Loading...
HomeMy WebLinkAbout20251231Tariff Advice No. IPC-TAE-25-04.pdf 0-10AHO POWER. RECEIVED DECEMBER 31, 2025 IDAHO PUBLIC GRANT T.ANDERSON UTILITIES COMMISSION Pricing and Tariff Manager ganderson(Didahopower.com VIA ENCRYPTED ELECTRONIC MAIL December 31, 2025 Commission Secretary Idaho Public Utilities Commission 11331 W. Chinden Blvd., Bldg 8, Suite 201-A (83714) PO Box 83720 Boise, Idaho 83720-0074 Re: Tariff Advice No. 25-04 Annual Compliance Filing to Update the Substation Allowance Amount under Rule N Dear Commission Secretary, Idaho Power Company ("Idaho Power" or"Company") hereby submits its proposed update to the Substation Allowance amount outlined in Rule N, Special Arrangements for Substation Allowances and Transmission Vested Interest (previously contained in Schedule 19, Large Power Service ("Schedule 19"). This annual compliance filing updates the Substation Allowance amount, as required by Idaho Public Utilities Commission ("Commission") Order Nos. 32893 and 32914. The following tariff sheet identifies the proposed modification: First Revised Sheet No. N-3 Cancelling Original Sheet No. N-3 In Case No. IPC-E-25-16, the Commission issued Order No. 36892, approving the Settlement Stipulation that moved the substation allowance and transmission vested interest provisions from Schedule 19 to newly established Rule N, effective January 1, 2026. Consistent with that Order, this tariff advice seeks to update the Substation Allowance under Rule N, with an effective date of March 15, 2026. Future annual compliance filings will accordingly be filed under Rule N. The cost estimation methodology the Company used in this tariff advice is the same methodology approved by the Commission in Case No. IPC-E-13-09 and subsequent annual filings. P.O.Box 70(83707) 1221 W.Idaho St. Boise,ID 83702 Commission Secretary December 31, 2025 Page 2 of 2 The proposed Substation Allowance amount reflects updated material costs, labor rates, and the stations overhead rate, which in total results in the proposed per megawatt Substation Allowance amount increasing from $99,826 to $104,806, or by approximately 5 percent. The primary drivers behind the proposed increase are increased material costs that have resulted in an approximate 2 percent increase in the cost of the 4-unit metalclad switchgear and an approximate 5 percent increase in the cost of the 138kV/13.09kV, 44.8 MVA transformer. The increases in the costs of these items in addition to an increase in the stations overhead rate from 2.64 percent to 3.36 percent contribute to the overall increase in the substation allowance. The workpapers used to calculate the per megawatt Substation Allowance amount and the stations overhead rate are provided as confidential attachments to this tariff advice. Please note that information in the workpapers is commercially sensitive and, if disclosed freely, could subject Idaho Power or its customers to risk of competitive disadvantage or other business injury. Because the Company files to update the Substation Allowance in accordance with a previously approved Commission methodology, it has submitted the request as a tariff advice. However, to ensure Staff has adequate time to complete its review,' the Company is requesting the same effective date proposed by Staff in the 2023 update. Accordingly, the Company respectfully requests that the proposed updates are approved and become effective by March 15, 2026. If you have any questions regarding this tariff advice, please contact Senior Regulatory Analyst Ashley Herrera at 208-388-2656 or aherrera(aD_idahopower.com. Sincerely, 1, �IIG�G/lddK. Grant T. Anderson GTA:sg Enclosures ' In the 2023 filing, the Company submitted IPC-TAE-23-03 with a proposed effective date of February 1, 2024. Staff recommended the Commission treat the Company's Tariff Advice as an application to allow a more in-depth analysis to ensure the components included in the allowance calculation reflect current, accurate costs. To provide that time, Staff recommended the Commission suspend the Company's proposed effective date until March 15, 2024. The Commission adopted Staff's recommendation and opened Case No. IPC-E-24-02. CERTIFICATE OF ATTORNEY ASSERTION THAT MATERIALS REQUESTED AND PROVIDED DURING THE COURSE OF AN IDAHO PUBLIC UTILITIES COMMISSION PROCEEDING ARE PROTECTED FROM PUBLIC INSPECTION Tariff Advice No. IPC-TAE-25-04 Idaho Power Company's Annual Compliance Filing to Update the Substation Allowance Amount Under Rule N The undersigned attorney, in accordance with Commission Rules of Procedure 67, believes that the attachments to Idaho Power Company's Tariff Advice No. 25-04 — Idaho Power Company's Annual Compliance Filing to Update the Substation Allowance Amount Under Rule N, dated December 31, 2025, contain information that constitutes trade secrets or other confidential business data exempt from disclosure under Idaho Code § 74-101, et seq., and/or § 48-801, et seq. As such, it is protected from public disclosure, inspection, examination, or copying. DATED this 31 st day of December 2025. Lisa C. Lance Counsel for Idaho Power Company P.O.Box 70(83707) 1221 W.Idaho St. Boise,ID 83702 Idaho Power Company First Revised Sheet No. N - 3 Cancels I.P.U.C. No. 30, Tariff No. 101 Original Sheet No. N - 3 RULE N SPECIAL ARRANGEMENTS FOR SUBSTATION ALLOWANCES AND TRANSMISSION VESTED INTEREST (Continued) Transmission Vested Interest Portion is that part of the