Gara — Pine Creek 115kV line section, will be eliminated with implementation of a switching station at O'Gara. Customers fed from transmission between the Benewah and Pine Creek stations will have redundant sources thus increased reliability. Equipment condition concerns at O'Gara are also alleviated with implementation of this option. Based on benefits described above, a rebuild of the O'Gara Station is the preferred option therefore the report was developed, and analysis performed based on this option. 5.1 .5. Star Point Configuratiu„ vvith O'Gara Switching Station The star point configuration at the O'Gara Station was considered in the analysis of the East Coeur d'Alene Lake System Reinforcement project. Currently the system is operated with the Benewah — Pine Creek 115kV line section open to reduce customer exposure to outages. If the Benewah — Pine Creek 115kV line remains normally open, the resulting Benewah 230/115kV Transformer outage results in 53.8MW of dropped load in the Heavy Summer scenario and 66.8MW of dropped load in the Heavy Winter scenario. Assuming the O'Gara Station will be re-built to a switching station, the customer exposure concern on the Benewah — Pine Creek 115kV line can be eliminated if the star point is removed and the Benewah — Pine Creek 115kV line is closed. Under this configuration, a new P1 voltage performance concern develops in the area based on our loading assumptions. There are several mitigation options to address this concern under heavy loading conditions. • Adjust star point at Garfield to transfer load to Moscow. • Adjust star point at Latah Tap to transfer load to Ninth & Central. • Install reactive support at Benewah on the 115kV system. • Install reactive support at O'Gara on the 115kV system. • Install a second 230/115 kV Autotransformer at Benewah. Page 38 of 44 East Coeur d'Alene Lake System Reinforcement 2024 The report was developed, and analysis was performed with both open and closed configurations for the Benewah — Pine Creek 115kV Transmission Line. Page 39 of 44 East Coeur d'Alene Lake System Reinforcement 2024 5.2. Distribution Integration Carlin Bay distribution integration buildout by year - Marshall Law 2024 ­54.• v p CDA Lake Crossing-Construction planned for2025 WP In.. 0 tf}i1000CN15 S ,y - —w- 22 VROM Budgetary Estimate-$625k(Ot Reinf) s• q sr 6.111111 � I Recloserit ZC999R Fume Normal Open Localim,- '+ South of Gocter Gi - Moscow Bay-C st cmn planned for 2024 (8.1 mi from sub) / soavci n CPC Jason Stippich SOLID Doors(Pole#032813) _ Replace 3 600'of 3-35OCN15 with 3-1000CN 15, CUTOUTSR C1016 `.'ROM Budgetary krstr Estimate-$375(D Reinf) SOLID Doors I i 4 A CUTOUTStC1015 � - 80T Fusee Burma Road -Design in 2026(TB.D.) • -..- -Constmction in 2027 Reonnfgure ked to Burma Road VROM Budgetxy,Estimate-$1Wk A SOLID Doors(Pokes 033205) S 2027 Viper Redcsers ZC1014R f (3.1 mi from sub) Ixud W laiBMa z025J Gan os Lane f1.1wi -Design in 2024(McCauley) -Constmcfion in 2025 Recondudor3,200'of344ACSR to3-556AA0 ':'RnM Budgetary Estimate-$350k gage l3 Road _r -Design in 20242025(TBD) - -Construction in 2026 - 2027 Cadin Cove : Construct new double circus line -Design in 20242025(TBD) )! 3000E of 3-556AAC 14-556AAC _ -Consbuction in 2027 800E of 3-S6AAC Recond,dor 4,000'of 3-#4ACSR to 3-556AAC 500E of 3-1000CNIS 60DA UG VROM Budgetary Estimate-$4001, VROM Budgetary Estimate-$5001, —s Martin Point- 2027 Carlin Bay Sub-Feeder Exits .. . - -Design in 2024(Jason Stippich) -Design in 2025/2026(Marshall L:::, -Construction in 2025 HOG Swrk fh#C1013 -Construction in 2027 - Reconductor 7000'of 244ACSR to 3-556AAC .. VROM Budgetary Estimate-$650k VROM BWgetary Estimate-$200k - i New Cad in Bay Feeder Configuration,. Switch#C644 Carlin Bay Sub CBY641-Tap Circuit g 115-13.2W 3-556 AAC (2)13.2kV Feeders -NoM Feeder(toward Go—er) y CBY642-Bottom Circuit 4-556 AAC-But Ckt&NIT ' __ -South Feeder(toward Harrison) _ eon Vi r Redoser#ZC645R PQ (3.8 mifrom sub) ena of 556— r �P.2 in, I Fix SOLID Doors C646 l" ., cal �• ois�o�nea�r c61aD x cfiuD 6oT Fnses ps`s "�•' Powd rh Constmobon planned for 20" "4 CPC Unassigned second d 10,30(Y f342ACSR to3-210ACSP Shared line with KEC VROM Budgetary Est—u,-$5001r(Distr Reif) Ston Road Construcuonin2024 CPCA fined:(Jason Stipich ;,. Rea d 4000E of 342ACSR to}2/OACSR and}350CN 1- Shared line with KEC Budgelary Estimate-5300k IDisVitiuLon Reinforcement) zcei:%�oa I • R #Z_618R " Fit Finus N rat Opel Locat'o" LIL ter:t.6�4 E f He,.iso R°nur 07-10 2024 I inch=3,000feet Carlin Bay Sub - Distribution Integration Route To:Marshall Law Page 40 of 44 East Coeur d'Alene Lake System Reinforcement 2024 Name BLU321 Lake Crossing Cable Location Higgins Point to Moscow Bay(Lake Coeur d'Alene) Normal feeder BLU321 Alternate feeder None Special Conditions The main feeder trunk of BLU321 crosses the Wolf Lodge arm of Lake Coeur d'Alene between