Loading...
HomeMy WebLinkAbout20251202Closing Brief.pdf RECEIVED DECEMBER 2, 2025 Clean Energy Opportunities for Idaho IDAHO PUBLIC UTILITIES COMMISSION Kelsey Jae (ISB No. 7899) Law for Conscious Leadership 521 E 41 st St,Apt. 506 Garden City, ID 83714 Phone: (208)391-2961 1kelsey0)kelseyjae.com Attorney for Clean Energy Opportunities for Idaho BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF IDAHO POWER CASE NO. IPC-E-24-44 COMPANY'S APPLICATION FOR APPROVAL OF SPECIAL CONTRACT Clean Energy Opportunities for Idaho AND TARIFF SCHEDULE 28 TO PROVIDE ELECTRIC SERVICE TO Closing Brief MICRON IDAHO SEMICONDUCTOR MANUFACTURING (TRITON) LLC. The Triton FAB load is transformational, unlike any existing customer. The magnitude of the incremental FAB load makes this a case of first impression. As a matter of first impression this case requires Commission policy updates to address the transformation that is now upon us. There are multiple open issues in this docket, but the key issue is who pays for resources which are solely caused by the FAB yet not solely used by the FAB. Resolving how to allocate the costs of the incremental bulk power system (Generation &Transmission, "G&T") resources caused by the FAB load necessitates a more thorough review than Idaho Power("the Company" or "IPC") has provided. The ESA should not be approved as submitted. In section 3.1 of this briefing, CEO recommends three ESA changes: to implement TOU energy rates, to clarify that any "additional transmission" costs are not limited to those needed as traditional "Interconnection Facilities", and to explicitly allow the ability to update the method used to determine FAB Energy and Demand charges. In addition, CEO requests that additional reviews should be ordered to address open matters enumerated in section 3.2. Failing to fully address these matters could harm existing IPC customers in this instance and will do further damage when the next very large load customer arrives. CEO's brief will address these matters in more detail below. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 1 Clean Energy Opportunities for Idaho Table of Contents 1 THE CASE AS PRESENTED HAS MULTIPLE DEFICIENCIES AND IS INADEQUATE TO SUPPORT ESA AND SCHEDULE 28 APPROVAL. 2 1.1 NO-HARM SCENARIOS-THE SINGULAR"BEST CASE"SCENARIO NO-HARM ANALYSIS THE COMPANY RAN WAS INSUFFICIENT TO JUSTIFY THE FAB RECEIVING EMBEDDED DEMAND RATE TREATMENT. ALTERNATE SCENARIOS PRODUCE DRAMATICALLY DIFFERENT OUTCOMES THAT SHOW SUBSTANTIAL HARM TO EXISTING CUSTOMERS. 2 1.2 TRANSFORMATIONAL,NOT TRADITIONAL-THE FAB LOAD IS SO MUCH LARGER THAN EXISTING CUSTOMERS THAT TRADITIONAL SPECIAL CONTRACTS APPROACHES ARE AN INAPPROPRIATE BASIS FOR JUSTIFYING THE USE OF TRADITIONAL COST ALLOCATION METHODS. 7 1.3 PERVERSE INCENTIVES-IN THIS ERA WHERE IOUS COMPETE FOR LARGE NEW LOAD"COMPETITIVE"CUSTOMERS, PROTECTION OF EXISTING"CAPTIVE"CUSTOMERS IS AT RISK. 10 1.4 BAD PRECEDENT-THE PROPOSED FAB COSTALLOCATION METHODS LIMIT FAIR TREATMENT FOR EXISTING CUSTOMERS FROM BOTH THE FAB AND SUCCESSIVE LARGE LOAD CUSTOMERS. 12 2 NEW VERY LARGE CUSTOMERS RAISE SEVERAL NEW ISSUES THAT REQUIRE CLARIFICATION AND POLICY GUIDANCE FROM THE COMMISSION. 13 2.1 WHAT CONSTITUTES A NEW LARGE LOAD? 13 2.2 WHEN DOES SUCH A NEW LARGE CUSTOMER BECOME"EXISTING"AND NO LONGER"NEW"? 14 2.3 SHOULD INCREMENTAL INFRASTRUCTURE COSTS THAT WOULD NOT OCCUR BUT FOR THE NEW LOAD BE CHARGED TO THAT NEW CUSTOMER? 14 2.4 HOW SHOULD A NEW LARGE LOAD CUSTOMER PAY FOR THE INCREASED REVENUE REQUIREMENTS IT CAUSES DUE TO UPWARD PRESSURE ON THE COMPANY'S FINANCING COSTS AND RETURN ON EQUITY(ROE)? 15 2.5 HOW ARE ANY INCREMENTAL COSTS A NEW LOAD CAUSES TO BE MEASURED AND ALLOCATED TO THAT CUSTOMER? 15 2.6 COULD SPECIAL RATE DESIGN CONCERNS RELATED TO NEW VERY LARGE CUSTOMERS BE REDUCED OR ELIMINATED BY CUSTOMER SELF-SUPPLY OR VIA FUNDING THROUGH A CIAO"LOAN"? 15 3 SUMMARY RECOMMENDATIONS AND REQUESTS 16 3.1 CHANGES TO THE ESA 17 3.2 STAFF LEAD FOLLOW-ON PROCESS 17 1 The case as presented has multiple deficiencies and is inadequate to support ESA and Schedule 28 approval. 1.1 No-harm scenarios-The singular"best case"scenario no-harm analysis the Company ran was insufficient to justify the FAB receiving embedded demand rate treatment. Alternate scenarios produce dramatically different outcomes that show substantial harm to existing customers. Company witness Ms. Aschbrenner explained that the Company went through a two-step process to develop the embedded demand cost approach it proposes for the FAB. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 2 Clean Energy Opportunities for Idaho First, the Company conducted a no-harm analysis purportedly showing that allocating both existing and incremental G&T costs on a load ratio basis would not harm existing customers by raising the rates they pay as demand charges. Second, the Company developed a marginal energy cost and embedded demand cost rate structure for the ESA. Other no-harm scenarios and rate design alternatives were not presented. The Company's no-harm analysis is the prime justification for proposing that the FAB not be directly charged for the incremental G&T costs it causes.' As will be shown below, that no-harm analysis is fatally flawed and the conclusion that granting the FAB embedded demand cost treatment is not warranted. Table 3 . LTCE Resource Selection `With vs . Without Micron" With Micron vs.Without Micron Geothermal Nuclear Year Coal Gas/H2 Wind Solar Storage OR EE Biomass 2026 - - - - - - - - 2027 - - 600 100 100 - - - 2028 - - - 100 200 - - - 2029 - 100 100 - 155 10 - - 2030 - 250 - - - - - - 2031 - - - - - - 8 - 2032 - (50) - - - - - - 2033 - (50) - 100 45 - 21 - 2034 - - - - (5) - 6 - 2035 - - - - - - 5 - Sub Total - 250 700 3W 49S 10 41 - Figure 1-List of FAB caused incremental generation resource requirementS2 It is not contested that serving the FAB load will require incremental generation resources (as displayed in Figure 1). These resources will be very expensive. Using unit prices for supply-side resources taken from the 2025 IRP, the FAB would cause IPC to procure (and rate base) more than $2 billion worth of additional generation resources3. ' CEO notes additional attempts to justify the embedded cost treatment by comparison,among other things, to rate treatment employed in the Lamb Weston and Brisbee special contracts. See section 1.2 below. 