BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER ) CASE NO. IPC-E-25-16
COMPANY'S APPLICATION FOR )
AUTHORITY TO INCREASE ITS RATES )
AND CHARGES FOR ELECTRIC SERVICE )
IN THE STATE OF IDAHO )
IN THE MATTER OF IDAHO POWER ) CASE NO. IPC-E-25-24
COMPANY'S APPLICATION TO UPDATE )
CLEAN ENERGY YOUR WAY )
CONSTRUCTION AGREEMENT PRICING )
ELEMENTS BASED ON THE 2025 IRP ) ORDER NO. 36928
On May 30, 2025, Idaho Power Company ("Company") applied to the Idaho Public
Utilities Commission ("Commission") requesting authority to increase its rates and charges for
electric service to its customers in the State of Idaho and for associated regulatory accounting
treatment("Case No. IPC-E-25-16").
On July 25, 2025, the Company applied for authority to update pricing elements for all
contracts under its Clean Energy Your Way("CEYW") Construction Program based on data from
the Company's 2025 Integrated Resource Plan("Case No. IPC-E-25-24").
On November 14, 2025, the Commission approved the Company's Application in Case
No. IPC-E-25-24, for authority to update pricing elements in its CEYW special contracts and
agreements and ordered the Company to submit revised tariffs that reflect the updated pricing
elements, as well as the date and Order Number, as a compliance filing. Order No. 36847.
On November 24, 2025, the Company submitted a Compliance Filing in Case No. IPC-E-
25-24 with updated tariffs for Schedules 26, 33, and 62, with an effective date of December 1,
2025. On December 19, 2025, the Commission approved the Company's tariffs and schedules, as
filed, effective December 1, 2025. Order No. 36876.
On December 12, 2025, the Company submitted a supplemental compliance filing
("Supplemental Compliance Filing")in Case No. IPC-E-25-24,requesting the Commission extend
the effective date of the updated tariffs and schedules to January 1, 2026, due to a timing conflict
regarding the implementation of the updated pricing elements.
ORDER NO. 36928 1
On December 30, 2025, the Commission approved the Company's proposed tariff sheets
in Case No. IPC-E-25-16, effective January 1, 2026. Order No. 36892.
On December 31, 2025, the Company filed a consolidated compliance filing
("Consolidated Compliance Filing") in Case Nos. IPC-E-25-16 and IPC-E-25-24 to update the
tariff sheets impacted by the Supplemental Compliance Filing and Order No. 36892.
On January 5, 2026, the Commission approved the Company's tariffs and schedules
included in the Supplemental Compliance Filing in Case No. IPC-E-25-24, effective January 1,
2026. Order No. 36900.
On January 23, 2026, the Company filed a supplemental consolidated compliance filing
("Supplemental Consolidated Compliance Filing"). In the December 31, 2025, Consolidated
Compliance Filing, the included tariffs did not reference Final Order No. 36900, approving the
tariffs and schedules included in the Supplemental Compliance Filing that updated the effective
date to January 1, 2026. The Supplemental Consolidated Compliance Filing is intended to ensure
clear alignment between the Commission's orders, effective dates, and the Company's updated
tariff sheets in Case Nos. IPC-E-25-16 and IPC-E-25-24.
COMMISSION FINDINGS AND DECISION
The Commission has jurisdiction over the Company's Application and the issues in this
case under Title 61 of the Idaho Code including Idaho Code §§ 61-301 through 303. The
Commission is empowered to investigate rates, charges,rules,regulations,practices, and contracts
of all public utilities and to determine whether they are just, reasonable, preferential,
discriminatory, or in violation of any provisions of law, and to fix the same by order. Idaho Code
§§ 61-501 through 503.
Having reviewed the record, the Company's Supplemental Consolidated Compliance
Filing, the Commission finds that the Company's tariffs and schedules filed on January 23, 2026,
comply with the Orders in Case Nos. IPC-E-25-16 and IPC-E-25-24, as filed, effective January 1,
2026.
ORDER
IT IS HEREBY ORDERED that the Company's tariffs and schedules filed on January 23,
2026, in Case Nos. IPC-E-25-16 and IPC-E-25-24, are approved with an effective date of January
1, 2026.
ORDER NO. 36928 2
THIS IS A FINAL ORDER. Any person interested in this Order may petition for
reconsideration within twenty-one (21) days of the service date upon this Order regarding any
matter decided in this Order. Within seven (7) days after any person has petitioned for
reconsideration, any other person may cross-petition for reconsideration. Idaho Code § 61-626.
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho, this 5ffi day of
February, 2026.
G
EDWARD LODGE, P DENT
7JR. HAMMOND IR., COMMISSIONER
DAYN HA4 IE, COMMISSIONER
ATTEST:
oni a ffm' i&Aanchez
Commission Secretary