Loading...
HomeMy WebLinkAbout20260403Direct Barretto - Redacted.pdf RECEIVED APRIL 3, 2026 IDAHO PUBLIC UTILITIES COMMISSION BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF THE APPLICATION ) OF IDAHO POWER COMPANY AND ) CASE NO. IPC-E-26-09 PACIFICORP D/B/A ROCKY MOUNTAIN ) POWER FOR CERTIFICATES OF PUBLIC ) CASE NO. PAC-E-26-06 CONVENIENCE AND NECESSITY FOR ) SEGMENT E-8 OF THE GATEWAY WEST ) 500-KV TRANSMISSION LINE . ) IDAHO POWER COMPANY DIRECT TESTIMONY OF LINDSAY BARRETTO 1 Q. Please state your name and business address . 2 A. My name is Lindsay Barretto. My business 3 address is 1221 West Idaho Street, Boise, Idaho 83702 . 4 Q. By whom are you employed and in what capacity? 5 A. I am employed by Idaho Power Company ("Idaho 6 Power" or "Company") as the 500 kilovolt ("kV") Projects 7 Senior Manager. 8 Q. Please describe your educational background. 9 A. I received a Bachelor of Science degree in 10 Civil Engineering from Purdue University, West Lafayette, 11 Indiana in 2005 . In 2007, I earned a Master of Science 12 degree in Civil Engineering from Purdue University. I am a 13 registered professional engineer in the state of Idaho. 14 Q. Please describe your work experience with 15 Idaho Power. 16 A. I began my employment with Idaho Power in 2010 17 as an engineer in Power Production' s Civil Engineering 18 department. As an engineer I worked on hydroelectric and 19 hatchery projects and regulatory compliance. In 2015, I 20 moved to Transmission and Distribution Engineering and 21 Construction as a project manager leading power line and 22 substation projects . In 2018, I became an Engineering 23 Leader, responsible for the Stations Engineering and Design 24 department. In 2020, I was promoted to my current position, 25 Senior Manager of 500kV Projects, where my responsibilities BARRETTO, DI 1 Idaho Power Company 1 include supervision over Idaho Power' s 500-kV projects . 2 Q. What are the parties requesting in this case? 3 A. Idaho Power and PacifiCorp d/b/a Rocky 4 Mountain Power and Pacific Power (collectively referred to 5 as "PacifiCorp") (together, the "Parties" or "each Party") 6 are requesting the Idaho Public Utilities Commission 7 ("Commission") issue an order granting Idaho Power and 8 PacifiCorp each a Certificate of Public Convenience and 9 Necessity ("CPCN") for Segment E-8 of the Gateway West 500- 10 kV line ("Segment E-8") . Segment E-8 of Gateway West will 11 create up to 2, 000 megawatts ("MW") of additional 12 transmission capacity, allowing the Company to maintain 13 adequate system reliability and providing the ability to 14 interconnect new generation resources across Idaho. In this 15 proceeding, the Parties request that the Commission find 16 Segment E-8 of Gateway West to be in the public interest 17 and grant each Party a CPCN allowing for the commencement 18 of construction of Segment E-8 . The Parties respectfully 19 request the Commission issue the CPCNs no later than 20 October 31, 2026, prior to the Parties entering into any 21 contracts associated with construction of Segment E-8 . 22 Q. What is the purpose of your testimony in this 23 proceeding? 24 A. My testimony begins with a summary of Idaho 25 Power' s involvement in Segment E-8 pre-construction BARRETTO, DI 2 Idaho Power Company 1 activities performed by PacifiCorp and discussed in the 2 Direct Testimony of Mr. Rick Vail . I will then provide a 3 description of the transmission line design of Segment E-8 4 and the standards and guidelines for which it will be 5 constructed and operated. Finally, I will describe the 6 planned Segment E-8 construction activities and discuss the 7 total estimated costs associated with the project. 8 Q. Have you prepared any exhibits? 9 A. Yes . Confidential Exhibit No . 5 includes a 10 summary of the Segment E-8 costs by cost category and by 11 project owner. 12 I . SEGMENT E-8 PRE-CONSTRUCTION ACTIVITIES 13 Q. Was Idaho Power involved in Segment E-8 pre- 14 construction activities being performed by PacifiCorp? 15 A. Yes . Although the Company was not directly 16 performing the pre-construction activities for Segment E-8, 17 and therefore not managing the capital budget for the 18 activities, under the Amended and Restated Gateway West 19 Transmission Project Development Agreement ("'Project 20 Development Agreement") including the associated First 21 through Fourth Amendments, PacifiCorp, as project manager, 22 has responsibilities for preparing and distributing reports 23 to Idaho Power following each calendar quarter regarding 24 projects costs paid and projected to be paid as well as 25 activities and progress towards meeting the project BARRETTO, DI 3 Idaho Power Company 1 development objectives . 