Company's transmission system in which a Transmission Vested Interest is held. Substation Allowance If a Schedule 9 or 19 Customer's request for service requires the installation of new or upgraded transformer capacity in Substation Facilities, the following considerations will be included in the separate agreement between the Customer and the Company: The Customer will initially pay for the cost of new or upgraded Substation Facilities required because of the Customer's request. The Customer will be eligible to receive a one-time Substation Allowance based upon subsequent sustained usage of capacity by the Customer. a. Substation Allowance: The maximum possible allowance will be determined by multiplying the Customer's actual increase in load by$104,806 per MW but will not exceed the actual cost of the Substation Facilities. b. Substation Allowance Refunds: The Substation Allowance will be refunded to the Customer over a five-year period, with annual payments based on the Customer's Basic Load Capacity at the time of refund. The first refund will be paid one year following the first month energy is delivered through the new Substation Facilities. The refunds will occur based on the following adjustment, which will be added to the Substation Allowance received in the previous year. If there is no change in load from the previous year, the Substation Allowance for that year is equal to the Substation Allowance from the previous year: ((Change in load from the previous year as measured in MW)x(Substation Allowance per MW)) Number of Substation Allowance Refunds remaining in five-year period The Customer's annual refunds will be made in accordance with the Substation Allowance amount stated in the separate construction agreement between the Customer and the Company. Transmission Vested Interest If a Schedule 9 or 19 Customer's request for service requires the installation of new or upgraded capacity in Transmission Facilities, and those Transmission Facilities are serving the Customer by a radial feed, the following considerations will be included in the separate agreement between the Customer and the Company: The Customer will initially pay for the cost of new or upgraded Transmission Facilities required because of the Customer's request. The Customer may be eligible to receive Transmission Vested Interest Refunds in accordance with Schedule 9 or 19. IDAHO Issued by IDAHO POWER COMPANY Issued - December 31, 2025 Timothy E. Tatum, Vice President, Regulatory Affairs Effective— March 15, 2026 1221 West Idaho Street, Boise, Idaho Advice No. 25-04 Idaho Power Company First Revised Sheet No. N - 3 Cancels I.P.U.C. No. 30, Tariff No. 101 Original Sheet No. N - 3 RULE N SPECIAL ARRANGEMENTS FOR SUBSTATION ALLOWANCES AND TRANSMISSION VESTED INTEREST (Continued) Transmission Vested Interest Portion is that part of the Company's transmission system in which a Transmission Vested Interest is held. Substation Allowance If a Schedule 9 or 19 Customer's request for service requires the installation of new or upgraded transformer capacity in Substation Facilities, the following considerations will be included in the separate agreement between the Customer and the Company: The Customer will initially pay for the cost of new or upgraded Substation Facilities required because of the Customer's request. The Customer will be eligible to receive a one-time Substation Allowance based upon subsequent sustained usage of capacity by the Customer. a. Substation Allowance: The maximum possible allowance will be determined by multiplying the Customer's actual increase in load by $99,826104,806 per MW but will not exceed the actual cost of the Substation Facilities. b. Substation Allowance Refunds: The Substation Allowance will be refunded to the Customer over a five-year period, with annual payments based on the Customer's Basic Load Capacity at the time of refund. The first refund will be paid one year following the first month energy is delivered through the new Substation Facilities. The refunds will occur based on the following adjustment, which will be added to the Substation Allowance received in the previous year. If there is no change in load from the previous year, the Substation Allowance for that year is equal to the Substation Allowance from the previous year: ((Change in load from the previous year as measured in MW)x(Substation Allowance per MW)) Number of Substation Allowance Refunds remaining in five-year period The Customer's annual refunds will be made in accordance with the Substation Allowance amount stated in the separate construction agreement between the Customer and the Company. Transmission Vested Interest If a Schedule 9 or 19 Customer's request for service requires the installation of new or upgraded capacity in Transmission Facilities, and those Transmission Facilities are serving the Customer by a radial feed, the following considerations will be included in the separate agreement between the Customer and the Company: The Customer will initially pay for the cost of new or upgraded Transmission Facilities required because of the Customer's request. The Customer may be eligible to receive Transmission Vested Interest Refunds in accordance with Schedule 9 or 19. IDAHO Issued by IDAHO POWER COMPANY Issued per Order No- December 31, 2025- Timothy E. Tatum, Vice President, Regulatory Affairs Effective— March 15, 2026 january , 1221 West Idaho Street, Boise, Idaho Advice No. 25-04