2 IPC-E-24-44 Ellsworth Surrebuttal page 9. 3 Calculated assuming that all the solar resource requirements would be procured via PPA rather than IPC owned and only 300 MWs of the wind resource would be IPC owned with the remainder procured via PPA for consistency with the 2025 IRP assumptions. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 3 Clean Energy Opportunities for Idaho The no-harm analysis the Company relied upon uses calculations based on the assumption that after the end of the ramp up period the FAB will never operate at less than full capacity over the next two decades. That full capacity implied a level of power consumption greater than 4 terawatt-hours/year over the remainder of the 20 year test period. At that level of consumption the FAB would attract existing G&T fixed costs in an amount that exceeds the cost of the incremental generation resources FAB requires. CEO refers to the Company's no-harm run as one based on the"best case"scenario. A comprehensive and sufficient no-harm analysis should include multiple scenario analyses rather than just a single, best-case set of assumptions. Under this"best case" no-harm scenario, the FAB could absorb enough fixed costs from existing G&T resources to offset the incremental cost of the new G&T resources it requires. If the demand charges associated with the > $2 billion in FAB caused incremental generation resource costs were to be spread across a lower amount of FAB consumption, a dramatically different result arises. In a no-harm scenario where calculations were based on an annual FAB power consumption pattern that aligns with the declining monthly billing demand quantities,4 the total amount charged to FAB declines almost 50%. Because such lower levels of FAB consumption do not reduce the cost of the FAB caused incremental generation resources, those costs are shifted to existing customers. At a minimum billing demand level of FAB power consumption, more than $1 billion of FAB caused incremental generation costs are shifted to existing customers.s While this billion-dollar cost shift alone should disqualify the interpretation the Company made on its no-harm analysis, other substantive deficiencies exist in the analysis method IPC utilized. One has to do with the treatment of Transmission related fixed costs. Both IIPA and CEO raised concerns about the Company's refusal to consider that some portion of the Transmission costs that IPC models as not changing between its"with FAB"and "without FAB" runs should actually be shown to vary between those runs. 4 IPC-E-24-44 Application Exhibit 2-2. 5 CEO is using only general references to amounts of cost transfer under other than"best case"no-harm scenarios. The Company marked Exhibits 1 and 3 no-harm excel spreadsheets as Confidential in their entirety. CEO challenged the extensive confidentiality protections claimed over the data in the spreadsheet. See Confidentiality Challenge filed on September 15,2025. Prior to this challenge CEO requested clarity via email on August 23rd and received a response from the Company. Follow-up emails regarding the challenge were exchanged on September 24th and 26th. The Company replied to the challenge on October 1 st but did not file its reply. CEO counter replied on October 9th,followed-up on October 17th and received additional unfiled comments from the Company on October 21 st. Idaho Power continues to claim"sensitive business information"protection over nearly all of the data and purports to require documents citing this data be submitted confidentially or in redacted form.CEO continues to dispute the appropriateness of this extensive secrecy. Here,CEO is choosing to reference the no-harm analysis using general terms rather than specific numerical values to avoid the stated requirement to submit this Closing Brief in redacted form. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 4 Clean Energy Opportunities for Idaho CEO focused on the timing of the buildout of Mayfield substation and extending the 500kV line running from Hemmingway to Mayfield to serve the massive load growth in south-east Boise.6 IIPA raised concerns about the costs associated with new transmission lines designed to access low cost energy markets. IPC ignored both sources of incremental transmission costs in its no-harm analysis. Either incremental transmission capacity was needed to serve the FAB and should be included in the no-harm analysis, or the excessive magnitude of transmission capacity in the Company's resource plan was selected to also improve energy costs. If the latter,then it is neither fair nor reasonable to allocate transmission infrastructure to the energy- intensive FAB as though those costs are 100% capacity related. An additional open issue arises from the fact that the no-harm analysis was calculated based on 2023 and then again on 2025 IRP conditions. In the IRP the Company only models new loads from committed large load customers who have entered into procurement or construction agreements with Idaho Power. This results in the 2025 IRP only reflecting about 300MWs of new large customer load growth beyond the FAB load.' By contrast, IPC