HomeMy WebLinkAboutAvista 260610-260612 Post Falls Construction IPUC Construction Inspection
Inspector(s): Galli Date(s): 260610 & 260612
Company/Owner: Avista Utilities Unit/OPID: 31232
Address: 4147 E Bogie Drive APT 101, 103 City/District: Post Falls
Contractor/Job #: NPL Foreman: Operator Supervisor: None
1036768663, 1036768705 A. Murphy
Job Description: '/" Service Line System Type: ❑x GD
One-Call Ticket: No Ticket. Customer provided trench Total Inspection Days: 2.0
Tasks: Procedure# Rating Comments
1. Materials-Handling, Storage, Labeling 3.12-3.13 SAT 3/" dated 11/2023
2. Trenching/Boring-Depth, Clearance 3.15 SAT 24" trench depth
3. Bedding/Backfill 3.15 SAT Bedding with sand
4. Pipe Installation (Tracer Wire) 3.13 SAT 12-gauge in open trench
5. Valve Installation 2.14 N/A
6. Coating Condition 2.12 N/A
7. Manuals-Field Procedures, O & M 1.4 SAT All procedures followed
8. Testing-Pressure, Duration, Type 2.12-13/3.18 SAT 100, 98, 102, 100 psi for 10 minutes
9. OQ Qualifications 4.31 SAT Verified
10. Casing Seal/Installation 3.42 N/A
11. Service Line Installation 3.16 SAT
12. Tie-In/Hot Tapping 3.32 N/A
13. Meter Location/Regulator Testing 2.22 SAT
14. Equipment Calibration Verification 5.11,14,21 SAT Verified
15. EFV Installation 3.16 SAT EFV 1200 preinstalled per maps
16. MAOP 4.15 N/A
17. Purge 3.17 SAT
18. Safety Equipment GESH 4 SAT Fire Extinguisher and JSA
19. Abandonment 5.16 N/A
20. Line Locating 4.13 N/A
21. Plastic Pine 3.23-25 SAT Lyco fitting
- Joiner(s) Qualified 3.34
- Squeeze
- Fusion Tools
- Heat Plate
- Joining Procedure
IPUC Form 4 Rev. 12/08/2025
IPUC Construction Inspection
22. Steel Pipe N/A
-Welder(s) Qualified 3.22
Pipe/Coating—Inspected/Repaired 2.12
- Cathodic Protection 2.32
-Non-Destructive Testing 3.12
-Welding Procedures
- Removal of asbestos wrap
- Exothermic Welding
Additional Comments:
Observations included (4147 E Bogie Drive APT 101): Safety equipment, JSA, verified operator
qualifications, verified equipment calibration, correct trench depth, Lyco fitting, EFV 1200 pre-installed
per maps, tracer wire, bedding with sand, successful pressure test and squeeze off. Quizzed employees on
applicable AOCs for squeeze off procedures. Quizzed employees on applicable AOCs of utility separation.
All observed procedures were followed in accordance with Avista procedures.
Observations included (4147 E Bogie Drive APT 103): Safety equipment, JSA, verified operator
qualifications, verified equipment calibration, correct trench depth, Lyco fitting, EFV 1200 pre-installed
per maps, tracer wire, bedding with sand, successful pressure test and squeeze off. All observed procedures
were followed in accordance with Avista procedures.
Observations included (4155 E Bogie Drive APT 101): Safety equipment, JSA, verified operator
qualifications, verified equipment calibration, correct trench depth, Lyco fitting, EFV 1200 pre-installed
per maps, tracer wire, bedding with sand, successful pressure test and squeeze off. All observed procedures
were followed in accordance with Avista procedures.
Observations included (4155 E Bogie Drive APT 103): Safety equipment, JSA, verified operator
qualifications, verified equipment calibration, correct trench depth, Lyco fitting, EFV 1200 pre-installed
per maps, tracer wire, bedding with sand, successful pressure test and squeeze off. All observed procedures
were followed in accordance with Avista procedures.
IPUC inspector Galli traveled back to Boise, ID on June 12, 2026.
Corrective Action Required: ❑ Yes ® No Compliance Letter#: NA
Lead Inspector: Galli Date: Reviewer: Brooks Date:
260612
Signature: /1 Signature: % �� — 1,0 6 kq
IPUC Form 4 Rev. 12/08/2025