HomeMy WebLinkAboutIntermountain Gas 260420 Ucon Construction Construction IPUC Constriction Inspection Inspector(s): Perkins Date(s): 260420 Company/Owner: Intermountain Gas Company(IGC) Unit/OPID: 8160 Address: 9347 N 25"E City/District: Ucon Contractor/Job#: KV-Utilities Foreman: Operator Supervisor: None W012471833 M.Doig Job Description: 3/4" Service Line/HPSS removal System Type: ® GD ❑ GT ❑ GG One-Call Ticket: 2026142184 Total Inspection Days: 1.0 Tasks: Procedure Rating Comments 1. Materials—Handling, Storage, OPS 11 SAT Labeling 2. Trenching/Boring—Depth, Clearance OPS 308 SAT OPS 322 3. Bedding/Backfill OPS 308 N/A SF 418 4. Pipe Installation(Tracer Wire) OPS 308 SAT Pull back after bore OPS 322 5. Valve Installation OPS 703 N/A 6. Coating Condition OPS 401 N/A OPS 402 OPS 403 7. Manuals—Field Procedures, O&M SAT IGC procedures followed 8. Testing—Pressure,Duration,Type OPS 505 N/A 9. OQ Qualifications OPS 800 SAT Verified 10. Casing Seal/Installation OPS 325 N/A 11. Service Line Installation OPS 302 SAT Only witnessed pull back on bore 12. Tie-In/Hot Tapping OPS 600 N/A 13. Meter Location/Regulator Testing OPS 302 N/A 14. Equipment Calibration Verification OPS 501 SAT Verified 15. EFV Installation OPS 301 SAT 1200 16. MAOP OPS 602 N/A OPS 606 OPS 900 OPS 1000 17. Purge OPS 603 N/A 18. Safety Equipment SF 418 SAT SF 422 19. Abandonment OPS 607 N/A IPUC Form 4 Rev.12/08/2025 IPUC Construction Inspection 20. Line Locating OPS 611 SAT Pot holing 21. Plastic Pipe OPS 307 SAT Fusing -Joiner(s)Qualified OPS 309 -Fusion Tools OPS 325 - Squeezing OPS 800 -Heat Plate -Joining Procedure 22. Steel Pipe OPS 200 N/A -Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 -Welding Procedures OPS 407 -Removal of asbestos wrap OPS 402 -Exothermic Welding OPS 403 Additional Comments: Observations included: (9347 N 25`h E,Ucon, ID): Safety equipment,valid dig ticket,verified operator qualifications,verified equipment calibration, correct trench depth, verified proper rollback of/a"butt fusion, 1200 EFV,tracer wire, boring and pullback of service line, and potholing. All observed procedures were followed in accordance with IGC procedures. Corrective Action Required: ❑ Yes ® No Compliance Letter#: N/A Lead Inspector: erkins Date: Reviewer: Brooks Date: 260420 i6 p 5 I Signature:. Signature: IPUC Form 4 Ray.12/08/2025