HomeMy WebLinkAbout20251105Notice_of_Proposed_Settlement_Order_No_36832.pdf Office of the Secretary
Service Date
November 5,2025
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER ) CASE NO. IPC-E-25-16
COMPANY'S APPLICATION FOR )
AUTHORITY TO INCREASE ITS RATES ) NOTICE OF PROPOSED
AND CHARGES FOR ELECTRIC SERVICE ) SETTLEMENT
IN THE STATE OF IDAHO )
NOTICE OF AMENDED
SCHEDULE
NOTICE OF CUSTOMER
HEARING
NOTICE OF COMMENT
DEADLINE
NOTICE OF TECHNICAL
HEARING
ORDER NO. 36832
On May 30, 2025, Idaho Power Company ("Company") applied to the Idaho Public
Utilities Commission ("Commission") requesting authority to increase its rates and charges for
electric service to its customers in the State of Idaho and for associated regulatory accounting
treatment. The Company requested a July 1, 2025, effective date.
On June 13, 2025, the Commission issued a Notice of Application, Notice of Suspension
of Proposed Effective Date, and Notice of Intervention Deadline. Order No. 36638 see also Errata
to Order No. 36638. The Commission granted intervention to: Clean Energy Opportunities for
Idaho("CEO");Idaho Irrigation Pumpers Association,Inc.("IIPA");the city of Boise City("Boise
City"); the Federal Executive Agencies ("FEA"); the Industrial Customers of Idaho Power
("ICIP"); Micron Technologies, Inc. ("Micron"); the Idaho Hydroelectric Power Producers Trust
("IdaHydro"); Gannon, et al., pro se ("Gannon"); the Kroger Co. ("Kroger"); and the Northwest
Energy Coalition ("NWEC") (collectively "Intervenors"). Order Nos. 36557, 36635, 36665,
36666, 36685, 36690, and 36691. On July 30, 2025, the Commission issued a Notice of Parties.
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 1
On August 21, 2025, the Commission issued a Notice of Schedule, Notice of Public
Workshop, Notice of Customer Hearings, Notice of Public Comment Deadline, and Notice of
Technical Hearing. Order No. 36731.
On September 9, 2025, September 29, 2025, and October 6, 2025, Commission Staff
("Staff'), the Company, and all Intervenors participated in settlement negotiations. Based upon
those settlement conferences, at the Commission's October 14, 2025, decision meeting, Staff
informed the Commission that Staff believed a settlement had been reached in principle, and Staff
requested that the Commission vacate the customer hearing scheduled on October 27, 2025, in
Twin Falls, Idaho, and the written testimony deadlines until such time as a Proposed Settlement
was filed for Commission approval, or the Commission was informed that a Proposed Settlement
would not be filed. On October 17, 2025, the Commission issued an Order Vacating Testimony
Deadlines and Customer Hearing. Order No. 36806.
On October 24, 2025, the Company filed a Stipulation and Settlement ("Proposed
Settlement") and a Motion for Approval of Stipulation and Settlement ("Motion"). The Proposed
Settlement was signed by Staff, the Company, Boise City, CEO, FEA, IIPA, Kroger, Micron, and
NWEC (collectively "the Parties").
NOTICE OF PROPOSED SETTLEMENT
YOU ARE HEREBY NOTIFIED that under the Proposed Settlement, the Company's
overall retail revenue will increase by $110 million annually for an average increase of 7.48
percent. Proposed Settlement at 2. The Parties agree that the Proposed Settlement represents a fair,
just, and reasonable compromise of the issues in this proceeding and that the Proposed Settlement
is in the public interest. Id.
YOU ARE FURTHER NOTIFIED that the Proposed Settlement sets forth certain revenue
requirement adjustments to the Company's filed case with accompanying explanation. Id. at 4.
The adjustments are summarized in the table below.
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 2
Summary of Stipulated Revenue Requirement Adjustments
(Figures reflect Idaho Jurisdictional Amounts
Filed Net Revenue Increase: $199,122,685
Stipulated Adjustments Adjustment Impact Net Rate Change
1. Cost of Capital
a. Return on Equity $27,687,577 $171,435,108
2. Rate Base
b. Adjustments to Plant in Service $21,605,673 $149,829,436
c. Customer Advances—Update to Actuals $1,411,447 $148,417,989
d. Customer Advances -BPA $986,816 $147,431,173
3. Revenue
e. Revenue Forecast—Update to Actuals $9,054,540 $138,376,633
4. Ex euses
f. Executive Comp, Training, and Travel $3,919,804 $134,456,829
g. Board of Directors Comp and Expenses $1,313,083 $133,143,746
h. Miscellaneous Adjustments $1,223,909 $131,919,837
5. Deferrals and Mechanisms
i. Wildfire O&M Base Update $10,722,564 $121,197,273
j. Insurance Base $5,328,358 $115,868,915
k. Wildfire Deferral Amortization $2,646,864 $113,222,051
1. Net Power Cost Update—Gas Prices $2,186,414 $111,035,637
in. Net Power Cost Update—EIM Benefits $995,491 $110,040,145
Id. at 5.