President Lisa Grow stated during the Company's 2Q25 earnings conference call: ,,The pipeline of prospective customers on our list exceeds our all-time peak load of around 3,800 megawatts." The no-harm analysis the Company ran to justify the rate design in the FAB ESA assumes that the FAB will get credit for sopping-up substantial quantities of currently under-utilized G&T capacity and their related demand costs. If the Company adds 3GWs of pipeline customers, they too will use up remaining under-utilized G&T capacity. Will those customers get a pro-rata share of the credit for sopping-up cost offsets that have already been credited to the FAB? If the potential for using up under-utilized G&T capacity is already incorporated in the FAB's rate design,will acceptance of the proposed FAB ESA treatment have produced an effective"first in time, first in right"allocation system? Company witness Mr.Anderson states: The ESA does not permanently fix demand-related pricing. Instead, it reflects cost responsibility.' The Company would have a FAB demand cost allocation method—referred to above as "cost responsibility" -that combines the incremental G&T costs the FAB causes with pre- existing embedded G&T costs and spreads those costs via a load-ratio share. A more s IPC-E-24-44 Heckler Rebuttal pages 5 and 6. 7 2025 IRP Appendix A pages 23 and 24. 8 Lisa Grow, IDACORP 2Q 2025 Earnings Conference Call,July 31,2025. 9 IPC-E-24-44 Anderson Direct page 17. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 5 Clean Energy Opportunities for Idaho robust no-harm review shows that such an allocation method would clearly harm existing customers should future FAB loads decline at a rate considered in the ESA. CEO has suggested a modification to the proposed demand costing method that could hold the existing customers harmless. In CEO's approach, the FAB would be charged for all the incremental G&T costs it is causing. The FAB could also be credited for any portion of existing G&T costs they were absorbing up to a level that equals but does not exceed the incremental costs they caused.10 CEO's suggested approach would hold existing customers harmless from G&T costs that a new very large customer causes. It would also finesse the first in time, first in right issue by allowing flexibility in how multiple future new large loads are credited for sopping-up some of the costs of existing underutilized G&T capacity. IIPA and CEO previously provided analyses that suggest not being charged the full cost of the incremental resources the FAB will require produces a greater than $1 billion benefit to FAB. CEO believes policy guidance on how to balance charging new megaload customers for the incremental costs they cause and how and to what extent existing customers should be shielded from these effects is clearly needed. CEO suggests that policy clarifications from the Commission are warranted at this time on several matters, including: • Should new megaload customers exclusively pay for all incremental costs their new Load causes even if such a rate design provides benefits to the existing customers that those customers would not receive absent the new load? • Should new megaload customers pay for their incremental costs but be granted some offsetting credit in their rate structure to reflect amounts of fixed charges the new customer attracts that reduce costs for existing customers? • Should the extent of any such credit be limited to the amount required just to keep existing customers"whole"? The Company suggests that relevant issues raised in this case are being fully vetted and the ESA should be approved without further delay." In contrast, CEO concludes that the proposed ESA and its associated Schedule 28 rate features merit more extensive review and modifications in order to adequately serve the public's interest.12 10 IPC-E-24-44 October 28 2025 Hearing transcript, Heckler Corn page 803. ""Further review beyond what is already scheduled as part of the Micron FAB case proceedings would only postpone resolution of issues that are already being thoroughly vetted." IPC-E-24-44 Aschenbrenner Surrebuttal page 11. 12 IPC-E-24-44 Heckler rebuttal page 2. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 6 V Clean Energy Opportunities for Idaho 1.2 Transformational, not traditional—The FAB load is so much larger than existing customers that traditional special contracts approaches are an inappropriate basis for justifying the use of traditional cost allocation methods. CEO pointed out the core unresolved issues in this case in March13 - The FAB represents a transformational load, so fundamentally different from all other of the Company's customers that traditional cost allocation methods are not adequate. There are many examples of how the Company and FAB counsel referred to traditional approaches for allocating the costs of shared system resources to justify ignoring the Long- standing"cost causer pays" principle. For example,while on the witness stand IIPA witness Dr. Kaufman was asked repeatedly about whether FAB would solely use power generated by the new resources its load will cause. Similarly, in her direct testimony Company witness Ms. Aschbrenner states: "Idaho Power does not procure generation or transmission resources that are solely dedicated to an individual customer".14 Company witness Mr. Ellsworth comments that the Mayfield substation is not: "solely attributable to Micron FAB's load."15 Company witness Mr. Anderson also focuses on the topic stating: "planned transmission projects are not solely necessitated by Micron FAB...These are system resources-not facilities dedicated solely to Micron FAB. System generation and transmission are planned,procured, and operated to optimize service for all customers. Assigning costs by vintage rather than by cost causation is not an approach the Company supports.16 Apparently in contrast, in her direct testimony Company witness Ms. Aschbrenner notes that: "It has been a long-standing policy of the Commission that, to the extent feasible, costs should be assigned to a cost-causer to mitigate upward pressure on rates that would otherwise exist."17 '3 IPC-E-24-44 March 21,2025 comments. 