HomeMy WebLinkAboutEnbridge 260219 & 260223 & 260225 & 250302 Salt Lake City Construction IPUC Pipeline Safety Inspection
Inspector(s): Galli, Brooks, Green Date(s): 260219, 260223-260225, 250302
Company/Owner: Enbridge Gas Unit/OPID: 12876
Standard: ® Training: ❑ TIMP/DIMP: ❑ OQ: ❑
Incident: ❑ Damage Prevention: ❑ Drug& Alcohol: ❑ Inspection Days:
Inspection Summary
February 19, 2026: (1.0 Standard Prep) (Galli 0.5) (Green 0.5)
Galli and Green reviewed Enbridge Control Room Management procedures against the PHMSA Inspection
Assistant (IA) to prepare for the 2026 Multi-State Control Room Audit with Utah, Idaho, and Wyoming.
February 22,2026: (3.0 Standard Travel)
Galli, Green, and Brooks traveled to Salt Lake City, UT.
February 23, 24, 25, 2026: (9.0 Standard)
Galli, Brooks, and Green met with Enbridge employees Steve Bursett, Justin Berg, Lary Flemming,
Weston Williams, and Josh Hunkele at the Enbridge Control Room along with Utah and Wyoming state
programs. PHMSA's IA Question Set for Control Room Management was used as a guide throughout the
audit to ensure all areas were completed in compliance with applicable regulations. Visited the control
room for observations and conducted a controller interview.
February 26, 2026: (3.0 Standard Travel)
Galli, Brooks, and Green traveled back to Boise, ID.
n'larch 2, 2026: (1.0 Standard Post) (Galli 0.5) (Green 0.5)
Green and Galli wrote a compliance letter, completed paperwork, and reviewed IA question set.
Discrepancies:
Unable to provide documentation showing all aspects of point to point have been completed to include Hi
Hi, Hi, Low, Low Low.
Unable to furnish sufficient training of lessons learned of close calls (near misses), post-rupture
investigations, operation and maintenance errors, emergency exercises or industry best practices will be
integrated into training and procedures where applicable.
Recommend changing language from should to shall regarding being away from the console for 15
minutes or more. Shift Handover Procedure 4.1,
Recommend adding verbiage that states the primary and secondary server are not affected by development
until the changes are pushed from the engineering server.
IPUC Form 1 Rev. 12/08/2025
IPUC Pipeline Safety Inspection
Recommend adding verbiage stating who has the final authority to initiate the switch between servers.
Recommend adding verbiage stating the senior controller can be used as an advisor during on call hours
and rest time will be adjusted accordingly.
Corrective Action Required: ® Yes ❑ No Compliance Letter#: E202601
Lead Inspector: Galli Date: Reviewer: Brooks Date:
260302
Signature: Signature:
IPUC Form 1 Rev.12/08/2025