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, the Parties agree
to a 9.6 percent return on equity("ROE")and a 7.410 percent overall rate of return("ROR")based
on the filed cost of debt and capital structure, applied to an authorized Idaho jurisdictional rate
base of$4,881,563,721. Id.
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, the Parties do not
agree on any particular class cost-of-service("CCOS")methodology and the Proposed Settlement
does not request that the Commission approve a particular CCOS methodology.Id. at 9.
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, the Parties agree
that the $110 million net revenue increase should be recovered by implementing tariffs in
conformance with Exhibit No. 1 attached to the Proposed Settlement.Id. The Parties represent that
the rate spread was generally developed using a method to increase the rates for each customer
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 3
class by a factor at least 0.3 times,but not more than 1.3 times of the overall 4.25 percent increase.
Id.
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, the Parties agree,
for settlement purposes, to the rate design and tariff provisions proposed by the Company in Mr.
Grant Anderson's direct testimony,updated to reflect the Proposed Settlement CCOS.Id. at 9-10.
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, the existing $15
Service Charge will remain for Schedules 1 (Residential Service Standard Plan), 3 (Master-
Metered Mobile Home Park Residential Service), 5 (Residential Service—Time-of-Use Plan), and
6 (Residential Service On-Site Generation), the existing $25 Service Charge will remain for
Schedules 7 (Small Generation Service), 8 (Small General Service On-Site Generation), and 9
(Large General Service— Secondary). Id. at 10.
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, a Service Charge
of$345 will be implemented for Schedule 9 (Large General Service—Primary and Transmission),
a $110 Service Charge will be implemented for Schedule 19 (Large Power— Secondary Service),
and a $450 Service Charge will be implemented for Schedule 19 (Large Power — Primary and
Transmission Service).Id.
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, Schedule 9 (Large
General Service—Primary and Transmission), Schedule 19 (Large Power Service), and Schedule
30 (Electric Service Rate for United States Department of Energy Idaho Operations Office), the
collection of demand-classified costs through the Demand and/or Basic Load Capacity charges
will reflect an approximate 40 percent movement toward cost of service for that pricing
component, as informed by the Proposed Settlement CCOS Study.Id.
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, Schedule 9 (Large
General Service) and 19 (Large Power Service), the time-of-use periods for On-Peak hours will
remain consistent with the Company's filed position and the Off-Peak hours will be defined as 10
a.m. to 2 p.m.,Monday through Saturday and all hours on Sundays and Holidays.Id. at 10-11. The
Mid-Peak hours will include all hours not designated as On-Peak or Off-Peak.Id. at 11.
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, the requested
effective date is January 1, 2026.Id.
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 4
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, the Company
agrees to initiate a single-issue case related to CCOS methodology for the Commission's
consideration in advance of filing a Notice of Intent for its next general rate case, but in no event
later than the end of the first quarter of 2026. Id.
YOU ARE FURTHER NOTIFIED that under the Proposed Settlement, the Company
agrees to initiate discussions with IIPA, and other interested parties, with the intent of developing
an optional Agricultural Irrigation Service (Schedule 24) time-of-use offering. Id.
YOU ARE FURTHER NOTIFIED that the Proposed Settlement contains provisions
concerning: a Test Year Methodology Workshop; Capital Investments; the Revenue Sharing
Mechanism; the Accumulated Deferred Investment Tax Credit Revenue Sharing Mechanism; the
Wood River Valley Distribution Line; the Power Cost Adjustment; Wheeling Tracking; the Fixed
Cost Adjustment; the Sales Based Adjustment Rate; Valmy and Bridger; and the Rule H Three
Phase Base Charge.Id. at 12-16.
YOU ARE FURTHER NOTIFIED that the Parties believe that the Proposed Settlement
represents a fair,just, and reasonable compromise of the positions of the Parties in this case, and
that the Proposed Settlement is in the public interest. Id. at 16.
YOU ARE FURTHER NOTIFIED that under Commission Rule 275, "[p]roponents of a
proposed settlement carry the burden of showing that the settlement is reasonable, in the public
interest, or otherwise in accordance with law or regulatory policy." IDAPA 31.01.01.275.
YOU ARE FURTHER NOTIFIED that the Commission is not bound by the Proposed
Settlement reached by the Parties. The Commission will independently review any proposed
settlement to determine whether the settlement is just, fair, and reasonable, and in the public
interest, or otherwise in accordance with law or regulatory policy. The Commission may accept a
settlement, reject a settlement, or state additional conditions under which a settlement will be
accepted. IDAPA 31.01.01.274-.276.