14IPC-E-24-44 Aschbrenner Direct page 9(emphasis added). 15 IPC-E-24-44 Ellsworth Surrebuttal page 4(emphasis added). 16 IPC-E-24-44 Anderson Surrebuttal page 7(emphasis added). "IPC-E-24-44Aschbrenner Direct, page 8. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 7 Clean Energy Opportunities for Idaho In response to questioning by counsel for ICIP, Ms. Aschbrenner confirmed that the Company's policies support this Commission policy and are implemented that: "growth pay[s]for growth. and that: "There has not been a policy in the State of Idaho, nor has that been accepted, that incremental generation is assigned directly to customers. Generation resources and transmission resources are utilized by all customers on our system."" As discussed in the no-harm section above, the FAB load is so large that it does solely require additional infrastructure resources even if in their use they will not solely serve FAB Load. It is feasible to assign these costs to the cost-causer. The lack of a previously established policy related to assigning incremental generation costs directly to particular customers is no justification for not doing so in this case. Under a different theory, Company witnesses also attempt to justify the proposed cost allocation method for determining demand pricing structure proposed for the FAB by comparing the proposed FAB costing method to methods approved for Lamb-Weston and Brisbie contracts. Specifically,they note consistency with "traditional cost-of-service principles and Commission precedent"20 when proposing FAB demand charges calculated on an embedded (rather than incremental) system capacity cost basis. CEO finds these comparisons largely specious and not persuasive regarding guidance on how FAB demand costs should be allocated. For example, the Company references the existing Brisbie Special Contract. The manner in which Brisbie procures RECs from a dedicated resource under a "Clean Energy Your Way" structure is not in anyway analogous to the rate design in the proposed FAB ESA. The comparison of the FAB to Brisbie is not informative regarding FAB rate design. Comparison to the costing methods in the Lamb Weston case is also problematic. Ironically, suggesting the FAB demand costs should be based upon embedded system costs appears to be directly contrary to the rationale used in developing the Lamb Weston Special Contract. Using the Lamb Weston rationale argues for a FAB rate design based on incremental rather than embedded costing. '$IPC-E-24-44 October 28 2025 Hearing transcript, page 370. 19 IPC-E-24-44 October 28 2025 Hearing transcript, pages 371 and 372. 21 IPC-E-25-16,Anderson direct page 7. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 8 Clean Energy Opportunities for Idaho Three quotes from the Application for a Special Contract with Lamb Weston (IPC-E-23-18) present this matter clearly. In section 15 of the Application in that case, under a sub- grouping of topics related to "Pricing Structure"the Company asserts that it has attempted to: develop pricing that would reduce potential cost-shifting and result in Lamb Weston fairly contributing to incremental system costs necessary to serve their new load.21 Later in Application section 19, the Company explains that the application of marginal energy costs in the Lamb Weston ESA is appropriate because the Company was energy constrained at the time the ESA was submitted, stating: Because the Company's system is currently facing near-term energy constraints, it is expected that the incremental load will cause an increase in the cost to provide energy to all customers.As such, the Company proposes to price Block 2 Energy on a marginal cost basis as more fully set forth below.22 In contrast, in section 17 of the Lamb Weston application, the Company explains that the use of demand rates based on embedded costs is warranted because Lamb Weston was a relatively small new load and not likely to require new generation or transmission investments: "The expansion of the Lamb Weston Facility is expected to Lamb Weston's peak load represents.7%of IPC result in an approximately average system load. By comparison,at> 18%of 14,000 kW increase in power average annual total system load by 2030,the FAB requirements, which is a summer load represents a 25 times larger share. relatively small increment as The two loads are not comparable. compared to Idaho Power's 20.0% 18.1% system load and is not expected to alone drive new generation 2 16.0% or transmission investments.As a result, the Company N 12.0°r° developed the demand rates to o 8.0% reflect embedded costs."23 6 4.0% 2 0.7% The FAB load is not a "small 0.0% increment" new power requirement, Lamb Weston FAB and the FAB load does alone drive Comparison of each company's peak Spec ialContract load expressed new generation or transmission asa%age of the Company's annual average total system load. investments. Figure 2—Lamb Weston and FAB are not comparable 2' IPC-E-23-18,Application section 15 page 7(emphasis added). 22 IPC-E-23-18,Application section 19, page 9(emphasis added). 