Intermountain Gas 250909 Kuna Construction
IPUC Construction Inspection Inspector(s): Galli, Brooks Date(s): 250909 Company/Owner: Intermountain Gas Company (IGC) Unit/OPID: 08160 Address: 11789 W Anthos Lane City/District: Kuna Contractor/Job #: W012279497 Foreman: Operator Supervisor: None Chris Dahl Job Description: '/" Service Line System Type: © GD ❑ GT ❑ GG One-Call Ticket: 2025353205 Total Inspection Days: 2.0 Tasks: Procedure# Rating Comments 1. Materials—Handling, Storage, Labeling OPS 11 SAT %" inch dated 07/2024 2. Trenching/Boring—Depth, Clearance OPS 308 SAT 24 inches OPS 322 3. Bedding/Backfill OPS 308 SAT Sand used SF 418 4. Pipe Installation (Tracer Wire) OPS 308 SAT 14 gauge observed in trench OPS 322 5. Valve Installation OPS 703 N/A 6. Coating Condition OPS 401 N/A OPS 403 7. Manuals—Field Procedures, O & M SAT 8. Testing—Pressure, Duration, Type OPS 505 SAT 100 psi for 15 minutes 9. OQ Qualifications OPS 800 SAT Verified 10. Casing Seal/Installation OPS 325 N/A 11. Service Line Installation OPS 302 SAT 12. Tie-In/Hot Tapping OPS 600 N/A 13. Meter Location/Regulator Testing OPS 302 SAT 3 feet away from electrical 14. Equipment Calibration Verification OPS 501 SAT Verified 15. EFV Installation OPS 301 SAT EFV 1200 16. MAOP OPS 602 N/A OPS 606 OPS 900 OPS 1000 17. Purge OPS 603 N/A 18. Safety Equipment SF 418 SAT Fire Extinguisher SF 422 19. Abandonment OPS 607 N/A 20. Line Locating OPS 611 SAT Valid dig ticket IPUC Form 4 Rev.12/10/2024 IPUC Construction Inspection 21. Plastic Pipe OPS 307 SAT Observed completed fusions of%" - Joiner(s) Qualified OPS 309 PE. - Fusion Tools OPS 325 Observed squeeze off - Squeezing OPS 800 - Heat Plate -Joining Procedure 22. Steel Pipe OPS 200 N/A - Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 -Welding Procedures OPS 407 - Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 Additional Comments: Observations included (11789 W Anthos Lane, Kuna, ID): Safety equipment, JSA, verified operator qualifications, verified equipment calibration, correct trench depth, verified proper rollback on completed 3/4"butt fusions, tracer wire installation, bedding, successful pressure test, squeeze off and backfill. Quizzed employees of AOC recognition of squeeze off and bedding. Observed employees complete a second pressure test due to 2 psi drop. All observed procedures were followed in accordance with IGC Operations and Maintenance Manual. Corrective Action Required: ❑ Yes ® No Compliance Letter#: NA Lead Inspector: Galli Date: Reviewer: Brooks Date: 250909 Signature: [ '� ' Signature: i IPUC Form 4 Rev. 12/10/2024