YOU ARE FURTHER NOTIFIED that if the Commission rejects any part or all of the
Proposed Settlement or imposes any additional material conditions on its approval, each Party
reserves the right to withdraw from the Proposed Settlement within fourteen (14) days of such
order. Proposed Settlement at 17.
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 5
YOU ARE FURTHER NOTIFIED that the Proposed Settlement in Case No. IPC-E-25-16
has been filed with the Commission and is available for public inspection during regular business
hours at the Commission's office or on the Commission's website at www.puc.idaho.gov. Click
on the"ELECTRIC"tab in the left-hand column of the home page, click"Open Cases,"and select
the case number as shown on the front of this document.
NOTICE OF AMENDED SCHEDULE
YOU ARE FURTHER NOTIFIED that the Commission establishes the following
amended procedural schedule:
• November 18, 2025: All Party Testimony
• November 20, 2025: In person and telephonic Customer Hearing in Boise, Idaho,
starting at 4:30 p.m. (local time) and ending at 7:30 p.m., or after all customer
testimony has been taken, whichever comes first.
• November 20, 2025: Public Comment Deadline
• December 2, 2025: Technical Hearing starting at 9:00 a.m. (local time) and
ending at 5:00 p.m.
• December 3-5, 2025: Technical Hearing continued as needed starting at 9:00 a.m.
(local time), and ending at 5:00 p.m.
YOU ARE FURTHER NOTIFIED that all testimony and exhibits in this matter must
comport with the requirements of Commission Rules of Procedure 231 and 267. IDAPA
31.01.01.231 and .267.
YOU ARE FURTHER NOTIFIED that all proceedings in this matter will be conducted
pursuant to the Commission's Rules of Procedure, IDAPA 31.01.01.000, et seq.
NOTICE OF CUSTOMER HEARING
YOU ARE FURTHER NOTIFIED that the Commission will hold a customer hearing in
this matter in Boise,Idaho, on Thursday,November 20,2025,starting at 4:30 p.m.(local time),
and ending at 7:30 p.m., or after all customer testimony has been taken, whichever comes
first. The Commission, in its discretion, may adjust the scheduled times as necessary. The
customer hearing will be held at the Idaho Public Utilities Commission, 11331 W. Chinden
Boulevard, Building 8, Suite 201-A, Boise, ID 83714. Persons attending the hearing in-person
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 6
will have an opportunity to provide testimony. Those planning to testify in-person are encouraged
to arrive at the hearing location by 4:15 p.m. (local time).
PLEASE NOTE: due to an update in the technology services used by the Commission, the
call-in information for the telephonic/online options have been updated from Order No.
36731.
To submit testimony over the phone, please call 1-208-985-2810 and enter meeting
number 798 879165#when prompted.
To listen to the hearing only, please call 1-208-985-2810 and enter meeting number 342
710 86#when prompted.
NOTICE OF PUBLIC COMMENT DEADLINE
YOU ARE FURTHER NOTIFIED that the Commission seeks comments from the public
on the Proposed Settlement. Persons desiring to state a position on the Proposed Settlement may
file a written comment explaining why the person supports or opposes the Proposed Settlement.
Persons must file comments by November 20, 2025. Comments must be filed through the
Commission's website or by e-mail unless computer access is unavailable. To comment
electronically,please access the Commission's home page at www.puc.idaho.gov. Click the"Case
Comment Form" and complete the form using the case number as it appears on the front of this
document.
YOU ARE FURTHER NOTIFIED that to file by e-mail, persons must e-mail the
comments to the Commission Secretary and the Company at the e-mail addresses listed below.
Persons submitting a comment by e-mail must provide their name, address, and the Case Number
under which they are commenting. Persons submitting a comment by e-mail also acknowledge
that submitting a comment in an open case constitutes a public record under Idaho Code § 74-101
(13), and all information provided by such person is available for public and media inspection.
YOU ARE FURTHER NOTIFIED that if computer access is unavailable, then comments
may be mailed to the Commission and Company at the addresses below. Persons submitting a
comment by mail must provide their name, address, and the Case Number under which they are
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 7
commenting. Persons submitting a comment by mail also acknowledge that submitting a comment
in an open case constitutes a public record under Idaho Code § 74-101 (13), and all information
provided by such person is available for public and media inspection.