2 Q. Does the Company have the opportunity to 3 review project expenditures? 4 A. Yes . In addition to the ability to dispute any 5 invoiced amounts, under the Project Development Agreement, 6 each owner, at any time, may inspect and audit the books 7 and records of the project manager. As owners of the 8 project, the Parties are jointly and collaboratively making 9 decisions specific to project development objectives 10 including permitting and pre-construction activities 11 associated with Segment E-8 of Gateway West. The Parties 12 anticipate similar provisions will be contained within the 13 Construction Funding Agreement, which will outline 14 construction activities and objectives, when executed. 15 Q. Are there any additional provisions of the 16 Project Development Agreement that outline Idaho Power' s 17 involvement in permitting and pre-construction activities 18 with PacifiCorp as project manager? 19 A. Yes . The Project Development Agreement 20 delegates a portion of the responsibilities for the project 21 to Idaho Power, including: (1) the attendance and support 22 in public presentations regarding federal and state 23 permitting of the project, (2) providing technical and 24 expert knowledge and landowner relationship interface 25 within the geographic boundaries of the project, (3) BARRETTO, DI 4 Idaho Power Company 1 assistance with customer inquiries associated with 2 permitting and the project itself, (4) technical and 3 environmental expertise related to the National 4 Environmental Policy Act permitting support, (5) design, 5 acquisition of the rights-of-way, and long lead materials 6 for substation work, and (6) design and purchase of long 7 lead material for communication regeneration sites . In 8 addition, under the Second Amendment to the Project 9 Development Agreement, PacifiCorp must regularly consult 10 with and obtain written approval from Idaho Power, with 11 respect to all material Segment E-8 activities, including 12 bid materials, the bid process, proposed contract terms and 13 conditions, design, engineering, geotechnical 14 investigations and securing private property interests . 15 II . THE DESIGN OF SEGMENT E-8 OF GATEWAY WEST 16 Q. Please describe the design of Segment E-8 of 17 the Gateway West project. 18 A. Segment E-8 of the Gateway West project will 19 be a new, 133-mile, single circuit 500-kV transmission line 20 that is constructed between the existing Midpoint 21 substation in Jerome, Idaho and the existing Hemingway 22 substation in Melba, Idaho. One communication regeneration 23 site will also be constructed as part of the project. In 24 addition to the construction of Segment E-8, expansion of 25 the Midpoint substation and modification of the Hemingway BARRETTO, DI 5 Idaho Power Company 1 substation will be required to accommodate the project. 2 Segment E-8 is designed to withstand a wide range of 3 physical conditions and extreme events . Because 4 transmission lines are so vital to the electrical grid, 5 design standards are stringent. Segment E-8 of Gateway West 6 will adhere to, and where appropriate, exceed, the required 7 codes or standards observed for high voltage transmission 8 line design. This approach to the design, construction, and 9 operation of Segment E-8 will establish utmost reliability 10 for the life of the transmission line. 11 Q. Are there guidelines or standards for which 12 the structure of a transmission line is designed? 13 A. Yes . Overhead transmission lines have been in 14 existence for over 100 years, and many codes and 15 regulations govern the design and operation of transmission 16 lines . Both Idaho Power and PacifiCorp have developed 17 transmission line standards in accordance with the codes 18 and regulation that incorporate safety, reliability, and 19 electrical performance into the design of transmission 20 lines . Several notable standards include the: (1) American 21 Concrete Institute 318—Building Code Requirements for 22 Structural Concrete, (2) American National Standards 23 Institute standards (for material specifications) , (3) 24 American Society of Civil Engineers ("ASCE") Manual No. 74- 25 Guidelines for Electrical Transmission Line Structural BARRETTO, DI 6 Idaho Power Company 1 Loading, (4) National Electrical Safety Code ("NESC") , (5) 2 Standard ASCE 10-15 Design of Lattice Steel Transmission 3 Structures , and (6) Institute of Electrical and 4 Electronics Engineers ("IEEE") Standard 951-96 Guide to the 5 Assembly and Erection of Metal Transmission Structures . 