Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
Intermountain Gas 251112 Nampa Construction
IPUC Construction Inspection In ps ector(s): Brooks, Green Date(s): 251112 Company/Owner: Intermountain Gas Company (IGC) Unit/OPID: 8160 Address: 5549&5550 E Lekeitio Village Dr City/District: Nampa Contractor/Job #: WO 12400937, Foreman: (Dasco) Operator Supervisor: None On-Site 12387441 H. Talamantez Job Description: '/" service line installations System Type: © GD ❑ GT ❑ GG One-Call Ticket: 2025452076, 2025432340 Total Inspection Days: 2.0 Tasks: Procedure# Rating Comments 1. Materials—Handling, Storage, Labeling OPS 11 SAT 2. Trenching/Boring—Depth, Clearance OPS 308 SAT OPS 322 3. Bedding/Backfill OPS 308 SAT SF 418 4. Pipe Installation(Tracer Wire) OPS 308 SAT OPS 322 5. Valve Installation OPS 703 N/A 6. Coating Condition OPS 401 N/A OPS 403 7. Manuals—Field Procedures, O & M SAT 8. Testing—Pressure, Duration, Type OPS 505 SAT 100 PSIG for 15 Minutes 9. OQ Qualifications OPS 800 SAT Verified 10. Casing Seal/Installation OPS 325 N/A 11. Service Line Installation OPS 302 SAT 12. Tie-In/Hot Tapping OPS 600 N/A 13. Meter Location/Regulator Testing OPS 302 N/A 14. Equipment Calibration Verification OPS 501 SAT Verified 15. EFV Installation OPS 301 SAT 16. MAOP OPS 602 N/A OPS 606 OPS 900 OPS 1000 17. Purge OPS 603 SAT 18. Safety Equipment SF 418 SAT SF 422 19. Abandonment OPS 607 N/A 20. Line Locating OPS 611 SAT IPUC Form 4 Rev.12/10/2024 IPUC Construction Inspection 21. Plastic Pine OPS 307 SAT - Joiner(s) Qualified OPS 309 - Fusion Tools OPS 325 - Squeezing OPS 800 - Heat Plate - Joining Procedure 22. Steel Pine OPS 200 N/A -Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 - Welding Procedures OPS 407 - Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 Additional Comments: Address: 5549 & 5550 E Lekeitio Village Dr Nampa, ID. Observations Included: trench depth, EFV installation, safety equipment, tracer wire, line locating, fusions,pressure test, line squeeze,purge, bedding and backfill, verification of OQ records, and discussed squeeze time requirements. Corrective Action Required: ❑ Yes ® No Compliance Letter: N/A Lead Inspector: Brooks Date: Reviewer: Date: 251112 Signature: Signature: IPUC Form 4 Rev. 12/10/2024