23 IPC-E-23-18,Application section 17, pages 8 and 9(emphasis added). IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 9 Clean Energy Opportunities for Idaho At seven/tenths of 1% of average system load, the incremental generation and transmission resources Lamb Weston's Special contract would require (if any)were deemed too small to warrant an incremental demand cost allocation. By contrast the FAB alone will cause multi-billion dollars of generation investments"." At >18% of average system load, the incremental generation and transmission resources that the FAB load will require are not comparable to the Lamb Weston requirements. The fact that the Company chose to price demand for Lamb Weston based on embedded costs does not justify a similar embedded demand cost treatment for the FAB. 1.3 Perverse Incentives- In this era where IOUs compete for large new load"competitive" customers, protection of existing"captive"customers is at risk. Growth in power required to serve new very large customers is changing the electricity market nationwide. We are in a new era of exploding demand for electric power. And in this new era, biases inherent to the traditional Investor Owned Utility(IOU) incentive structure become increasingly problematic. These biases serve to favor the IOU and new large load customers at the expense of existing customers. In the past, IOUs faced a low but relatively stable increase in demand for their product. They didn't grow fast but were reliable sources of earnings and related dividend payments. Even then the IOU was incented to propose additions to its infrastructure (with related increases in the rate base that drives its earning capacity) but methods were developed to balance that incentive. Traditionally, careful resource planning, competitive procurements and CPCN review have provided protection to the captive customers residing in the IOU's service territory. An IRP identifies the need for additional resources. RFP based competition ensures good value when the new resources are needed. And a CPCN review confirms the current need and appropriateness of this particular resource to serve that need . Overall this regulatory process protects the captive customers from excessive procurement the Company incentives could otherwise produce. What has recently changed the game is an element of competition between IOUs for a new class of extremely large customers. Should these new customers choose to build within a particular IOU's service territory the IOU could potentially justify massive increases in its infrastructure and rate base. That's what is happening here, and the FAB is just the first of a procession of new megaload customers coming to southern Idaho. 24 If the Company were to procure all the Gas/1-12,Wind,Solar and Storage resources shown on Table 3 directly(rather than via PPA)at the price per MW values in the 2025 IRP that sum of"capital costs"would exceed$3.5 billion. With adjustment for resource requirements being met via PPA rather than IPC ownership the capital costs for FAB required generation resources would exceed$2 billion. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 10 4'1d11,6, Clean Energy Opportunities for Idaho The potential for new megaload customers justifying enormous increases in IOU earning power is like spreading chum in front of financial analysts. IPC President Grow also testified in the Company's most recent rate case: ... Idaho Power expects to double its rate base over the next four years."2' This new condition presents a big new challenge for regulators. The financial structure incents IOUs to propose low-rate contracts to new megaload customers in order to win the new"competitive"customers to their service territories and support massive rate base growth. A low rate structure benefits the new megaload customer. That customer's decision to add its massive new load in the IOU's service territory benefits the IOU. But what about the interests of existing captive customers that already take power in the IOU's service territory? How do regulators balance the interests of the Company's existing captive customers with the benefits new customer growth can provide?" CEO Policy Director Heckler has testified that the proposed ESA represents a sweet deal27 for both parties. Figure 3 shows that adding the incremental generation resources needed to serve the FAB load will provide IPC an opportunity to earn an extra $1.5 trillion over the next 20 years. Over a 20-year ESA duration,IPC would receive>$1.5 bllion of incremental return on investment on Company purchases of the FAB caused incremental generation resources presented in Mr. Ellsworth's testimony(excludes all solar&most of the wind as PPAs) $160,000,000 $120,000,000 $80,000,000 $40,000,000 $- I, co 0) N M ' 'D r M 0 O .--I N M V '0 N N N M M M M M M M M M M a 8 8 8 9 a a N N N N N N N N N N N N N N N N N N N N Annual return on investment on net depreciated value of incremental generation resources Figure 3-Rate base increases to meet incremental FAB generation requirement are highly beneficial to IPC earnings potential 25 Lisa Grow Direct, IPC-E-25-16,24:14-15(May 30,2025). 26 For related discussion see Extracting Profits from the Public: How Utility Ratepayers Are Paying for Big Tech's Power Eliza Martin and Ari Peskoe, Environmental and Energy Law Program, Harvard Law School March 2025. 27 IPC-E-24-44 October 28 2025 Hearing transcript, Heckler Com, page 802. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 11 1p Clean Energy Opportunities for Idaho In addition to the very favorable overall implied rate structure offered 2025 IRP forecasts marginal energy costs to decline more than 60%over FAB lifetime to the FAB in the ESA, a different but Boor equally concerning implication of the proposed ESA was raised regarding 80% the option it effectively grants the FAB 60% to transition out of being charged aOX. marginal energy rates. 