6 NESC provides for minimum guidelines and industry standards 7 for safeguarding persons from hazards arising from the 8 construction, maintenance, and operation of electric supply 9 and communication lines and equipment. Segment E-8 of 10 Gateway West will be designed, constructed, and operated in 11 accordance with the transmission line standards of both 12 utilities, that meet, and in most cases exceed, the 13 provisions of NESC. 14 Q. Why is Segment E-8 of Gateway West being 15 designed and proposed to be constructed to exceed some NESC 16 provisions? 17 A. The transmission line standards developed by 18 both Idaho Power and PacifiCorp, and utilized for all 19 transmission line builds, typically exceed NESC standards 20 as the NESC provisions outline the bare minimum 21 requirements for transmission line construction. Physical 22 loads induced onto transmission structures and foundations 23 supporting the phase conductors and shield wires for 24 Segment E-8 are derived from three phenomena: wind, ice, 25 and tension. Under certain conditions, ice can build up on BARRETTO, DI 7 Idaho Power Company I phase conductors and shield wires of transmission lines . 2 When transverse wind loading is also applied to these iced 3 conductors, it can produce structural loading on towers and 4 foundations far greater than normal operating conditions 5 produce . As a result, some design weather cases for Segment 6 E-8 exceed the requirements in the NESC. In addition, 7 multiple loading conditions that will be incorporated into 8 the design of Segment E-8, including torsional loadings, 9 unbalanced loads, differential ice loads, broken phase 10 conductors, broken sub-phase conductors, heavy ice loads, 11 extreme wind loads, extreme ice and wind loads, 12 construction loads, and full dead-end structure loads . 13 Q. Are there guidelines or standards for design 14 of transmission line foundations? 15 A. Yes . The 2023 NESC Rule 250A4 observes the 16 structure capacity obtained by designing for NESC wind and 17 ice loads at the specified strength requirements is 18 sufficient to resist earthquake ground motions . 19 Additionally, ASCE Manual No. 74 states transmission 20 structures need not be designed for ground-induced 21 vibrations caused by earthquake motion. Historically, 22 transmission structures have performed well under 23 24 25 BARRETTO, DI 8 Idaho Power Company 1 earthquake events, ' and transmission structure loadings 2 caused by wind/ice combinations and broken wire forces 3 exceed earthquake loads . It is common industry practice to 4 design transmission line structures to withstand wind and 5 ice loads that are equal to, or greater than, these NESC 6 requirements . 7 Q. What specific measures have been taken with 8 respect to the design of Segment E-8 for earthquakes? 9 A. Experience has demonstrated that high-voltage 10 transmission lines, like foundations, are very resistant to 11 ground-motion forces caused by earthquake, so much so that 12 national standards do not require these forces be directly 13 considered in the design because the wind and ice loading 14 and specified strength requirements are sufficient to 15 resist earthquake ground motions . However, Segment E-8 16 towers will be located such that they do not straddle known 17 fault lines and foundations will be set back from known 18 surficial fault lines by a distance equal to one and a half 19 times the foundation depth. 20 Q. Did the Parties identify any geologic hazards 21 that would be of risk to the structure? 