Higgins Point and the mouth of Beauty Bay underwater, and then continues as underground cable to its 600A riser near Moscow Bay. The cable is 350CN15 and the majority was installed in 1992 as direct buried cable. There is one section that was installed later in 2008 and is in 3-3" conduit. Given the critical nature of this section of cable. along with the high loading levels experienced on this feeder during winter peak conditions, soil resistivity analysis was performed in 2023 as part of an effort to develop more refined cable rating values. The following chart summarizes the calculated winter and summer rating values at 3 separate locations along the overland cable route. Note that the rating of the cable installed in the lake itself is assumed to be a higher ampacity than the sections of cable installed in soil, and as such is not considered to be a limiting factor with the current configuration. Winter Rating Summer Rating (0 deg C ambient) 40 deg C ambient Cable Section#3 in 2"conduit 440 A 387 A Cable Section#5(Direct Bury) 560 A 490 A Cable Section#7(Direct Bury) 422 A 369 A With the given topology of the feeder, and the fact there is very little load between the C966D disconnects(600A riser at Cable Section#7) and the ZC150R midline recloser, a reasonable "worse case" approximation for loading on the cable is to assume the loading levels observed at ZC150R is equal to the loading at Cable Section#7. If cable loading levels reach 95%of the Section#7 rating(400 A for winter or 350 A for summer), then a contingency plan should be developed to reduce loading below the 95% levels. Potential contingency options for shedding load would include temporarily de-energizing customers on the following 1-ph laterals, depending on which phase(s)were exceeding the rating: • A-phase: 80T Fuse at Pole#026495 on Arrow Road Approximately 30 A-this will de-energize 52 customers • B-phase: 50T Fuse at Pole#026251 at Gozzer& Burma Roads Approximately 40 A—this will de-energize 55 customers • C-phase: 80T Fuse at Pole#433473 on Eddyville Road Approximately 35 A—this will de-energize 135 customers The load shed plan should not be executed until the loading level measured at ZC150 reaches 100%of the Cable Section #7 rating, i.e. 422 A on any phase for winter loading. Prior to executing on a contingency load shed.the particular loading scenario should be analyzed with SynerGi if possible.to confirm the identified contingency plan is anticipated to fully address the loading concerns. SPECIAL CONDITIONS BLU321 Lake DATE 3/5/2024 !t Crossing Cable PAGE 1 of 2 ,dir-4� ISTA Utilities SPEC SC-CDA-24-001 Page 41 of 44 East Coeur d'Alene Lake System Reinforcement 2024 Special Conditions (continued) If the elevated loading levels observed at ZC150R are a result of cold load pickup after a sustained outage downstream of that recloser, then the cable's emergency rating will allow for exceeding the 422 A rating up to as high as 485 A as long as it is for a short duration. If the cold load pickup loading hasn't dropped below 422 A within 30 minutes of the outage restoration. then a load shed contingency plan should be pursued as described above. The de-energized customers should have their power restored as soon as the loading level at ZC150R has decreased to a point where the projected load restoration will not exceed the 422 A winter rating for more than 30 minutes (with anticipated cold load pickup included). Page 42 of 44 East Coeur d'Alene Lake System Reinforcement 2024 ay s yea CENTENNIAL TRAIL Gpe�T p P epe LaKe ID90-MP20 NTEa� STATE 00 aPP®m.pry Gr.axer paw lztem w saM vde pf ws+e trail 3J•waYYfivnwwpaeeaVa - 'NTERSTgT E90 Exeang Lake Cmaaing CaMe-Appmc 3000' Riser Poet 121820 to JC 1722 Retain exeting aroaung for felling .No.—A south side of crossing one as ememenoy loop 1eee. New Lake Crossing Co -ApDroximatery 5700' New Rixr ear Po"121820 to New 600JE3 on Vault n China Ne[onluty Bay. e mu Ne n a w Bea in oteeapury Bay _ i4•an xam at omh Soft 31000CN15 pnmary(with 113 ne 1) e� 8e' HIGHWAY 97 I BLU321 - Lake Crossing Cable Replacement / Re-route NOTICE THIS�L� LmaOwn olMvfa Ua�ies'ficives on Nis map are appmamae only. IWnISTA ALEGALD GUMENT oe u, e.a� mw is wue l w`o°r'a�°o+�� Printed: 08-05-2024 1 Inch=400 feet Lai. Rcw rme I..awe.I..o-Na mauve:�a�rmaoo�a o�e cair eefw.awdawwk. Route To: Jason Stippich Page 43 of 44 East Coeur d'Alene Lake System Reinforcement 2024 JEl , Existing 600A JE3 DEEM WILLIAM 91uFEM DON.1lDOETU, 1 - 1 11 1 1 Proposed Route-1600' 4 Fsn Mnlss4t4xa Proposed new 600A JE3 on vault - _ Old cabin JEs Proposed new 600A JE3 on vault NEIEN F STO W ELL IFNEVOC�BIE iRUer TE ----------------- Existing BOOA JE3 Existing 1PH Cable Route-1700' xELEN F srov,Fi�IroeEwe•elE musr mE JA A' Nlnted:av-24-2024 ,;Rtn=,sorest BLU321 -600A Cable Route trMM ......�.... 'n..a...d„d....o."""`Route To:Jeson Stipplch Page 44 of 44