28 20% The 2025 IRP projects substantial 0% declines in energy prices as SWIP and N N N N N M M M M M M M M M M 0 0 0 0 0 0 0 0 0 0 0 0 0 o g 8 8 8 8 N N N N N N N N N N N N N N N N N N N N B2H improve market access in the Annual marginal enegy cost as a%age of2026value next decade. — Figure 4-Improved market access is forecasted to drive down energy prices in the coming decades. ESA terms imply that energy consumption at the FAB will rise over a ramp-up period in the remainder of this decade and then could plateau during the following decade and a half. Even a cursory review of the data shown in Figure 4 suggests that the option to choose whether to remain at marginal energy prices or convert to an embedded energy rate around 2030 grants a substantial benefit to the FAB. The rational for charging marginal energy rates to the FAB was based on a belief that the FAB would increase energy demand, that the increase in energy demand would cause energy prices to rise, and that the FAB would absorb the energy price increase. The 2025 IRP forecasts flip that rationale on its head. If the IRP forecasts are correct, in the 2030s the ESA effectively grants the FAB the choice to buy its energy at a rate that is lower than the overall energy cost charged to existing customers. The FAB is proposed to get a very low demand rate and the Company gets a very large increase in its return on investment. The FAB will ostensibly face a marginal price for its energy but even the ESA provides a concerning"option"to the FAB on that matter. The proposal in the ESA is clearly good for the parties to the ESA contract. Absent changes to that ESA and subsequent efforts to resolve related open issues, CEO concludes that approval of the ESA as proposed is not in the public interest. 1.4 Bad Precedent-the proposed FAB cost allocation methods limit fair treatment for existing customers from both the FAB and successive large load customers. 28 See IPC-E-24-44 Heckler Rebuttal page 11. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 12 Clean Energy Opportunities for Idaho In rebuttal testimony CEO raised concerns about the precedential risk that could arise from the FAB ESA.29 As detailed above, CEO believes the FAB can be clearly distinguished from any other customer in the Company's service territory. Terms in section 13.2 of the proposed ESA appear to attempt to constrain Commission actions by requiring showings that those actions are"nondiscriminatory". As a unique level of load the FAB is in a class of one and has no analogous customer against which it would receive a discriminatory treatment. However,the next megaload customer is not going to be in a class of one and will have a basis for arguing that they are being discriminated against if they don't get treatment analogous to that provided to the FAB. Approval of the ESA as proposed without addressing the open issues delineated in the brief section below may prove unduly constraining on future Commission decisions. With billions of dollars riding on how FAB open issues are resolved, CEO sees a substantial risk of a future megaload customer suing to receive FAB like treatment.31 Approval of the ESA as proposed would provide a dangerous precedent. For that and other reasons, the ESA should not be approved without modification. 2 New very large customers raise several new issues that require clarification and policy guidance from the Commission. 2.1 What constitutes a new large load? IPC witness Ms. Aschbrenner explains that current Company policy considers any new customer with an expected load greater than 1 megawatt a "large load customer"and any customer with a load greater than 20 megawatts is of a size requiring a special contract31. The FAB (and presumably many of the loads in the additional 3 gigawatt"pipeline") are orders of magnitude larger than these classifications. In some states a size threshold is used to define a large load, for example 75 or 100 megawatts. In other states an impact test is employed, for example any new customer who requires infrastructure beyond what current resource plans call for adding over the next decade is a new large customer. As explained above, one of the fundamental distinctions between the FAB and other recent special contract customers such as Lamb Weston is the need for additional resources to serve the new FAB load. Guidance from the Commission regarding whether new customers with certain size or impact characteristics should receive a different rate design 29 IPC-E-24-44 Heckler Rebuttal page 13. 30 See Heckler comment regarding Supreme Court, IPC-E-24-44 October 28 2025 Hearing transcript, Heckler Com page 803. 3' IPC-E-24-44 Aschbrenner Direct page 5. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 13 Clean Energy Opportunities for Idaho treatment would be very valuable in light of the likelihood of additional new large customers being added in the Company service territory in the immediate future. 2.2 When does such a new large customer become"existing"and no longer"new"? The ESA Staff witness Mr. Eldred raised concerns that the FAB not be allowed to transfer from paying a marginal energy cost without a showing that doing such would not harm other customers.32 The option for the FAB to initiate a transition out of the marginal energy rate structure was timed to align with the end of the FAB load ramp period. One could conclude that this implies that once a new customer reaches its full planned level of consumption that the customer transitions to an "existing"customer status. Elsewhere in the ESA the treatment of stranded asset risk via a declining minimum demand charge suggests that some element of customer"newness"extends over a couple of decades.ss Guidance from the Commission concerning how to distinguish new very large customers - whether their size requires that they receive some special rate treatment and