22 ' Risk Assessment of Transmission System under Earthquake Loading. J.M. Eidinger, and L. Kemper, Jr. Electrical Transmission and Substation Structures 2012, Pg. 183-192, ASCE 2013; see also Earthquake Resistant Construction of Electric Transmission and Telecommunication Facilities Serving the Federal Government Report. Felix Y. Yokel. Federal Emergency Management Agency (FEMA) . September 1990. BARRETTO, DI 1 Idaho Power Company 1 A. At this time, no high-risk geologic hazard 2 areas have been identified. If, during the process of final 3 design, an area is found to be high-risk, the first option 4 would be to microsite, route around, or span over the 5 hazard. If avoidance is not feasible, the design team would 6 seek to stabilize the hazard, or if the problematic soils 7 are relatively shallow, the tower foundations can be 8 designed to pass through the weaker soils and embed into 9 competent soils . 10 Q. How does the potential for lightning impact 11 the design? 12 A. Segment E-8 of Gateway West is in an area 13 where the ground flash density ranges from 0 . 9 to 2 . 5 14 flashes per square kilometer per year which is utilized to 15 define insulation requirements and confirm shielding for 16 the project. Because Segment E-8 will utilize an existing 17 lattice tower family, it has an established shielding angle 18 of 15 degrees, which will adequately dissipate a lightning 19 strike on the shield wires or structures if it were to 20 occur. The electrical grounding requirements for the 21 project will be determined by performing ground resistance 22 testing throughout the project alignment, and by designing 23 adequately sized counterpoise or using driven ground rods 24 with grounding attachments to the steel rebar cages within 25 the concrete foundations as appropriate. BARRETTO, DI 2 Idaho Power Company 1 Q. Please describe Idaho Power' s plans to reduce 2 risks associated with wildfire during operation of Segment 3 E-8 . 4 A. Idaho Power has developed a Wildfire 5 Mitigation Plan.2 This plan details how the Company uses 6 situational awareness of wildfire and weather conditions to 7 change the way the system is operated. It also includes 8 best practices that internal and contract crews follow for 9 construction and maintenance activities during wildfire 10 season, vegetation management practices, and transmission 11 system and distribution system hardening efforts . Segment 12 E-8 was included in the initial system risk modeling 13 conducted during development of the Idaho & Montana 2026 14 Wildfire Mitigation Plan and will continue to be evaluated 15 through future risk model updates as the project in-service 16 date approaches . 17 Q. Are there any other hazards the Segment E-8 18 design must take into account? 19 A. No. However, during the preliminary 20 construction phase, geotechnical surveys and ground 21 surveys, light detection and ranging surveys ("LiDar") help 22 verify potentially hazardous conditions . If a potentially 23 hazardous area cannot be avoided, the design process will 2 Idaho & Montana 2026 Wildfire Mitigation Plan, see also In the Matter of Idaho Power Company's 2026 Wildfire Mitigation Plan (Case No. IPC-E-25-32) . BARRETTO, DI 3 Idaho Power Company 1 seek to stabilize the area. 2 Q. Was any consideration made in the event of a 3 direct physical attack? 4 A. Yes . A direct physical attack on Segment E-8 5 may remove the line' s ability to deliver power to 6 customers . In the case of a direct attack, the line is 7 fundamentally no different than any other supply-side 8 resource under a direct physical attack. However, because 9 Gateway West is connected to the transmission grid, a 10 direct physical attack on any specific generation site in 11 the Pacific Northwest or Mountain West region will not 12 limit Segment E-8' s ability to deliver power from other 13 generation in the region. In this context, Segment E-8 14 provides additional ability for generation resources to 15 serve load if a physical attack were to occur on a specific 16 generation resource or location within the region and 17 therefore increases the resiliency of the electric grid as 18 a whole. 19 If a direct physical attack were to occur on Segment 20 E-8 and force the line out of service, the rest of the grid 21 would adjust to account for the loss of the line . Per the 22 Western Electricity Coordinating Council facility rating 23 process, the capacity rating of Segment E-8 is such that an 24 outage of the line would not overload any other system 25 element beyond equipment emergency ratings . Idaho Power and BARRETTO, DI 4 Idaho Power Company 1 PacifiCorp also keep a supply of emergency transmission 2 towers that can be quickly deployed to replace a damaged 3 tower allowing the transmission line to be quickly returned 4 to service. Transmission lines add to the resiliency of the 5 grid by providing additional paths for electricity should 6 one or more generation resources or transmission lines 7 experience a catastrophic event. 