For the Commission: For the Company:
Commission Secretary Donovan E. Walker
Idaho Public Utilities Commission Megan Goicoechea Allen
P.O. Box 83720 Timothy Tatum
Boise, ID 83702 Connie Aschenbrenner
secretga&puc.idaho.gov Matt Larkin
1221 West Idaho Street(83702)
P.O. Box 70
Boise, Idaho 83707
dwalker&idahopower.com
m goicoecheaallengidahopower.com
ttatum(kidahopower.com
caschenbrenner(d),idahopower.com
mlarkin&idahopower.com
dockets(&,idahopower.com
NOTICE OF TECHNICAL HEARING
YOU ARE HEREBY NOTIFIED that the Commission will conduct a technical hearing in
this matter on Tuesday, December 2, 2025, starting at 9:00 a.m. (local time) and ending at
5:00 p.m.The technical hearing shall continue as necessary each day,Wednesday,December
3 through Friday, December 5, 2025, starting at 9:00 a.m. (local time) and ending at 5:00
p.m. The technical hearing will be held at the Idaho Public Utilities Commission, 11331 W.
Chinden Boulevard, Building 8, Suite 201-A, Boise, ID 83714. A technical hearing is an
opportunity for the parties to the case to present witnesses, testimony, and exhibits. IDAPA
31.01.01.241.04. Persons interested in listening to or watching the testimony and presentations at
the technical hearing may attend the meeting using the information below:
PLEASE NOTE: due to an update in the technology services used by the Commission, the
call-in information for the telephonic/online options have been updated from Order No.
36731.
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 8
Day Scheduled To participate online: To participate by
time (local telephone:
time
December 9:00 a.m. — To watch the hearing online, To listen to the hearing
2' 2025 5:00 p.m. please visit teams.live.com and over the phone, please
click on the "Join a meeting" call 1-208-985-2810 and
option on the upper left side of the enter meeting number
December page. 599 758 120# when
3-5, 2025
Next,type 229 001 621 2474 in the prompted.
Meeting ID window. Then type
(As Needed) Rc6Nv9Qu in the Meeting
passcode window.
YOU ARE FURTHER NOTIFIED that all hearings and prehearing conferences in this
matter will be held in facilities meeting the accessibility requirements of the Americans with
Disabilities Act ("ADA"). Persons needing the help of a sign language interpreter or other
assistance to participate in or to understand testimony and argument at a public hearing may ask
the Commission to provide a sign language interpreter or other assistance at the hearing. The
request for assistance must be received at least five working days before the hearing by contacting
the Commission Secretary at:
IDAHO PUBLIC UTILITIES COMMISSION
P.O. BOX 83720
BOISE, IDAHO 83702
Telephone: (208) 334-0338
Facsimile: (208) 334-3762
Email: secretary(apuc.idaho.gov
YOU ARE FURTHER NOTIFIED that the record in this matter is available for public
inspection during regular business hours at the Commission's office. These documents are also
available on the Commission's website at www.puc.idaho.gov. Click on the "ELECTRIC" icon,
select"Open Cases," and click on the case number as shown on the front of this document.
ORDER
IT IS HEREBY ORDERED that the Commission amends the procedural schedule as set
forth above.
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 9
IT IS FURTHER ORDERED that written testimony in support of, or opposition to, the
Proposed Settlement is due on November 18, 2025.
IT IS FURTHER ORDERED that persons desiring to submit public written comments
must do so by November 20, 2025.
IT IS FURTHER ORDERED that the Commission shall hold a customer hearing in Boise,
Idaho, on Thursday,November 20,2025, starting at 4:30 p.m. (local time)and ending at 7:30 p.m.,
or after all customer testimony has been taken, whichever comes first.
IT IS FURTHER ORDERED that the Commission will conduct a technical hearing in this
matter on Tuesday, December 2, 2025, starting at 9:00 a.m. (local time) and ending at 5:00 p.m.
The technical hearing shall continue as necessary each day, Wednesday, December 3 through
Friday, December 5, 2025, starting at 9:00 a.m. (local time) and ending at 5:00 p.m. The technical
hearing will be held at the Idaho Public Utilities Commission, 11331 W. Chinden Boulevard,
Building 8, Suite 201-A, Boise, ID 83714.
IT IS FURTHER ORDERED that parties comply with Order No. 35375, issued April 21,
2022. Generally, all pleadings should be filed with the Commission electronically and will be
deemed timely filed when received by the Commission Secretary.See Rule 14.02. Service between
parties should continue to be accomplished electronically when possible. However, voluminous
discovery-related documents may be filed and served on CD-ROM or a USB flash drive.
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 10
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 51h day of
November 2025.
G
Gv�
EDWARD LODGE,WPRE I ENT
HN R. HAMMOND JR., COMMISSIONER
DAYN HARDI , COMMISSIONER
ATTEST:
ga4- -A--
Laur Calderon Robles
Interim Commission Secretary
I:\Legal\ELECTRIC\IPC-E-25-16_GRC\orders\IPCE2516_Ntc_PSet_Sch_em.docx
NOTICE OF PROPOSED SETTLEMENT
NOTICE OF AMENDED SCHEDULE
NOTICE OF CUSTOMER HEARING
NOTICE OF COMMENT DEADLINE
NOTICE OF TECHNICAL HEARING
ORDER NO. 36832 11