for how long a duration such rate treatment is warranted - remain relevant open questions worthy of Commission direction. Alternatives covered in section 2.6 below could effectively make this issue moot. 2.3 Should incremental infrastructure costs that would not occur but for the new load be charged to that new customer? CEO contends that if the timing and/or magnitude of a new large customer's load necessitates establishing or accelerating procurement of G&T system resources that customer should pay such costs associated with those assets. In Table 3 from Mr. Ellsworth's surrebuttal testimony the Company effectively acknowledges that the FAB will necessitate procuring additional generation resources. Both CEO and IIPA have also noted that the FAB will also cause the Company to incur costs related to the timing and magnitude of additional transmission resources the FAB will need that extend beyond the interconnection assets it has covered via Contributions in Aid of Construction (CIAC) payments. The FAB, as leader in a long pipeline of new very large customer loads, raises issues that warrant policy review. Collectively these new loads will require massive new Company funding. The rate and magnitude of this increase in funding need will likely raise the Company's overall cost of capital. A rising ROE and/or debt cost will impact all customers. 32 IPC-E-24-44 Eldred Direct page 11. 33 IPC-E-24-44 Heckler Rebuttal page 12. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 14 jp Clean Energy Opportunities for Idaho Should this increase in financing costs be charged to all customers or should it be allocated directly to the new loads causing this cost increase? 2.4 How should a new large load customer pay for the increased revenue requirements it causes due to upward pressure on the Company's financing costs and Return On Equity(ROE)? Large load customers put upward pressure on rates when they put upward pressure on ROE. As a result existing customers allocated a higher portion of total revenue requirements (e.g., residents) bear a higher portion of that increase. In IPC-E-25-16, the Company requested a higher ROE. The Company attributed that ROE increase in part because "high capital expenditures and increasing debt have recently worsened Idaho Power's financial profile. Oral testimony on October 28 discussed how large customers such as the FAB are driving increases in capital expenditures in a manner different than existing customers.35 The proposed ESA fails to address the upward pressure on rates caused by the FAB's disproportionate impact on ROE. CEO recommends that the Commission direct the Company to propose remedies to this matter in the filing of the Class Cost of Service docket stipulated in the IPC-E-25-16 settlement,the next GRC, or whatever proceeding viewed most appropriate by the Commission. 2.5 How are any incremental costs a new load causes to be measured and allocated to that customer? Table 3 estimates the quantity, timing and types of incremental generation resources the FAB would require through 2035 based on the set of assumptions underlying the 2025 IRP estimating tool. The actual additional generation resources that the Company will procure to serve load growth from the FAB will likely differ from the resource mix shown in Table 3. If we have a situation in the future where resources are being added to serve multiple new very large customers how will the actual costs incurred by the Company be allocated to the individual customers? Because resources must be procured before the load they will serve arises, how will costs incurred in one year be allocated to customers whose load requirement drove those procurement needs but whose actual load only occurs in subsequent years? 2.6 Could special rate design concerns related to new very large customers be reduced or eliminated by customer self-supply or via funding through a CIAC"loan"? 34 IPC-E-25-16,Thompson Direct 32:21-22. 35 Cross Ex of Idaho Power witness Aschenbrenner by Pete Richardson. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 15 Clean Energy Opportunities for Idaho Some states are requiring new very large customers to procure their own generation resources at their cost thus reducing cost impacts to existing customers. CEO believes that there are efficiencies that arise from having the Company directly procure incremental G&T resources and thus suggested a CIAC based alternative.36 Traditional CIAC payments are made to cover costs for resources that only benefit the customer making the CIAC payment (such as interconnection assets that only serve that customer). The CIAC payment is made and the customer receives a direct benefit, such as an interconnection. The customer will need interconnection for as long as it remains a customer so the CIAC payment is not expected to be repaid to the customer. CEO's suggestion focused on a slightly different approach. As has been discussed above, bulk system G&T resources are inherently used by multiple customers, so a new very large load customer would not get a sole benefit by making a CIAC payment to cover G&T costs. Existing customers arguably do deserve some protection from stranded asset risk related to costs the Company incurs to procure the additional G&T resources the new customer requires. CEO's suggestion is that the new large load customer be required to provide CIAC funding in an amount adequate to cover the present value of that customer's future G&T resource needs. Having made the CIAC payment, the new customer would not have caused the embedded G&T costs to increase so that new customer could be charged embedded demand rates. A difference between CEO's suggestion and traditional CIAC payments is that the funding be temporary. CEO suggests that the