8 III . CONSTRUCTION OF SEGMENT E-8 9 Q. PacifiCorp witness Mr. Rick Vail indicated 10 Idaho Power will take over management of the project when 11 construction activities begin. When does the Company 12 anticipate construction will begin? 13 A. Construction of Segment E-8 is expected to 14 commence in October 2027 and will be performed in three 15 phases, though the scope of work is consistent across each 16 phase and includes all necessary vegetation management, 17 access road construction, pull-site construction, 18 foundations, self-supporting lattice steel structure supply 19 and installation, phase conductor, static wire, optical 20 ground wire and hardware supply and installation, along 21 with commissioning, testing and restoration. 22 The first phase of the project, the Mayfield 23 Maintenance Section, is anticipated to take approximately 24 eight months, and will include construction of 25 approximately 17 miles of the transmission line, consisting BARRETTO, DI 5 Idaho Power Company 1 of 68 structures, phase conductor, static wire and optical 2 ground wire . In addition, two cutover sections ("Crossover 3 #1" and "Crossover #2") will be constructed. These are 4 necessary for the existing 500-kV line to stay energized 5 while work on the Mayfield substation occurs . Finally, the 6 realignment of approximately five structures at mile 20 . 5 7 will be performed in Phase I as Segment E-8 will utilize an 8 existing right-of-way for approximately 1 mile and return 9 to a new and separate alignment dedicated to Segment E-8 . 10 The targeted in-service date of Phase I is summer 2028 . 11 Q. What does the second phase of construction of 12 Segment E-8 entail? 13 A. Phase II, the Hemingway to Crossover #1 14 section, consists of the construction of 126 structures 15 that extend approximately 30 miles, beginning at the 16 Hemingway substation and connecting to Crossover #1 built 17 in Phase I . This phase is expected to take approximately 18 seven months to build with a targeted in-service date of 19 late 2028 . Activities during this phase include all civil 20 work, installation of structures, phase conductor and 21 optical ground wire. In addition, from Crossover #1 to 22 Crossover #2 along the existing 500-kV line, work includes 23 removal of the existing static line and installation of new 24 optical ground wire. 25 BARRETTO, DI 6 Idaho Power Company 1 Q. What activities will occur during the final 2 phase of construction? 3 A. During Phase III of the construction of 4 Segment E-8, the Crossover #2 to Midpoint section, the 5 remaining 84 miles of the new line will be constructed and 6 is anticipated to take approximately seven months . Similar 7 to Phase II, activities include all civil work, 8 installation of structures, phase conductor and optical 9 ground wire. Phase III also includes construction of a 10 communication regeneration site. The target in-service date 11 of Phase III is summer 2030 . 12 Q. You identified a different in-service date for 13 each phase of construction. Will all three phases of 14 construction need to be completed before Segment E-8 can be 15 energized? 16 A. No. Phases I and II include the construction 17 of Segment E-8 from the Hemingway substation to the 18 Mayfield substation along with the necessary crossovers and 19 therefore provides for energization of the Hemingway to 20 Mayfield section once completed in late 2028 . Phase III, 21 the Mayfield to Midpoint section of Segment E-8, will 22 follow with energization of the second section targeted to 23 occur in summer 2030 . 24 Q. Has Idaho Power begun the competitive 25 solicitation process to secure a contractor for material BARRETTO, DI 7 Idaho Power Company 1 procurement and construction of Segment E-8? 