Company would gradually refund the CIAC payments to the customer as a credit against its embedded cost billing. Simultaneously the Company would shift the credited portion of the CIAC payment from a CIAC status and into the Company's rate base. If the new customer did not ultimately procure the full amount of power upon which its need for new G&T resources was predicated it would not receive a full refund of its CIAC payments thus protecting existing customers from a stranded asset risk. 3 Summary recommendations and requests The ESA should not be approved as proposed. Questions related to the FAB's share of future revenue requirements should be resolved within a follow-on process set up within this docket. The FAB should be provided some temporary pricing structure for use until those questions are resolved and implemented.37 36 See IPC-E-24-44 Heckler Rebuttal page 10. 37 IPC-E-24-44 Heckler Surrebuttal page 19. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 16 Clean Energy Opportunities for Idaho 3.1 Changes to the ESA CEO proposes at least three changes to the proposed ESA. 1. Revise Schedule 28 Time of Use (TOU) Energy Rate and the associated update methodology to more accurately reflect the hourly, time-varying nature of cost causation. No party has opposed the proposal by CEO to implement TOU energy rates for Schedule 28. The Company has proposed a strawman of such rates in its Surrebuttal, and parties in this docket also agreed to modified time periods in the IPC-E-25-16 Settlement Agreement. CEO asks the Commission to direct the Company to file a revision to Schedule 28 in which energy rates are updated with a time-of-use pricing structure that reflects the same or similar new time periods as the Schedule 19 TOU time periods stipulated in the IPC-E-25-16 General Rate Case Settlement Agreement.38 2. In section 6.1 and any other relevant portions of the ESA should be amended to make clear that any"additional transmission"costs not be limited to those needed as traditional"Interconnection Facilities"and those costs should be covered by Triton making additional upfront CIAC payments.39 3. The ESA should explicitly allow the ability to update the method used to determine Energy and Demand charges. 3.2 Staff lead follow-on process Issues listed in sections 2.1 through 2.6 above should be resolved within a follow-on process setup within this docket. CEO recommends that Staff be directed to lead this process. The next GRC is an inappropriate forum for resolving such issues. GRCs can be used to determine how much revenue should be collected from the FAB based on test year data but they should not be relied upon to determine the specific method for calculating the amount of revenue that should be collected from the FAB. If the Commission approves the proposed settlement in GRC IPC-E-25-16 and the Company opens a docket to address cost of service issues,that docket could address some matters raised in this case. However, other matters are specific to large load customers and should be addressed via a process specific to large load customers. CEO requests that the Commission provide guidance on the means for addressing each of the following matters: • Guidelines regarding what constitutes a new Large Load Customer. • When does anew large load customer transition from new to existing. 38 As described in IPC-E-24-44 White Surrebuttal, page15. 39 IPC-E-24-44 Hecker rebuttal page 6. IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 17 Clean Energy Opportunities for Idaho • Which incremental costs caused by the new large load customer should be charged to that customer, and how those costs should be measured. • Guidelines for how customers that disproportionately cause upward pressure on ROE and financing costs should pay for those impacts. • Guidelines for No-Harm Scenario Analyses for large load customers so that the Commission can adequately weigh the risks of harm to existing customers. • Consideration of alternatives such as whether payments made in the form of self- supply or CIAC could protect existing customers. • The degree to which G&T infrastructure provide energy benefits and the means of reflecting those in energy rates. Respectfully submitted, Courtney White Michael Heckler Managing Director Policy Director Clean Energy Opportunities for Idaho Clean Energy Opportunities for Idaho IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 18 CERTIFICATE OF SERVICE I hereby certify that on this 2nd day of December, 2025, 1 delivered true and correct copies of the foregoing CLOSING BRIEF to the following persons via the method of service noted: Electronic Mail Delivery (See Order No. 34602) Idaho Public Utilities Commission Monica Barrios-Sanchez Commission Secretary secretary(ilpuc.idaho.gov Idaho PUC Staff f Chris Burdin Deputy Attorney General Idaho Public Utilities Commission chris.burdin(@puc.idaho.gov Idaho Power Company Megan Goicoechea Allen Donovan Walker Connie Aschenbrenner Grant Anderson mgoicoecheaallenOidahopower.com dwalker@idahopower.com caschenbrennerna idahopower.com ganderson(@idahopower.com dockets idahopower.com Industrial Customers of Idaho Power, Inc. Peter J. Richardson Dr. Don Reading peter@richardsonadams.com dreadingna mindspring.com Idaho Irrigation Pumpers Association, Inc. Eric L. Olsen Lance Kaufman, Ph.D. elo(a)echohawk.com lance(a�aegisinsight.com IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 19 Micron Technology, Inc. Austin Rueschhoff Thorvald A. Nelson Austin W. Jensen Kristine A.K. Roach Holland & Hart, LLP darueschhoff0hollandhart.com tnelson aphollandhart.com awj ensen@hollandhart.com aclee(a)hollandhart.com karoach(a)hollandhart.com 'U Kelsey Jae Attorney for CEO IPC-E-24-44 Clean Energy Opportunities for Idaho's Closing Brief 20