2 A. Yes . In January 2026, the Company issued a 3 Request for Information ("RFI") to provide prospective 4 bidders an opportunity to showcase their creativity and 5 ability to sequence and plan their work to fit the 6 sensitive time frames required by the Parties for 7 construction of Segment E-8 . Because the project is still 8 in the design phase, the technical design information 9 provided at the time was limited. Bidders were encouraged 10 to use the information provided, combined with their 11 technical expertise and industry knowledge of best 12 practices to develop a well thought out, reasonable 13 response to the Technical Questionnaire and provide a 14 critical path method and linear schedule based on the 15 information provided. 16 Q. When are responses to the RFI due? 17 A. The Parties requested responses to the RFI be 18 provided by April 10, 2026 . Following evaluation by the 19 Company and PacifiCorp, notifications will be provided to 20 successful bidders with a formal Request for Proposal event 21 anticipated in July 2026 . Execution of a construction 22 contract is expected to occur by December 2026 to allow for 23 the commencement of construction in October 2027 . As such, 24 the Parties are requesting the Commission issue a CPCN no 25 later than October 31, 2026, prior to the Parties entering BARRETTO, DI 8 Idaho Power Company 1 into any contracts associated with material procurement and 2 construction of Segment E-8 . A final Commission decision in 3 October 2026 is critical to allowing for commencement of 4 construction of the project in time to meet the late 2028 5 in-service date. 6 Q. You indicated the construction of additional 7 facilities will be required for Segment E-8 of Gateway 8 West . Will the construction contractor be responsible for 9 the additional work required? 10 A. No. In addition to the construction of Segment 11 E-8, expansion of the Midpoint substation, modification of 12 the Hemingway substation, and construction of the 500-kV 13 portion of the new Mayfield substation will be required to 14 accommodate the project. However, Idaho Power will utilize 15 Company personnel or retained contractors to perform the 16 substation work as construction can occur coincident to the 17 Segment E-8 transmission line build. 18 IV. SEGMENT E-8 COSTS 19 Q. Do the Parties have an estimate of the costs 20 of Segment E-8 of Gateway West? 21 A. Yes . Based on the most recent forecast, the 22 total cost of the project, including costs associated with 23 permitting, pre-construction activities, construction of BARRETTO, DI 9 Idaho Power Company 1 Segment E-8 and substation work,3 as well as a contingency, 2 overheads, and Allowance for Funds Used During Construction 3 ("AFUDC") , is approximately , or 4 associated with Idaho Power' s share and $ 5 associated with PacifiCorp' s share, on a project ownership 6 basis . Confidential Exhibit No. 5 to my testimony includes 7 a summary of Segment E-8 costs by cost category and by 8 project owner. 9 Q. You indicated a contract has not yet been 10 executed for the construction contractor . Do the Parties 11 anticipate the project cost estimate to change 12 significantly once a contract is executed? 13 A. No. The construction cost estimate was 14 developed utilizing costs associated with construction of 15 other segments of Gateway West and therefore the Parties 16 believe the cost estimate is based on the best information 17 available at this time. Further, the competitive 18 solicitation process has already occurred for pre- 19 construction activities, including the engineer of record, 20 right of entry, right of way, biological and cultural 21 resource surveying, LiDar, and permitting consultants . 22 However, though the cost estimate was determined using a 60 23 percent detailed design, the Parties expect a 90 percent 3 Includes the Mayfield station and line terminal 500-kV facilities, the Hemingway and Midpoint line terminals, and the communication regeneration station. BARRETTO, DI 10 Idaho Power Company 1 detailed design will be available in June 2026 and expect 2 to further refine the cost estimate after that time . 3 Q. What is a detailed design? 4 A. A design starts with a preliminary design 5 based on available data and as additional information is 6 made available, such as detailed topography captured by 7 LiDAR, the design progresses . With more site-specific data, 8 detailed engineering progresses and economization occurs 9 based on on-the-ground data. The 60 percent detailed design 10 includes the design of the latticed steel transmission 11 structures being utilized for Segment E-8, the proposed 12 route location and length, preliminarily sited towers and 13 access roads, and identified primary station equipment. 14 Q. How does this translate to a cost estimate? 15 A. Based on the design, PacifiCorp utilized their 16 utility and industry experience with current market values 17 for materials, equipment, and labor to arrive at the 18 Segment E-8 estimate. They utilize the transmission line 19 design that locates every latticed steel tower and access 20 road needed for the project based on the proposed route 21 location and length and perform a partial material take off 22 for all major items (towers, phase conductors, foundations, 23 roads, rights-of-way, etc. ) using the fewest assumptions 24 possible. PacifiCorp uses the results to develop a cost 25 estimate for the transmission line component of the project BARRETTO, DI 11 Idaho Power Company 1 based on their expertise and experience. 2 Q. Are the varying percentage levels of detailed 3 design indicative of the percentage accuracy of the cost 4 estimate? 5 A. No. The difference between preliminary design 6 and the levels of detailed design are some of the areas 7 around which assumptions must be made about project 8 requirements . As with any large project, the goal is to 9 increase certainty over time and reduce contingencies and 10 unknowns as the project matures . The design percentage is 11 indicative of the unknowns that have been eliminated. 12 Therefore, the Segment E-8 cost estimate includes a budget 13 for those various unknowns . The Parties have worked 14 collaboratively to calibrate the project cost estimate 15 using PacifiCorp' s experience on recent 500-kV projects and 16 the 60 percent detailed design to develop a cost estimate 17 with as much precision as possible. 18 Q. Do the Parties have cost controls in place for 19 construction of Segment E-8 of Gateway West? 20 A. Yes . Strict project cost controls for internal 21 and external personnel are in place. Regular monthly 22 forecast updates, including the tracking of budgets and 23 schedules, are part of the project controls suites that the 24 project management team employs . All material and 25 construction services will be competitively bid, and BARRETTO, DI 12 Idaho Power Company 1 construction services contracts will include a schedule 2 with milestone dates that will be tied to monetary 3 penalties for the contractor if key dates slip. 4 V. CONCLUSION 5 Q. Please summarize your testimony. 6 A. Segment E-8 of Gateway West will be vital to 7 the electrical grid and designed to adhere to, and in most 8 cases, exceed, the required codes or standards observed for 9 high voltage transmission line design to establish utmost 10 reliability for the life of the transmission line . The 11 project is in the preliminary construction phase with 12 selection of a construction contractor to occur later this 13 year. Construction of Segment E-8 is planned to begin in 14 October 2027 to ensure energization of the first section of 15 the line can occur in 2028 . As a result, the Parties are 16 requesting the Commission issue a CPCN no later than 17 October 31, 2026, prior to the Parties entering into any 18 contracts associated with material procurement and 19 construction of Segment E-8 . 20 Q. Does this conclude your testimony? 21 A. Yes . BARRETTO, DI 13 Idaho Power Company 1 DECLARATION OF LINDSAY BARRETTO 2 I, Lindsay Barretto, declare under penalty of 3 perjury under the laws of the state of Idaho: 4 1 . My name is Lindsay Barretto. I am employed 5 by Idaho Power Company as the 500kV Projects Senior 6 Manager. 7 2 . On behalf of Idaho Power, I present this 8 pre-filed direct testimony Confidential Exhibit No. 5 in 9 this matter. 10 3 . To the best of my knowledge, my pre-filed 11 direct testimony and exhibits are true and accurate . 12 I hereby declare that the above statement is true to 13 the best of my knowledge and belief, and that I understand 14 it is made for use as evidence before the Idaho Public 15 Utilities Commission and is subject to penalty for perjury. 16 SIGNED this 3rd day of April 2026, at Boise, Idaho. 17 18 19 Signed: L/ 20 Lindsay Barretto 21 BARRETTO, DI 14 Idaho Power Company BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION CASE NO. IPC-E-26-09 IDAHO POWER COMPANY BARRETTO, DI TESTIMONY CONFIDENTIAL EXHIBIT NO. 5